This document contains details of reinforcement bar requirements for 29 columns (C1-C23) for a construction project. It includes the column mark, type of pilecap, column size dimensions, pilecap depth, quantities of different bar diameters (T10, T12, T16, T20, T25, T32) in kilograms, number of bars required, and total bar weight for each column. The total bar weight required for all 29 columns is 70,472.67 kg.

Uploaded by

Fariddinqs
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
43 views1 page

Starter Bar To Column Taking Off

This document contains details of reinforcement bar requirements for 29 columns (C1-C23) for a construction project. It includes the column mark, type of pilecap, column size dimensions, pilecap depth, quantities of different bar diameters (T10, T12, T16, T20, T25, T32) in kilograms, number of bars required, and total bar weight for each column. The total bar weight required for all 29 columns is 70,472.67 kg.

Uploaded by

Fariddinqs
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

Dwg No: ST/B-Column/101B - Starter Bar To Column

No
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29

Column
Mark
C1
C2
C3
C3
C4
C4
C5
C6
C7
C7
C7a
C8
C9
C10
C10a
C11
C12
C13
C14
C14
C15
C16
C17
C18
C19
C20
C21
C22
C23

Type Of
Pilecap
3P1 & 4P1
4P2
2P3
2P2
1P3
2P3
2P3
2P3
7P1
6P1
8P1
9P1 & 8P1
13P1
10P1
11P1
12P1
10P1
16P1
6P1
7P1
5P1
14P1
10P1
4P2
8P1
10P1
7P1
11P1
9P1
TOTAL

Column Size
L
B
0.45 0.60
0.30 0.60
0.30 0.45
0.30 0.45
0.20 0.23
0.20 0.23
0.30 0.30
0.20 0.23
0.60 1.00
0.60 1.00
0.80 0.80
0.60 1.20
0.75 1.50
0.60 1.40
0.85 1.00
0.60 1.60
0.75 1.20
0.75 1.80
0.75 0.75
0.75 0.75
0.45 1.30
0.75 1.60
0.90 1.00
0.45 0.45
0.85 0.85
0.90 0.90
0.80 0.80
0.95 0.95
0.95 0.95

Pilecap
Depth
1.20
0.90
0.65
0.90
0.48
0.65
0.65
0.65
1.60
1.40
1.60
1.60
1.80
1.60
1.60
1.80
1.60
1.80
1.40
1.60
1.40
1.80
1.60
0.90
1.60
1.60
1.60
1.60
1.60
39.18

T10
13.51
5.65
3.51
1.48
0.81
0.81
2.95
1.41
29.52
29.52
12.94
45.30
63.52
46.46
43.40
60.13
45.47
77.49
24.80
31.00
24.00
65.74
45.05
7.28
35.43
37.78
32.36
39.86
39.87
0.00

T12

Reinforcement Bar (kg)


T16
T20
T25
289.91
170.17
31.29
18.20
13.58
15.74
42.27
42.27

T32

850.71
800.36
853.36
1,097.18
1,553.77
1,137.82
1,208.49
1,381.13
1,137.82
1,985.38
686.02
731.46
457.35
1,726.42
1,137.82
170.17

0.00

0.00

0.00

0.00

1,056.55
1,178.46
853.36
1,300.37
1,056.55
0.00

Nos
16
13
29
1
33
1
3
1
7
1
1
17
6
5
1
1
2
1
2
1
1
1
1
1
1
1
1
1
1
151

Total
(KG)
4,873.92
2,297.36
1,028.05
20.58
490.71
17.20
137.61
44.33
6,172.81
831.28
867.90
19,449.36
9,714.54
5,929.40
1,253.49
1,443.06
2,369.78
2,064.67
1,424.44
764.06
482.75
1,793.96
1,184.47
178.35
1,093.58
1,217.84
887.32
1,341.83
1,098.02

70,472.67