100% found this document useful (1 vote)
3K views2 pages

Tile Work Checklist

This document is a checklist for inspecting tile work on walls and floors of a construction project. It lists 14 items to check, including using the approved tile materials, ensuring tiles are the proper color and size, that mechanical, electrical, and plumbing work is complete beforehand, and that tiles are installed according to specifications and manufacturer instructions. The checklist is used to inspect tile installation and ensure it meets standards before final approval.

Uploaded by

Mohdali416
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
3K views2 pages

Tile Work Checklist

This document is a checklist for inspecting tile work on walls and floors of a construction project. It lists 14 items to check, including using the approved tile materials, ensuring tiles are the proper color and size, that mechanical, electrical, and plumbing work is complete beforehand, and that tiles are installed according to specifications and manufacturer instructions. The checklist is used to inspect tile installation and ensure it meets standards before final approval.

Uploaded by

Mohdali416
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
You are on page 1/ 2

TILE WORK - WALL & FLOOR CHECKLIST

Project:

WIR Ref:

Client :

Checked Date

Consultant :

Inspection Date

Contractor :

Sub - Contractor:

Construction Drawing No (s) :


Building Zone:

Level:

Item/Structure Description:
Sr. No

Description

Approved Tile Material & Mortar/Glue

Calibration of the tiles checked, different


batches checked for variance in colour
shades

MEP services completed and confirmed


with MEP Sub-Contractor

Tiles soaked in clean water as specified

Mixing and application of dry mortar for


floors done to the specified slope

Mixing and application of adhesive done


as recommended by the manufacturer

Setting of tiles done as specified in the


shop drawings

Trimmers and spacers fixed at specified


places

Skirting / wall tiles laid as specified

10

Debonded tiles are replaced

11

Mixing and application of approved


colour grout done as recommended
by the manufacturer

12

Cut tiles are properly aligned

Grid Line:
Checked

Comments

YES NO NA

Must, if answer is 'NO'

Floor Tiles joints are matched with


wall tile joints
Cleaning and final inspection carried
14
out
Designation
Name
Company Signature
13

Civil Engineer

MEP Engineer

QC Engineer

Sub-Contractor

Date

Surveyour

Tile Work - Wall & Floor


Checklist

Rev:00