Rodolfo Castillo: 1 Project Schedule Precon Submtl 2 3.4 N/A A N
Rodolfo Castillo: 1 Project Schedule Precon Submtl 2 3.4 N/A A N
DATE
TRANSMITTAL NO.
05/28/2015
01 32 01.00 10-1
FROM:
a.
W91278-13-D-0012 0005
Tarapoto,
b.
Project Schedule
PRECON SUBMTL
NO.
OF
COPIES
d.
CONTRACT REFERENCE
DOCUMENT
SPEC.
PARA. NO.
e.
3.4
DRAWING
SHEET NO.
f.
CHECK ONE:
X THIS IS A NEW TRANSMITTAL
THIS IS A RESUBMITTAL OF
TRANSMITTAL ___________
CHECK ONE: THIS TRANSMITTAL IS
FOR
FIO X GA
DA
CR
FOR
VARIATION
CONTRACTOR
(See
USE CODE
Instruction
No. 6)
N/A
g.
h.
FOR
CE
USE
CODE
i.
REMARKS
Rodolfo
Castillo
(ER 415-1-10)
SHEET 1 OF 1
DATE
(Proponent: CEMP-CE)
CONTRACT:
W91278-13-D-0012
Task Order 0005
DESIGN / BUILD
FIVE BRIDGES UPPER HUALLAGA VALLEY
LEONCIO PRADO, PERU
PROJECT SCHEDULE
AGUAJE BRIDGE
Id
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
Texto1
Task Name
Duracin
01 PUENTE AGUAJE
01.01
DEMOLICION DE ESTRUCTURAS EXISTENTES
01.01.01
DEMOLICION DE CONCRETO SIMPLE
01.01.02
ELIMINACION MATERIAL EXCEDENTE EN CARRETILLA (50 M )
01.01.03
DESMONTAJE PUENTE MADERA ROLLIZA
01.02
TRABAJOS EN EL SITIO
01.02.01
ALMACEN Y GUARDIANIA
01.02.02
TRAZO Y REPLANTEO
01.02.03
MOVILIZACION Y DESMOVILIZACION DE EQUIPO
01.02.04
ENERGIA ELECTRICA TEMPORAL
01.03
ACCESOS DE PUENTE
01.03.01
MOVIMIENTO DE TIERRAS
01.03.01.01
EXCAVACION CON EQUIPO EN ACCESOS
01.03.01.02
CONFORMACION DE TERRAPLENES EN ACCESOS, CAPAS DE E=0.20 m.
01.03.02
CUNETAS DE DRENAJE PLUVIAL
01.03.02.01
PERFILADO DE CUNETAS C/MAQ.
01.03.02.02
CONCRETO F'C=210 KG/CM2 EN CUNETAS
01.03.02.03
ACERO DE REFUERZO FY=4200 KG/CM2 GRADO 60 EN CUNETAS
01.03.02.04
ENCOFRADO Y DESENCOFRADO EN CUNETAS
01.03.02.05
JUNTA DE DILATACION EN CUNETAS
01.03.03
LOSA DE APROXIMACION
01.03.03.01
PERFILADO PARA LOSA DE APROXIMACION
01.03.03.02
CONCRETO F'C=210 KG/CM2 EN LOSA DE APROXIMACION
01.03.03.03
ACERO DE REFUERZO FY=4200 KG/CM2 GRADO 60 EN LOSA DE APROXIMACION
01.03.03.04
ENCOFRADO Y DESENCOFRADO EN LOSA DE APROXIMACIN
01.03.03.05
JUNTA DE DILATACIN EN LOSA DE APROXIMACIN/ESTRIBO
01.04
ACCESOS PROVISIONAL
01.04.01
MEJORAMIENTO ACCESO PROVISIONAL
01.05
SUB ESTRUCTURA
01.05.01
MOVIMIENTO DE TIERRAS
01.05.01.01
EXCAVACION DE TIERRA BAJO AGUA C/MAQ.
01.05.01.02
EXCAVACION DE TIERRA EN TERRENO ARCILLOSO C/MAQ. EN ESTRIBOS
01.05.01.03
RELLENO CON MATERIAL PROPIO SELECCIONADO EN ESTRIBOS
01.05.01.04
CAMA DE ARENA CON MATERIAL GRANULAR
01.05.02
OBRAS DE CONCRETO SIMPLE
01.05.02.01
SOLADO DE CONCRETO DE 4"
01.05.02.02
CONCRETO F'C=210 KG/CM2 EN ESTRIBOS + 30% P.G.
01.05.02.03
ENCOFRADO Y DESENCOFRADO CARAVISTA EN ESTRIBOS
01.05.03
DRENAJE
01.05.03.01
TUBERIA PVC CLASE 10, 3"
01.06
SUPERESTRUCTURA
01.06.01
OBRAS DE CONCRETO ARMADO
01.06.01.01
CONCRETO ARMADO F'C=280 KG/CM2 EN SUPERESTRUCTURA
01.06.01.02
ENCOFRADO Y DESENCOFRADO CARAVISTA EN SUPERESTRUCTURA
01.06.01.03
ACERO DE REFUERZO FY=4200 KG/CM2 GRADO 60 EN SUPERESTRUCTURA
01.06.01.04
FALSO PUENTE
01.06.02
JUNTAS
01.06.02.01
JUNTA DE DILATACIN APOYO FIJO
01.06.02.02
JUNTA DE DILATACIN APOYO MVIL
Comienzo
Fin
100 das
lun 01/06/15 mi 09/09/15
4 das mar 02/06/15 sb 06/06/15
3 das mar 02/06/15
vie 05/06/15
3 das mi 03/06/15 sb 06/06/15
1 da
jue 04/06/15
vie 05/06/15
5 das
lun 01/06/15 sb 06/06/15
2 das
lun 01/06/15 mi 03/06/15
2 das mi 03/06/15
vie 05/06/15
1 da
vie 05/06/15 sb 06/06/15
1 da mi 03/06/15
jue 04/06/15
38 das sb 04/07/15 mar 11/08/15
24 das sb 04/07/15 mar 28/07/15
4 das sb 04/07/15 mi 08/07/15
20 das mi 08/07/15 mar 28/07/15
14 das mar 28/07/15 mar 11/08/15
1 da mar 28/07/15 mi 29/07/15
4 das
jue 06/08/15
lun 10/08/15
4 das mi 29/07/15 dom 02/08/15
4 das dom 02/08/15
jue 06/08/15
1 da
lun 10/08/15 mar 11/08/15
13 das mar 28/07/15
lun 10/08/15
1 da mar 28/07/15 mi 29/07/15
3 das
jue 06/08/15 dom 09/08/15
4 das mi 29/07/15 dom 02/08/15
4 das dom 02/08/15
jue 06/08/15
1 da dom 09/08/15
lun 10/08/15
3 das sb 06/06/15 mar 09/06/15
3 das sb 06/06/15 mar 09/06/15
31 das mar 09/06/15
vie 10/07/15
24 das mar 09/06/15
vie 03/07/15
2 das
jue 11/06/15 sb 13/06/15
2 das mar 09/06/15
jue 11/06/15
3 das mar 30/06/15
vie 03/07/15
2 das sb 13/06/15
lun 15/06/15
25 das
lun 15/06/15
vie 10/07/15
1 da
lun 15/06/15 mar 16/06/15
18 das
jue 18/06/15
lun 06/07/15
24 das mar 16/06/15
vie 10/07/15
1 da mar 16/06/15 mi 17/06/15
1 da mar 16/06/15 mi 17/06/15
37 das mar 28/07/15
jue 03/09/15
35 das mar 28/07/15 mar 01/09/15
6 das mi 26/08/15 mar 01/09/15
10 das dom 09/08/15 mi 19/08/15
8 das mar 18/08/15 mi 26/08/15
10 das mar 28/07/15
vie 07/08/15
17 das dom 09/08/15 mi 26/08/15
1 da mar 25/08/15 mi 26/08/15
1 da mar 25/08/15 mi 26/08/15
junio
julio
agosto
septiembre
17/05 24/05 31/05 07/06 14/06 21/06 28/06 05/07 12/07 19/07 26/07 02/08 09/08 16/08 23/08 30/08 06/09 13/09 2
Task
External Milestone
solo duracin
Hito externo
Split
Tarea inactiva
Progress
Milestone
Hito inactivo
Resumen manual
Deadline
Summary
Hito inactivo
solo el comienzo
Project Summary
Resumen inactivo
solo fin
External Tasks
Tarea manual
Tareas externas
Page 1
Id
Texto1
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
01.06.02.03
01.06.03
01.06.03.01
01.06.04
01.06.04.01
01.06.05
01.06.05.01
01.07
01.07.01
01.08
01.08.01
01.08.02
01.08.03
01.08.04
01.08.05
01.08.06
01.09
01.09.01
Task Name
Duracin
Comienzo
1 da dom 09/08/15
10 das dom 16/08/15
10 das dom 16/08/15
1 da dom 09/08/15
1 da dom 09/08/15
2 das mar 01/09/15
2 das mar 01/09/15
1 da
jue 03/09/15
1 da
jue 03/09/15
13 das
vie 03/07/15
3 das
vie 03/07/15
10 das
lun 06/07/15
4 das dom 12/07/15
4 das dom 12/07/15
3 das sb 04/07/15
5 das sb 04/07/15
6 das
jue 03/09/15
6 das
jue 03/09/15
Fin
lun 10/08/15
mi 26/08/15
mi 26/08/15
lun 10/08/15
lun 10/08/15
jue 03/09/15
jue 03/09/15
vie 04/09/15
vie 04/09/15
jue 16/07/15
lun 06/07/15
jue 16/07/15
jue 16/07/15
jue 16/07/15
mar 07/07/15
jue 09/07/15
mi 09/09/15
mi 09/09/15
junio
julio
agosto
septiembre
17/05 24/05 31/05 07/06 14/06 21/06 28/06 05/07 12/07 19/07 26/07 02/08 09/08 16/08 23/08 30/08 06/09 13/09 2
Task
External Milestone
solo duracin
Hito externo
Split
Tarea inactiva
Progress
Milestone
Hito inactivo
Resumen manual
Deadline
Summary
Hito inactivo
solo el comienzo
Project Summary
Resumen inactivo
solo fin
External Tasks
Tarea manual
Tareas externas
Page 2
CONTRACT:
W91278-13-D-0012
Task Order 0005
DESIGN / BUILD
FIVE BRIDGES UPPER HUALLAGA VALLEY
LEONCIO PRADO, PERU
PROJECT SCHEDULE
TARAPOTO BRIDGE
Id
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
Texto1
Task Name
Duracin
01 PUENTE TARAPOTO
01.01
DEMOLICION DE ESTRUCTURAS EXISTENTES
01.01.01
DEMOLICION DE CONCRETO SIMPLE
01.01.02
ELIMINACION MATERIAL EXCEDENTE EN CARRETILLA (50 M )
01.01.03
DESMONTAJE PUENTE MADERA ROLLIZA
01.02
TRABAJOS EN EL SITIO
01.02.01
ALMACEN Y GUARDIANIA
01.02.02
TRAZO Y REPLANTEO
01.02.03
MOVILIZACION Y DESMOVILIZACION DE EQUIPO
01.02.04
ENERGIA ELECTRICA TEMPORAL
01.03
ACCESOS DE PUENTE
01.03.01
MOVIMIENTO DE TIERRAS
01.03.01.01
EXCAVACION CON EQUIPO EN ACCESOS
01.03.01.02
CONFORMACION DE TERRAPLENES EN ACCESOS, CAPAS DE E=0.20 m.
01.03.02
CUNETAS DE DRENAJE PLUVIAL
01.03.02.01
PERFILADO DE CUNETAS C/MAQ.
01.03.02.02
CONCRETO F'C=210 KG/CM2 EN CUNETAS
01.03.02.03
ACERO DE REFUERZO FY=4200 KG/CM2 GRADO 60 EN CUNETAS
01.03.02.04
ENCOFRADO Y DESENCOFRADO EN CUNETAS
01.03.02.05
JUNTA DE DILATACION EN CUNETAS
01.03.03
LOSA DE APROXIMACION
01.03.03.01
PERFILADO PARA LOSA DE APROXIMACION
01.03.03.02
CONCRETO F'C=210 KG/CM2 EN LOSA DE APROXIMACION
01.03.03.03
ACERO DE REFUERZO FY=4200 KG/CM2 GRADO 60 EN LOSA DE APROXIMACION
01.03.03.04
ENCOFRADO Y DESENCOFRADO EN LOSA DE APROXIMACIN
01.03.03.05
JUNTA DE DILATACIN EN LOSA DE APROXIMACIN/ESTRIBO
01.04
ACCESOS PROVISIONAL
01.04.01
MEJORAMIENTO ACCESO PROVISIONAL
01.05
SUB ESTRUCTURA
01.05.01
MOVIMIENTO DE TIERRAS
01.05.01.01
EXCAVACION DE TIERRA BAJO AGUA C/MAQ.
01.05.01.02
EXCAVACION DE TIERRA EN TERRENO ARCILLOSO C/MAQ. EN ESTRIBOS
01.05.01.03
RELLENO CON MATERIAL PROPIO SELECCIONADO EN ESTRIBOS
01.05.01.04
CAMA DE ARENA CON MATERIAL GRANULAR
01.05.02
OBRAS DE CONCRETO SIMPLE
01.05.02.01
SOLADO DE CONCRETO DE 4"
01.05.02.02
CONCRETO F'C=210 KG/CM2 EN ESTRIBOS + 30% P.G.
01.05.02.03
ENCOFRADO Y DESENCOFRADO CARAVISTA EN ESTRIBOS
01.05.03
DRENAJE
01.05.03.01
TUBERIA PVC CLASE 10, 3"
01.06
SUPERESTRUCTURA
01.06.01
OBRAS DE CONCRETO ARMADO
01.06.01.01
CONCRETO ARMADO F'C=280 KG/CM2 EN SUPERESTRUCTURA
01.06.01.02
ENCOFRADO Y DESENCOFRADO CARAVISTA EN SUPERESTRUCTURA
01.06.01.03
ACERO DE REFUERZO FY=4200 KG/CM2 GRADO 60 EN SUPERESTRUCTURA
01.06.01.04
FALSO PUENTE
01.06.02
JUNTAS
01.06.02.01
JUNTA DE DILATACIN APOYO FIJO
01.06.02.02
JUNTA DE DILATACIN APOYO MVIL
01.06.02.03
NEOPRENE SHORE DE (0.45 X 0.30 X 0.05)
01.06.03
BARANDAS
01.06.03.01
BARANDAS METALICAS INC. ARENADO, TRANSPORTE, PINTURA E INSTALACIN
01.06.04
DRENAJE
01.06.04.01
TUBERIA PVC CLASE 10, 3"
01.06.05
PAVIMENTOS
01.06.05.01
CARPETA ASFALTICA EN FRIO DE 2"
01.07
SEALIZACION
01.07.01
SEALES INFORMATIVAS SEGUN DISEO INC. SUMINISTRO Y COLOC.
01.08
PROTECCION DE MARGENES CON GAVIONES
01.08.01
EXCAVACION DE TIERRA EN TERRENO ARCILLOSO C/MAQ. EN GAVIONES
70 das
4 das
3 das
3 das
1 da
5 das
2 das
2 das
1 da
1 da
36 das
22 das
4 das
18 das
14 das
1 da
4 das
4 das
4 das
1 da
8 das
1 da
2 das
2 das
2 das
1 da
2 das
2 das
23 das
15 das
1 da
2 das
2 das
2 das
18 das
1 da
13 das
17 das
1 da
1 da
19 das
18 das
4 das
6 das
4 das
3 das
9 das
1 da
1 da
1 da
8 das
8 das
1 da
1 da
1 da
1 da
1 da
1 da
13 das
3 das
Comienzo
junio
julio
agosto
septiembre
octubre
noviembre
diciembre
24/05 31/05 07/06 14/06 21/06 28/06 05/07 12/07 19/07 26/07 02/08 09/08 16/08 23/08 30/08 06/09 13/09 20/09 27/09 04/10 11/10 18/10 25/10 01/11 08/11 15/11 22/11 29/11 06/12 13/12 2
jue 01/10/15
vie 02/10/15
vie 02/10/15
sb 03/10/15
dom 04/10/15
jue 01/10/15
jue 01/10/15
sb 03/10/15
lun 05/10/15
sb 03/10/15
sb 24/10/15
sb 24/10/15
sb 24/10/15
mi 28/10/15
dom 15/11/15
dom 15/11/15
mar 24/11/15
lun 16/11/15
vie 20/11/15
sb 28/11/15
dom 15/11/15
dom 15/11/15
vie 20/11/15
lun 16/11/15
mi 18/11/15
dom 22/11/15
mar 06/10/15
mar 06/10/15
jue 08/10/15
jue 08/10/15
sb 10/10/15
jue 08/10/15
mi 21/10/15
dom 11/10/15
mar 13/10/15
mar 13/10/15
vie 16/10/15
mi 14/10/15
mi 14/10/15
mi 14/10/15
dom 15/11/15
dom 15/11/15
dom 29/11/15
vie 20/11/15
mi 25/11/15
dom 15/11/15
vie 20/11/15
sb 28/11/15
sb 28/11/15
vie 20/11/15
sb 21/11/15
sb 21/11/15
vie 20/11/15
vie 20/11/15
jue 03/12/15
jue 03/12/15
vie 04/12/15
vie 04/12/15
vie 23/10/15
vie 23/10/15
Task
Project Summary
Tarea inactiva
Slo duracin
Slo fin
Split
External Tasks
Hito inactivo
Progress
Milestone
External Milestone
Resumen inactivo
Resumen manual
Deadline
Summary
Tarea inactiva
Tarea manual
Slo el comienzo
Page 1
Id
61
62
63
64
65
66
67
Texto1
01.08.02
01.08.03
01.08.04
01.08.05
01.08.06
01.09
01.09.01
Task Name
Duracin
10 das
4 das
4 das
3 das
5 das
6 das
6 das
Comienzo
lun 26/10/15
dom 01/11/15
dom 01/11/15
sb 24/10/15
sb 24/10/15
vie 04/12/15
vie 04/12/15
junio
julio
agosto
septiembre
octubre
noviembre
diciembre
24/05 31/05 07/06 14/06 21/06 28/06 05/07 12/07 19/07 26/07 02/08 09/08 16/08 23/08 30/08 06/09 13/09 20/09 27/09 04/10 11/10 18/10 25/10 01/11 08/11 15/11 22/11 29/11 06/12 13/12 2
Task
Project Summary
Tarea inactiva
Slo duracin
Slo fin
Split
External Tasks
Hito inactivo
Progress
Milestone
External Milestone
Resumen inactivo
Resumen manual
Deadline
Summary
Tarea inactiva
Tarea manual
Slo el comienzo
Page 2
CONTRACT:
W91278-13-D-0012
Task Order 0005
DESIGN / BUILD
FIVE BRIDGES UPPER HUALLAGA VALLEY
LEONCIO PRADO, PERU
PROJECT SCHEDULE
PUCAYAQUILLA BRIDGE
Id
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
Texto1
Task Name
Duracin
Comienzo
Fin
24/05
01 PUENTE PUCAYAQUILLO
01.01
DEMOLICION DE ESTRUCTURAS EXISTENTES
01.01.01
DEMOLICION DE CONCRETO SIMPLE
01.01.02
ELIMINACION MATERIAL EXCEDENTE EN CARRETILLA (50 M )
01.01.03
DESMONTAJE PUENTE MADERA ROLLIZA
01.02
TRABAJOS EN EL SITIO
01.02.01
ALMACEN Y GUARDIANIA
01.02.02
TRAZO Y REPLANTEO
01.02.03
MOVILIZACION Y DESMOVILIZACION DE EQUIPO
01.02.04
ENERGIA ELECTRICA TEMPORAL
01.03
ACCESOS DE PUENTE
01.03.01
MOVIMIENTO DE TIERRAS
01.03.01.01
EXCAVACION CON EQUIPO EN ACCESOS
01.03.01.02
CONFORMACION DE TERRAPLENES EN ACCESOS, CAPAS DE E=0.20 m.
01.03.02
CUNETAS DE DRENAJE PLUVIAL
01.03.02.01
PERFILADO DE CUNETAS C/MAQ.
01.03.02.02
CONCRETO F'C=210 KG/CM2 EN CUNETAS
01.03.02.03
ACERO DE REFUERZO FY=4200 KG/CM2 GRADO 60 EN CUNETAS
01.03.02.04
ENCOFRADO Y DESENCOFRADO EN CUNETAS
01.03.02.05
JUNTA DE DILATACION EN CUNETAS
01.03.03
LOSA DE APROXIMACION
01.03.03.01
PERFILADO PARA LOSA DE APROXIMACION
01.03.03.02
CONCRETO F'C=210 KG/CM2 EN LOSA DE APROXIMACION
01.03.03.03
ACERO DE REFUERZO FY=4200 KG/CM2 GRADO 60 EN LOSA DE APROXIMACION
01.03.03.04
ENCOFRADO Y DESENCOFRADO EN LOSA DE APROXIMACIN
01.03.03.05
JUNTA DE DILATACIN EN LOSA DE APROXIMACIN/ESTRIBO
01.04
ACCESOS PROVISIONAL
01.04.01
MEJORAMIENTO ACCESO PROVISIONAL
01.05
SUB ESTRUCTURA
01.05.01
MOVIMIENTO DE TIERRAS
01.05.01.01
EXCAVACION DE TIERRA BAJO AGUA C/MAQ.
01.05.01.02
EXCAVACION DE TIERRA EN TERRENO ARCILLOSO C/MAQ. EN ESTRIBOS
01.05.01.03
RELLENO CON MATERIAL PROPIO SELECCIONADO EN ESTRIBOS
01.05.01.04
CAMA DE ARENA CON MATERIAL GRANULAR
01.05.02
OBRAS DE CONCRETO SIMPLE
01.05.02.01
SOLADO DE CONCRETO DE 4"
01.05.02.02
CONCRETO F'C=210 KG/CM2 EN ESTRIBOS + 30% P.G.
01.05.02.03
ENCOFRADO Y DESENCOFRADO CARAVISTA EN ESTRIBOS
01.05.03
DRENAJE
01.05.03.01
TUBERIA PVC CLASE 10, 3"
01.06
SUPERESTRUCTURA
01.06.01
OBRAS DE CONCRETO ARMADO
01.06.01.01
CONCRETO ARMADO F'C=280 KG/CM2 EN SUPERESTRUCTURA
01.06.01.02
ENCOFRADO Y DESENCOFRADO CARAVISTA EN SUPERESTRUCTURA
01.06.01.03
ACERO DE REFUERZO FY=4200 KG/CM2 GRADO 60 EN SUPERESTRUCTURA
01.06.01.04
FALSO PUENTE
01.06.02
JUNTAS
01.06.02.01
JUNTA DE DILATACIN APOYO FIJO
01.06.02.02
JUNTA DE DILATACIN APOYO MVIL
01.06.02.03
NEOPRENE SHORE DE (0.45 X 0.30 X 0.05)
01.06.03
BARANDAS
01.06.03.01
BARANDAS METALICAS INC. ARENADO, TRANSPORTE, PINTURA E INSTALACIN
01.06.04
DRENAJE
01.06.04.01
TUBERIA PVC CLASE 10, 3"
01.06.05
PAVIMENTOS
01.06.05.01
CARPETA ASFALTICA EN FRIO DE 2"
01.07
SEALIZACION
01.07.01
SEALES INFORMATIVAS SEGUN DISEO INC. SUMINISTRO Y COLOC.
01.08
PROTECCION DE MARGENES CON GAVIONES
01.08.01
EXCAVACION DE TIERRA EN TERRENO ARCILLOSO C/MAQ. EN GAVIONES
junio
31/05
07/06
14/06
21/06
julio
28/06
05/07
12/07
19/07
26/07
agosto
02/08
Task
Project Summary
Tarea inactiva
Slo duracin
Slo fin
Split
External Tasks
Hito inactivo
Progress
Milestone
External Milestone
Resumen inactivo
Resumen manual
Deadline
Summary
Tarea inactiva
Tarea manual
Slo el comienzo
Page 1
09/08
16/08
23/08
septiembre
30/08 06/09
13/09
20/09
Id
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
Texto1
01.08.02
01.08.03
01.08.04
01.08.05
01.08.06
01.08.07
01.08.08
01.08.09
01.08.10
01.08.11
01.08.12
01.08.13
01.08.14
01.09
01.09.01
Task Name
Duracin
Comienzo
Fin
vie 14/08/15
vie 14/08/15
vie 14/08/15
mi 05/08/15
vie 07/08/15
mi 02/09/15
sb 05/09/15
lun 07/09/15
mi 09/09/15
jue 10/09/15
vie 11/09/15
dom 30/08/15
lun 31/08/15
sb 19/09/15
sb 19/09/15
24/05
junio
31/05
07/06
14/06
21/06
julio
28/06
05/07
12/07
19/07
26/07
agosto
02/08
Task
Project Summary
Tarea inactiva
Slo duracin
Slo fin
Split
External Tasks
Hito inactivo
Progress
Milestone
External Milestone
Resumen inactivo
Resumen manual
Deadline
Summary
Tarea inactiva
Tarea manual
Slo el comienzo
Page 2
09/08
16/08
23/08
septiembre
30/08 06/09
13/09
20/09
CONTRACT:
W91278-13-D-0012
Task Order 0005
DESIGN / BUILD
FIVE BRIDGES UPPER HUALLAGA VALLEY
LEONCIO PRADO, PERU
PROJECT SCHEDULE
MALA NOCHE BRIDGE
Id
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
Texto1
Task Name
Duracin
Comienzo
24/05
01 PUENTE MALANOCHE
01.01
DEMOLICION DE ESTRUCTURAS EXISTENTES
01.01.01
DEMOLICION DE CONCRETO SIMPLE
01.01.02
ELIMINACION MATERIAL EXCEDENTE EN CARRETILLA (50 M )
01.01.03
DESMONTAJE PUENTE MADERA ROLLIZA
01.02
TRABAJOS EN EL SITIO
01.02.01
ALMACEN Y GUARDIANIA
01.02.02
TRAZO Y REPLANTEO
01.02.03
MOVILIZACION Y DESMOVILIZACION DE EQUIPO
01.02.04
ENERGIA ELECTRICA TEMPORAL
01.03
ACCESOS DE PUENTE
01.03.01
MOVIMIENTO DE TIERRAS
01.03.01.01
EXCAVACION CON EQUIPO EN ACCESOS
01.03.01.02
CONFORMACION DE TERRAPLENES EN ACCESOS, CAPAS DE E=0.20 m.
01.03.02
CUNETAS DE DRENAJE PLUVIAL
01.03.02.01
PERFILADO DE CUNETAS C/MAQ.
01.03.02.02
CONCRETO F'C=210 KG/CM2 EN CUNETAS
01.03.02.03
ACERO DE REFUERZO FY=4200 KG/CM2 GRADO 60 EN CUNETAS
01.03.02.04
ENCOFRADO Y DESENCOFRADO EN CUNETAS
01.03.02.05
JUNTA DE DILATACION EN CUNETAS
01.03.03
LOSA DE APROXIMACION
01.03.03.01
PERFILADO PARA LOSA DE APROXIMACION
01.03.03.02
CONCRETO F'C=210 KG/CM2 EN LOSA DE APROXIMACION
01.03.03.03
ACERO DE REFUERZO FY=4200 KG/CM2 GRADO 60 EN LOSA DE APROXIMACION
01.03.03.04
ENCOFRADO Y DESENCOFRADO EN LOSA DE APROXIMACIN
01.03.03.05
JUNTA DE DILATACIN EN LOSA DE APROXIMACIN/ESTRIBO
01.04
ACCESOS PROVISIONAL
01.04.01
MEJORAMIENTO ACCESO PROVISIONAL
01.05
SUB ESTRUCTURA
01.05.01
MOVIMIENTO DE TIERRAS
01.05.01.01
EXCAVACION DE TIERRA BAJO AGUA C/MAQ.
01.05.01.02
EXCAVACION DE TIERRA EN TERRENO ARCILLOSO C/MAQ. EN ESTRIBOS
01.05.01.03
RELLENO CON MATERIAL PROPIO SELECCIONADO EN ESTRIBOS
01.05.01.04
CAMA DE ARENA CON MATERIAL GRANULAR
01.05.02
OBRAS DE CONCRETO SIMPLE
01.05.02.01
SOLADO DE CONCRETO DE 4"
01.05.02.02
CONCRETO F'C=210 KG/CM2 EN ESTRIBOS + 30% P.G.
01.05.02.03
ENCOFRADO Y DESENCOFRADO CARAVISTA EN ESTRIBOS
01.05.03
DRENAJE
01.05.03.01
TUBERIA PVC CLASE 10, 3"
01.06
SUPERESTRUCTURA
01.06.01
OBRAS DE CONCRETO ARMADO
01.06.01.01
CONCRETO ARMADO F'C=280 KG/CM2 EN SUPERESTRUCTURA
01.06.01.02
ENCOFRADO Y DESENCOFRADO CARAVISTA EN SUPERESTRUCTURA
01.06.01.03
ACERO DE REFUERZO FY=4200 KG/CM2 GRADO 60 EN SUPERESTRUCTURA
01.06.01.04
FALSO PUENTE
01.06.02
JUNTAS
01.06.02.01
JUNTA DE DILATACIN APOYO FIJO
01.06.02.02
JUNTA DE DILATACIN APOYO MVIL
01.06.02.03
NEOPRENE SHORE DE (0.45 X 0.30 X 0.05)
01.06.03
BARANDAS
01.06.03.01
BARANDAS METALICAS INC. ARENADO, TRANSPORTE, PINTURA E INSTALACIN
01.06.04
DRENAJE
01.06.04.01
TUBERIA PVC CLASE 10, 3"
01.06.05
PAVIMENTOS
01.06.05.01
CARPETA ASFALTICA EN FRIO DE 2"
01.07
SEALIZACION
01.07.01
SEALES INFORMATIVAS SEGUN DISEO INC. SUMINISTRO Y COLOC.
01.08
PROTECCION DE MARGENES CON GAVIONES
01.08.01
EXCAVACION DE TIERRA EN TERRENO ARCILLOSO C/MAQ. EN GAVIONES
junio
31/05
07/06
14/06
21/06
julio
28/06
05/07
12/07
19/07
26/07
agosto
02/08
90 das
jue 11/06/15
4 das
vie 12/06/15
3 das
vie 12/06/15
3 das sb 13/06/15
1 da dom 14/06/15
5 das
jue 11/06/15
2 das
jue 11/06/15
2 das sb 13/06/15
1 da
lun 15/06/15
1 da sb 13/06/15
38 das
lun 13/07/15
24 das
lun 13/07/15
4 das
lun 13/07/15
20 das
vie 17/07/15
14 das
jue 06/08/15
1 da
jue 06/08/15
4 das sb 15/08/15
4 das
vie 07/08/15
4 das mar 11/08/15
1 da mi 19/08/15
8 das
jue 06/08/15
1 da
jue 06/08/15
2 das mar 11/08/15
2 das
vie 07/08/15
2 das dom 09/08/15
1 da
jue 13/08/15
3 das mar 16/06/15
3 das mar 16/06/15
30 das
vie 19/06/15
23 das
vie 19/06/15
3 das dom 21/06/15
2 das
vie 19/06/15
3 das
jue 09/07/15
2 das mi 24/06/15
23 das
vie 26/06/15
1 da
vie 26/06/15
18 das
lun 29/06/15
22 das sb 27/06/15
1 da sb 27/06/15
1 da sb 27/06/15
28 das
jue 06/08/15
27 das
jue 06/08/15
4 das sb 29/08/15
10 das
vie 14/08/15
6 das dom 23/08/15
6 das
jue 06/08/15
15 das
vie 14/08/15
1 da
vie 28/08/15
1 da
vie 28/08/15
1 da
vie 14/08/15
10 das mi 19/08/15
10 das mi 19/08/15
1 da
vie 14/08/15
1 da
vie 14/08/15
1 da mi 02/09/15
1 da mi 02/09/15
1 da
jue 03/09/15
1 da
jue 03/09/15
46 das dom 12/07/15
3 das dom 12/07/15
Task
Project Summary
Tarea inactiva
Slo duracin
Slo fin
Split
External Tasks
Hito inactivo
Progress
Milestone
External Milestone
Resumen inactivo
Resumen manual
Deadline
Summary
Tarea inactiva
Tarea manual
Slo el comienzo
Page 1
09/08
16/08
23/08
septiembre
30/08
06/09
13/09
Id
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
Texto1
01.08.02
01.08.03
01.08.04
01.08.05
01.08.06
01.08.07
01.08.08
01.08.09
01.08.10
01.08.11
01.08.12
01.08.13
01.08.14
01.09
01.09.01
Task Name
Duracin
10 das
4 das
4 das
3 das
5 das
2 das
3 das
2 das
2 das
1 da
1 da
1 da
1 da
6 das
6 das
Comienzo
24/05
mi 15/07/15
mar 21/07/15
mar 21/07/15
lun 13/07/15
lun 13/07/15
dom 16/08/15
mar 18/08/15
vie 21/08/15
dom 23/08/15
mar 25/08/15
mi 26/08/15
vie 14/08/15
sb 15/08/15
jue 03/09/15
jue 03/09/15
junio
31/05
07/06
14/06
21/06
julio
28/06
05/07
12/07
19/07
26/07
agosto
02/08
Task
Project Summary
Tarea inactiva
Slo duracin
Slo fin
Split
External Tasks
Hito inactivo
Progress
Milestone
External Milestone
Resumen inactivo
Resumen manual
Deadline
Summary
Tarea inactiva
Tarea manual
Slo el comienzo
Page 2
09/08
16/08
23/08
septiembre
30/08
06/09
13/09
CONTRACT:
W91278-13-D-0012
Task Order 0005
DESIGN / BUILD
FIVE BRIDGES UPPER HUALLAGA VALLEY
LEONCIO PRADO, PERU
PROJECT SCHEDULE
SALTEADOR BRIDGE
Id
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
Texto1
Task Name
Duracin
01 PUENTE SALTEADOR
01.01
DEMOLICION DE ESTRUCTURAS EXISTENTES
01.01.01
DEMOLICION DE CONCRETO SIMPLE
01.01.02
ELIMINACION MATERIAL EXCEDENTE EN CARRETILLA (50 M )
01.01.03
DESMONTAJE PUENTE MADERA ROLLIZA
01.02
TRABAJOS EN EL SITIO
01.02.01
ALMACEN Y GUARDIANIA
01.02.02
TRAZO Y REPLANTEO
01.02.03
MOVILIZACION Y DESMOVILIZACION DE EQUIPO
01.02.04
ENERGIA ELECTRICA TEMPORAL
01.03
ACCESOS DE PUENTE
01.03.01
MOVIMIENTO DE TIERRAS
01.03.01.01
EXCAVACION CON EQUIPO EN ACCESOS
01.03.01.02
CONFORMACION DE TERRAPLENES EN ACCESOS, CAPAS DE E=0.20 m.
01.03.02
CUNETAS DE DRENAJE PLUVIAL
01.03.02.01
PERFILADO DE CUNETAS C/MAQ.
01.03.02.02
CONCRETO F'C=210 KG/CM2 EN CUNETAS
01.03.02.03
ACERO DE REFUERZO FY=4200 KG/CM2 GRADO 60 EN CUNETAS
01.03.02.04
ENCOFRADO Y DESENCOFRADO EN CUNETAS
01.03.02.05
JUNTA DE DILATACION EN CUNETAS
01.03.03
LOSA DE APROXIMACION
01.03.03.01
PERFILADO PARA LOSA DE APROXIMACION
01.03.03.02
CONCRETO F'C=210 KG/CM2 EN LOSA DE APROXIMACION
01.03.03.03
ACERO DE REFUERZO FY=4200 KG/CM2 GRADO 60 EN LOSA DE APROXIMACION
01.03.03.04
ENCOFRADO Y DESENCOFRADO EN LOSA DE APROXIMACIN
01.03.03.05
JUNTA DE DILATACIN EN LOSA DE APROXIMACIN/ESTRIBO
01.04
ACCESOS PROVISIONAL
01.04.01
MEJORAMIENTO ACCESO PROVISIONAL
01.05
SUB ESTRUCTURA
01.05.01
MOVIMIENTO DE TIERRAS
01.05.01.01
EXCAVACION DE TIERRA BAJO AGUA C/MAQ.
01.05.01.02
EXCAVACION DE TIERRA EN TERRENO ARCILLOSO C/MAQ. EN ESTRIBOS
01.05.01.03
RELLENO CON MATERIAL PROPIO SELECCIONADO EN ESTRIBOS
01.05.01.04
CAMA DE ARENA CON MATERIAL GRANULAR
01.05.02
OBRAS DE CONCRETO SIMPLE
01.05.02.01
SOLADO DE CONCRETO DE 4"
01.05.02.02
CONCRETO F'C=210 KG/CM2 EN ESTRIBOS + 30% P.G.
01.05.02.03
ENCOFRADO Y DESENCOFRADO CARAVISTA EN ESTRIBOS
01.05.03
DRENAJE
01.05.03.01
TUBERIA PVC CLASE 10, 3"
01.06
SUPERESTRUCTURA
01.06.01
OBRAS DE CONCRETO ARMADO
01.06.01.01
CONCRETO ARMADO F'C=280 KG/CM2 EN SUPERESTRUCTURA
01.06.01.02
ENCOFRADO Y DESENCOFRADO CARAVISTA EN SUPERESTRUCTURA
01.06.01.03
ACERO DE REFUERZO FY=4200 KG/CM2 GRADO 60 EN SUPERESTRUCTURA
01.06.01.04
FALSO PUENTE
01.06.02
JUNTAS
01.06.02.01
JUNTA DE DILATACIN APOYO FIJO
01.06.02.02
JUNTA DE DILATACIN APOYO MVIL
01.06.02.03
NEOPRENE SHORE DE (0.45 X 0.30 X 0.05)
01.06.03
BARANDAS
01.06.03.01
BARANDAS METALICAS INC. ARENADO, TRANSPORTE, PINTURA E INSTALACIN
01.06.04
DRENAJE
01.06.04.01
TUBERIA PVC CLASE 10, 3"
01.06.05
PAVIMENTOS
01.06.05.01
CARPETA ASFALTICA EN FRIO DE 2"
01.07
SEALIZACION
01.07.01
SEALES INFORMATIVAS SEGUN DISEO INC. SUMINISTRO Y COLOC.
01.08
PROTECCION DE MARGENES CON GAVIONES
01.08.01
EXCAVACION DE TIERRA EN TERRENO ARCILLOSO C/MAQ. EN GAVIONES
82 das
4 das
3 das
3 das
1 da
5 das
2 das
2 das
1 da
1 da
36 das
22 das
4 das
18 das
14 das
1 da
4 das
4 das
4 das
1 da
8 das
1 da
2 das
2 das
2 das
1 da
3 das
3 das
29 das
22 das
2 das
2 das
3 das
2 das
23 das
1 da
18 das
22 das
1 da
1 da
23 das
22 das
4 das
8 das
5 das
4 das
12 das
1 da
1 da
1 da
10 das
10 das
1 da
1 da
1 da
1 da
1 da
1 da
13 das
3 das
Comienzo
junio
julio
agosto
septiembre
octubre
noviembre
diciembre
24/05 31/05 07/06 14/06 21/06 28/06 05/07 12/07 19/07 26/07 02/08 09/08 16/08 23/08 30/08 06/09 13/09 20/09 27/09 04/10 11/10 18/10 25/10 01/11 08/11 15/11 22/11 29/11 06/12 13/12 2
sb 19/09/15
dom 20/09/15
dom 20/09/15
lun 21/09/15
mar 22/09/15
sb 19/09/15
sb 19/09/15
lun 21/09/15
mi 23/09/15
lun 21/09/15
mar 20/10/15
mar 20/10/15
mar 20/10/15
sb 24/10/15
mi 11/11/15
mi 11/11/15
vie 20/11/15
jue 12/11/15
lun 16/11/15
mar 24/11/15
mi 11/11/15
mi 11/11/15
lun 16/11/15
jue 12/11/15
sb 14/11/15
mi 18/11/15
jue 24/09/15
jue 24/09/15
dom 27/09/15
dom 27/09/15
mar 29/09/15
dom 27/09/15
vie 16/10/15
jue 01/10/15
sb 03/10/15
sb 03/10/15
mar 06/10/15
dom 04/10/15
dom 04/10/15
dom 04/10/15
mi 11/11/15
mi 11/11/15
dom 29/11/15
mar 17/11/15
mar 24/11/15
mi 11/11/15
mar 17/11/15
sb 28/11/15
sb 28/11/15
mar 17/11/15
jue 19/11/15
jue 19/11/15
mar 17/11/15
mar 17/11/15
jue 03/12/15
jue 03/12/15
vie 04/12/15
vie 04/12/15
lun 19/10/15
lun 19/10/15
Task
Project Summary
Tarea inactiva
Slo duracin
Slo fin
Split
External Tasks
Hito inactivo
Progress
Milestone
External Milestone
Resumen inactivo
Resumen manual
Deadline
Summary
Tarea inactiva
Tarea manual
Slo el comienzo
Page 1
Id
61
62
63
64
65
66
67
Texto1
01.08.02
01.08.03
01.08.04
01.08.05
01.08.06
01.09
01.09.01
Task Name
Duracin
10 das
4 das
4 das
3 das
5 das
6 das
6 das
Comienzo
jue 22/10/15
mi 28/10/15
mi 28/10/15
mar 20/10/15
mar 20/10/15
vie 04/12/15
vie 04/12/15
junio
julio
agosto
septiembre
octubre
noviembre
diciembre
24/05 31/05 07/06 14/06 21/06 28/06 05/07 12/07 19/07 26/07 02/08 09/08 16/08 23/08 30/08 06/09 13/09 20/09 27/09 04/10 11/10 18/10 25/10 01/11 08/11 15/11 22/11 29/11 06/12 13/12 2
Task
Project Summary
Tarea inactiva
Slo duracin
Slo fin
Split
External Tasks
Hito inactivo
Progress
Milestone
External Milestone
Resumen inactivo
Resumen manual
Deadline
Summary
Tarea inactiva
Tarea manual
Slo el comienzo
Page 2