Questions and Answers
Questions and Answers
o
o
o
Identified all the integration points of SAP SD/LE/MM module with other SAP
modules and non- sap systems.
Subject Matter Expert for SAP SD/LE/MM module
Some of the project deliverables that I created were
TO-BE document
Functional requirement document for each configuration
Functional requirement document for each RICEF object and then
coordinated with the technical team to help them create the technical
design document
Created the functional test case scenarios and test cases and linked them
to each functional requirement to define test coverage
Responsibilities pertaining to project management
Administered the share point website to make sure the latest approved
project documents were uploaded by the team members.
Provided the Work Break Down hours for each identified RICEF object and
configuration. Effort in hours for unit testing and getting more resources
onboard if required or releasing the resources.
Coordinated getting sign off on business blue print document from the
core team.
Coordinated getting sign off on the functional requirement document and
signed off the technical requirement documents.
Go Live Phase
o Coordinated with the basis team to transport the configurations to production
environment
documentation
identify and document all the
RICEF(W)
Deliverables or artifacts:
Functional Specifications
Document
Technical Specifications
Document
Functional Test scenarios and Test
cases
To be documentation
collision list
Realization Phase:
This phase is mostly done in iterations and each iteration consists
of configuration of RICEF objects and standard configuration, Unit
testing by Functional Team, Integration Testing by Functional team
and user acceptance testing by the CORE team
Pre-Go Live:
Go-Live
5) Explain briefly about the last project you worked on. What was your role in the that
project?
Scope Management
Requirements Management
Schedule Management
Quality Management
Resource Management
Communications Management
Project Change Management
Risk Management
6) Project management is critical to success in this role. What are some of the
projects that you handled in your current or previous role?
I have been handling project management tasks for last 3 positions that I
have held.
When I was working in Allstate as a senior consultant for one of the minor
release we had an issue in which proper change request was not created by
one of the consultant and due to SOX non-compliance we were not being
allowed to move the changes to production and this was a critical production
issue.
I accepted that as a team we had made a mistake and had
to write a request email to the director to allow us to make changes so that
we become SOX compliant and be able to move the changes to production.
The root cause of this mistake was a
communication gap between our internal release coordinator and the
consultant. I made sure that we include all the details in the internal release
guidelines for the team. Creation of Change Request was no longer an
assumption and was discussed it in each release meeting.
10)