Office Move Plan
Office Move Plan
Task
Mode
0
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
Task Name
Duration
Start
Jan 24, '16 Finish
S
Feb 7, '16
S M T
Br
Task
Inactive Task
Start-only
Split
Inactive Milestone
Finish-only
Milestone
Inactive Summary
Deadline
Summary
Manual Task
Progress
Project Summary
Duration-only
Manual Progress
External Tasks
External Milestone
Manual Summary
Page 1
ID
Task
Mode
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
Task Name
Duration
Start
Jan 24, '16 Finish
S
Feb 7, '16
S M T
Task
Inactive Task
Start-only
Split
Inactive Milestone
Finish-only
Milestone
Inactive Summary
Deadline
Summary
Manual Task
Progress
Project Summary
Duration-only
Manual Progress
External Tasks
External Milestone
Manual Summary
Page 2
Mar 6, '16
S M T
El
Task
Inactive Task
Start-only
Split
Inactive Milestone
Finish-only
Milestone
Inactive Summary
Deadline
Summary
Manual Task
Progress
Project Summary
Duration-only
Manual Progress
External Tasks
External Milestone
Manual Summary
Page 3
Mar 6, '16
S M T
Task
Inactive Task
Start-only
Split
Inactive Milestone
Finish-only
Milestone
Inactive Summary
Deadline
Summary
Manual Task
Progress
Project Summary
Duration-only
Manual Progress
External Tasks
External Milestone
Manual Summary
Page 4
Apr 3, '16
S M T
Ele
Task
Inactive Task
Start-only
Split
Inactive Milestone
Finish-only
Milestone
Inactive Summary
Deadline
Summary
Manual Task
Progress
Project Summary
Duration-only
Manual Progress
External Tasks
External Milestone
Manual Summary
Page 5
Apr 3, '16
S M T
Task
Inactive Task
Start-only
Split
Inactive Milestone
Finish-only
Milestone
Inactive Summary
Deadline
Summary
Manual Task
Progress
Project Summary
Duration-only
Manual Progress
External Tasks
External Milestone
Manual Summary
Page 6
May 1, '16
S M T
May 8, '16
S M T
Electricians
Data[50%],Electricians[50%]
Carpenters
Carpenters
Paint[50 Gallon],Painters
Carpenters
Carpenters
Task
Inactive Task
Start-only
Split
Inactive Milestone
Finish-only
Milestone
Inactive Summary
Deadline
Summary
Manual Task
Progress
Project Summary
Duration-only
Manual Progress
External Tasks
External Milestone
Manual Summary
Page 7
May 1, '16
S M T
May 8, '16
S M T
Task
Inactive Task
Start-only
Split
Inactive Milestone
Finish-only
Milestone
Inactive Summary
Deadline
Summary
Manual Task
Progress
Project Summary
Duration-only
Manual Progress
External Tasks
External Milestone
Manual Summary
Page 8
ay 29, '16
T
Jun 5, '16
S M T
Task
Inactive Task
Start-only
Split
Inactive Milestone
Finish-only
Milestone
Inactive Summary
Deadline
Summary
Manual Task
Progress
Project Summary
Duration-only
Manual Progress
External Tasks
External Milestone
Manual Summary
Page 9
Jul 3, '16
S M T
ay 29, '16
T
T
F
S
Carpenters
Data
Jun 5, '16
S M T
Carpenters[50%],Painters[50%]
6/8
Data
Movers
Travel[$1,500.00],Movers
Movers
Data
6/20
Data
Travel[$750.00],John Benoy,John Smith
Data
Data
6/28
6/28
Task
Inactive Task
Start-only
Split
Inactive Milestone
Finish-only
Milestone
Inactive Summary
Deadline
Summary
Manual Task
Progress
Project Summary
Duration-only
Manual Progress
External Tasks
External Milestone
Manual Summary
Page 10
Jul 3, '16
S M T