Unit Shut Down Procedure
Unit Shut Down Procedure
DOWN
PROCEDURE
PMI Revision 00
Presentation outline
Planned Shut Down procedure
APH Washing
Hydrogen purging
ATT
PMI Revision 00
PMI Revision 00
Planned shutdown
Preparation for shut down.
Mobilization of resources for overhauling- Manpower ,
Spares, consumables
Identification all Jobs to be carried out.
Carry out performance testing and identify performance
gaps, parameter deviations and action plan for rectification.
Necessary clearance from RLDC/bulk customers .
PMI Revision 00
Activities
All coal bunkers should be preferably made empty before
long shut down. Stop/ regulate coal feeding to bunkers
accordingly.
Charging of auxiliary steam from other unit.
Ensure availability of all oil guns.
Take trial run of all emergency equipments like Dc Scanner
air fan, DC EOP,DC SOP, DG set etc.
Ensure SGC oil and SLC of oil system is ON
PMI Revision 00
PMI Revision 00
PMI Revision 00
PMI Revision 00
PMI Revision 00
PMI Revision 00
10
PMI Revision 00
11
PMI Revision 00
12
PMI Revision 00
13
PMI Revision 00
14
PMI Revision 00
15
PMI Revision 00
16
PMI Revision 00
17
PMI Revision 00
18
PMI Revision 00
19
PMI Revision 00
20
PMI Revision 00
21
APH WASHING.
Purpose- for cleaning of baskets of air heater
High pressure water jet is used
Washing to be carried out when the air heater is in
hot condition (Temp.about 200oC).immediately after
boiler shut down
Open the r plugs of APH ash hopper
Open the duct drains of SA and PA ducts
PMI Revision 00
22
PMI Revision 00
23
Hydrogen Purging.
Ensure that the generator is tripped condition
Reduce the Hydrogen pressure to 0.5 KSC by opening the
purge valve.
Connect CO2 cylinders to the filling manifold.
Start filling CO2 through the CO2filling valve
Crack open the purge valve to maintain the casing pr. At 0.5
ksc
Continue filling CO2 till purity of 95% is achieved.
PMI Revision 00
24
PMI Revision 00
25
PMI Revision 00
26
SALIENT FEATURES
Individual testing of each protective device and stop/control
valve assembly.
Automatic functional protective substitute devices that
protect turbine during ATT.
Only its pretest is carried out without any faults i.e. if the
substitute circuit is healthy, the main test begins.
.
PMI Revision 00
27
PMI Revision 00
28
PMI Revision 00
29
AUTOMATIC TESTING OF
PROTECTIVE DEVICES
ATT sub group for protective devices covers the following
devices.
1. Remote trip solenoid-1.
2. Remote trip solenoid-2.
3. Over speed trip device.
4. Hydraulic low vacuum trip device.
5. Thrust bearing trip device.
PMI Revision 00
30
PMI Revision 00
31
PMI Revision 00
32
PMI Revision 00
33
PMI Revision 00
34
PMI Revision 00
35
SWITCHYARD OPERATION
Co-ordination with RLDC for unit synchronization,
line charging etc.
Line up of electrical systems
Ensuring healthiness of switchyard equipments like
transformers, breakers, isolators, CTs etc.
PMI Revision 00
36
PMI Revision 00
37
PMI Revision 00
38
Charging of transmission
line
PMI Revision 00
39
PMI Revision 00
40
THANK YOU
PMI Revision 00
41