0% found this document useful (0 votes)
56 views

Gant Chart

The activity chart outlines the schedule for a construction project over 15 months. It includes 18 main tasks from pre-construction activities like preparing drawings through final construction stages like installing windows and exterior finishes. The detailed estimate provides a breakdown of material and labor costs for a proposed one-storey building project in Manila. It estimates costs for items like concreting, masonry works, formsworks, plumbing, electrical, and paint. The labor cost is estimated by month based on number of workers employed, their wages, and number of days worked each month. The total estimated project cost is 944,260 Philippine Pesos.

Uploaded by

Mon Boom
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
56 views

Gant Chart

The activity chart outlines the schedule for a construction project over 15 months. It includes 18 main tasks from pre-construction activities like preparing drawings through final construction stages like installing windows and exterior finishes. The detailed estimate provides a breakdown of material and labor costs for a proposed one-storey building project in Manila. It estimates costs for items like concreting, masonry works, formsworks, plumbing, electrical, and paint. The labor cost is estimated by month based on number of workers employed, their wages, and number of days worked each month. The total estimated project cost is 944,260 Philippine Pesos.

Uploaded by

Mon Boom
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 8

ACTIVITY CHART

ID
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15

16
17
18

Task Name
Pre Construction
Prepare Contract Drawings
Permit (Foundation)
Permit (Full Building)
Site Utility Relocation
Construction
Notice to Proceed
Site Clearing
Excavation
Footings
Pre-Cast Walls
Columns
Slabs
MEP Layout & Rough-in
Mechanical, Electrical, & Lighting Install 1st
Mechanical, Electrical, & Lighting Install 2nd
Painting, Traffic Coating & Markings
Ceiling 1st F
Walls 1st F
Ceiling 2nd F
Walls 2nd F
Install Windows & Doors 1st F
Install Windows & Doors 2nd F
Install Wood Panels
Exterior Finishes
CONSTRUCTION DURATION

Month
Week
Duration
94
90
1
1
2
153
0
2
5
4
15
12
8
23
15
12
14
3
4
3
4
8
10
6
5
341

May
2
3

May
4

June
2
3

July
2
3

August
2
3

September
1
2
3
4

October
1
2
3

October
4

November
1
2
3
4

December
1 2
3
4

January
1
2
3

February
1
2
3
4

March
2
3

March
4

April
2
3

Project:
Location:
Owner:
Subject:

PROPOSED ONE (1) STOREY


2031 ESCALER, STA.CRUZ, MANILA
HERCO JASON TAN LAM & HENRICK WAPI TAN LAM
DETAILED ESTIMATE

I. MOBILIZATION
A. Excavation & Backfiling
II. CONCRETTING (Footing, Columns, Beams & Flooring)
A. Cement
B. Sand
C. Gravel
D. Steel Works
II. MASONRY WORKS
A. Hallow Blocks
B. Cement
C. Sand
IV. FORMSWORKS
A. Coco Lumber
B. Plywood
V. MISCELLANEOUS
A. Tie Wires # 16
B. Assorted Nails
C. Bolts & Nuts
D. Waterproofing
VI. WINDOWS, DOORS, ETC.
VII. PLUMBING
A. Pipe & etc
VIII. ELECTRICAL
X. PAINT
XI. LABOR COST
MONTH
MAY
JUNE
JULY
AUGUST
SEPTEMBER
OCTOBER

BREAKDOWN
EMPLOYED

PER MONTH
#

WAGE

Architect
Foreman
Foreman
Supervisor
Foreman

1
2
2
1
3

1,100
450
450
500
450

NOVEMBER
DECEMBER

JANUARY
FEBRUARY

MARCH

TRANSPORT

Electrical Eng
Supervisor
Foreman
Supervisor
Foreman
Electrical Eng
Supervisor
Foreman
Supervisor
Foreman
Driver
Supervisor
Foreman
Driver
Supervisor
L-300
Fuel

1
1
2
1
3
1
1
3
1
4
1
1
3
1
1
1
1

700
500
450
600
450
700
500
450
600
450
450
500
450
450
600
500
350

WAPI TAN LAM

TOTAL COST
25000.00
50880.00
40700.00
29550.00
38680.00

45,900.00
29,550.00
35,590.00

37,460.00
32,670.00

5,500.00
8,490.00
4,980.00
22,800.00

159810.00

111040

70130

41,770.00

45,020.00

MATERIAL COST

DAYS EMPLOYED

66
15
20
4
20

61,220.00
69,010.00
70,110.00
653,110.00
218,550.00
TOTAL COST OF LABOUR

72,600.00
13,500.00
18,000.00
2,000.00
27,000.00

2,800.00
2,000.00
18,000.00
2,400.00
27,000.00
2,800.00
2,000.00
27,000.00
2,400.00
36,000.00
1,350.00
2,000.00
24,300.00
1,350.00
2,400.00
2,500.00
1,750.00

4
4
20
4
20
4
4
20
4
20
3
4
18
3
4
5
5
TOTAL PROJECT
COST

944,260.00

You might also like