HVAC VRF Installation Method Statement
HVAC VRF Installation Method Statement
utilized to minimize joints on site. Furthermore all of the following points should be
adhered to.
2.1 All copper pipes up to 1 1/8 (28 mm) outside diameter (O/D) shall be fabricated
from refrigerant quality tube to BS EN 12449:1999. Tube shall be fully annealed up
to 7/8 (22 mm) outside diameter (O/D) only. Tube shall be delivered to site
internally degreased and shall be stored in clean dry conditions with ends sealed
until required for installation.
2.2 All due consideration and allowances shall be taken to keep pipe work clean and
dry during the installation works, ensuring that all pipe work unfinished ends are
capped off at all times.
2.3 The number of joints bends and sets are to be kept to a minimum. Butt joints
will not be accepted; properly swaged joints must be formed. Bends and sets are to
be machine pulled to an approved radius where possible.
2.4 Flared joints must only be used when connecting to the manufacturer
equipment.
2.5 Pipe work to be properly fixed and supported using a recognized industry
approved support system.
2.6 Brazing shall be carried out in accordance with British Refrigeration Association
Specification for Brazing and BS 14324:2004. Brazing rods shall be cadmium free
and conform to BS EN 1044:1999. At all times, when brazing, a small amount of dry
nitrogen must be purged through the pipe to prevent oxidation and scaling
internally. Any component susceptible to heat during the brazing process that may
be damaged must be protected. Soft solder shall never be used for jointing of
refrigeration pipe work.
2.6.1 All completed R410A systems will be strength and leak tested with dry
nitrogen as per itemized below and BS EN 378. If the system is found to be leak
free, the final pressure readings for both strength and leak testing are to be
witnessed by either the main contractor, the consultant or end-user and recorded
in the test result Log Book.
21 bar, Strength test for a period of time that is acceptable to show any signs of
deformation to the pipe work.
21 bar for final leak test for minimum 24 hours. Pressure testing signage will be
clearly visible on site during testing periods.
2.6.2 All completed R410A systems will be leak tested with dry nitrogen as
below and BS EN 378. If the system is found to be leak free, the final pressure
readings for leak testing are to be witnessed and entered into the log Book
4. Electrical Work
The contractor shall include for the design and installation (unless otherwise
specified), including connecting all items of mechanical equipment. The Contractor
shall provide and install all wiring, cables, conduit, trunking, cable trays, termination
points, local means of isolation, control wiring etc., to mechanical plant items to
ensure that all items of equipment and controls fully function in accordance with
manufacturers recommendations and the current IEE Wiring Regulations, CIBSE
Codes of Practice, British Standards and UK Building Regulations.
4.1 All electrical cables used for power distribution will comply with the latest
Edition IEE Regulations. All cables used for data/control must be greater than 1.25
mm 2-core screened.
4.2 Appropriate glands will be fitted to each item of equipment in accordance with
environmental conditions.
4.3 The whole installation will be in full accordance with the IEE Wiring Regulations
in every respect with particular attention to clipping, earthing of equipment,
grounding off, final connections and isolating.
4.4 Earth bonds on refrigeration, cold water and drainage pipe work to be applied
throughout.
4.5 Equi-potential bonding between exposed conductive parts and extraneous
conductive parts at the same potential, to be applied throughout.
4.6 On completion the installation should be tested in accordance with the
requirements of Inspection and testing section of the IEE Wiring Regulations.
Inspection shall include physical check that all equipment has been securely fixed
and that all electrical connections are mechanically sound.
4.7 Where necessary, to prevent damage to components of equipment, the
equipment shall be disconnected for the duration of the relevant tests.
4.8 Heat resisting cable should be used in all locations where wiring is subjected to
ambient temperatures in excess of 40C (104F).
4.9 A suitable means of isolating the electricity supply shall be fitted adjacent to
and within reach and sight of the equipment with over current protections.
4.10 When running interconnecting control wiring it is essential to avoid the risk of
electronic control signals being corrupted. Care should therefore be taken to avoid
running control cables too close to power cables.
5. Insulation
Thermal insulating material used within any building shall, when tested in
accordance with BS 476-4:1970, be classified as non-combustible also free from
substances which in the event of a fire would generate appreciable quantities of
6.7 All ductwork systems will be fitted with sufficient volume control dampers to
enable system balancing. To prevent noise regeneration final trimming to 10% only
of airflows to be carried out using the opposed blade dampers fitted to terminal
devices.
6.8 Fire dampers are to be fitted to ductwork passing through designated fire
barriers, these dampers to be fitted with HEVAC installation frames where passing
through structural walls.
6.9 Flexible ducting shall be used to form the final connection to the air terminal
device. The maximum length not to exceed 1.5 meters and incorporate a change in
direction of not greater than 90.
6.10 Flexible ducting will be manufactured from aluminum/polyester/aluminum
laminate enclosing a high tensile steel wire helix. Where required flexible ducting
will be of the insulated type with an outer jacket of reinforced aluminum laminate
giving a Class O rating.
6.11 Joints between flexible and rigid ductwork to be secured by worm drive clip
with the rigid ductwork spigot incorporating a swaged end.
6.12 Insulation will be applied to the following ductwork systems: - Fresh air intake
ductwork, ventilation return air ducts passing through unheated spaces - All
conditioned air ductwork (unless an architectural feature and adequate control is
provided to prevent condensation forming on the ductwork).
6.13 Insulation shall be either Rockwool duct wrap minimum 25mm thick, or
phenolic foam, with reinforced aluminum foil vapor barrier giving a Class O rated
finish and a thermal conductivity of 0.018W/M/K. The insulation is to be applied in
accordance with the manufacturers recommendations. All joints to be securely
taped with 75mm wide self adhesive aluminium tape and further secured with wire
loops at 1.0m intervals.
6.14 All ductwork will be fitted with identification bands and directional arrows in
accordance with BS 1710:1984.
6.15 Air terminal devices will be selected to provide the required air flows/throws for
the system design, are to provide a draught free environment in all operating
conditions and take into account the acoustic requirements of the installation.
Generally terminal neck velocities will not exceed 3.5m/s to prevent noise
regeneration.
6.16 All outdoor duct work will be insulated with a 50mm thick Rockwool duct wrap
minimum or phenolic foam , with reinforced aluminum foil vapor barrier giving a
Class O rated finish and a thermal conductivity of 0.018W/M/K, with additional
aluminum cladding as anti weather.
7. Pre-commissioning
The following items must be checked prior to any systems being switched on.
7.1 A marked up scale site drawing showing all VRF units and refrigeration pipe
work, address settings (for units and remote controllers and BC branch connections)
and model/serial numbers must be produced.
7.2 City Multi Indoor Units, BC Boxes, Outdoor Units addressing and screened wiring
(greater than 1.25mm) as per the VRF specification (refer to data book).
7.3 All control wiring and remote controllers must be complete and connected but
final connection to TB3 & TB7 left disconnected.
7.4 Before the Power Supply to Outdoor Unit is turned on, the mains wiring must be
checked phase to neutral, neutral to earth. Once this is complete the mains isolator
can be switched on to allow the crankcase heater to warm up the oil (minimum 24
hours).
7.5 All power supply wiring to Indoor Units (and BC controllers if R2 system) must be
complete, tested and left switched on at Indoor Unit isolators.
7.6 All Indoor Units must be clearly marked with marker pen or similar indication
and label indicating address and branch controller connection (R2 only) and
model/serial number.
7.7 Pressure test and evacuation of system refrigerant pipe work must be
completed as per section
2.6.1, 2.6.2 & 2.7.
7.8 Condensate pipe work must be completed and tested.
7.9 Total lengths of liquid line pipe work installed, must be confirmed by installation
Engineers and marked on drawings for additional refrigerant charge calculation.
7.10 Sufficient supply of refrigerant R410A in dumpy cylinders must be on site
adjacent to the Outdoor Units ready for use.
7.11 Now charge refrigerant into pipe work based upon the additional refrigerant
charge calculation.
7.12 Outdoor Unit service valves must now be opened.
8. Commissioning
8.1 Connect Monitor Tool and check system connect information is correct i.e.
Outdoor Unit, BC port, Indoor Unit and Remote controller addresses.
8.2 Start up the system and run each Indoor Unit one by one in cooling mode to
confirm correct operation superheat and pipe temperatures.
8.3 Then change over all Indoor Units to heating mode and check operation, subcooling and pipe temperatures.
8.4 Set up and configure all controllers/time clocks/G50 centralized controllers.
8.5 Check operation of all accessories interlocks i.e. time clocks, centralized
controllers etc.
8.6 Carry out airflow and static pressure drops on any units connected to ductwork.
8.7 Check operation of all condensate pumps if fitted.
8.8 Monitor operation for at least 1 hour. Observe and record all data.
8.9 Complete Commissioning Log Book via paper forms provided or via (handheld
device).