Man Hour Estimate - Chlorinator - MH Asset - 03
Man Hour Estimate - Chlorinator - MH Asset - 03
Description
Man Hours
Man Hours
Man Hours
Part 2.1
Pretendering
Stage Activities
407
385
308
1100
Part 2.2
Bid Evaluation
Stage Activities
49
46
37
132
Part 2.3
Project
Implementation
Stage Activities
358
339
271
968
TOTAL
814
770
616
2200
UnitManHourRate
(InRupees)
1853.94
1556.19
955.06
Total
(InRupees)
15,09,107.16
11,98,266.30
5,88,316.96
ManHourEstimateChlorinator_MHAsset_03
32,95,690.42
Page1of2