Information Check List: Evaluating Weather Delay EOT Claims

This document provides information for evaluating claims for extensions of time due to inclement weather. It defines what constitutes inclement weather and the requirements for a valid weather delay claim, including that the delay must be outside the contractor's control, impact the critical path of work, and not have been reasonably allowed for in the project schedule. It describes the types of authoritative weather data and construction records needed to support a claim, and notes that the work must be of a type affected by weather conditions. Flow charts and bar diagrams are recommended to show how the weather delay disrupted the planned work schedule.

Uploaded by

vinayak_geotech
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
83 views2 pages

Information Check List: Evaluating Weather Delay EOT Claims

This document provides information for evaluating claims for extensions of time due to inclement weather. It defines what constitutes inclement weather and the requirements for a valid weather delay claim, including that the delay must be outside the contractor's control, impact the critical path of work, and not have been reasonably allowed for in the project schedule. It describes the types of authoritative weather data and construction records needed to support a claim, and notes that the work must be of a type affected by weather conditions. Flow charts and bar diagrams are recommended to show how the weather delay disrupted the planned work schedule.

Uploaded by

vinayak_geotech
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

rjha limited

Inclement Weather Extension of Time Claims Information Sheet

Information Check List

Descriptor

Definition of Inclement Weather

Time Loss

Requisite

1.

It has to be an excusable
non-compensable delay.

Outside of the contractors


control

2.

It has to cause a delay to an


activity on the critical path.

That cannot be made up by


any other means

3.

It has to relate to progress


that the contractors
programme indicated should
have been achieved at that
time.

It is not permissible for the


contractors own late
delivery problems to be
ignored in assessing why the
delay has occurred

1.

Has to be genuine.

That cannot be made up by


any other means

2.

Has to be beyond what


might have been allowed for.

The contractors programme


allowance should reflect a
period for inclement days
that would normally be
expected

Typically this should be


shown as an activity at the
end of the programme
preceding the completion
date

Should be shown as 5, 10, 15


etc. days depending on
period of project and time of
year work is undertaken

Precipitation in mm

3.

Has to be weather subject to


extremes.

4.

Not as expected for the


period it occurred.

5.

Characteristic Data

Authorative Data

Construction Methodology

Notes

Could not have been


forecast by using historical
records.

1.

Data that reflects patterns


over months or days.

Wind Speed km/h

2.

Data sourced from records


for a defined period typically
5 or 10 year period reviews.

Temperature Degrees C

1.

Site Diary Notes.

Contractor must record daily

2.

NIWA Records.

Available as Public Record

1.

Is the work placement


subject to climatic conditions

Roading

Paint System Curing etc.

Evaluating Weather Delay EOT Claims

rjha limited

rjha limited

Inclement Weather Extension of Time Claims Information Sheet

Descriptor

Requisite

Supporting Information

1.

Notes

Notes

Flow Chart or Bar Diagrams


showing what was planned
and how the delay has
disrupted the work flow in
relation to the Critical Path

2.

Bar Chart Information

Wind Delay Bar


Rain Delay Bar
Temperature Delay Bar
Safety Delay Bar
Re work Delay Bar

Consider

Temperature affected work

Relative Humidity affected


work

Curing

Clean Up

Actions / Information Needs

Evaluating Weather Delay EOT Claims