100% found this document useful (1 vote)
130 views

Project Schedule Alto Maipo - 122014

1) The document outlines the schedule for the Alto Maipo Hydroelectric Project, which includes construction of surface works, water intakes, water conveyance systems, tunnels, and transmission lines between 2014-2018. 2) Major activities include construction of access roads, intake structures at La Engorda, Colina, Las Placas, and El Morado, a stilling basin at El Volcan, tunnels, and a transmission line between Alto Volcan and La Engorda Intake. 3) The schedule is detailed over multiple pages with estimated start and end dates for over 80 individual construction activities and projects. The critical path appears to run through intake construction and tunneling activities.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
130 views

Project Schedule Alto Maipo - 122014

1) The document outlines the schedule for the Alto Maipo Hydroelectric Project, which includes construction of surface works, water intakes, water conveyance systems, tunnels, and transmission lines between 2014-2018. 2) Major activities include construction of access roads, intake structures at La Engorda, Colina, Las Placas, and El Morado, a stilling basin at El Volcan, tunnels, and a transmission line between Alto Volcan and La Engorda Intake. 3) The schedule is detailed over multiple pages with estimated start and end dates for over 80 individual construction activities and projects. The critical path appears to run through intake construction and tunneling activities.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 3

ALTO MAIPO SpA

PROJECT HYDROELECTRIC ALTO MAIPO


PROJECT SCHEDULE
#

1
2
3
4

Activity ID

Activity Name

Remaining Start
Duration

ALTO MAIPO CON


CONSTRUCTION PROGRAM Rev.00
SURFACE WORKS
SISTEMA ADUCCION ALTO
A
VOLCAN
ACCESS ROAD FROM BEM to BLE

Finish

1125 11-Dec-13

06-Jun-18

1125 11-Dec-13

06-Jun-18

691 09-Dec-14

04-Dec-17

101 09-Dec-14

20-Apr-15

ACCNM6170CON01

CONSTRUCTION OF ACCESS ROAD FROM EL MORADO TO DESANDER

23 09-Dec-14*

08-Jan-15

ACCNM6170CON02

CONSTRUCTION OF TEMPORARY CROSSING OVER RIO EL MORADO

15 09-Jan-15

28-Jan-15

ACCNM6170CON03

TEMPORARY ACCESS ROAD FROM PUENTE MORADO TO BOCATOMA LAS PLACA

21 28-Jan-15

24-Feb-15

ACCNM6170CON04

TEMPORARY ACCESS ROAD FROM BOCATOMA LAS PLACAS TO BOCATOMA COL

21 24-Feb-15

23-Mar-15

ACCNM6170CON05

TEMPORARY ACCESS ROAD FROM BOCATOMA COLINA TO BOCATOMA LA ENGO

21 23-Mar-15

20-Apr-15

305 21-Apr-15

22-Sep-16

10

SCOPE SEGMENT: LA ENGORDA INTAKE

11

ACCNM6105CON01

DIVERSION WORKS AND COFFERDAM CONSTRUCTION

14 21-Apr-15

08-May-15

12

ACCNM6105CON02

SOIL AND ROCK EXCAVATION FOR STRUCTURES

21 09-May-15

04-Jun-15

13

ACCNM6105CON03

CONCRETE WORKS

90 05-Jun-15

01-Dec-15

14

ACCNM6105CON04

INSTALLATIO N OF GATES AND HYDRO-MECHANIC EQUIPMENTS

60 02-Dec-15

19-Feb-16

15

ACCNM6105CON05

INSTALLATIO N OF STEEL STRUCTURES

60 19-Feb-16

07-May-16

16

ACCNM6105CON06

INSTALLATIO N ELECTRIC WORKS, CCTV & COMMUNICATION SYSTEM

60 09-May-16

22-Sep-16

365 21-Apr-15

10-Dec-16

17

SCOPE SEGMENT: COLINA


CO
INTAKE

2015
2016
2017
2018
2019
Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr ay
13
14 15 16 17 18
19 20 21
22 23 24 25
26 27 28 29 30
31 32 33 34 35
36 37 38 39 40 41 42
43 44 45 46 47
48 49 50 51 52 53 54 55 56
57 58 59
60 61 62 63 64 65 66

CONSTRUCTION OF ACCESS ROAD FROM EL MORADO TO D ESANDER


CONSTRUCTION OF TEMPORARY CROSSING OVER RIO EL MORADO
TEMPORARY ACCESS ROAD FROM PUENTE MORADO TO BOCATOMA LAS PLACAS
TEMPORARY ACCESS ROAD FROM BOCATOMA LAS PLACAS TO BOCATOMA COLINA
TEMPORARY ACCESS ROAD FROM BOCATOMA COLINA TO BOCATOMA LA ENGORDA
DIVERSION WORKS AND COFFERDAM CONSTRUCTION
SOIL AND ROCK EXCAVATION FOR STRUCTURES
CONCRETE WORKS
INSTALLATIO N OF GATES AND HYDRO-MECHANIC EQUIPMENTS
INSTALLATIO N OF STEEL STRUCTURES
INSTALLATIO N ELECTRIC WORKS, CCTV & COMMUNICATION SYSTEM

18

ACCNM6110CON01

DIVERSION WORKS AND COFFERDAM CONSTRUCTION

14 21-Apr-15

08-May-15

DIVERSION WORKS AND COFFERDAM CONSTRUCTION

19

ACCNM6110CON02

SOIL AND ROCK EXCAVATION FOR STRUCTURES

14 09-May-15

27-May-15

SOIL AND ROCK EXCAVATION FOR STRUCTURES

20

ACCNM6110CON03

INTAKE CONCRETE WORKS

150 27-May-15

10-Feb-16

21

ACCNM6110CON04

INSTALLATIO N OF HYDRO-MECHANIC EQ UIPMENTS

60 19-Feb-16

07-May-16

22

ACCNM6110CON05

INSTALLATIO N OF STEEL STRUCTURES

60 09-May-16

22-Sep-16

23

ACCNM6110CON06

INSTALLATIO N ELECTRIC WORKS, CCTV & COMMUNICATION SYSTEM

60 23-Sep-16

10-Dec-16

24

SCOPE SEGMENT: LAS PLACAS INTAKE

282 11-Feb-16

11-Apr-17

INTAKE CONCRETE WORKS


INSTALLATIO N OF HYDRO-MECHANIC EQ UIPMENTS
INSTALLATIO N OF STEEL STRUCTURES
INSTALLATIO N ELECTRIC WORKS, CCTV & C OMMUNICATION SYSTEM

25

ACCNM6115CON01

DIVERSION WORKS AND COFFERDAM CONSTRUCTION

28 11-Feb-16

17-Mar-16

DIVERSION WORKS AND COFFERDAM CONSTRUCTION

26

ACCNM6115CON02

SOIL AND ROCK EXCAVATION FOR STRUCTURES

14 17-Mar-16

06-Apr-16

SOIL AND ROCK EXCAVATION FOR STRUCTURES

27

ACCNM6115CON03

INTAKE CONCRETE WORKS

90 06-Apr-16

29-Sep-16

28

ACCNM6115CON04

INSTALLATIO N OF HYDRO-MECHANIC EQ UIPMENTS AND RACKS

45 29-Sep-16

26-Nov-16

29

ACCNM6115CON05

INSTALLATIO N OF STEEL STRUCTURES

45 28-Nov-16

24-Jan-17

30

ACCNM6115CON06

INSTALLATIO N ELECTRIC WORKS, CCTV & COMMUNICATION SYSTEM

60 25-Jan-17

11-Apr-17

345 09-May-16

04-Dec-17

31

SCOPE SEGMENT: EL V
VOLCAN WATER CONVEYANCE SYSTEM

INTAKE CONCRETE WORKS


INSTALLATIO N OF HYDRO-MECHANIC EQ UIPMENTS AND RACKS
INSTALLATIO N OF STEEL STRUCTURES
INSTALLATIO N ELECTRIC WORKS, CCTV & COMMUNICATION SYSTEM

24 09-May-16

07-Jun-16

33

ACCNM6130CON01

SOIL AND ROCK EXCAVATION

14 09-May-16

25-May-16

34

ACCNM6130CON02

PLACING PRE-CAST CONCRETE PIPES

14 17-May-16

03-Jun-16

PLACING PRE-CAST CONCRETE PIPES

35

ACCNM6130CON03

STRUCTURAL AND COMPACTED FILL

14 20-May-16

07-Jun-16

STRUCTURAL AND COMPACTED FILL

189 23-Sep-16

26-May-17

32

36

LA ENGORDA CAMARA
CAMA
EMPALME SECTION (TRAMO 1; 0+000 to 0+467.175 m)

BOCATOMA LA COLIN
COLINA - JUNCTION CHAMBER COLINA (TRAMOS 3; 0+021.300 to 1+415.62 m)

37

ACCNM6130CON04

SOIL AND ROCK EXCAVATION

84 23-Sep-16

10-Jan-17

38

ACCNM6130CON05

CONCRETE AND OTHERS

154 21-Oct-16

10-May-17

39

ACCNM6130CON06

STRUCTURAL AND COMPACTED FILL

154 07-Nov-16

26-May-17

190 25-Jan-17

04-Dec-17

40

JUNCTION CHAMBER COLINA - BOCATOMA LAS PLACAS (TRAMOS 4; 1+442.886 to 2+400 m)

41

ACCNM6130CON07

SOIL AND ROCK EXCAVATION

58 25-Jan-17

07-Apr-17

42

ACCNM6130CON08

CONCRETE AND OTHERS

96 11-May-17

16-Nov-17

43

ACCNM6130CON09

STRUCTURAL AND COMPACTED FILL

96 26-May-17

04-Dec-17

44

EL MORADO SIPHON

72 19-Dec-16

20-Mar-17

45

ACCNM6130CON10

SURFACE WATER CONTROL

14 19-Dec-16

05-Jan-17

46

ACCNM6130CON11

SOIL AND ROCK EXCAVATION FOR STRUCTURES

14 05-Jan-17*

23-Jan-17

47

ACCNM6130CON12

CONCRETE AND OTHERS

30 24-Jan-17

02-Mar-17

48

ACCNM6130CON13

STRUCTURAL AND COMPACTED FILL

14 02-Mar-17

20-Mar-17

554 28-Jan-15

23-May-17

49

SCOPE SEGMENT: STILLING


STI
BASIN EL VO LCAN

50

ACCNM6125CON01

SOIL AND ROCK EXCAVATION FOR STRUCTURES

51

ACCNM6125CON02

CONCRETE WORKS FOR THE STILLING BASIN STRUCTURE

52

ACCNM6125CON03

53
54
55

84 28-Jan-15

18-May-15

260 19-May-15

22-Aug-16

INSTALLATIO N OF HYDRO-MECHANIC EQ UIPMENTS AND RACKS

90 23-Aug-16

19-Dec-16

ACCNM6125CON04

INSTALLATIO N OF STEEL STRUCTURES

60 19-Dec-16

04-Mar-17

ACCNM6125CON05

INSTALLATIO N ELECTRIC WORKS, CCTV & COMMUNICATION SYSTEM

60 06-Mar-17

23-May-17

335 19-May-15

28-Nov-16

SCOPE SEGMENT: EL M
MORADO INTAKE

SOIL AND ROCK EXCAVATION

SOIL AND ROCK EXCAVATION


CONCRETE AND OTHERS
STRUCTURAL AND COMPACTED FILL
SOIL AND ROCK EXCAVATION
CONCRETE AND OTHERS
STRUCTURAL AND COMPACTED FILL
SURFACE WATER CONTROL
SOIL AND ROCK EXCAVATION FOR STRUCTURES
CONCRETE AND OTHERS
STRUCTURAL AND COMPACTED FILL
SOIL AND ROCK EXCAVATION FOR STRUCTURES
CONCRETE WORKS FOR THE STILLING BASIN STRUCTURE
INSTALLATIO N OF HYDRO-MECHANIC EQ UIPMENTS AND RACKS
INSTALLATIO N OF STEEL STRUCTURES
INSTALLATIO N ELECTRIC WORKS, CCTV & C OMMUNICATION SYSTEM

56

ACCNM6120CON01

DIVERSION WORKS AND COFFERDAM CONSTRUCTION

14 19-May-15

04-Jun-15

57

ACCNM6120CON02

SOIL AND ROCK EXCAVATION FOR STRUCTURES

21 05-Jun-15

01-Sep-15

58

ACCNM6120CON03

INTAKE CONCRETE WORKS

120 02-Sep-15

08-Feb-16

59

ACCNM6120CON04

INSTALLATIO N OF HYDRO-MECHANIC EQ UIPMENTS

60 09-Feb-16

26-Apr-16

60

ACCNM6120CON05

INSTALLATIO N OF STEEL STRUCTURES

60 27-Apr-16

09-Sep-16

61

ACCNM6120CON06

INSTALLATIO N ELECTRIC WORKS, CCTV & COMMUNICATION SYSTEM

60 10-Sep-16

28-Nov-16

62

PROJECTED BRIDGE

60 09-Feb-16

26-Apr-16

63

ACCNM6120CON07

BRIDGE - INFRASTRUCTURE AND CONCRETE DECK

30 09-Feb-16

17-Mar-16

BRIDGE - INFRASTRUCTURE AND CONCRETE DECK

64

ACCNM6120CON08

BRIDGE - SUPERSTRUCTURE AND FINISHING

30 17-Mar-16

26-Apr-16

BRIDGE - SUPERSTRUCTURE AND FINISHING

71 23-Aug-16

23-Nov-16

65

SCOPE SEGMENT: EL M
MORADO WATER CONVEYANCE SYSTEM

DIVERSION WORKS AND COFFERDAM CONSTRUCTION


SOIL AND ROCK EXCAVATION FOR STRUCTURES
INTAKE CONCRETE WORKS
INSTALLATIO N OF HYDRO-MECHANIC EQ UIPMENTS
INSTALLATIO N OF STEEL STRUCTURES
INSTALLATIO N ELECTRIC WORKS, CCTV & C OMMUNICATION SYSTEM

66

ACCNM6132CON01

SOIL AND ROCK EXCAVATION FOR STRUCTURES

21 23-Aug-16*

17-Sep-16

67

ACCNM6132CON02

CONCRETE AND OTHERS

44 20-Sep-16

14-Nov-16

CONCRETE AND OTHERS

68

ACCNM6132CON03

STRUCTURAL AND COMPACTED FILL

30 05-Oct-16

12-Nov-16

STRUCTURAL AND COMPACTED FILL

ACCNM6132CON04

BUILDING AND COMPACTION OF EMBANKMENT

69
70

DESENDER - ACCESS TO VOLCAN TUNNEL (TRAMOS 5 ; 728 m)

7 12-Nov-16

23-Nov-16

171 19-Dec-16

29-Sep-17

71

ACCNM6130CON14

SOIL AND ROCK EXCAVATION

44 19-Dec-16

13-Feb-17

72

ACCNM6130CON15

CONCRETE AND OTHERS

88 13-Feb-17

07-Jun-17

73

ACCNM6130CON16

STRUCTURAL AND COMPACTED FILL

88 08-Mar-17

31-Aug-17

74

ACCNM6130CON17

BUILDING AND COMPACTION OF EMBANKMENT

21 31-Aug-17

29-Sep-17

75

TRANSMISSION LINE

240 09-May-16

16-May-17

240 09-May-16

16-May-17

949 22-Aug-14

06-Jun-18

890 26-Sep-14

06-Jun-18

76
77
78

ACCNM6180CON01

Medium Voltage line Alto Volcan Between C12200 And La Engorda Intak e

SISTEMA TUNNEL ALTO


ALT VOLCAN
ENTRANCE PORTAL V1

79

ACCNM6165CON01

OPEN-CUT EXCAVATION AND ROCK SUPPORT

90 26-Sep-14*

23-Jan-15

80

ACCNM6165CON02

INSTALLATIO N OF FALSE TUNNEL

14 23-Jan-15

10-Feb-15

81

ACCNM6165CON03

CONCRETE AND OTHERS

30 11-Apr-18

18-May-18

82

ACCNM6165CON04

INSTALLATIO N OF BULKHEAD

14 19-May-18

06-Jun-18

Remaining Level of Effort

Actual Work

Remaining Work

SOIL AND ROCK EXCAVATION FOR STRUCTURES

BUILDING AND COMPACTION OF EMBANKMENT


SOIL AND ROCK EXCAVATION
CONCRETE AND OTHERS
STRUCTURAL AND COMPACTED FILL
BUILDING AND COMPACTION OF EMBANKMENT
Medium Voltage line Alto Volcan Between C12200 And La Engorda Intak e

OPEN-CUT EXCAVATION AND ROCK SUPPORT


INSTALLATIO N OF FALSE TUNNEL

Critical Remaining Work

CONCRETE AND OTHERS


INSTALLATIO N OF BULKHEAD

Milestone

Summary

Page 1 of 3

ALTO MAIPO SpA

PROJECT HYDROELECTRIC ALTO MAIPO


PROJECT SCHEDULE
#

83

Activity ID

Activity Name

Remaining Start
Duration
184 22-Aug-14

MODIFIED PORTAL V5 (EL YESO)

Finish

22-Apr-15

84

ACCNM6150CON01

OPEN-CUT EXCAVATION AND ROCK SUPPORT

90 22-Aug-14*

19-Dec-14

85

ACCNM6150CON02

INSTALLATIO N OF FALSE TUNNEL

14 19-Dec-14

08-Jan-15

86

ACCNM6150CON03

CONCRETE AND OTHERS

30 09-Jan-15

16-Feb-15

87

ACCNM6150CON04

INSTALLATIO N OF BULKHEAD

50 17-Feb-15

22-Apr-15

894 01-Apr-14

12-Oct-17

785 01-Apr-14

24-Apr-17

88

SISTEMA ADUCCION EL
E YESO

89

MUCK DEPOSIT N2

90

ACCNM6176CON01

CLEANING AND SCARPMENT OF MUCK DEPOSIT

14 01-Apr-14*

17-Apr-14

91

ACCNM6176CON02

CONSTRUCTION OF DRAIN DITCHES

14 17-Mar-17

04-Apr-17

92

ACCNM6176CON03

FINISHING OF MUCK DEPOSIT PLACES WITH SCARP SOIL

14 04-Apr-17

24-Apr-17

642 30-Mar-15

12-Oct-17

93

SCOPE SEGMENT: SECTOR


SEC
EL YESO INTAKE WORKS

94

ACCNM6135CON01

SURFACE WATER CONTROL STAGE-1

30 30-Mar-15

08-May-15

95

ACCNM6135CON02

SURFACE WATER CONTROL STAGE-2

30 16-May-16

22-Jun-16

96

STAGE-1 WORKS

261 09-May-15

14-May-16

97

ACCNM6135CON03

SOIL AND ROCK EXCAVATION

98

ACCNM6135CON04

CONCRETE AND OTHERS

99

ACCNM6135CON05

100

ACCNM6135CON06

101

30 09-May-15

16-Jun-15

150 17-Jun-15

30-Jan-16

STRUCTURAL AND COMPACTED FILL

21 01-Feb-16

26-Feb-16

INSTALLATIO N OF HYDRO-MECHANICAL EQUIPMENT

60 26-Feb-16

14-May-16

321 22-Jun-16

12-Oct-17

STAGE-2 WORKS

102

ACCNM6135CON07

SOIL AND ROCK EXCAVATION

103

ACCNM6135CON08

CONCRETE AND OTHERS

104

ACCNM6135CON09

105
106
107

30 22-Jun-16

29-Aug-16

150 30-Aug-16

11-Mar-17

STRUCTURAL AND COMPACTED FILL

21 13-Mar-17

07-Apr-17

ACCNM6135CON10

INSTALLATIO N OF STEEL STRUCTURES

60 07-Apr-17

26-Jun-17

ACCNM6135CON11

INSTALLATIO N ELECTRIC WORKS, CCTV & COMMUNICATION SYSTEM

60 27-Jun-17

12-Oct-17

196 17-Jun-15

31-Mar-16

EL YESO WATER CONVEYANCE


CONV
SYSTEM, SQUARE SECTION 2,8x2,8M (Km 0,000 to Km 0,367)

2015
2016
2017
2018
2019
Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr ay
13
14 15 16 17 18
19 20 21
22 23 24 25
26 27 28 29 30
31 32 33 34 35
36 37 38 39 40 41 42
43 44 45 46 47
48 49 50 51 52 53 54 55 56
57 58 59
60 61 62 63 64 65 66
OPEN-CUT EXCAVATION AND ROCK SUPPORT
INSTALLATIO N OF FALSE TUNNEL
CONCRETE AND OTHERS
INSTALLATIO N OF BULKHEAD

K DEPOSIT
CONSTRUCTION OF DRAIN DITCHES
FINISHING OF MUCK DEPOSIT PLACES WITH SCARP SOIL
SURFACE WATER CONTROL STAGE-1
SURFACE WATER CONTROL STAGE-2
SOIL AND ROCK EXCAVATION
CONCRETE AND OTHERS
STRUCTURAL AND COMPACTED FILL
INSTALLATIO N OF HYDRO-MECHANICAL EQUIPMENT
SOIL AND ROCK EXCAVATION
CONCRETE AND OTHERS
STRUCTURAL AND COMPACTED FILL
INSTALLATIO N OF STEEL STRUCTURES
INSTALLATIO N ELECTRIC WORKS, CCTV & COMMUNICATION SYSTEM

108

ACCNM6140CON01

SOIL AND ROCK EXCAVATION IN DITCH

52 17-Jun-15

24-Sep-15

109

ACCNM6140CON02

CONCRETE CULVERT 2,8M X 2,8M; T= 30 Cm

117 24-Sep-15

24-Feb-16

CONCRETE CULVERT 2,8M X 2,8M; T= 30 Cm

110

ACCNM6140CON03

STRUCTURAL AND COMPACTED FILL

117 29-Oct-15

31-Mar-16

STRUCTURAL AND COMPACTED FILL

440 24-Sep-15

19-May-17

111

EL YESO WATER CONV


CONVEYANCE SYSTEM, CIRCULAR SECTION D=3,1 m (Km 0,367 to Km 1,323)

112

ACCNM6140CON04

SOIL AND ROCK EXCAVATION IN DITCH

134 24-Sep-15

16-Mar-16

113

ACCNM6140CON05

CONCRETE CULVERT D=3.1M; T=30cm

282 24-Feb-16

24-Mar-17

114

ACCNM6140CON06

STRUCTURAL AND COMPACTED FILL

282 19-Apr-16

19-May-17

35 24-Mar-17

11-May-17

115

SPECIAL WORKS JUNC


JUNCTION EL YESO CONVEYANCE - EL YESO SIPHON

116

ACCNM6140CON07

SUPPLY AND ASSEMBLY OF STEEL PIPE FOR JUNCTION. ASTM A53 Gr.B, Diameter

14 24-Mar-17

11-Apr-17

117

ACCNM6140CON08

CONCRETE EMBEDMENT AND ANCHORING

21 12-Apr-17

11-May-17

697 05-Jan-15

28-Sep-17

118

EL YESO SIPHON

146 17-Mar-16

21-Oct-16

120

ACCNM6145CON01

SOIL AND ROCK EXCAVATION

121 17-Mar-16

20-Sep-16

121

ACCNM6145CON02

COMPACTED T=6 FILL

121 04-Apr-16

06-Oct-16

122

ACCNM6145CON03

INSTALLATIO N OF STEEL PIPE

121 12-Apr-16

13-Oct-16

123

ACCNM6145CON04

STRUCTURAL FILL, BUILDING AND COMPACTION OF EMBANKMENT

121 20-Apr-16

21-Oct-16

155 21-Oct-16

12-May-17

119

124

STRETCH-1 FROM JUNCTION


JU
TO SIPHON (0+00 to 1+300)

SIPHON RIO YESO (1+300


(1+
to 1+426)

125

ACCNM6145CON05

SURFACE WATER CONTROL

14 21-Oct-16

09-Nov-16

126

ACCNM6145CON06

SOIL AND ROCK EXCAVATION

14 09-Nov-16

28-Nov-16

127

ACCNM6145CON07

COMPACTED T=6 FILL

7 28-Nov-16

07-Dec-16

128

ACCNM6145CON08

INSTALLATIO N OF STEEL PIPE

17 07-Dec-16

29-Dec-16

129

ACCNM6145CON09

CONCRETE EMBEDMENT AND ANCHORING

45 29-Dec-16

24-Feb-17

130

ACCNM6145CON10

BUILDING AND COMPACTION OF EMBANKMENT

14 24-Feb-17

15-Mar-17

131

ACCNM6145CON11

REMOVAL OF DIVERSION WORKS

7 04-May-17

12-May-17

606 05-Jan-15

04-May-17

451 05-Jan-15

13-Oct-16

132

EL YESO TUNNEL (SO


(SOIL EXCAVATION) SECC. 13,5 m2 L= 1.021m

133

MUCK DEPOSIT N3

134

ACCNM6177CON01

CLEANING AND SCARPMENT OF MUCK DEPOSIT

14 05-Jan-15*

21-Jan-15

135

ACCNM6177CON02

CONSTRUCTION OF DRAIN DITCHES

14 06-Sep-16

26-Sep-16

136

ACCNM6177CON03

FINISHING OF MUCK DEPOSIT PLACES WITH SCARP SOIL

14 26-Sep-16

13-Oct-16

294 17-Mar-16

04-May-17

137

ACCESS PORTAL

138

ACCNM6150CON05

SOIL AND ROCK EXCAVATION

21 17-Mar-16

14-Apr-16

139

ACCNM6150CON06

INSTALLATIO N OF TEMPORARY FALSE TUNNEL

14 14-Apr-16

02-May-16

140

ACCNM6150CON07

CONCRETE AND OTHERS

30 24-Feb-17

04-Apr-17

141

ACCNM6150CON08

STRUCTURAL AND COMPACTED FILL

21 04-Apr-17

04-May-17

35 22-Jan-15

06-Mar-15

142

TAILRACE PORTAL

143

ACCNM6150CON09

SOIL AND ROCK EXCAVATION

21 22-Jan-15

17-Feb-15

144

ACCNM6150CON10

INSTALLATIO N OF TEMPORARY FALSE TUNNEL

14 18-Feb-15

06-Mar-15

641 18-Feb-15

30-Aug-17

31 18-Feb-15

28-Mar-15

7 01-Jun-17

09-Jun-17

145

STRETCH-2 FROM SOIL


SO TUNNEL TAILRACE PORTAL TO ACCESS ROAD (2+453 to 2+786)

146

ACCNM6145CON12

SOIL AND ROCK EXCAVATION

147

ACCNM6145CON13

COMPACTED T=6 FILL

148

ACCNM6145CON14

INSTALLATIO N OF STEEL PIPE

31 09-Jun-17

17-Aug-17

149

ACCNM6145CON15

STRUCTURAL FILL, BUILDING AND COMPACTION OF EMBANKMENT

31 13-Jun-17

22-Aug-17

150

ACCNM6145CON16

PLACING GRANULAR LAYER

7 22-Aug-17

30-Aug-17

STRETCH-3 FROM ACCESS


AC
ROAD TO BRIDGE MANZANITO (2+786 to 2+936)

83 15-May-17

28-Sep-17

151

SOIL AND ROCK EXCAVATION IN DITCH

SOIL AND ROCK EXCAVATION IN DITCH


CONCRETE CULVERT D=3.1M; T=30cm
STRUCTURAL AND COMPACTED FILL
SUPPLY AND ASSEMBLY OF STEEL PIPE FOR JUNCTION. ASTM A53 Gr.B, Diameter = 3.10m, e=10mm Lining
CONCRETE EMBEDMENT AND ANCHOR ING

SOIL AND ROCK EXCAVATION


COMPACTED T=6 FILL
INSTALLATIO N OF STEEL PIPE
STRUCTURAL FILL, BUILDING AND COMPACTION OF EMBANKMENT
SURFACE WATER CONTROL
SOIL AND ROCK EXCAVATION
COMPACTED T=6 FILL
INSTALLATIO N OF STEEL PIPE
CONCRETE EMBEDMENT AND ANCHORING
BUILDING AND COMPACTION OF EMBANKMENT
REMOVAL OF DIVERSION WORKS

CLEANING AND SCARPMENT OF MUCK DEPOSIT


CONSTRUCTION OF DRAIN DITCHES
FINISHING OF MUCK DEPOSIT PLACES WITH SCARP SOIL
SOIL AND ROCK EXCAVATION
INSTALLATIO N OF TEMPORARY FALSE TUNNEL
CONCRETE AND OTHERS
STRUCTURAL AND COMPACTED FILL
SOIL AND ROCK EXCAVATION
INSTALLATIO N OF TEMPORARY FALSE TUNNEL
SOIL AND ROCK EXCAVATION
COMPACTED T=6 FILL
INSTALLATIO N OF STEEL PIPE
STRUCTURAL FILL, BUILDING AND COMPACTION OF EMBANKMENT
PLACING GRANULAR LAYER

152

ACCNM6145CON17

SOIL AND ROCK EXCAVATION

14 15-May-17

31-May-17

153

ACCNM6145CON18

COMPACTED T=6 FILL

14 09-Jun-17

27-Jun-17

154

ACCNM6145CON19

INSTALLATIO N OF STEEL PIPE

14 18-Aug-17

05-Sep-17

155

ACCNM6145CON20

STRUCTURAL FILL, BUILDING AND COMPACTION OF EMBANKMENT

14 05-Sep-17

25-Sep-17

STRUCTURAL FILL, BUILDING AND COMPACTION OF EMBANKMENT

156

ACCNM6145CON21

PLACING GRANULAR LAYER

3 26-Sep-17

28-Sep-17

PLACING GRANULAR LAYER

75 12-Sep-15

19-Dec-15

157

CIVIL WORKS - YESO RIVER CROSSING

SOIL AND ROCK EXCAVATION


COMPACTED T=6 FILL
INSTALLATIO N OF STEEL PIPE

158

ACCNM6145CON22

BRIDGE - INFRASTRUCTURE AND CONCRETE DECK

45 12-Sep-15

10-Nov-15

BRIDGE - INFRASTRUCTURE AND CONCRETE DECK

159

ACCNM6145CON23

BRIDGE - SUPERSTRUCTURE AND FINISHING

30 11-Nov-15

19-Dec-15

BRIDGE - SUPERSTRUCTURE AND FINISHING

44 21-Dec-15

16-Feb-16

160

CIVIL WORKS - MANZANITO


MANZ
STREAM PIPE CROSSING

161

ACCNM6145CON24

INFRASTRUCTURE FOR PIPE CROSSING

30 21-Dec-15

29-Jan-16

162

ACCNM6145CON25

INSTALLATIO N OF STEEL PIPE

14 29-Jan-16

16-Feb-16

282 21-Dec-15

20-Jan-17

163

STRETCH-4 FROM BRIDGE


BR
MANZANITO TO PO RTAL VA4 (3+000 to 4+838)

INFRASTRUCTURE FOR PIPE CROSSING


INSTALLATIO N OF STEEL PIPE

164

ACCNM6145CON26

SOIL AND ROCK EXCAVATION

172 21-Dec-15

29-Aug-16

SOIL AND ROCK EXCAVATION

165

ACCNM6145CON27

COMPACTED T=6 FILL

172 26-Jan-16

04-Oct-16

COMPACTED T=6 FILL

Remaining Level of Effort

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Summary

Page 2 of 3

ALTO MAIPO SpA

PROJECT HYDROELECTRIC ALTO MAIPO


PROJECT SCHEDULE
#

Activity ID

Activity Name

Remaining Start
Duration

Finish

166

ACCNM6145CON28

INSTALLATIO N OF STEEL PIPE

172 17-Feb-16

25-Oct-16

167

ACCNM6145CON29

STRUCTURAL FILL, BUILDING AND COMPACTION OF EMBANKMENT

172 24-Feb-16

02-Nov-16

168

ACCNM6145CON30

PLACING GRANULAR LAYER

60 02-Nov-16

20-Jan-17

969 21-May-14

08-Mar-18

319 21-May-14

11-Sep-15

169
170

SISTEMA TUNNEL ALFALFAL


ALF
II
ACCESS ROAD From E
EL YESO TO PORTAL VA4

171

ACCNM6172CON01

PERMITS FOR ACCESS ROAD

172

SCOPE SEGMENT: ROAD


RO
ACCESS ADIT VA4 - EL YESO

0 18-Nov-14*
319 21-May-14

2015
2016
2017
2018
2019
Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr ay
13
14 15 16 17 18
19 20 21
22 23 24 25
26 27 28 29 30
31 32 33 34 35
36 37 38 39 40 41 42
43 44 45 46 47
48 49 50 51 52 53 54 55 56
57 58 59
60 61 62 63 64 65 66
INSTALLATIO N OF STEEL PIPE
STRUCTURAL FILL, BUILDING AND COMPACTION OF EMBANKMENT
PLACING GRANULAR LAYER

PERMITS FOR ACCESS ROAD


11-Sep-15

173

ACCNM6172CON02

CONSTRUCTION OF ACCESS ROAD FROM BRIDGE EL YESO TO BRIDGE MANZAN

30 21-May-14*

27-Jun-14

174

ACCNM6172CON03

TEMPORARY BRIDGE CROSSING

21 25-Nov-14*

22-Dec-14

175

ACCNM6172CON04

PHASE-1; ACCESS ROAD TO MD4 AND PORTAL VA4

28 23-Dec-14

29-Jan-15

176

ACCNM6172CON05

PHASE-2 EXCAVATION AND FILLING OF ACCESS ROAD

150 29-Jan-15

11-Sep-15

58 29-Jan-15

15-Apr-15

ESS ROAD FROM BRIDGE EL YESO TO BRIDGE MANZANITO


TEMPORARY BRIDGE CROSSING
PHASE-1; ACCESS ROAD TO MD4 AND PORTAL VA4
PHASE-2 EXCAVATION AND FILLING OF ACCESS ROAD

177

MUCK DEPOSIT N4

178

ACCNM6178CON01

CLEANING AND SCARPMENT OF MUCK DEPOSIT

14 29-Jan-15

16-Feb-15

CLEANING AND SCARPMENT OF MUCK DEPOSIT

179

ACCNM6178CON02

CONSTRUCTION OF COFFER DAM

30 17-Feb-15

26-Mar-15

CONSTRUCTION OF COFFER DAM

180

ACCNM6178CON03

DRAIN DITCHES

14 26-Mar-15

15-Apr-15

801 29-Jan-15

08-Mar-18

181

PORTAL TUNNEL ALFA


ALFALFAL II AND BULKHEAD

DRAIN DITCHES

182

ACCNM6205CON01

OPEN-CUT EXCAVATION AND ROCK SUPPORT

57 29-Jan-15

14-Apr-15

183

ACCNM6205CON02

CONCRETE OTHERS

57 27-Nov-17

08-Feb-18

OPEN-CUT EXCAVATION AND ROCK SUPPORT

184

ACCNM6205CON03

BULKHEAD INSTALLATION

22 09-Feb-18

08-Mar-18

BULKHEAD INSTALLATION

185

ACCNM6205CON04

STRUCTURE AND COMPACTED FILL

22 09-Feb-18

08-Mar-18

STRUCTURE AND COMPACTED FILL

186

TRANSMISSION LINE

120 11-Dec-13

17-May-14

CONCRETE OTHERS

187

ACCNM6181CON01

MEDIUM VOLTAGE LINE EL YESO TO VA4 ADIT C21750 and C23290

120 11-Dec-13

17-May-14

TO VA4 ADIT C21750 and C23290

188

ACCNM6181CON02

MEDIUM VOLTAGE LINE EL YESO TO EL YESO INTAKE C22100 and C22240

120 11-Dec-13

17-May-14

TO EL YESO INTAKE C22100 and C22240

842 08-Jan-15

18-May-18

842 08-Jan-15

18-May-18

977 10-Feb-15

18-May-18

189
190
191

UNDERGROUND WORKS
SISTEMA TUNNEL ALTO
ALT VOLCAN
TUNNEL IN SOIL (Sect. 14 m2; L =198 m )

192

ACCNM6155CON01

UNDERGROUND EXCAVATION AND ROCK SUPPORT

67 10-Feb-15

21-Apr-15

193

ACCNM6155CON02

CONCRETE LINING 200m SOIL TUNNEL +100m ROCK TUNNEL

90 17-Feb-18

18-May-18

820 21-Apr-15

17-Feb-18

194

SCOPE SEGMENT: D&B TUNNEL FROM V1 TOWARDS V5

195

ACCNM6155CON03

UNDERGROUND EXCAVATION OF TUNNEL FROM PV1 to PV5, Cross Section: A = 17

765 21-Apr-15

23-Dec-17

196

ACCNM6155CON04

CONCRETE PAVEMENT, THICKNESS Min.120mm. REINFORCEMENT MESH Min.6.5 K

55 23-Dec-17

17-Feb-18

73 08-Jan-15

22-Mar-15

197

SCOPE SEGMENT: D&B TUNNEL V5 (TBM LAUNCHING TUBE)

198

ACCNM6160CON01

DRILL AND BLAST TUNNEL EXCAVATION, Cross Sections: A=21.35 M2 (Length = 130m

45 08-Jan-15

22-Feb-15

199

ACCNM6160CON02

CONCRETE WORKS (STARTBLOCK FOR TBM)

14 22-Feb-15*

08-Mar-15

200

ACCNM6160CON03

CONCRETE PAVEMENT, THICKNESS Min.120mm. REINFORCEMENT MESH Min.6.5 K

14 08-Mar-15

22-Mar-15

776 29-Jan-15

09-Jun-17

201

SCOPE SEGMENT: TBM EXCAVATION OF TUNNEL FROM V5

06-Jun-16

45 06-Jun-16

21-Aug-16

201 21-Aug-16

16-Mar-17

UNDERGROUND EXCAVATION OF TUNNEL FROM PV1 to PV5, Cross Section: A = 17M2


CONCRETE PAVEMENT, THICKNESS Min.120mm. REINFORCEMENT MESH Min.6
DRILL AND BLAST TU NNEL EXCAVATION, Cross Sections: A=21.35 M2 (Length = 130m)
CONCRETE WORKS (STARTBLOCK FOR TBM)
CONCRETE PAVEMENT, THICKNESS Min.120mm. REINFORCEMENT MESH Min.6.5 Kg/M2 D8@ 30c/c

ACCNM6160CON04

MOBILIZATION, TRANSPORT, ASSEMBLY, START OF TBM 4.10m DIAMETER, INCLUD

203

ACCNM6160CON05

EXCAVATION OF TUNNEL WITH TBM, NET DIAMET ER D=4,1M. LENGT H=7000m

204

ACCNM6160CON06

TBM DISMANTLING (TBM 4.10M , BACKUP)

205

ACCNM6160CON07

UNDERGROUND. EXCAVATION OF TUNNEL, CR.SEC.: A= 17 M2 (FROM 7000m TO 8

206

ACCNM6160CON08

CONCRETE WORKS FOR BULKHEAD

60 16-Mar-17*

19-May-17

CONCRETE WORKS FOR BULKHEAD

207

ACCNM6160CON09

INSTALLATIO N OF BULKHEAD

21 19-May-17

09-Jun-17

INSTALLATIO N OF BULKHEAD

892 07-Mar-15

14-May-17

SISTEMA TUNNEL SOIL


SO (L=1.021m)

30-Mar-15

CONCRETE LINING 200m SOIL TUNNEL +100m ROCK TUNNEL

202

208

60 29-Jan-15
389 30-Mar-15

UNDERGROUND EXCAVATION AND ROCK SUPPORT

MOBILIZATION, TRANSPORT, ASSEMBLY, START OF TBM 4.10m DIAMETER, INCLUDING BACK-UP SYSTEM, CONVEYOR SYSTEM AND VENT
EXCAVATION OF TUNNEL WITH TBM, NET DIAMET ER D=4,1M. LENGT H=7000m
TBM DISMANTLING (TBM 4.10M , BACKUP)
UNDERGROUND. EXCAVATION OF TUNNEL, CR.SEC.: A= 17 M2 (FROM 7000m TO 8500m)

209

ACCNM6150CON11

EL YESO TUNNEL (SOIL EXCAVATION) SECC. 13,5 m2 L= 1.021m

592 07-Mar-15

06-Sep-16

210

ACCNM6150CON12

INSTALLATIO N OF STEEL PIPE

261 06-Sep-16

09-Apr-17

INSTALLATIO N OF STEEL PIPE

211

ACCNM6150CON13

CONCRETE EMBEDMENT

261 13-Sep-16

19-Apr-17

CONCRETE EMBEDMENT

212

ACCNM6150CON14

GROUTING AROUND THE CONCRETE LINING

120 03-Feb-17

14-May-17

840 14-Apr-15

26-Nov-17

213

SISTEMA TUNNEL ALFALFAL


ALF
II

214

ACCNM6210CON01

UNDERGROUND EXCAVATION AND ROCK SUPPORT, CR. SEC.= 26,3 M2 (LENGTH

67 14-Apr-15

21-Jun-15

215

ACCNM6210CON02

UNDERGROUND EXCAVATION AND ROCK SUPPORT, CR. SEC.= 26,3 M2 (LENGTH

487 21-Jun-15

06-Jan-17

216

ACCNM6210CON03

CONCRETE PAVEMENT, THICKNESS 120 MM. RFT. MESH Min 6,5 Kg/M2

31 06-Jan-17

06-Feb-17

217

ACCNM6210CON04

CONCRETE WORKS - STARTBLOCK FOR TBM

21 06-Jan-17*

27-Jan-17

218

ACCNM6210CON05

TBM ERECTION

219

ACCNM6210CON06

EXCAVATION OF TUNNEL WITH TBM, Net Dia. D=4,1M. (LENGTH = 3000M)

220

ACCNM6210CON07

TBM DISMANTLING (TBM 4.10M , BACKUP)

221

MILESTONE COMPLETION
COM

45 06-Feb-17

23-Mar-17

150 23-Mar-17

26-Sep-17

60 26-Sep-17

26-Nov-17

90 08-Mar-18

06-Jun-18

222

MSCNM6100-02

COMPLETION OF CRITICAL MILESTONE-A

06-Jun-18*

223

MSCNM6100-03

COMPLETION OF CRITICAL MILESTONE-B

08-Mar-18*

Remaining Level of Effort

Actual Work

Remaining Work

Critical Remaining Work

EL YESO TUNNEL (SOIL EXCAVATION) SECC. 13,5 m2 L= 1.021m

GROUTING AROUND THE CONCRETE LINING


UNDERGROUND EXCAVATION AND ROCK SUPPORT, C R. SEC .= 26,3 M2 (LEN GTH = 200M)
UNDERGROUND EXCAVATION AND ROCK SUPPORT, C R. SEC .= 26,3 M2 (LEN GTH = 3050M)
CONCRETE PAVEMENT, THICKNESS 120 MM. RFT. MESH Min 6,5 Kg/M2
CONCRETE WORKS - STARTBLOCK FOR TBM
TBM ERECTION
EXCAVATION OF TUNNEL WITH TBM, Net Dia. D=4,1M. (LENGTH = 3000M)
TBM DISMANTLING (TBM 4.10M , BACKUP)

COMPLETION OF CRITICAL MILESTONE-A


COMPLETION OF CRITICAL MILESTONE-B

Milestone

Summary

Page 3 of 3

You might also like