Piperack Guide2 (7 May, 02)
Piperack Guide2 (7 May, 02)
1.0 GENERAL
A - TERMINOLOGY
A.1. Structure
A.2. Foundations
B – DEFINITION CRITERIA
A – MATERIAL USED
B – SELECTION CRITERIA
A – PERMANENT LOAD
B – LIVE LOAD
D – CLIMATIC LOAD
D.1. Snow
D.2. Wind
E – SEISMIC LOAD
/opt/scribd/conversion/tmp/scratch2733/32324641.doc
1
F – TEMPERATURE LOAD
G – OTHER LOADS
H – COMBINATION OF LOADS
I – CONDITION OF DEFLECTION
A – CONSTRUCTION ARRANGEMENT
A – VARIOUS FORMS
B – METHODS OF EXECUTION
C.1. Studies
C.2. Calculations
D – CONSTRUCTION ARRANGEMENT
D.1. Reinforcement
D.2. Fixation of Cooler
D.3. Accessories
/opt/scribd/conversion/tmp/scratch2733/32324641.doc
2
1.0 GENERAL
1. INTRODUCTION
This document is a guide on the procedures or working methods in the field of civil.
In case of contradiction of this document with the General Protocols, this document
superceded the General Protocols.
2. OBJECTIVE
This document covers the regulation by service 347 and 357 of TECHNIP for the
piperacks in the petroleum, petrochemicals and similar industries.
Any deviation from this regulation shall be approved by the Head of Service, however
the customer particular rules or requirements have priority over this requirement.
3. REFERENCES
A. TERMINOLOGY
- Concrete foundation.
A.1. Structure
/opt/scribd/conversion/tmp/scratch2733/32324641.doc
3
A.1.2. Portal Frame
The element of piperack forms by two posts and one or more main
cross beams.
The width of piperack is the distance between the axis of the posts.
/opt/scribd/conversion/tmp/scratch2733/32324641.doc
4
PIPE-RACKS
LONGITUDINAL BEAM
COLUMN
PORTAL
FRAME
MAIN CROSS BEAM
I= WIDTH OF PIPERACK
L
= PORTAL SPACING LONGITUDINAL STABILITY
/opt/scribd/conversion/tmp/scratch2733/32324641.doc
5
A.2. Foundations
A.2.1. Footing
50
/opt/scribd/conversion/tmp/scratch2733/32324641.doc
6
B. DEFINITION CRITERIA
/opt/scribd/conversion/tmp/scratch2733/32324641.doc
7
2.0 MATERIAL SELECTION
A. MATERIAL USED
- Metal frame
- Concrete
- Mixed (metal frame – concrete)
The choice of materials used must be made by specialist engineers after detail
economic survey in agreement with the project engineer and various factor especially
the contract requirement :
- Fireproofing.
- Planning schedule (duration)
- Reduce time for studies (in the case of standard contract of fixed price for studies).
This chapter will explains the determination methods for loads on piperacks.
A - PERMANENT LOAD
B - LIVE LOAD
/opt/scribd/conversion/tmp/scratch2733/32324641.doc
8
C - EXAMPLES ON THE DETERMINATION FOR THE DISTRIBUTION OF VERTICAL
LOAD ON PIPERACK
D - CLIMATIC LOAD
D.1. Snow
D.2. Wind
E - SEISMIC LOAD
F - THERMAL LOAD
G - OTHER LOADS
H - LOAD COMBINATIONS
I - CONDITIONS OF DEFLECTION
A. PERMANENT LOAD
The actual weight of the elements constituting the piperacks shall be used especially
for concrete piperacks.
/opt/scribd/conversion/tmp/scratch2733/32324641.doc
9
A.3. Weight of pipe
The weight of pipes size between 2” to 12” shall be taken as uniform load as set
out in the following sections.
The empty space between pipes can be used (unless stated otherwise) for pipes with
diameter equal to the average pipe size.
2) Normally the uniform load per m2 for insulated pipes is smaller than
the uninsulated pipes due to the space provided between pipes for
the insulated pipes.
The calculation can be simplified by taking the average diameter of pipes for
load calculation.
Pipes with diameter more than twice the average diameter of pipes layer
shall be considered as follows:-
/opt/scribd/conversion/tmp/scratch2733/32324641.doc
10
A.3.3 Piping Load Distribution Coefficient Between Main Cross Beam (M) And
Intermediate Cross Beam (I)
Ø < 2” 0.9 0.1 0.8 0.2 0.7 0.3 0.6 0.4 0.4 0.6
3” - 4”
Ø 2” 0.9 0.1 0.8 0.2 0.6 0.4 0.4 0.6B
ZONE
Note : When the large pipes can support the smaller pipes, the intermediate
cross beam is not necessary.
B. OPERATING LOAD
The calculation of the liquid loads in the piping be determined from simplified
assumptions as follows :-
- Particular cases :
/opt/scribd/conversion/tmp/scratch2733/32324641.doc
11
In these particular case, the operating load will be the load provided by the
service piping, however the other possible loads due to operation shall be
considered.
The value of the operation load will be the actual values provided by the
service piping.
DISTANCE LOAD IN KG
EXTERNAL
NOMINAL BETWEEN ½ Full ¾ Full Full
DIAMETER SCHEDULE
DIAMETER CENTRE OF
(mm) Kg/m Kg/m 2
Kg/m Kg/m 2
Kg/m Kg/m2
PIPES
Load on platform and access shall be considered (value provided on particular rule)
/opt/scribd/conversion/tmp/scratch2733/32324641.doc
12
- Average pipe load (Dead Load + Operating Load)
510
=21.3 kg/m length
24
IMPORTANT NOTE :
Since the largest pipe size is not more than 2 times the average diameter, the
option of average pipe is conservative.
When one or more of the pipes obviously deviate from the average diameter,
it is better to calculate them separately.
Point loads shall be considered separately for lines with dia > 12”
If it is obvious that the average pipes size in some part is different from the
other part, the average pipe for each part shall be used.
C.2 Load Distribution Between Main Cross Beam And Intermediate Cross Beam
(Generated By The Pipes)
/opt/scribd/conversion/tmp/scratch2733/32324641.doc
13
C.2.2 Pipes Layer with Maximum Ø < 12”
1 0 2
MB
MB
MB
IB
IB
L1 = 7.5m L2 = 9m
LOAD DISTRIBUTION
BETWEEN (IB) AND (MB)
AS PER TABLE A.3.3
(PAGE 11)
For dead load case distribution, load on cross beam will be as follow:
Main cross beam = 110 x 6.97 = 797 kg/m See Table § A.3.1
Intermediate cross beam = 110 x 0.75 = 82.5 kg/m (Page 10)
Intermediate cross beam = 110 x 1.8 = 198 kg/m
/opt/scribd/conversion/tmp/scratch2733/32324641.doc
14
Load distribution on the cross beam.
67 x 7.5 = 502.5 kg
Point load from pipe Ø 12” shall be reduce by the value equivalent to the
3” ref pipe.
P = 381 kg
367 kg/m
C.2.4 Summary
/opt/scribd/conversion/tmp/scratch2733/32324641.doc
15
D. CLIMATIC LOAD
D.1 Snow
The effect of snow on the piperacks support and pipes are not considered (unless
otherwise stated in the particular regulation)
D.2. Wind
H = Qh x Ct x Sp
Where
Where
/opt/scribd/conversion/tmp/scratch2733/32324641.doc
16
D.2.3. Example of calculation for transverse wind load.
Qh = 100 kg/m²
Pipe layer
EL + 5.5 Larger Ø = 400
EL + 4.5
7.5m
Note :
However wind load shall be applied at the right location when justified by
beam size/or location, mainly for tie beam.
1 680 kg
H1
2.75
2.75
H3 H2
/opt/scribd/conversion/tmp/scratch2733/32324641.doc
17
Wind load at Elev. 0 : H2 – H3
Remark : Wind load distribution on column for pipe rack with two layer of
pipes
H1
for calculation of H1
H2
for calculation of H2
for calculation of H3
H3 V3
Ct = shape factor
- All columns
Where
0.05
Bottom layer
Values of B
0.05
/opt/scribd/conversion/tmp/scratch2733/32324641.doc
18
c) Wind load on vertical piping layer
H = Qh x Sp
Sp
H = Qh (Ø + 0.1 I) L
H = Qh x 0.6 Ø x I
Load to be applied :
/opt/scribd/conversion/tmp/scratch2733/32324641.doc
19
At the tie beam level
H1 H2
h
H3 H5 H5 H3
A B C D
PIPERACK UNDER
STARTING
CONSIDERATION
STARTING
POINT
POINT
L1 L2
/opt/scribd/conversion/tmp/scratch2733/32324641.doc
20
At The Base of Column
- Normal Foundation
H1 - H2
Longitudinal shearing load = H+
2
h
Vertical load = ± (H1 + H2) x
∆
E SEISMIC LOAD
Important Note
If the particular rule require to check for seismic, it will be checked for para
paraseismic regulation.
F THERMAL LOAD
The concrete pipe rack with tie beam cast in situ to the column, the
problem will be severe as the beam cannot expand freely. In this
/opt/scribd/conversion/tmp/scratch2733/32324641.doc
21
case the effect of expansion or shrinkage of concrete shall be
considered as it will result of several bars of constraint.
/opt/scribd/conversion/tmp/scratch2733/32324641.doc
22
In practice the distance between the expansion joint shall not exceed
the following value :-
- Anchorage :
Important note :
The vertical load combination for calculating the thermal forces are :-
Ff = 0.1 x p
/opt/scribd/conversion/tmp/scratch2733/32324641.doc
23
The force Ff shall be applied on the top
flange of the intermediate cross beam with
the following assumptions :-
Ff = ϕ xpx∝
% ∝
0 to 40 0.4
41 to 60 0.6
61 to 80 0.8
81 to 100 1
/opt/scribd/conversion/tmp/scratch2733/32324641.doc
24
- The anchoring force always act on the top flange of the
cross beam, the design of main cross beam is identical to
the previous intermediate cross beam.
IMPORTANT NOTE
Ft
Ft
/opt/scribd/conversion/tmp/scratch2733/32324641.doc
25
d) On portal (longitudinal forces)
- Anchor
- Friction
The total friction force applied on the pipe rack restrain is the
sum of various forces on the main cross beam.
Examples :-
FF FF FA
Case 1 ∑ FF RN ≠ 0
FA FF FA
Case 2 ∑ FF = 0
FF FF
Case 3 ∑ FF ≠ 0
/opt/scribd/conversion/tmp/scratch2733/32324641.doc
26
As shown in the example, it is difficult to generalise a method to
determine the total friction force on the piperack.
The value of the anchoring force will reach it maximum when the
displacement due to temperature effect has stopped. This mean
the combination force of anchoring and friction is only happen
during early stage.
Conclusion :
In the operating condition, the anchoring and friction force will not
be added for determination of overall forces on the piperack
restrain.
Ff = ϕ xpx∝
f) Summary
• Anchoring : 0
• Friction : 0.1 x p = Ff
• Friction : px∝xβ = Ff
/opt/scribd/conversion/tmp/scratch2733/32324641.doc
27
- For stability bay (longitudinal action)
• Friction : Ff = ϕ x p x ∝
G OTHER LOADS
This document provides the necessary guide for calculation and design of elements
in the piperacks for supporting the pipes.
During the progress of the calculation of piperack, the forces due to this equipment
shall be considered in the various load cases :
- Dead loads
- Live (operating) loads
- Climatic loads
It is should be noted that the possible dynamic loads by these equipments shall never
be combined with climatic loads.
H LOAD COMBINATIONS
- Dead loads :
• members
• walkways
• pipes P
• insulation
• fire proofing (operating load only)
• liquid loads G
• live (passage) loads
Thermal loads
• structure expansion D
• anchorage load A
• longitudinal friction loads F
/opt/scribd/conversion/tmp/scratch2733/32324641.doc
28
- Seismic load S
/opt/scribd/conversion/tmp/scratch2733/32324641.doc
29
LOAD COMBINATIONS
COMBINATION FOR LOAD LOAD COMBINATIONS FOR LOAD COMBINATION FOR COMBINATION
CASE
ON FOUNDATION STEEL STRUCTURE CONCRETE STRUCTURE NO.
P + Vt 1.33 P + 1.5 Vt P + Vt 1
NORMAL CASE
P + Vl 1.33 P + 1.5 Vl P + Vl 2
P + Wt P + Wt P + Wt 3
EXTREME CASE
P + Wl P + Wl P + Wl 4
P + 1.5 G + A + 1.5 Vt
9
EXTREME P + G + A + Wt P + G + A + Wt P + G + A + Wt
SERVICE CASE P + G + A + Wl P + G + A + Wl P + 1.5 G + A + 1.5 Vl 10
P + G + A + Wl
Note : Loading case (D : Structural expansion), any other possible cases shall be added to the combinations.
/opt/scribd/conversion/tmp/scratch2733/32324641.doc
30
J CONDITIONS OF DEFLECTION
The deflection of these beams due to total “Service” load shall not
exceed 1/400 of the length.
The total deflection (intermediate cross beam + tie beam) under total
loads in the service case shall not exceed 1/200 of the intermediate
cross beam.
Note :
The deflection o these beams due to total “Service” load shall not exceed
1/300 of the length.
Others elements
Checking of deflection for beam with L/H < 15 normally is not necessary.
/opt/scribd/conversion/tmp/scratch2733/32324641.doc
31
Note :
A CONSTRUCTION ARRANGEMENT
When the percentage of hot lines is high, it is better to use the profile HEA type which
provide better inertia in the horizontal direction (friction).
CONNECTION
1
INTERMEDIATE CROSS BEAM
POST
CONNECTION
2
LONGITUDINAL BEAM
Connection 1 :
This type of connection shall not transmit shearing force to the base of post
which produce torsion to the cross beam.
Connection 2 :
- The connection shall be able to ensure the stability of the post due to
friction load on the intermediate cross beam.
/opt/scribd/conversion/tmp/scratch2733/32324641.doc
32
In practice, the connection are shown below :-
Connection 1
POSSIBLE OVERHANG
POST
Connection 2
GUSSET IF NECESSARY
POSSIBILITY
/opt/scribd/conversion/tmp/scratch2733/32324641.doc
33
A.1.2 Other Provisions
TIE BEAM
POSSIBLE OVERHANG
INTERMEDIATE CROSS
BEAM
TIE BEAM
/opt/scribd/conversion/tmp/scratch2733/32324641.doc
34
A.2 LONGITUDINAL BEAM
The tie beam profile type IPE is connected to the column by pin joint
connection using double cleat.
= ~ 15 H
Elevation
For lattice members, they shall be checked for horizontal buckling (lateral
restrain).
(For low weight pipe layer). The tie beam can be supported by stay wire
and braced horizontally.
Stay Wire
For example :
/opt/scribd/conversion/tmp/scratch2733/32324641.doc
35
A.3 PORTAL FRAME
STIFFNER
BRACING
The column are always profile type H to ensure maximum radius of gyration for good
buckling strength.
Transverse members generally not made from profile type H, but made from profile type
IPE.
- Stiffners
- bracing members
/opt/scribd/conversion/tmp/scratch2733/32324641.doc
36
A.4 POST – FOUNDATION CONNECTION
However the connection of column to foundation in the axis of portal can be pin-jointed or
fixed type.
Advantage :
- no moment transfer
- simple connection
Disadvantages
Advantages :
Disadvantages :
- large foundation
- lot of bolts
- massive connection
Synthesis
/opt/scribd/conversion/tmp/scratch2733/32324641.doc
37
A.5 STABILITY BAY
A.5.1 Purpose
The length of the section is limited to 60m for the French climate for
negligible effect of thermal expansion.
INCORRECT
POSITION OF
ISOLATION
F F
ANCHORING PRINCIPAL
/opt/scribd/conversion/tmp/scratch2733/32324641.doc
38
A.5.3 Position of Bracing
- The distance between two bracing stability does not exceed 60m
(for French climate).
A.5.4 Principle
Advantages :
Disadvantages
MAIN BRACING
PRINCIPLE
/opt/scribd/conversion/tmp/scratch2733/32324641.doc
39
b) Portal Stability Bay
Advantages :
• No obstruction
Disadvantages :
STIFFNER
PROFILE COMBINATION
Important Note :
/opt/scribd/conversion/tmp/scratch2733/32324641.doc
40
A.6 PARTICULAR CASE
Principal
Increase the Iy inertial of the main cross beam or provide additional support.
ANCHOR
MINI
ANCHOR LINE
/opt/scribd/conversion/tmp/scratch2733/32324641.doc
41
5.0 CONCRETE PIPERACK
The concrete piperacks are generally comprises of concrete main frame. The
frame is connected by concrete or steel tie beams.
When the width of the piperack is less than 3m, normally only one column is
required at the centre.
/opt/scribd/conversion/tmp/scratch2733/32324641.doc
42
/opt/scribd/conversion/tmp/scratch2733/32324641.doc
43
DISTANCE
RACK WIDTH
BETWEEN COLUMN CROSS BEAM TIE BEAM
L
PORTAL
4500 6000 400 x 400 400 x 300 400 x 300
6000 6000 400 x 400 400 x 300 400 x 300
7500 6000 400 x 400 500 x 300 400 x 300
7500 7500 400 x 400 500 x 300 500 x 300
7500 9000 500 x 400 500 x 300 600 x 300
9000 7500 500 x 400 600 x 300 500 x 300
9000 9000 500 x 400 600 x 300 600 x 300
PREDIMENSION
PIPE RACK 1 LEVEL
VALID FOR PIPES AVERAGE Ø ≤ 12"
/opt/scribd/conversion/tmp/scratch2733/32324641.doc
44
VARIOUS METHODS OF EXECUTION
All the piperack members are casted at place. No prefabricated member is used.
The horizontal beams (longitudinal beams, cross beams, tie beams) are
prefabricated.
The columns and beam (longitudinal beam, cross beam, tie beams) are
prefabricated.
- size of piperack
• Perhaps the selected Subcontractor does not have necessary material for
prefabrication.
• The local agent of the subcontractor does not want to construct the rack as method
prerecognise by TECHNIP. If the subcontractor is requested to follow the TECHNIP
prerecognise method, the subcontractor will always try to find ways for change order.
• Generally, the subcontractor under estimate the priority of the execution of concrete
racks, they will wait at the last minute to look at the drawings.
It should not be believed that prefabrication reduce the cost of the rack
appreciably but it can save a lot of time.
/opt/scribd/conversion/tmp/scratch2733/32324641.doc
45
C. ANALYSIS AND DESIGN
C.1 ANALYSIS
C.1.1 Purpose
C.1.2 Method
Note :
If possible, the dimension of the footing is carried out during the calculation for
reinforcement. It is necessary to indicate the bottom level of foundation and dimension,
for presence of other foundation, pipe & etc.
The table of predimensions are valid for normal case, however the designer need to
check it.
/opt/scribd/conversion/tmp/scratch2733/32324641.doc
46
DISTANCE
RACK WIDTH
BETWEEN COLUMN CROSS BEAM TIE BEAM
L
PORTAL
4500 6000 400 x 400 400 x 300 400 x 300
6000 6000 400 x 400 400 x 300 400 x 300
7500 6000 400 x 400 500 x 300 400 x 300
7500 7500 400 x 400 500 x 300 500 x 300
7500 9000 500 x 400 500 x 300 600 x 300
9000 7500 500 x 400 600 x 300 500 x 300
9000 9000 500 x 400 600 x 300 600 x 300
PREDIMENSION
PIPE RACK 1 LEVEL
VALID FOR PIPES AVERAGE Ø ≤ 12"
/opt/scribd/conversion/tmp/scratch2733/32324641.doc
47
DISTANCE
RACK WIDTH
BETWEEN COLUMN CROSS BEAM TIE BEAM
L
PORTAL
4500 6000 400 x 400 400 x 300 400 x 300
6000 6000 400 x 400 400 x 300 400 x 300
7500 6000 500 x 400 500 x 300 400 x 300
7500 7500 500 x 400 500 x 300 500 x 300
7500 9000 600 x 400 600 x 300 600 x 300
9000 7500 600 x 400 600 x 300 500 x 300
9000 9000 600 x 400 600 x 300 600 x 300
PREDIMENSION
PIPE RACK 2 LAYERS
VALID FOR PIPES AVERAGE Ø ≤ 12"
/opt/scribd/conversion/tmp/scratch2733/32324641.doc
48
DISTANCE TIE BEAM
RACK WIDTH
BETWEEN COLUMN CROSS BEAM
L UPPER LOWER
PORTAL
7500 6000 700 x 500 700 x 400 700 x 400 400 x 300
7500 7500 700 x 500 700 x 400 700 x 400 500 x 300
7500 9000 800 x 500 800 x 400 800 x 400 600 x 300
9000 7500 800 x 500 800 x 400 800 x 400 500 x 300
9000 9000 800 x 500 800 x 400 800 x 400 600 x 300
PREDIMENSION
PIPE RACK 1 LEVEL + AEROS
VALID FOR PIPES AVERAGE Ø ≤ 12"
/opt/scribd/conversion/tmp/scratch2733/32324641.doc
49
DISTANCE TIE BEAM
RACK WIDTH
BETWEEN COLUMN CROSS BEAM
L UPPER LOWER
PORTAL
7500 6000 700 x 500 600 x 300 700 x 400 400 x 300
7500 7500 700 x 500 600 x 300 700 x 400 500 x 300
7500 9000 800 x 500 700 x 400 800 x 400 600 x 300
9000 7500 800 x 500 700 x 400 800 x 400 500 x 300
9000 9000 800 x 500 700 x 400 800 x 400 600 x 300
PREDIMENSION
PIPE RACK 2 LEVEL + AEROS
VALID FOR PIPES AVERAGE Ø ≤ 12"
/opt/scribd/conversion/tmp/scratch2733/32324641.doc
50
DISTANCE TIE BEAM
RACK WIDTH
BETWEEN COLUMN CROSS BEAM
L UPPER LOWER
PORTAL
7500 6000 700 x 500 600 x 300 700 x 400 400 x 300
7500 7500 700 x 500 600 x 300 700 x 400 500 x 300
7500 9000 800 x 500 700 x 400 800 x 400 600 x 300
9000 7500 800 x 500 700 x 400 800 x 400 500 x 300
9000 9000 800 x 500 700 x 400 800 x 400 800 x 300
PREDIMENSION
PIPE RACK 3 LEVEL + AEROS
VALID FOR PIPES AVERAGE Ø ≤ 12"
/opt/scribd/conversion/tmp/scratch2733/32324641.doc
51
C.2. DESIGN
C.2.1 Purpose
The amount of reinforcement in the member shall not exceed 150 kg/m³
of the concrete. The size of the section shall be increase if the amount of
reinforcement is high.
D. CONSTRUCTION DETAILING
D.1 REINFORCEMENT
In order to facilitate the execution of piperack at site, the reinforcement of all the elements
shall be detail as follows :
D.1.1 Column
Steel for the columns are similar except for the diameter (range between
Ø12 and 25).
φ 12 to φ 25
90 45
130
400
45 90
/opt/scribd/conversion/tmp/scratch2733/32324641.doc
52
COLUMN 400 X 600
REINFORCEMENT DETAIL
/opt/scribd/conversion/tmp/scratch2733/32324641.doc
53
COLUMN 500 X 800
REINFORCEMENT DETAIL
/opt/scribd/conversion/tmp/scratch2733/32324641.doc
54
D.1.2 Beam (Main Cross Beam or Tie Beam)
/opt/scribd/conversion/tmp/scratch2733/32324641.doc
55
D.2. FIXATION OF AIR COOLER
The air coolers are installed on piperack in four different ways, i.e.:
/opt/scribd/conversion/tmp/scratch2733/32324641.doc
56
D.2.3 The Feet of Cooler on Overhang Beam Supported on Tie-Beam
/opt/scribd/conversion/tmp/scratch2733/32324641.doc
57
D.3 ACCESSORIES
Accessories are required for fixing of small frames, piping slide, installation of electric
elements.
/opt/scribd/conversion/tmp/scratch2733/32324641.doc
58
D.3.1 Base Plate or Insert Plates
Base plate or insert plates are used for fixing (particularly the post) the
secondary steel frames for supporting pipings, walkways etc.
It is needed for allowing slip of pipings and fixing of anchor on the cross
beams or tie-beams. The flat plates are generally 150 mm wide x 10 mm
thick.
Flat plate must be provided on the cross beams and fix to the concrete
by steel Ø 8.
50 50
4 x φ 8 per metre
150
10
5
5
120
φ 8 welded
50
/opt/scribd/conversion/tmp/scratch2733/32324641.doc
59
These special adhesives are produce by companies such as :-
- “BOSTIK”
or
- “SIKA”
D.3.3 Sleeves
D.3.4 Rails
ACIBAT
Z.I. 68190 UNGERSHEIM – Tel. (89) 48.13.03
TECNER
25, Rue Trebois
92300 LEVALLOIS-PERRET
/opt/scribd/conversion/tmp/scratch2733/32324641.doc
60
As an indication, a profile 50/30, the basic load is 4.5 ton/meter length
with 4 bolts Ø 20.
D.3.5 Conclusion
It is obvious that the use of anchoring rail will make it easy to fix apparatus
or secondary frame. However as it is very costly, it shall not be their
installed especially for ‘turnkey contract”. In the service contract, they
only be used when requested by client.
The plats on tie-beam are optional. The need is decided after studing the
general drawings.
The plats are anchor to the concrete, if they are install before casting of
concrete or adhesive by special product. The adhesive cannot be used
for slide (anchoring of lines).
/opt/scribd/conversion/tmp/scratch2733/32324641.doc
61