SAP Invoice
SAP Invoice
30
On the basis of days, periods or fiscal years one can plan payment flows i.e. revenues
and expenditure.
In WBS elements, manual planning of revenues and expenditure is by period. At
commitment item level (Project Cash Management master data) planning takes place.
The quantity structure in the network and the billing plans in the WBS or SD document
are valuated in the automatic planning of financial data.
Automatic planning will be done by day. Planned line items will be written.
Based on assignment to G/L accounts commitment items will be determined. Unlike
revenue and costs calculation, payment date calculation takes account of the
customer and vendor payment terms respectively.
Note: The credit side payment plan of the network is determined using the
asynchronous network costing only.
The dates and the payment terms are used in the PS billing plan for planning incoming
payments. Sales order items will also be used in assigning the billing plan data and
payment terms(of the dates or sales order item).The delivery date including the
payment conditions is used if there is no billing plan for the sales order item.
31
31
32
Invoicing planes can be created for externally-processed activities, externallyprocured material components, service activities and cost activities.
32
Depending on the transaction, you can calculate costs for one network (example: network
maintenance) or a range of networks (example: all networks for selected WBS elements
in structure planning or the project planning board).
You can calculate network costs asynchronously. The advantage of this is that you can select
and cost broader ranges (example: A to Z) and carry out costing in the background.
33
Costing variant controls calculation of planned and actual cost. Costing variant
is assigned to order type. Networks are of order category 20.
The valuation procedure is defined by valuation variant which is a component of
costing variant. Based on valuation variant prices are determined by the system to
value componenets material, activity type, processes, subcontracting and external
activities. Valuation variant searches for prices in sequence from the price sources.
Price entered first is selected first
Materials:Price is selected either from purchasing date or material master record
Activity type & Processes: Price is selected either from activity based costing or
cost center accounting
Externallly processed activity:price is selected either from the activity or from
purchasing information record
34
When customizing the order value update, you stipulate, for each order category and
type, whether the order or network is appended - that is, whether its planned costs are
added to the project cost plan for assigned WBS elements.
There are two tables for the order type (network type). The first is defined per order type,
the second (parameters for network) per order type and plant.
A third important table is the network profile, containing default values for the network and
its activities.
The costing variants for plan and actual costs are determined at network header level.
The costing sheet and overhead key are determined at activity level. They control process
cost accounting or application of overhead. Depending on the creation process, these
keys are inherited from the network header or the assigned WBS element.
35
The costing variant contains the basic control information needed to carry out
costing. The valuation variant contains all the information which controls the
valuation of:
Material components
Internal activities
External activities
This information also
controls how
overheads are
applied.
Valuation can be
determined plant by plant.
The "By period" indicator enables you to calculate costs for internally-processed
activities period by period.
The costing type contains further detailed information for controlling costing.
36
You can classify the resources in broadly 2 categories from the networks point of
view: Internal and external activities.
Internally processed activities: These activities / work are carried out by
machines and / or persons of own company. You can schedule the activities as
per requirement, distribute the work among persons.
Externally processed activities: these activities are executed / processed by other
companies. These are carried out by purchasing department. The service
activities are also procured externally however different from externally
processed activity that you need to define service specification and the limit for
the unplanned activities which is provided by the service provider.
37
Business scenario
To execute a project, materials are required
which can be procured externally (purchasing) or
manufactured in own company (Production). These
materials are managed in project-specific stock.
As the project controller, you are interested in:
The values in the project, at the different stages of purchasing or production
(project controlling)
Stocks of raw materials, semi-finished and finished products used for your project
38
(stock controlling)
Materials provide linkage between many other SAP functional modules like
Materials Management (Purchasing and Inventory Management), Sales and
Distribution, plant maintenance and Production Planning and Control.
The materials are assigned to activities which helps in material requirement and
planning in a project.
The product which is manufactured in your project is in turn made up of
a variety of material components.
The first step is to plan the procurement and consumption of the required
components in your project.
Projects are linked to Materials management, Sales and Distribution and
Production Planning via materials.
38
39
The item category "stock item" (L) is used for materials kept in stock. When you save
your data, the system creates a reservation for the required material. A purchase
requisition - which is passed on to Purchasing - can also be created for components
procured externally.
The main function of material requirements planning is to ensure material availability
(in other words, to procure the required quantities in time - both in-house and for sales
and distribution). This includes monitoring stocks and, above all, creating procurement
proposals for purchasing and production.
Independent requirements - that is, requirements for finished products, assemblies or raw
materials - trigger requirements planning. In order to cover the requirements, order
quantities and dates have to be determined, and the corresponding procurement elements
scheduled. The procurement element for requirements planning is a planned order and,
for external procurement, a purchase requisition. Furthermore, the dependent
requirements for materials produced in-house (in other words, the quantity of components
required to manufacture a finished product or assembly) are determined by exploding the
bill of material. Planned orders are created at each BOM level to cover requirements
when a material shortage occurs.
40
Once quantities and dates have been planned in requirements planning, these
planned procurement elements are converted to "exact" procurement elements: for
production, this is the production order and, for external procurement, the purchase
order. When the order or purchase order is being processed, the production order
is delivered or a goods receipt is posted to stock (plant stock or project/sales order
stock).
The goods issue that takes place as a result of this activity reduces the stock
and posts actual costs to the "consuming" network activity.
Item Category L (stock item) is used for components kept in stock .
Ensuring material availability is the main function of MRP which includes monitoring
stocks and creating procurement proposals for purchasing and production .
Requirement for finished products, saleable assemblies and spare parts
trigger requirement planning.
Order quantities and dates have to be determined in order to cover the
requirements .
For requirement planning the procurement element is the planned order and
for external procurement it is purchase requisition .
Planned procurement elements are converted into exact procurement elements
once the quantities and dates are planned.
It is Production order for production and purchase order for external procurement.
40
The item category "non-stock item" (N) is used for components that are not procured
by way of warehouse stock or project/sales order stock, but are procured directly by a
network activity instead.
Purchase requisitions are created for these components. These requisitions are passed
on directly to Purchasing. When the goods are received, they are not placed into stock,
but posted to the activity.
Non-stock items cannot be managed as project stock or sales order stock.
Non Stock Item (N) :
These are the items which are procured directly by network activity and not through
warehouse stock, project stock or sale order stock .
Purchase requisitions are created first and then passed directly to purchasing.
When the goods are received they are directly posted to activity .
Non stock items cannot be managed as project stock or sale order stock .
There are two procurement types for direct procurement with item category N :
41
41
42
For instance In this case the way in which the material can be procured
depends on both item category and material attributes.
43
43
44
The BOM transfer functionality in SAP PS helps you to assign the material from BOM to
the network activities based on the reference point field which is assigned to the material
and network activities.
WBS BOMs can be assigned to Project BOMs using the BOM Transfer transaction .
The corresponding selection parameters must be chosen to perform the same.
Advantage of BOM transfer functionality is that the changes in the BOM during the course
of the project will change in the activities (you need to run BOM-transfer again every time
you make changes in BOM).
You can also manually assign materials to network activities without reference point fields.
45
Reference point : This is the logical link between a BOM component and a
network activity. It ensures that the automatic assignment of the material
component happens correctly.
While the assignments by themselves are project specific, they can be made
simultaneously for a large number of networks in the project.
Individual components, individual BOM assemblies or a multi level BOM can
be assigned.
These assignments can happen manually without reference points as well.
Procedure For BOM Transfer:
Field in the BOM and the network activity which needs to be used as
the reference point needs to be specified.
These fields must have the same structure in both the objects. For
instance : CHAR, eight digits .
Possible entries for the reference point can be defined in
customizing.
Reference points in the BOM Components and the network activities
must be defined.
The BOM PS Interface must be started (after changing the BOM)
46
46
A material that you allocate to activities in a network can be kept in various stocks.
Depending on your project, you can access different types of stock for materials
planning:
Sales order stock and project stock are important for controlling purposes (for monitoring
the stock value in a sales order or project) and from an MRP point of view (the stocks
are reserved for the sales order item or WBS element; other stock elements cannot
access them).
The various stock types are managed for each material component using the account
assignment category. You define the account assignment category when you assign the
material to the network activity (popup in manual assignment, strategies in BOM-PS
interface and standard network).
The possible account assignment categories depend on the assignment of the network
activity to a stock object (WBS element or sales order item), on the item category for
the assignment (direct procurement for non-stock items) on the material master, which
can exclude collective or specialist stock management.
As of Release 4.5A, you can use MRP elements (grouping) to manage a joint project
stock for an entire project or for several projects (this is a rougher method than managing
stock per individual WBS element).
You maintain the account assignment categories possible for network purchase
47
requisitions in customizing.
47
Instead of managing the material either in a plant stock or for each individual WBS
element and having no control at all over procurement or being fully responsible we
can go for requirement grouping. Through requirement grouping we can determine
the degree of control ourselves.
Prerequisites for using requirement grouping :
Valuated group stock
Grouping WBS elements
MRP Groups that allow requirement grouping
Assigned components should have periodic lot sizes.
The most basic scenario involves grouping the requirement of all the WBS
elements in the project into one WBS element.
Or we can create projects which are only meant for grouping requirement of other
projects.
48
49
Valuated project stock must be allowed in the project definition control data.
With the exception of automatic requirement grouping MRP element indicator
must be set for WBS elements.
MRP groups involved in requirement grouping must be determined in customizing
for the WBS.
50
51
52
It is common in engineering projects for critical components with long and unreliable
delivery times to be purchased at an early stage in the project much before the
project activities in which the components will be used are specified. Advance
procurement process is used in such situations.
Advance procurement can only be used when you are using sales order or project
stock .
53
54
You can assign various SAP orders to a project; examples include internal orders,
production orders, and plant maintenance orders. You can then use the project
hierarchy reports to evaluate these assigned orders with the WBS element.
Each order is a cost object with its own costing parameters such as planned costing
variant, actual costing variant, and overhead sheet. The planned costs of assigned
orders are used to determine the planned costs of the project.
You assign orders to the project either by assigning a WBS element to the order
header or by assigning the order to a network and activity as a subnetwork. If the
assignment is required only for cost control and analysis, you need to assign order to
the relevant WBS element. If the assignment is required both for scheduling and
cost control, you need to assign the order as a subnetwork. The WBS element is
derived from the network activity. Note that production orders cannot be assigned as
subnetworks.
Documents are used to enter business transactions in the R/3
System. Orders are one type of business transaction.
Orders are determined by their order category.
The network is an order category. Order types are prescribed by the system for the
relevant applications.
You can define your own order types within an order category. The order type
describes how the order is controlled.
Customizing includes two tables, one for the order type and another for the
order type/plant combination.
The order type is used to control:
Number assignment
Default value settings
User-specific status management Userspecific field control
Plant and order type parameters are used to control:
If the network is activity- or header-assigned
Planned and actual costing variants
The settlement rule strategy
54
You can use the "appended" indicator to specify, per order category, whether an
order is appended - that is, whether the planned values for the order are included
in the planned value of the corresponding WBS element:
1. If the "appended" indicator is set, the order planned value increases the
WBS element planned value. The information system shows the total
as the project plan. When cost planning is taken over as the budget,
the values from appended orders also contribute to the budget.
2. If the "appended" indicator is not set, the order planned value is not
added to the WBS planned value. In budgeting, the plan total for such
orders must be added manually so that these orders can use funds
later.
55
You can use the "appended" indicator to specify, per order category, whether an
order is appended - that is, whether the planned values for the order are included
in the planned value of the corresponding WBS element:
Once released, all orders are apportioned - this means that their plan, commitment,
and actual values are funds assignments against the funds in the project. The
order value table contains an indicator which you can use to make orders
"apportioned" earlier, at the "created" stage.
You can set appended and apportioned indicator based on the order category,order
type, and controlling area
An exception to apportionment at release is in the case of networks for preliminary
planning.In Project System customizing,you can specify network types to be used
for preliminary planning.Preliminary planning networks are never apportioned.Their
related plan values do no increase the assigned value for the relevant WBS
element
In the case of networks (order category 20), you can use the network type
parameters to determine whether the network is:
Header-assigned or activity-assigned - that is, whether costs are managed in
the network activities or collected in the header
56
56
Header-Assigned Networks
In a Header-assigned networks all the costs (activity and material) are assigned at
network header level
After assignment of network header to a WBS element, All costs are transferred to
WBS element. Assignment of activities to WBS elements is only to summarize the
dates
We you have to use header-assigned networks to assign networks to sales order in
case sales order are not assigned to projects as no assignments can be made to a
sales order item in the network activity.
Activity-Assigned Networks
Costs are collected on activities in case activites are used as account assigned
objects.Plant/network type parameters deines the condition if the network header
or network activities are to be used as cost objects.
Activity- assigned networks are usually used when activities are assigned to various
WBS elements.Here every activity in the network is an account assignment object.
Which implies we can analyze planned costs, commitments and actual costs
for each activity.
The costs are aggregated and displayed for the WBS elements to which
the activities are assigned.
57
Activity account assignment is a special feature of networks. All other order types are
header-assigned. Activity account assignment is controlled via the appropriate
indicator in the table "Parameters for network type".
Header assigned networks should be used when networks are assigned to sales
orders without WBS.Header assigned networks can also be used when the
enitre network is assigned to a single WBS element
57
58
59
59
Activity-Based Costing offers a facility for allocating and distributing the overhead to its cause.
Activity-Based Costing provides useful information on:
Overheads reduction by process improvement
Profitability increase by highlighting unprofitable products or customers
Activity-Based Costing is advantageous for having:
Transparent overheads
Parallel quantity and value flows
Precise assignment of internal activities to consumer
Peanut butter effect" can be avoided through even distribution of overheads among all
the cost drivers.
60
In Activity-Based Costing, processes are the controlling objects. Prices can be either
maintained manually or using activity and cost input planning in the case of cost
centers and activity types. Through activity based costing, processes are debited to
cost objects or profitability segments.
60
Templates are created in Customizing and determined by controlling area, costing sheet,
overhead key and template environment (for networks 004; for WBS 005) for the
function. In the Project System, templates can be assigned to WBS elements, networks
(header assigned), or network activities. Process costs are allocated to cost objects or
profitability segments by assigning a process template. Process costs are calculated based
on the templates selected for the project.
61
project
The price for the process and the allocation cost element are determined by
entering one process per line in the process template. Multi-level processes can be
mapped by referencing another process template in the working template.
The quantity used by the cost object is determined using the cost driver. This enables
the allocation of the relevant values to all the levels in the process hierarchy as far
as cost objects or profitability segments.
Cost drivers can originate from many different sources in the R/3 System or external
systems. Examples : weight (material master), number of components, activities of a
particular category, work center (network), number of sales orders for market
segment (LIS) etc. The quantities determined by the cost driver are multiplied by the
price of the process. The resulting value is charged to the cost object (in the
example, the WBS or network/activity), and the process is credited.
61
Actual prices for activity types and business processes are calculated in Overhead
cost controlling at the end of the period.
Actual prices = Actual costs / Quantities consumed
The possibility of revaluation at actual prices and its specification for each
activity type are controlled in Customizing in the parameters for the actual
version depending on the fiscal year.
The difference between the actual price and the originally allocated price is
charged to the cost objects.
Revaluation at actual prices for activities and business processes can be done
in the Project System and in the Cost Object Controlling.
Revaluation at actual prices using an activity type is illustrated in the example given
in the slide
62
Overheads calculation is used to allocate overhead costs to cost objects such as activities
and WBS elements. Calculations are done based on the Costing sheet entered in
the cost object and the overhead key entered on the WBS element,
network header or network activity. Overheads can be calculated for
planned, commitment and actual values. Overhead calculations are
done using the quantity based or percentage allocation rates.
The following postings get generated through overheads allocation:
63
63
Costing sheet is derived by means of the costing variant from the "Parameters for
Network Type" table, in the case of networks. The costing sheet and the overhead key
can be changed in the network header.
The costing sheets to be used in the activities are made a default through this.
For WBS elements, the costing sheet is derived directly from the project profile. In
the case of Easy Cost Planning and the unit costing for WBS elements, the cost
planning draws on a costing sheet for a costing variant which is assigned to the
project profile through the planning profile.
Overhead keys for activities are inherited from their respective WBS elements.
64
65
networks/activities.
As part of the network costing, the system automatically determines planned
costs when you plan dates and resources for the following objects:
a. For internally processed activities: activity inputs
b. For externally processed activities & service activities: Primary costs
c. For genreal costs activities: primary costs
d. Material componenets: primeary costs.
You can use planning templates to create quantity structures for Easy Cost
Planning.
You can enter quantities and prices in the template, or regulate activation using
formulas or conditions.
You can use characteristics assigned to the planning template as variables for the
formulas/conditions. The characteristics are valued by the user when the
planning templates are copied into Easy Cost Planning.
66
Unit costing is done to calculate cost plan per WBS element. Here we use
planned quantities instead of cost.
It is not period dependent
At cost element level, plan values are displayed
Input information related to sources of supply, quantities and prices mark the use
of unit costing to generate cost plan per WBS element
67
68
68
The plan profile is used to control overall cost/revenue planning. It contains costing variants
for the unit costing or Easy Cost Planning.
It also contains indicators for updating revenue plan values via customer quotations or sales
orders.
You assign the plan profile to the project by way of the project profile. You can change it in the
project definition.
Costs and revenues can be planned in different CO plan versions.
You either specify the plan version during planning or, if you are using Easy Cost Planning,
you assign it to the controlling area.
Planning layouts are used to plan costs, revenues, payments, and statistical key figures.
You can use the Report Painter to create the layouts and can assign them to planner profiles.
Users can choose planner profiles and assign them to the user master record.
Planning profile: Use transaction OPSB
The Planning profile contains the settings related to planning. It control overall
cost/revenue planning. Planning profile is assigned to project using project profile. Costing
variant are
69
69
Planning profile is contains the settings for overall planning, detailed planning
and unit costing
Details for each field can be checked using
F1 Important field details are as:
Total Value: Defines overall planning without any reference to fiscal year
Annual Planning: Defines overall planning with reference to fiscal year
Bottom up Planning: Overall planning values are extrapolated after saving
Exchange rate type: Determines which exchange rate is to be used for currency
conversion of overall values
70
71
Internally-processed activities:
If no distribution key or work center is maintained in the activity, the costs are distributed
evenly over the earliest dates in the activity. Valuation is at the rate in the valuation variant.
Depending on the strategy being used, the system can determine the most current date.
valuation is determined by the rate maintained in the valuation variant. Based on the
strategy adopted, system determines the latest date. If no work center/distribution key is
maintained, the system distributes the cost evenly over the earliest dates.
Costs activity:
Case 1:Invoice plan maintained:the values in periods are as per the values mentioned
in invoicing plan
Case 2:Invoicing plan not maintained and distribution key maintained:The activity value
is
72
distributed to the periods based on the distribution key maintained in the activity
Case 3:Invoicing plan not maintained and distribution key not maintained:The
costs are distributed evenly over the earliest dates in the activity
If an invoicing plan has been maintained, the values in the periods are set
as specified in the invoicing plan.
Otherwise, the activity value is distributed to the periods using the distribution key in
the activity. If no distribution key is maintained in the activity, the costs are distributed
evenly over the earliest dates in the activity.
Service activities or externally-processed activities:
Case 1:Invoice plan maintained:the values in periods are as per the
values mentioned in invoicing plan
Case 2:Invoicing plan not maintained:The activity value is set in the period of the
latest activity start date.Also the system determines the price from the purchasing info
record or the activity value.
Invoicing plan has priority for the values
If an invoicing plan has been maintained, the values in the periods are set
as specified in the invoicing plan.
Otherwise, the activity value is set in the period of the latest activity start
date.
The invoicing plan has priority for the values. If no invoicing plan has been
maintained, the system determines the price from the purchasing info record or
the activity value.
Material components:
Case 1:Invoice plan maintained:the periods and ,in some cases,values are
taken from invoicing plan
Case 2:Invoicing plan not maintained:The system determines the price from the
purchasing info record or the price is taken from material master as per
valuation variant.Here material requirement date determines the period
If an invoicing plan has been maintained, the periods and, in some cases, the
values are taken from the invoicing plan. If no invoicing plan has been maintained,
the values are taken from the purchasing info record or the price is taken from the
72
material master per the valuation variant. In this case, the period is that from
the material requirements date.
72
The customer accepts the quotation. A sales order is created in the system, where
appropriate using the quotation as a template. The activities listed in the quotation
are entered in the sales order as sales order items.
The items are assigned to the project. They are used for revenue planning and for
posting revenues to the project by means of milestone billing.
Two companies are responsible for executing the project - IDES AG and IDES UK.
IDES UK creates a sales order for IDES AG and assigns the document item to the
billing element T-100##.1.2.
Later on, IDES UK bills its services to IDES AG on a resource-related basis.
A billing request is created in the system via resource-related billing. This is billed and
results in revenues for IDES UK.
73
74
Item Category
Item Category controls function for Sales Order like Item Type,
Pricing, Billing Plan, resource related or delivery related.
74
75
76
77
78
In the SD document, you can define a detailed billing plan with a number of billing dates
instead of just a single billing date. A billing plan is a schedule containing individual billing
data for a particular sales document.
Milestone billing is widely used in projects (for example, construction projects).
If you use milestone billing, the total value to be billed is apportioned to the individual dates
in the billing plan per defined rules.
Billing plan dates can be blocked for billing
You can set billing blocks manually or remove them by activating billing milestones.
As of Release 4.0, billing plans can also be entered for billing elements in projects. Such
billing plans can, if required, be copied to the sales order later (make sure you delete
any existing billing plan in the billing element; if you do not, the planned revenues will be
determined via the PS billing plan and not the SD billing plan).
A billing plan can contain down payment dates. These dates affect payment, but not
revenue.
79
80
The term "Version" is used in the project system in different contexts. Different
types of versions include simulation versions, project versions and CO planning
versions are available in SAP Project System which are discussed below.
Project versions, are snapshots of a project at a specific point in time, and are
used for documenting the progress of a project over time. Both quantities and
values are stored in versions and it can be created either manually, or
automatically when a status changes. In the case of status change, the project
profile contains a reference to a version profile which specifies the name of
the project version to be created when a particular user or system status is
set.
Simulation versions: In the Project System, these are versions that you can
change. You might, for example, create simulation versions in the following
situations:
In the quotation phase: generally speaking, at this stage there is not yet
an operative project.
To draw up alternative planning scenarios for existing operative projects
or parts of these.
CO plan versions are used to plan revenues and costs. You can copy values
from one version to another. You can change planned values manually in every
version and cost values are retained.
81
You can create simulation versions even at the time of execution of project,
where you can copy from operative to simulation versions, compare, analyze
and work with other versions and transfer them back to the operative
project.
The system performs the test run while transfer to check if the operative
or simulation version can be transferred.
82
83
When you transfer data from operative projects to simulation versions (or
vice versa), the following objects are copied:
Work breakdown structure
Milestones
Capacity requirements
Invoicing plan for the network, and billing plan for the WBS element
(as of Release 4.5A)
Production resources/tools
84
You can create a project version automatically (i.e. triggered by a system or user
status).
Data transfer when Version profile settings are used while using these transactions:
1. Status dependent project versions.
2. TC network maintenance CN22 or WBS element maintenance CJ02
Data transfer which is Independent of version profile and dependent on
database profile:
3. TC CN71 and CN72
4. Structure information system
85
85
You use a version profile to define two different kinds of information. First, you
specify which version is created automatically when a specific system status or
user status is set. Second, you specify which data is to be written to the
versions that are created automatically.
You need to define a version profile, if you wish to have versions created
automatically, or if you wish to generate versions directly when editing the WBS
or networks.
You do not need to define a version profile, if you wish to generate versions
manually from the Structure/Dates information system.
The version profile is entered in the project profile and network profile.
86
Project planning board is a tool in SAP PS which helps and enable you to
process / edit the entire project structure which are WBS element, activities,
relationships, milestones, material components, PS texts, documents and
assigned objects to them.
It is similar to Gantt chart based on interactive SAP environment.
This comprises of hierarchy structure of your project and the corresponding
date situation.
You can custom made the display in project planning board to suite your
requirement.
Project planning board can also be useful for planning dates and resources
i.e. work, external processing, for planning costs using activities.
87
Project planning board profile contains default values for the appearance
of planning board.
The settings in this project planning board profile is valid for both, simulation
versions and operative projects.
The graphical display can be changed and adapt as per user needs in
the planning board and customization using project planning board
assistant.
88
Project planning board is a graphical interface based on Gantt chart which can
be used for creating and maintaining data like project definition, WBS element,
activities, relationships, milestones, documents and PS texts.
Useful for Scheduling and monitoring.
You can view date view, and other overviews of project at the bottom of Gantt
chart like capacity overview.
You can view logs, hierarchal graphic of WBS element and Networks and
network activities.
This is the only transaction where we can change simulation versions for
releases earlier than SAP R34.6C, i.e. create of change of WBS elements
in simulation version based on the user specific options.
The entire period in the project planning board screen is called as Evaluation
period which consists of Pre-evaluation period, Planning period and Postevaluation period. These are defined by time settings and determined by 3
profiles which are created in customizing and assigned to project planning board
profile.
89
90
Also, the calculated cost will be transferred from network the sales order.
While saving the sales document, WBS element structure & project definition will
be created which is identified by sales order number.
Since the sales document and the project is directly connected, any changes
one object will update / reflect in other automatically.
90
The requirement class which is assigned with the sales order while creating it will
start assembly processing, one assembly order automatically created by system
and start assembly processing in the back ground. By this method MRP is ignored
and an operational order created directly from Sales Order.
Below is the list of Assembly order which can be created:Network, Production Order, planned order, Plant maintenance or Service order and
Process Order.
Assembly Processing contains all the date of Sales order and assembly order. So
if there is any change done later to any document it will reflects in both document.
91
92
93