Chapter 04 Defining The Project

This document contains 30 multiple choice questions about defining projects and key project elements like work breakdown structures (WBS), organization breakdown structures (OBS), responsibilities matrices, and project scope. It tests understanding of how to collect information throughout a project's life cycle using tools like the WBS, how to develop project deliverables and work packages, and how to integrate the project structure with the organizational structure using the OBS and responsibilities matrix. The questions cover topics like the levels of the WBS, what should and should not be included in work packages, defining a project's objectives and scope, and common risks to project success like scope creep.

Uploaded by

PKyromitis
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
963 views7 pages

Chapter 04 Defining The Project

This document contains 30 multiple choice questions about defining projects and key project elements like work breakdown structures (WBS), organization breakdown structures (OBS), responsibilities matrices, and project scope. It tests understanding of how to collect information throughout a project's life cycle using tools like the WBS, how to develop project deliverables and work packages, and how to integrate the project structure with the organizational structure using the OBS and responsibilities matrix. The questions cover topics like the levels of the WBS, what should and should not be included in work packages, defining a project's objectives and scope, and common risks to project success like scope creep.

Uploaded by

PKyromitis
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 7

Chapter04DefiningtheProject

1.Themethodusedtocollectinformationtousethroughallphasesoftheprojectlife
cycleiscalled
A.Responsibilitymatrix
B.Organizationbreakdownstructure
C.Workbreakdownstructure
D.Prioritymatrix
E.Workpackage
2.Joseislookingatadocumentthatoutlinesthespecifictasksandsubtasksrequiredto
completethewritingofatechnicalsupportmanual.Themethodthatwasprobablyused
todevelopthedocumentismostlikely
A.Responsibilitymatrix
B.Organizationbreakdownstructure
C.Workbreakdownstructure
D.Prioritymatrix
E.Workpackage
3.Thefirststepincreatingthenecessaryinformationtomanageaprojectisto
A.Establishprojectpriorities
B.Definetheprojectscope
C.Verifythebudgetavailable
D.Assignteammemberstoworkontheproject
E.Determinetherequiredcompletiondate
4.Lindahasjustbeenassignedaprojecttodevelopanewadvertisingcampaignforan
establishedproduct.Herfirststepshouldbeto
A.Establishprojectpriorities
B.Definetheprojectscope
C.Verifythebudgetavailable
D.Assignteammemberstoworkontheproject
E.Determinetherequiredcompletiondate
5.Researchshowsthemostfrequentlymentionedbarriertoprojectsuccessis
A.Notenoughbudgetresources
B.Poorperformancebyteammembers
C.Weakprojectleadership
D.Poorlydefinedscopeormission
E.Politicalinfighting
6.Anexpectedoutputoverthelifeofaprojectwouldbeclassifiedas
A.Adeliverable
B.Aproduct
C.Anendobject

D.Anobjective
E.Atarget
7.Thefirststepofprojectscopedefinitionisto
A.Analyzethestrategicplan
B.Analyzethecurrentbudgetplan
C.Meetwithteammembers
D.Selectteammembers
E.Definetheoverallobjectivetomeetthecustomer'sneeds
8.Inreviewingtheprojectplan,SusanseesthatthefirstprototypeisduebyOctober12.
Thiswouldbebestclassifiedasa
A.Projecttarget
B.Limititem
C.Milestone
D.Projectobjective
E.Criticalgoal
9.Theabilityof911emergencysystemstoidentifythecaller'sphonenumberand
locationareconsideredtobea
A.Technicalrequirement
B.Milestone
C.Projectlimit
D.Projectexclusion
E.Projectdeliverable
10.Whichofthefollowingisnotoneoftheitemsthatwouldappearonaprojectscope
checklist?
A.Deliverables
B.Technicalrequirements
C.Objectives
D.Workbreakdownstructure
E.Reviewswithcustomer
11."Toconstructahighquality,customhomewithinfivemonthsatcostsnottoexceed
$150,000"isbestclassifiedas
A.Adeliverable
B.Amilestone
C.Anobjective
D.Alimit
E.Anexclusion
12.Thesecondstepinthedefiningofaprojectwouldbeto
A.Analyzethestrategicplan
B.Analyzethecurrentbudgetplan
C.Establishprojectpriorities

D.Selectteammembers
E.Definethemajorobjectivestomeetthecustomer'sneeds
13.Whichofthefollowingisnotoneofthebasicclassificationsofprojectpriorities?
A.Profit
B.Cost
C.Time
D.Performance
E.Allofthesearebasicclassifications
14.Ifaprojectcriterionindicatesthattheprojectmustmeetaspecificdate,thatcriterion
isclassifiedas
A.Constrained
B.Enhanced
C.Accepted
D.Limited
E.Fixed
15.Scotthasjustbeengivenaprojectthathasaspecifictargetdate.Afterdiscussion
withtopmanagementhefindsthatwhilethedateisimportantthecostismoreimportant
andaslipindeliverywouldbeacceptableifrequiredtomeetthecosttargets.Thetarget
dateisbestclassifiedas
A.Constrain
B.Enhance
C.Accept
D.Limit
E.Optional
16.Thetoolusedtoassistinmakingprojecttradeoffsbetweenschedule,budget,and
performanceobjectivesiscalleda
A.Responsibilitymatrix
B.Workbreakdownstructure
C.Projectprioritymatrix
D.Workpackage
E.Criterionmatrix
17.ThelowestelementinthehierarchicalbreakdownoftheWBSis
A.Adeliverable
B.Aworkpackage
C.Acostaccount
D.Alowestsubdeliverable
E.Anobject

18.ThehighestelementinthehierarchicalbreakdownoftheWBSis
A.Aworkpackage
B.Subdeliverables
C.Acostaccount
D.Majordeliverables
E.Theproject
19.Allofthefollowingaretrueaboutworkpackagesexcept
A.Consumeresources
B.Assignedtoonlyonemanager
C.Havemediumtolongduration
D.Definitivestartsandstopsdates
E.Allofthesearetrue
20.Allofthefollowingareusuallyincludedinaworkpackageexcept
A.Whatwillbedone?
B.Thetimeneededtocompletethework.
C.Asinglepersonwhoisresponsibleforitscompletion.
D.Allthecostsfortheworkpackage.
E.Alloftheseareincludedinaworkpackage.
21.Theintegrationofprojectworkpackageswithintheorganization'smanagement
structureisknownas
A.Responsibilitymatrix
B.Organizationbreakdownstructure
C.Workbreakdownstructure
D.Prioritymatrix
E.Processbreakdownstructure
22.ThefinalstepinthecreationofaWorkBreakdownStructureisto
A.CodetheWBSfortracking
B.Assignthecostaccounttoamanager
C.Assigntheworkpackagetoamanager
D.Developtheresponsibilitymatrix
E.Alloftheseareincludedinthefinalstep
23.TheintersectionoftheWBSandtheOBSiscalledthe
A.Responsibilitymatrix
B.Prioritymatrix
C.Workpackage
D.Costaccount
E.Projectoverlap
24.Creatinganextranetwebsiteoraninternalsoftwaredatabasesystemwouldbemost
closelyassociatedwiththe

A.Responsibilitymatrix
B.Organizationbreakdownstructure
C.Workbreakdownstructure
D.Prioritymatrix
E.Processbreakdownstructure
25.Ifaprojectissmallorofnarrowscopeanddoesnotrequireanelaboratesystem,
whichofthefollowingisagoodchoice?
A.Responsibilitymatrix
B.Organizationbreakdownstructure
C.Workbreakdownstructure
D.Prioritymatrix
E.Processbreakdownstructure
26.Theprojectscopestatementindicatesthattheclientisresponsiblefortrainingthe
peoplewhowillbeusingtheequipmentandthattheprojectteamwilltraintheclient's
trainers.Thisisanexampleof:
A.Projectobjectives
B.Deliverables
C.Limitsandexclusions
D.Technicalrequirements
E.Milestones
27.Thetendencyfortheprojectdeliverablestoexpandovertimeusuallybychanging
requirements,specifications,andprioritiesiscalled:
A.Scopeerosion
B.Scopecreep
C.Projectbloat
D.Scopeenhancement
E.Projectaddons
28.WhichofthefollowingisagoodexampleofaProcessBreakdownStructure?
A.Newcarprototype
B.Newsoftwareprogram
C.Newcomputerhardware
D.Newsportsstadium
E.Newprojectmanagementbook
29.WhichofthefollowisleastlikelytobeincludedinaWorkPackage?
A.Materials
B.Labor
C.Overhead
D.Duration

E.Responsibilities
30.TheSnapshotfromPracticedealingwithBigBerthaIIillustratedhowimportanta
project's__________istothesuccessfulcompletionofaproject.
A.Objective
B.Deliverables
C.Technicalrequirements
D.Milestones
E.Limitsandexclusions

Chapter04DefiningtheProject
1=C
2=C
3=B
4=B
5=D
6=A
7=E
8=C
9=A
10=D
11=C
12=C
13=A
14=A
15=C
16=C
17=B
18=E
19=C
20=E
21=B
22=A
23=D
24=C

25=A
26=C
27=B
28=B
29=C
30=C