Check List Piping Layout
Check List Piping Layout
Job No.:
Client:
Date :
DD/MM/YYYY
Drawing Title : PIPING GENERAL ARRANGEMENT DRAWING
Notes:
1. This checklist is intended for checking of layout drawings.
2. As a minimum, the checklist shall be completed for the first issue of the layout drawing.
Drawing No. :
3. Items like Fire and Gas detectors and other E, I & T items (e.g. JBs, switch boards,
lighting fittings, etc.) need not be shown in Piping Layouts.
Sr. No
Check Points
Y/N
Remarks
DESIGN
1
Plant North is shown.
Grade and paving levels and paving extents are shown.
2
(Dimensions of paving not required.)
3
Equipment and instrument tag nos. are indicated as per P&ID.
All equipments are shown with locating coordinates/dimensions
4
and elevations (centerline, BTL, u/s of base plate, etc.).
All equipment nozzles and vendor package terminal points are
5
clearly identified and tagged.
All tie-in points and battery limits are clearly identified and
6
tagged and coordinates/elevations are indicated.
All lines are identified by line numbers and major locating
7
dimensions & elevation are given.
Flow directions and slope symbols are indicated as per the
8
P&IDs.
All secondary pipe supports (standard & special) are indicated
9
and tagged and the locating dimensions marked.
All primary pipe supports are identified by appropriate symbols
10
(e.g. guide, axial stop, etc.).
Laydown/dropdown areas, space for exchanger tube removal and
11
maintenance access areas are identified.
All buildings/shelters/technological structures are located with
12
coordinates/dimensions. Names/tag nos and overall dimensions
are given.
Structural grid numbers of pipe racks, buildings and shelters are
13
shown.
Piperacks and sleepers are shown with locating
14
coordinates/dimensions, widths, TOS elevations and tag numbers
(if applicable).
The cross sections of piperacks, multi-level technological
15
structures, culverts, etc., are shown wherever required.
All platforms and ladders/staircases are located with dimensions
16
and elevations are marked.
DRAFTING
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
Name:
Designation:
Revision number:
Date: