PRINCE2 Slide Notes
PRINCE2 Slide Notes
Introduction to PRINCE2
PRINCE2 is a structured project management method based on the experience of scores
of project managers, who have contributed, some from their mistakes or omissions,
others from their success.
PRINCE2 has a process-based approach to project management. The processes define the
management activities to be carried out during the project. In addition, PRINCE2
describes a number of components that are applied within the appropriate activities.
The Processes
The PRINCE2 process model consists of eight distinctive management processes
covering the activities from setting the project off on the right track, through controlling
and managing the projects progress, to the completion of the project. The common
Planning (PL) process is used by four of the other processes.
Any project run under PRINCE2 will need to address each of these processes in some
form. However, the key to successful use of the process model, is in tailoring it to the
needs of the individual project. Each process should be approached with the question:
How extensively should this process be applied to this project?
The eight processes are:
Planning (PL)
www.executive-development.co.uk
The Components
The eight components that are applied as appropriate to each of the processes are:
The Business Case. The existence of a viable Business Case is the main
control condition of a PRINCE2 project. The Business Case is verified by the
Project Board before a project begins and at every major decision point
throughout the project. The project should be stopped if the viability of the
Business Case disappears for any reason.
Plans. PRINCE2 offers a series of plan levels that can be tailored to the size
and needs of a project and an approach to planning based on products rather
than activities.
www.executive-development.co.uk
Change Control. PRINCE2 emphasises the need for change control, and this
is enforced with a change control technique plus identification of the
processes that capture, analysis and progress the change control.
www.executive-development.co.uk
The Processes
Starting up a Project (SU)
Fundamental Principles
There must be a basic business requirement that triggers the project. Indeed,
before any work is commenced or resources committed, there is a requirement to
be able to answer the basic question: Do we have a viable and worthwhile
project? This question must be answered honestly to ensure that resources are
not committed and wasted
Nothing can be done in the project until responsibilities are defined and key roles
have been filled. Someone has to kick-start the project into being and make the
first decisions
An initiation Stage Plan must be submitted for approval before the imitation stage
can be entered
This is the first process within PRINCE2. The project begins once this process has been
conducted and the Project Board has approved commencement of project initiation.
Projects can be identified in a variety of ways and thus have a wide variation in the
management information available to the project management team at the time of startup. The trigger for the project is the Project Mandate. This is normally provided by
corporate or programme management. It is accepted that the Project Mandate may be
anything from a verbal request to a full Project Brief.
Process Description
The work of the process is built around the production of seven elements:
Ensuring that the information required for the Project Brief is available
www.executive-development.co.uk
The objective of the process is to enable a controlled start to the project by ensuring that:
All the necessary project management authorities exist for undertaking the project
Individuals are appointed who will undertake the work required in project
initiation and/or will take significant project management roles in the project
The organisation that will host the project team is informed of the existence and
implications of the new project.
www.executive-development.co.uk
All parties must be clear on what the project is intended to achieve, why it is
needed, how the outcome is to be achieved and what their responsibilities are, so
that there can be genuine commitment to the project.
Following these principles will ensure that the project can be successfully scoped and
managed to its completion.
Process Description
The purpose of Initiating a Project is to draw up a contract in the form of a Project
Initiation Document between the Project Board and the Project Manager, so that there is a
common understanding of:
www.executive-development.co.uk
The next commitment that the Project Manger needs (the next stage plan)
This information can be agreed as informally as the Project Board and the Project
Manger wish. The Project Manager should always document the understanding,
however small the project, and get it signed by the project board, even if this is one
person. Peoples recollection of a verbal agreement can differ weeks, or even days
later.
In formal terms, the objectives of Initiating a Project are to:
Document and confirm that an acceptable Business Case exists for the project
Enable and encourage the Project Board to take ownership of the project
Provide the benchmark for the decision-making processes required during the
projects life
www.executive-development.co.uk
will typically delegate the day-to-day charge of the project to a Project Manager.
However, the Executive must exercise overall control and be responsible for the key
decisions. It is also important that levels of authority and decision-making processes are
clearly identified.
Process Description
The objectives of Directing a Project (DP) are to:
Ensure the effective management of all people and resources concerned with the
project
Ensure that the project and the products remain consistent with business plans and
the external environment
www.executive-development.co.uk
This process covers the direction of the project throughout its life cycle. The project
board pro-actively manages the projects response to the external environment. Within
the project, the Project Board should manage by exception. The Project Board
members are normally busy executives with a range of responsibilities; demands on their
time should be kept to a minimum while fulfilling their responsibilities to the project.
The key responsibilities are:
Resource commitment.
The key processes for the Project Board are predominately event driven and focus the
Project Board members on a small number of key decision points, plus informal
discussions where required. These key processes break into four main areas:
Project closure (confirming the project outcome and bringing the project to a
controlled close, or premature closure of the project should the Business Case no
longer be valid).
www.executive-development.co.uk
Focus the resources used during the stage towards this end
Carefully monitor any movement away from the direction and products agreed at
the start of the stage to avoid scope-creep and loss of focus.
Process Description
The objectives of Controlling a Stage are to:
www.executive-development.co.uk
10
Update plans with actuals, enabling progress to be checked against the plan
Ensure that projects are stopped or redirected if the reasons for setting them up
have been invalidated by internal or external events.
Central to the ultimate success of the project is the day-to-day control of the work that is
being conducted. Throughout a stage, this will consist of a cycle of:
Reporting (CS6)
If changes are observed that are forecast to cause deviations beyond agreed Stage and/or
project tolerances, Capturing Project Issues (CS3), Examining Project Issues (CS4),
Reviewing Stage Status (CS5) and Escalating Project Issues (CS8) cover the activities of
bringing the situation to the attention of the Project Board.
Other factors that must be borne in mind are as follows:
The current stage contains work and involves resource expenditure that has been
authorised by the Project Board. It is therefore important to give the Project Board
feedback on progress against its expectations.
If the project is to be successful, the Project Manager and Project Board must
react quickly to changes and deviations from the agreed Stage Plan.
www.executive-development.co.uk
11
Get it done
This agreement to do a defined amount of work is parcelled into Work Packages. Where
external suppliers are involved, the acceptance of Work Packages will be affected by the
terms of their contract.
The Team Manager ensures that planned products are created and delivered by the team
to the project by:
Ensuring that work links to any interfaces identified in the Work Package
Ensuring that work progress, quality inspections and forecasts are regularly
assessed
www.executive-development.co.uk
12
Assure the Project Board that all products in the current Stage Plan have been
completed as defined
Provide the information needed for the Project Board to assess the continuing
viability of the project
Obtain authorisation for the start of the next stage, together with its delegated
tolerance margins
Record any information or lessons that can help later stages of this project and/or
other projects.
There could be changes of personnel and management, needing changes to the project
management team.
There is also the requirement to review the Project Quality Plan and Project Approach to
check whether they need changing or refining.
The stage that follows initiation is normally approved at the same time as the Project
Initiation Document. If so, this process would need customising for that situation.
www.executive-development.co.uk
13
Is always more successful than the natural tendency to drift into use and
subsequent modification of the product. It is recognition by all concerned that:
o The original objectives had not been met
o The current project has run its course
o Either the operational regime must now take over the products from this
project, or that they should become inputs into some subsequent project or
into some larger programme.
Provides an opportunity to ensure that all unachieved goals and objectives are
identified so that they can be addressed in the future.
Process Description
The approach to Closing a Project (CP) has to be tailored to suit the needs of the
particular project. For example, if the project is part of a programme or a series of
projects, this may affect how some of the fundamental principles, such as how follow-on
actions are handled. The project may be closely connected with a subsequent project and
may have been planned ahead that way. All the results of the first project feed into the
subsequent one, in which case there may be no need to be concerned about maintenance
or subsequent operational arrangements, or other follow-on actions. As another example,
if the project had delivered an intangible product for example to bring about a change in
philosophy then the objective of ensuring that operational and support arrangements are
in place may not be appropriate.
The following is an illustrative list of the aims of the Closing a Project (CP) process.
Depending on the type of project, they may not all be required:
Ensure that the objectives or aims set out in the Project Initiation Document have
been met
Ensure that all expected products have been handed over and accepted by the
customer or relevant subsequent project
www.executive-development.co.uk
14
Ensure that the acceptance criteria have all been met and get the customers
confirmation of this
Ensure that arrangements for the support and operation of the projects products
are in place (where appropriate)
If the project has been closed prematurely, document what has been achieved and
recommend the way forward
Prepare notification to the host location of the intention to disband the project
organisation and resources
This process covers the Project Managers work to close the project either at its end or at
premature close. Most of the work is to prepare input into the Project Board to obtain its
confirmation that the project may close. If the project is being brought to a premature
close, this process will have to be tailored to the actual project situation. It will be a case
of what can be saved for use by another project or what remedial work is now required to
fill any gaps left by the cancellation of this project.
The Project Initiation Document is examined to check the actual results of the project
against the original expectations of (or as modified by the Project Board). All planned
products should have been approved and delivered to the customer or be ready for
handover. There must be documented confirmation from the customer that all Acceptance
Criteria, defined at the outset of the project, have been met.
The Project Manager prepares an End Report that comprehensively evaluates the actual
project results versus that envisaged in the Project Initiation Document.
There may be a number of Project Issues that were put in suspension by the Project
Board. These may lead to new projects or enhancements to the products of the current
project during its operational life. The project Manager sorts these out into appropriate
Follow-on Action Recommendations.
www.executive-development.co.uk
15
www.executive-development.co.uk
16
Planning (PL)
Fundamental Principles
Effective project management relies on an effective planning and control process. Even
small projects require planning.
Planning provides all personnel involved in the project with information on:
What is required
How it will be achieved and by whom, using what specialist equipment and
resources
The Planning (PL) process is where the technique of product-based planning is used, this
being one of the key techniques used by PRINCE2. A brief description of this technique
follows.
Product-based Planning
Four products are created within the product-based planning technique:
Understand the detailed nature, purpose and function of the final product
www.executive-development.co.uk
17
Enable identification of activities to develop and quality control the final product
Define the people or skills required to develop and check the final product.
Identify additional products needed to build and support the final products
Build a consensus on the best product groupings that should be used to generate
ideas on what products have to be created or obtained.
www.executive-development.co.uk
18
Plans are constructed by identifying the products required, and then the activities
and appropriate resources necessary to deliver them
There should be assurance that all activities are thought through in advance and to
a level consistent with the control requirements identified in the Project Initiation
Document.
The product-base planning technique provides a start to the planning activity and a
planning framework. It involves:
Determining the sequence in which each of the products should be produced and
any dependencies.
www.executive-development.co.uk
19
Producing the budget form the cost of effort plus any materials and equipment
that must be obtained
The steps involved are the same for all levels of plan.
www.executive-development.co.uk
20
www.executive-development.co.uk
21
www.executive-development.co.uk
22