Gant Chart
Gant Chart
ID
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
Task Name
Pre Construction
Prepare Contract Drawings
Permit (Foundation)
Permit (Full Building)
Site Utility Relocation
Construction
Notice to Proceed
Site Clearing
Excavation
Footings
Pre-Cast Walls
Columns
Slabs
MEP Layout & Rough-in
Mechanical, Electrical, & Lighting Install 1st
Mechanical, Electrical, & Lighting Install 2nd
Painting, Traffic Coating & Markings
Ceiling 1st F
Walls 1st F
Ceiling 2nd F
Walls 2nd F
Install Windows & Doors 1st F
Install Windows & Doors 2nd F
Install Wood Panels
Exterior Finishes
CONSTRUCTION DURATION
Month
Week
Duration
94
90
1
1
2
153
0
2
5
4
15
12
8
23
15
12
14
3
4
3
4
8
10
6
5
341
May
2
3
May
4
June
2
3
July
2
3
August
2
3
September
1
2
3
4
October
1
2
3
October
4
November
1
2
3
4
December
1 2
3
4
January
1
2
3
February
1
2
3
4
March
2
3
March
4
April
2
3
Project:
Location:
Owner:
Subject:
I. MOBILIZATION
A. Excavation & Backfiling
II. CONCRETTING (Footing, Columns, Beams & Flooring)
A. Cement
B. Sand
C. Gravel
D. Steel Works
II. MASONRY WORKS
A. Hallow Blocks
B. Cement
C. Sand
IV. FORMSWORKS
A. Coco Lumber
B. Plywood
V. MISCELLANEOUS
A. Tie Wires # 16
B. Assorted Nails
C. Bolts & Nuts
D. Waterproofing
VI. WINDOWS, DOORS, ETC.
VII. PLUMBING
A. Pipe & etc
VIII. ELECTRICAL
X. PAINT
XI. LABOR COST
MONTH
MAY
JUNE
JULY
AUGUST
SEPTEMBER
OCTOBER
BREAKDOWN
EMPLOYED
PER MONTH
#
WAGE
Architect
Foreman
Foreman
Supervisor
Foreman
1
2
2
1
3
1,100
450
450
500
450
NOVEMBER
DECEMBER
JANUARY
FEBRUARY
MARCH
TRANSPORT
Electrical Eng
Supervisor
Foreman
Supervisor
Foreman
Electrical Eng
Supervisor
Foreman
Supervisor
Foreman
Driver
Supervisor
Foreman
Driver
Supervisor
L-300
Fuel
1
1
2
1
3
1
1
3
1
4
1
1
3
1
1
1
1
700
500
450
600
450
700
500
450
600
450
450
500
450
450
600
500
350
TOTAL COST
25000.00
50880.00
40700.00
29550.00
38680.00
45,900.00
29,550.00
35,590.00
37,460.00
32,670.00
5,500.00
8,490.00
4,980.00
22,800.00
159810.00
111040
70130
41,770.00
45,020.00
MATERIAL COST
DAYS EMPLOYED
66
15
20
4
20
61,220.00
69,010.00
70,110.00
653,110.00
218,550.00
TOTAL COST OF LABOUR
72,600.00
13,500.00
18,000.00
2,000.00
27,000.00
2,800.00
2,000.00
18,000.00
2,400.00
27,000.00
2,800.00
2,000.00
27,000.00
2,400.00
36,000.00
1,350.00
2,000.00
24,300.00
1,350.00
2,400.00
2,500.00
1,750.00
4
4
20
4
20
4
4
20
4
20
3
4
18
3
4
5
5
TOTAL PROJECT
COST
944,260.00