Queuing Ex Solutions

The document describes three queueing systems and provides calculations to determine various performance measures for each system. The first system involves a machine repair crew with an average of 3 repairs per day. The crew can service 8 machines per day on average. The utilization rate is calculated to be 0.375 and the average downtime for a machine is 0.2 days. The second system is a car wash with an average arrival rate of 10 cars per hour and a service rate of 12 cars per hour. The average number of cars waiting is 4.167 and the utilization rate is 0.8333. The third system involves a movie theater ticket booth with an average arrival rate of 210 patrons per hour and a service

Uploaded by

Hồng Diễm
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
92% found this document useful (13 votes)
3K views

Queuing Ex Solutions

The document describes three queueing systems and provides calculations to determine various performance measures for each system. The first system involves a machine repair crew with an average of 3 repairs per day. The crew can service 8 machines per day on average. The utilization rate is calculated to be 0.375 and the average downtime for a machine is 0.2 days. The second system is a car wash with an average arrival rate of 10 cars per hour and a service rate of 12 cars per hour. The average number of cars waiting is 4.167 and the utilization rate is 0.8333. The third system involves a movie theater ticket booth with an average arrival rate of 210 patrons per hour and a service

Uploaded by

Hồng Diễm
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
You are on page 1/ 3

SOLUTIONS

1.TheRockwellElectronicsCorporationretainsaservicecrewtorepairmachinebreakdowns
thatoccuronanaverageof=3perday(approximatelyPoissoninnature).
Thecrewcanserviceanaverageof=8machinesperday,witharepairtimedistributionthat
resemblestheexponentialdistribution.
(a)Whatistheutilizationrateofthisservicesystem?
(b)Whatistheaveragedowntimeforamachinethatisbroken?
(c)Howmanymachinesarewaitingtobeservicedatanygiventime?
(d)Whatistheprobabilitythatmorethanonemachineisinthesystem?Probabilitythatmore
thantwoarebrokenandwaitingtoberepairedorbeingserviced?Morethanthree?Morethan
four?
a. The utilization rate, ,

= 0.375
b. The average down time, W,
W

1
1 = 0.2 day

83

c. The number of machines waiting to be served, Lq, is, on average,


Lq

2
32 = 0.225 machine waiting

8 8 3

d. Probability that more than one machine is in the system


Pn k

k 1

9
3
Pn 1
0.141
64
8

Probability that more than two machines are in the system:


3

Pn 2

27
3

0.053
512
8
4

81
3
Pn 3
0.020
4, 096
8
5

Pn 4

243
3

0.007
32, 768
8

2.Fromhistoricaldata,HarrysCarWashestimatesthatdirtycarsarriveattherateof10per
houralldaySaturday.Withacrewworkingthewashline,Harryfiguresthatcarscanbecleaned
attherateofoneevery5minutes.Onecaratatimeiscleanedinthisexampleofasingle
channelwaitingline.
AssumingPoissonarrivalsandexponentialservicetimes,findthe
(a)averagenumberofcarsinline.
(b)averagetimeacarwaitsbeforeitiswashed.
(c)averagetimeacarspendsintheservicesystem.
(d)utilizationrateofthecarwash.
(e)probabilitythatnocarsareinthesystem.

= 10 cars/hour, = 12 cars/hour.
a. The average number of cars in line, Lq,

2
102
102

= 4.167 cars
12 12 10 12 2

Lq

b. The average time a car waits before it is washed, Wq, is given by


Wq

10
10

= 0.4167 hour
12 12 10 12 2

c. The average time a car spends in the service system, W, is given by


W

1
1
1

hour
12 10 2

d. The utilization rate, , is given by

10

0.8333
12

e. The probability that no cars are in the system, P0, is given by:
P0 1

1 1 0.8333 0.1667

3.MikeDreskinmanagesalargeLosAngelesmovietheatercomplexcalledCinemaI,II,III,
andIV.Eachofthefourauditoriumsplaysadifferentfilm;thescheduleissetsothatstarting
timesarestaggeredtoavoidthelargecrowdsthatwouldoccurifallfourmoviesstartedatthe
sametime.Thetheaterhasasingleticketboothandacashierwhocanmaintainanaverage
servicerateof280moviepatronsperhour.
Servicetimesareassumedtofollowanexponentialdistribution.Arrivalsonatypicallyactive
dayarePoissondistributedandaverage210perhour.Todeterminetheefficiencyofthecurrent
ticketoperation,Mikewishestoexamineseveralqueueoperatingcharacteristics.
(a)Findtheaveragenumberofmoviegoerswaitinginlinetopurchaseaticket.
(b)Whatpercentageofthetimeisthecashierbusy?

(c)Whatistheaveragetimethatacustomerspendsinthesystem?
(d)Whatistheaveragetimespentwaitinginlinetogettotheticketwindow?
(e)Whatistheprobabilitythattherearemorethantwopeopleinthesystem?Morethanthree
people?Morethanfour?

= 210 patrons/hour, = 280 patrons/hour.


a. The average number of patrons waiting in line, Lq, is given by
Lq

2
2102
44,100 44,100

2.25 patrons in line


=
280 280 210 280 70 19, 600

b. The average fraction of time the cashier is busy, , is given by

210

0.75
280

c. The average time a customer spends in the ticket-dispensing system, W, is given by


1
1
1

= 0.0143 hour in the line


280 210 70

d. The average time spent by a patron waiting to get a ticket, Wq, is given by
Wq

210
210

= 38.6 seconds
280 280 210 280 70

e. The probability that there are more than two people in the system, Pn>2, is given by
Pn k

k 1

Pn 2

210

0.422
280

The probability that there are more than three people in the system, Pn > 3, is given by
4

210
0.316
280

Pn 3

The probability that there are more than four people in the system, Pn > 4, is given by
5

Pn 4

210

0.237
280