Concrete structures cost is determined by formwork area, reinforcing steel weight, concrete volume, and finishing/curing area. Formwork costs depend on material type and quality, structure complexity, reuse potential, and labor for installation and removal. Reinforcing steel cost is based on bar size, shape complexity, installation labor and skills. Concrete cost considers materials (sand, aggregate, cement, water), mixing, transporting, placement labor and equipment depending on job size, location and concrete specifications.
Concrete structures cost is determined by formwork area, reinforcing steel weight, concrete volume, and finishing/curing area. Formwork costs depend on material type and quality, structure complexity, reuse potential, and labor for installation and removal. Reinforcing steel cost is based on bar size, shape complexity, installation labor and skills. Concrete cost considers materials (sand, aggregate, cement, water), mixing, transporting, placement labor and equipment depending on job size, location and concrete specifications.
Formwork- SFCA -square feet on concrete area. + Reinforced Steel pounds of weight + Concrete cubic yards of volume + Finishing & Curing are measured in square feet.
10.1 FORMS Wall height -ft; Plywood -sf; Lumber bf, Form -tiles; Labor hours making forms -carpenter, helper-; Labor hours erecting and removing the forms carpenter, helper-
CHAPTER 10 CONCRETE STRUCTURES
Con crete Structures
Concrete is a malleable material which can be used to
produce almost any shape, implying variation in cost. Cost of forms for complicated shapes implies extra material -lumber, plywood, steel, aluminium and composite materials bolts, nails10.2 COLUMN FORMS and labor -installing, removing and cleaning- better to spend Hight -ft; Plywood sf; Lumber money in quality materials than in cost required to build them, bf,;Labor-hours making forms while a reusable form will produce a lower total cost of the carpenter, helper-; Labour hours structure. erecting and removing the forms Size of forms, type of material [extend of prefabricate carpenter, helperpanels 3/4, 7/8 x 4 x 8, 10, 12, Polyform (HDO 100 uses) 10.3 CONCRETE BEAMS can be reused more times than plywood- Lumber in Beam width -in; Number of uses; dimensions of 2ft (8ft-18ft), Nails (10-20lb/1000bf, 5-10lb/ Plywood -sf; Lumber -bf; Form -tiles; 1000bf), form oil (300-500 sf/gal), Form Tiles (units safe loads Labor hours -carpenter, helper3,000-5,000 lb), Form Liners (PVC 4 x10)], shape of structure, location of the forms, rigidity of dimension requirements, and 10.4 FLAT SLAB CONCRETE the extend of the forms that can be prefabricated and FLOOR transported to the site are the factors that determine the Ceiling hight -ft; Thickness of slab in,;Plywood -sf; Lumber -bf; Labour amount of labor. Reusable forms must estimate hours -carpenter helperseparately the assemble, remove and cleaning. [tables specify the labor-hour, verify union regulation ratio if apply] Forms 10.5 METAL-PLAN for slab on grade placed directly on the ground, side form CONCRETE FLOOR of metal or constructed of 2in, lumber commonly used, Ceiling hight -ft; Floor thickness -in; secured with wood stakes or metal pins, wired mesh or Lumber -bf; Labour hours -carpenter reinforced steel is placed then concrete -finished and cured-. helperFooting and foundation walls include beam footing, 10.8 REINFORCED STEEL basement walls, retaining walls, vertical walls for water BARS reservoirs, etc. Wall forms -plywood, lumber, form ties and Type of work (beams and girders, labour hours- for multiples of 2 other measures or openings columns, elevated slabs, footings Slab will be a wastage of material. Prefabricated Panels 2 wide on grade, Spirals and stirrups, walls) x 2, 4, 6, 8 long-2x4x3/4 lumber for frames will permit Bar size -5/8 and less, 3/4 and over. flexibility, permit ties and eliminate the need of holes. 10.9 WELDED-WIRE FABRIC Commercial Prefabricated forms -Polyform sheathing Stile -no, Weight -lb per sf, Spacinf of wire- attached to steel or aluminium frames can be purchased or in longitudinal, in transverse, Gauge rented-. Forms for concrete columns -forms for round number -longitudinal, in transverse, columns are made of fibre tube, fibreglass or steel, clamps are Sectional area of wires -in longitudinal, in installed around the forms prior to filling. Clamps are installed transverse to ensure the form resist the maximum internal pressure. The 10.10 CEMENT QUANTITIES four sides of columns forms are usually prefabricated; Sacs of cement, Water -gal, Weights of assembled and fastened with clamps, securely located, saturated surface-dry aggregate -lb fine , reinforcement is placed and concrete is poured. Labor is lb coarse, 28 day compressive strength psi calculated in two operations making the forms and then erecting and removing them. By using in you design the same 10.11 PLACING CONCRETE columns type on you design, considerable saving can be HR/CY achieved. Columns heads , capitals and drop panels are Type of work (continuous footing, a common practice to provide more distribution of the load spread footing, grade beams, slabs on between the column and the slab; and it generally increases the grade, walls, beams and girders, cost of the formwork. columns elevated slabs) , Method of Shores and care folding -lumber, aluminium, are handling - direct chute, Crane bucket, Pumpedinstalled single member and tied horizontal and diagonal with braces- are used to support beams , girders, floor slabs, roof slabs bridge decks and other members to ensure the concrete has gained sufficient strength to be self-supported. Several methods are used to construct the Concrete Beams forms, lumbers -vertical direction provide more resistant to deflection-should be cleated together -3 intervals-,ledgers attached to vertical blocking carry the joist load to the shoring. Kickers at the bottom -to resist lateral TWA NY 1962 pressure from the concrete. Forms for flat-slab concrete
Mumbai Airport Terminal 2, 2014
floors as beams can be supported by the column heads,
Patented forms for floor slabs, material and labor hours corrugated steel forms -metal or fibreglass patented forms are available for two way floor system, pans & domes reduce the cost of material and labor cost-. Metal-pan concrete floor requires lumber, connecting strips, stringers, shores and bracers, vertical shores or scaffolding. Corrugate steel forms -available in several gauges widths and lengths- for floor and roof slabs supported by steel beams and precast concrete joists. Cellular-steel floor system -have multiple cells that can be used for telephone power and computer cables available in 24 & 36- roll steel shape panels and plates are electrically welded together to provide routing for wire through the floor slab in to the room area. Concrete stairs cost per unit of volume or area varies greatly, depending on the length and width of the tread -squared or rounded- & height of the riser -open or closed with curbs- steel dowels should be set in the concrete floor and beam supporting the landing prior placing the concrete, dowels are died to the reinforcing steel. Labor is difficult to calculate carpenter & helper should install about 25 br/ht of lumber.
Reinforced steel is a deformed bars or
welded wire fabric used separately or together cost is estimated by lb or sf, shop drawings are necessary -cut length, bending details, price of steel, charge depends on the complexity and quantity- for the fabrication, the estimator must submit drawings to the supplier. Labor cost depends on size, shape, complexity, distance and height, bars spacing, extent of tying & workers skills. Time is depends on the amount tons and bars types. Welded-wire fabric is used for concrete sidewalks, pavements floors, canal lining because its lower cost compared to reinforcing steel bars. Labor is calculated by the area, cuts, lapping the edges and ends, labor rate is .25hr to .50 hr/100sf. Concrete Cost is determined by the materials: sand, aggregate, cement, water, admixture, mixing transporting and placing the concrete. ready mix will vary with the job size, location and concrete quality. Price is estimated by cubic yards and a waste of 10% for small jobs and 5% for larger jobs must be calculated, considering also the 28 days. Crew task is to place, spread, vibrate and finish the surface, equipment -gas or power-, location - below, on or above ground, drilling, pumping, belts, trucks, trailers, skids- , type of structure. Also light weight concrete and tilt up is available for floors, roof or decks to lower cost.
A Practical Workshop Companion for Tin, Sheet Iron, and Copper Plate Workers: Containing Rules for Describing Various Kinds of Patterns used by Tin, Sheet Iron, and Copper Plate Workers, Practical Geometry, Mensuration of Surfaces and Solids, Tables of the Weights of Metals, Lead Pipe, Tables of Areas and Circumferences
Sexton's Pocket-Book for Boiler-Makers and Steam Users: Comprising a Variety of Useful Information for Employer and Workmen, Government Inspectors, Board of Trade Surveyors, Engineers in Charge of Works and Ships, Foreman of Manufactories, and the General Steam-Using Public