3 Days 4 Days 3 Days 4 Days 5 Days 5 Days 2 Days 5 Days 5 Days 2 Days 2 Days 2 Days 2 Days 1 Day
3 Days 4 Days 3 Days 4 Days 5 Days 5 Days 2 Days 5 Days 5 Days 2 Days 2 Days 2 Days 2 Days 1 Day
Task Name
1
2
3
4
5
6
7
8
9
10
11
12
13
14
Duration
Oct 25, '15 Nov 1, '15 Nov 8, '15 Nov 15, '15 Nov 22, '15 Nov 29, '15 Dec 6, '15 Dec 13, '15 Dec 20, '15 Dec 27, '15
T S M W F S T T S M W F S T T S M W F S T T S M W F S T T S M W F
11/1
3 days
Project: Project1
Date: December 12, 2015
12/31
Task
External Milestone
Split
Inactive Task
Manual Summary
Milestone
Inactive Milestone
Start-only
Summary
Inactive Summary
Finish-only
Project Summary
Manual Task
Deadline
External Tasks
Duration-only
Progress
Page 1