SCDL Project Management Text Book
SCDL Project Management Text Book
OPERATIONS
PROGRAMME COORDINATOR
Prof. Viraj Atre
COURSE WRITERS
Madhup Gandhi
Sonali Gandhi
EDITORS
Ms. Deepashri Karandikar
PREFACE
We are glad to write this SLM on "Project Management" for the students of SCDL. With economic
growth and globalization, the businesses are expanding. This results in new projects as well as expansion
of projects being undertaken by the industry and infrastructure projects being implemented by the
Government. The growth in software industry requiring implementation of software projects and ever
used market research projects has resulted in increasing the demand for project managers. In fact,
project management is required in every facet of life; right from construction of house to completion
of education, at each step, we are required to do project management. If done in a systematic manner,
the probability of success of project improves and results can be better. To manage these projects, the
requirement of project managers is enormous for planning organizing and implementing in the field
of construction, engineering, software industry as well as consultancy services.
Even in banks, project managers are required for project evaluations. It may be hard to imagine living
without the project management knowledge. We could not just think of isolating ourselves from the
project management in any organization. To help the professionals manage the projects in effective
way, this SLM covers the basic fundamentals of project management.
Each unit contains detailed presentation of concepts and generalisation. Each topic has been
supplemented with clear explanatory diagrams to give the students a clear understanding of the topic.
This book mentions the objective, the summary followed by key words and a list of questions for
self-assessment. It also includes Activity questions for self learning. Special stress has been laid on
the simplicity of language in all its explanation.
We sincerely hope that this SLM will be interesting and useful and will help students and readers
to learn this subject in a more meaningful and useful manner. We take this opportunity to sincerely
extend thanks to the SCDL staff for believing in us and giving us an opportunity to write this book.
Finally, our heartfelt thanks to our parents for their valuable encouragement and inspiration. Last but
not the least, lots of thanks to our daughter Palak and Son Chirag for bearing with us and sacrificing
their entertainment and outings during the time the SLM was being written. Thanks to all those, who
directly or indirectly helped us in completing our work.
M.K. Gandhi
Sonali M. Gandhi
iii
iv
CONTENTS
Unit No.
1
TITLE
Introduction to Projects
Page No.
1-24
1.1 Introduction
1.2 Defining Project
1.3 Types of Projects
1.4 Characteristics of Projects
1.5 Understanding Project Management
1.6 History of Project Management
Summary
Key Words
Self-Assessment Questions
Answers to Check your Progress
Suggested Reading
2
25-50
51-76
Unit No.
4
vi
Page No.
TITLE
Project Estimation and Economic Analysis
4.1 Estimation of Time and Cost in Project
4.2 Economic Analysis of Projects
4.3 Return on Investment
4.4 Time Value of Money
4.5 Internal Rate of Return
4.6 Net Present Value
4.7 Economic Value Added
4.8 Payback Period
Summary
Key Words
Self-Assessment Questions
Answers to Check your Progress
Suggested Reading
Organising Projects
5.1 Introduction to Organisational Structures
5.2 Types of Organisational Structures
5.3 Project Management Office
5.3.1 Types of Project Management Offices
5.4 Responsibilities of Project Manager
5.5 Project Teams
5.6 Conflict Management
Summary
Key Words
Self-Assessment Questions
Answers to Check your Progress
Suggested Reading
Project Planning
77-102
103-128
129-158
Unit No.
7
TITLE
Page No.
159-188
189-216
217-242
vii
Unit No.
10
11
12
TITLE
Controlling Projects
10.1 Project Control Process
10.2 Schedule Management
10.3 Resource Management
10.4 Cost Management
10.5 Quality Management
10.6 Issue Management
10.7 Change Management
10.8 Risk Management
10.9 Communication Management
10.10 Execution of Communication Plan/Distribution of Information
10.11 Reporting Project's Performance
10.12 Reviewing the Project Execution and Control Phase
10.13 Closing Processes
Summary
Key Words
Self-Assessment Questions
Answers to Check your Progress
Suggested Reading
Projects Contracts Management
11.1 Understanding Contracts
11.2 Project Contract Process
11.3 Project Contract Terms
11.4 Contract Administration
11.5 Types of Contracts
Summary
Key Words
Self-Assessment Questions
Answers to Check your Progress
Suggested Reading
Management Risk in Projects
12.1 Understanding Project Risks
12.2 Risk Management Process
12.3 Risk Identification
12.4 Risk Assessment
12.5 Risk Mitigation
12.6 Risk Management Planning
12.7 Risk Communication
12.8 Tools for Risk Management
Summary
Key Words
Self-Assessment Questions
Answers to Check your Progress
Suggested Reading
viii
Page No.
243-270
271-300
301-328
Unit No.
13
14
15
TITLE
Project Quality Management
Page No.
329-356
357-384
385-412
413
ix
UNIT
Structure: 1..:y1
1.1 Introduction
1.2
Defining Project
Introduction to Projects
Notes
Obj ectives
After going through this unit, you will be able to:
1.1 INTRODUCTION
Everyone talks about project management, but what exactly is it? Isn't
project management just organising little work to get the big work done? Isn't
project management really just a series of events to create something, by some
point, way off in some hazy future? Not really.
To define what project management is we first need to define what projects
are. A project, technically, is a short-term endeavour to create a unique product
or service. A project, in practical terms, is an assignment or undertaking to
create a deliverable that satisfies the mission of the project customers.
An important factor of the project is more than 50% of the projects fail
because of poor definition. This stage actually lays the foundation for a sound
working of the project and its eventual success.
What should a definition (Scope) cover and articulate?
1.
2.
3.
4.
5.
Limits and exclusions: Clear definition of the limits of the scope of the
project. A failure here can set a false level of expectations as also openended project with respect to costs and time overruns. Care should also be
taken to define what the project will not attempt to achieve
6.
Notes
Also, the project manager has to ensure that the projective objectives are
clear sub-sets of the company mission statement and strategy plan. If it is not
the same, then they should either be aligned or the project should be abandoned.
The project has to help the company achieve its objectives set in the strategic
plans.
A typical project scope document should look like the example below:
Title: Manufacturing unit for production of motors.
Deliverables: This should capture the customer specifications with respect to
cost, time and technical specs.
For example,
1.
2.
3.
4.
5.
Milestones:
1.
2.
3.
4.
Technical specifications:
1.
2.
3.
4.
2.
3.
Piping and electrical work is not included in the factory and other building.
Introduction to Projects
3 111
Notes
Capture all the activities in fine details and define the scope of each activity.
b.
c.
d.
e.
f.
g.
h.
Such structure also tells manager the total requirement of all resources
with respect to their relations to the schedules and thus enables him to define
the crunch time zones and solutions thereof.
Responsibility Matrix
The WBD structure mentioned above gives rise to relation of each task
in the project to functions and individuals in the organisation. It brings out few
things clearly. How many and which functions and people are required for each
task and how long is one such output. The second one is, in how many tasks of
the project, each function and individual are involved and the respective time
duration. The matrix clearly tells the crowding of many tasks in one time zone
for each individual as also the possible idle time zones. This could be further
Project Management Operations
2.
Notes
LI _
Notes
The same is true with the schedule. There must be enough time to plan
and execute the project in order to achieve the project's scope. Unrealistic
expectations on the schedule usually lead to waste, rework, frustrations and a
decline in morale. In some instances this may also lead to cheap tequila.
As the Project Management profession progresses into the 21st century
we are going to have to move to a new level in the project management body of
knowledge and develop extensions that define the differences in requirements
and approach for different kinds of projects such as construction, new product
development, and information systems. We will have to define the unique
characteristics of different types of projects as well as establish a typology
or taxonomy of different kinds of projects. The cl4ssification is based on the
product or deliverable of a project. The different characteristics of project are
as follows:
Level of detail in plans (days or hours for maintenance vs. months for
research)
1.
Project, technically, is a
product or service.
Introduction to Projects
Notes
Notes
Variable
1. Stability of scope
2. Degree of uncertainty or risk
3. Type of worker
otes
Notes
401
ActwaY
Activity 1
List down the different types of projects that you have come across in your
career.
2.
3.
4.
5.
It is a team work.
6.
7.
8.
9.
It is dynamic in nature.
10.
11.
2.
or blue collar. In most cases, time pressures are moderate and cost is a
very important variable. The processes of construction are typically well
known and the foremen are very experienced.
3.
4.
5.
Note's
Event: This is a one of a kind project where scope may change during the
project and uncertainty is high. Time is critical to meet a specific date. It
is probably a complex project.
7.
8.
9.
Research: Research projects are usually long term where quality takes
precedence over time. It is an intellectual process where scope may not
be defined at all in the beginning.
2.
3.
Introduction to Projects
11
Notes
4.
5.
6.
7.
8.
9.
Size
Duration (Length of project time)
Industrial sector
Geographic location
Number of workers involved
Cost (large, medium or small)
Complexity
7.
8.
Urgency
9.
Organisational design
Type Projects by
Product
1.Administrative
2.Construction
3.Software
4. Design
5.Maintenance
6.Event
7.Equipment
8.New Product
9.Research
12
Type of
Worker
White
Blue
High Tech
White
Blue
White
Blue
White
High Tech
Degree of
Uncertainty
Low
Low
High
Medium
High
Low
Low
High
High
Time
Pressure
Low
Low
Medium
Medium
High
Medium
Low
High
Low
Stability
of Scope
High
High
Low
Medium
Low
High
High
Low
Low
Level of
Technology
Low
Low
High
High
Low
Medium
Low
High
High
Importance
of Cost
Low
High
Low
Medium
Low
Medium
Low
Low
Low
Notes
mtmtv Activity 2
Visit any nearby project site and list down the characteristics of the project.
Introduction to Projects
Notes
Once the project requirements have been agreed upon then the project
manager, the project team, and in some instances the project stakeholders will
create a plan on how to achieve the project objectives. This isn't a one-time
process. Planning is an iterative process that happens throughout the project
duration. Planning is cornerstone of project management if you skip planning
or do it half-heartedly, the project is doomed.
Executing the project
"Plan your work and then work on your plan." This is the working part.
The executing process group is the project team executing the project work
according to plan and the project manager working with any vendors that may
be involved in the execution or support of the deliverables needed for the project
completion.
Controlling the project
Controlling isn't about micromanaging; it's about compliance with the
project plan. There's balance between execution and control. The project
manager works with the project team, not over them, to ensure that they 're
doing the work as it was planned, and if not, then the project manager makes
corrective actions to get the project back in alignment with the project plan.
Controlling is also about balancing the time, cost, and scope constraints
as the project moves along. The project manager has to measure, compare, and
adjust controls within the project to ensure project success. If we do not measure
we cannot improve.
Closing the project
This process group centres on closing out the project accounts, completing
final, formal acceptance of the project deliverables, finalising any time, cost, or
quality reports, completing the project's lessons learned documentation, and
finalising any financial or procurement audits. The project manager may have to
complete a review of each team member, a review of the vendors, and a review
of their own actions in the project.
Project closure also involves some rewards and recognition. For some,
this means bonuses, vacation time, or other rewards. If this isn't appropriate
or available in the organisation, the project manager should at least verbally
reward the project team for their hard work and a job well-done.
Putting it all together
As you know projects are short-term endeavours to create a unique
product or service. Projects are out of the normal duties you do as part of
your operations. Projects are constrained by time, cost and scope and other
constraints such as regulations, resources, or even vendors.
The Iron Triangle of project management points that all projects are
constrained by time, cost, and scope. If one angle of the project is out the whole
project suffers.
Introduction to Projects
Notes
Notes
Projects, and technically even project phases, move through five process
groups: initiating, planning, executing, controlling and closing. Each process
group has key activities that lend to a successful project. The most important
group is planning. Without planning the project is destined for failure.
What we've discussed in this introduction to project management is a
good foundation for how projects are to operate, their constraints, and some
challenges every project manager faces. On top of this strong foundation, there
are nine knowledge areas which also affect a project's success:
1.
2.
3.
4.
5.
6.
Communications Management
7.
8.
9.
Projects are successful based on the ability of the project manager to lead,
manage and motivate the project team to complete the project plan. The project
plan supports the vision the project manager has inherited from the project
stakeholders. If the project manager and the project stakeholder don't have the
same vision of the desired future state, the project is doomed.
Projects fail at the beginning, not at the end
Project management in the modern sense began in the early 1960s, although
it has its roots much further back in the latter years of the 19th century. The need
for project management was driven by businesses that realised the benefits of
organising work around projects and the critical need to communicate and coordinate work across departments and professions.
Here is the main definition of what project management is:
1.
2.
3.
4.
5.
Engineering
Managing Resources
iii.
iv.
v.
Skill Development
Training to Staff
Knowledge Management
Notes
Notes
specialists since then. AACE continued its pioneering work in 2006 releasing
the first integrated process for portfolio, programme and project management
with their Total Cost Management Framework.
1957: The Critical Path Method (CPM) invented by the Dupont Corporation
Developed by Dupont, CPM is a technique used to predict project duration
by analysing which sequence of activities has the least amount of scheduling
flexibility. Dupont designed it to address the complex process of shutting
down chemical plants for maintenance and then with maintenance completed
restarting them. The technique was so successful it saved the corporation $1
million in the first year of its implementation.
1958: The Program Evaluation Review Technique (PERT) Invented for the
US Navy's Polaris Project
The United States Department of Defence's US Navy Special Projects
Office developed PERT as part of the Polaris mobile submarine launched
ballistic missile project during the cold war. PERT is a method for analysing the
tasks involved in completing a project, especially the time needed to complete
each task and identifying the minimum time needed to complete the total
project.
1962: United States Department of Defence Mandate the Work Breakdown
Structure (WBS) Approach
The United States Department of Defence (DOD) created the WBS concept
as part of the Polaris mobile submarine launched ballistic missile project. After
completing the project, the DOD published the work breakdown structure it
used and mandated that this procedure be followed in future projects of this
scope and size. WBS is an exhaustive, hierarchical tree structure of deliverables
and tasks that need to be performed to complete a project. Later adopted by the
private sector, the WBS remains one of the most common and effective project
management tools.
1965: The International Project Management Association (IPMA) Founded
IPMA was the world's first project management association, started
in Vienna by a group as a forum for project managers to network and share
information. Registered in Switzerland, the association is a federation of about
50 national and internationally oriented project management associations.
Its vision is to promote project management and to lead development of the
profession. Since its birth in 1965, IPMA has grown and spread worldwide with
over 40,000 members in more than 40 countries.
1969: Project Management Institute (PMI) launched to promote the Project
Management Profession
Five volunteers founded PMI as a non-profit professional organisation
dedicated to advance the practice, science and profession ofproject management.
The Commonwealth of Pennsylvania, USA issued Articles of Incorporation for
PMI in 1969 which signified its official start. During that same year, PMI held
Notes
Notes
20
will keep the resources levelly loaded, but will need them to be flexible in their
start times and to switch quickly between tasks and task chains to keep the
whole project on schedule.
1998: PMBOK becomes a Standard
The American National Standards Institute (ANSI) recognises PMBOK
as a standard in 1998, and later that year by the Institute of Electrical and
Electronics Engineers (IEEE).
2006: "Total Cost Management Framework" released by AACE
International
Total cost management is the name given by AACE International to a
process for applying the skills and knowledge of cost engineering. It is also
the first integrated process or method for portfolio, programme and project
management. AACE first introduced the idea in the 1990s and published the
full presentation of the process in the "Total Cost Management Framework".
2008: 4th Edition of PMBOK Guide released
The fourth edition of the guide continues the PMI tradition of excellence in
project management with a standard that is easier to understand and implement,
with improved consistency and greater clarification. The updated version has
two new processes not in the previous versions.
2009: Major PRINCE2 Revision by Office of Government Commerce
(OGC)
A major revision has seen the method made simpler and more easily
customisable, a common request from users. The updated version has seven
basic principles (not in the previous version) that contribute to project success.
Overall the updated method aims to give project managers a better set of tools
to deliver projects on time, within budget and to the right quality.
What's Next?
With globalisation come ever bigger challenges and the need for
increased speed to market with products and services. Projects become larger,
more complex and increasingly difficult to manage. Teams are more diverse
and spread across the world. The economic crisis pushes work offshore to low
cost countries, which itself presents several issues. The world is changing and
project management will need to change with it.
No doubt new techniques and better practices will arise as we push the
boundaries of what is possible and new challenges arise. Human need drives
us forward to a better future and with it will come improvements in the way we
manage projects. When and where these developments will happen is uncertain,
but they will happen.
Introduction to Projects
i-Notes
Notes
PMBOK Guide
PRINCE2
Revision
PRINCE Method
1910 1920 1930 1940 1950 1960 1970 1980 1990 2000 2010
AACE Formed
Hoover Dam Project
CPM Invented
- PERT Invented
Summary
An important factor of the project is that more than 50% of the projects
fail because of poor definition. This stage actually lays the foundation for
a sound working of the project and its eventual success.
There are a four basic ways in which we can set up a classification system
of projects as follows: (1) Geographical location, (2) Industrial sector
(Standard Industrial Classification System), (3) Stage of the project
life cycle and (4) Product of the project (construction of a building or
Project Management Operations
development of a new product). The most important and the most useful
breakdown is by type ofproduct or deliverable that the project is producing
such as building a building, developing a new product, developing new
computer software program or performing a maintenance turnaround or
outage on a chemical plant or electric generating station.
The Iron Triangle of project management posits that all projects are
constrained by time, cost and scope. If one angle of the project is hit the
whole project suffers.
Projects, and technically even project phases, move through five process
groups: initiating, planning, executing, controlling and closing. Each
process group has key activities that lend to a successful project. The most
important group is planning. Without planning the project is destined for
failure.
Keywords
Self-Assessment Questions
1.
2.
3.
"If the scope of project is not defined properly, it will fail." Do you agree?
What is the scope of project management?
4.
5.
Why projects fail? Explain the steps that can be taken to avoid failure of
projects.
Introduction to Projects
Notes
2.
3.
Engineering
ii.
Managing Resources
2.
Suggested Reading
1.
2.
3.
UNIT
25
Notes
Objectives
After going through this unit, you will be able to:
Quality
Scope
Cost
1.
2.
3.
4.
More recently, this has given way to a project management diamond, with
time, cost, scope and quality the four vertices and customer expectations as a
central theme. No two customers' expectations are the same so you must ask
what their expectations are.
Time
Quality
Expectations
Cost
Scope
emotes
11,11
Add time delay the project to give you more time to add the functionality
Add cost recruit, hire or acquire more people to do the extra work
Cut quality trade off some non-essential requirements for the new
requirements
If the art of management lies in making decisions, then the art of project
management lies in making decisions quickly! When faced with scope creep
you cannot ignore it. You need to tackle it in one of the ways described above
(more later) and the sooner the better. Delaying raises the risk of your project
failing.
A poor project manager will see the scope triangle as a strait-jacket by
which their project is irrevocably constrained. A better project manager will
make better use of one or more of the axes and will shift the emphasis in the
project to one of the other axes. The best project managers will juggle all three
like hot potatoes and will make decisions every day which effectively trade-off
time vs. quality vs. resources. ,
Many things can go wrong in project management. These things are often
called barriers. Here are some possible barriers:
Poor communication
Disagreement
Misunderstandings
Bad weather
Union strikes
Personality conflicts
Poor management
A good project management discipline will not eliminate all risks, issues
and surprises, but will provide standard processes and procedures to deal with
them and help prevent the following:
Project management seen as not adding value and as a waste of time and
money.
Notes
Noses
management vis-a-vis GDP estimates. And it is here that a note of caution must
be injected.
Take two hypothetical projects, identical in all respects except the calibre
of their project management. One project comes in on budget, having used the
planned resources. The other dramatically exceeds its budget, using far more
resources than planned. Which has the greater contribution to GDP? The latter.
Overtime payments, additional employees, replacements for materials wasted
or otherwise found faulty perversely, these additional expenditures contribute
positively to GDP, not negatively.
As a result, while GDP based estimates of the value of prof ect management
to the UK economy are useful starting points, a more rounded insight into
the value of project management to the UK economy must come from more
qualitative data.
Project Management and Innovation
Almost by definition, innovation relies onproj ect management. Irrespective
of whether the innovation concerns a new product, or a new process, or indeed a
contribution to pure science, better project management, on the whole, will see
a successful outcome reached more quickly, having consumed fewer resources.
And innovation is important to the UK economy. As a succession of
reports from the UK government's Department of Trade and Industry (DTI)
has highlighted over the years, innovative businesses are more successful, and
innovative industries grow faster, export more, are more competitive, more
productive, and have a better long-term future.
Stating the benefits of innovation is one thing defining innovation itself,
or quantifying it, is another.As successive generations of statisticians have
found, the measurement of innovation is almost as slippery a concept as the
measurement of project management.
An interesting table (see Table 1) from the current DTI innovation report
breaks down the innovation carried out by a number of manufacturing industries
based on one widely used proxy measure RandD spending, commonly reported
by companies in their annual accounts.
Even so, this almost certainly understates the true level of innovation
activity, especially with respect to process innovation. The engineering
departments and process improvement groups of manufacturing companies
routinely make process improvements that go unrecorded as RandD, for
example.
Industry
12.9
- of which pharmaceuticals
Plastic and rubber products
Food, drink and tobacco
Textiles
Textiles
Manufacturing total/average
18.5
44.2
0.8
1.1
0.4
7.0
Notes mime
6.6
5.5
31
Notes
correlation between the regional pattern of RandD (both public and private
sector) and regional economic performance. Again, it is project management
that underpins that RandD, and manages the process of turning ideas into
actionable innovations.
Project Management and Project-Intensive Industries
Every business undertakes projects of some sort. But some undertake far
more than others. Similarly, some industries are more project-intensive than
others. Aerospace and defence, for example, are extremely project-intensive,
working for years on long-term contracts or development projects that will
eventually bring forth a new jet aircraft, missile system, ship or piece of
electronic wizardry. Likewise, almost by definition, construction is another
industry that exhibits a high degree of project activity.
Food, retailing and textiles, on the other hand, are less project-intensive.
Even so, care must be taken. While corner shops may not be prone to launching
new projects, the major supermarkets are, each year sees a number of new
distribution depots, IT systems, retail outlets and the like.
The corner shop should not be overlooked altogether, though. Taken
together, the UK's 3.7 million SMEs account for approximately 40% of the
UK's GDP, and have combined sales revenues of 1 tm. Employing over 12
million people in the UK, they account for 85% of the 2.3 million extra jobs
created by new businesses in the period 1995-99, and over 50% of the 3.5
million jobs gained from expansion of existing firms over the same period.
Impressive though these figures are it is highly probable that enhanced
project management capabilities would have seen an even greater transformation.
That, in essence, is the scale of the opportunity facing the UK, and indeed many
other developed economies.
Richard Pharro, managing director of accreditation and examination
body APMG, which commissioned this research, comments: "At last we are
beginning to see research which proves how important project management
is to the UK and global economies. All kinds and sizes of organisations in
both the public and private sectors should sit up and take note of this because
without well-trained and capable project managers the percentage of GDP
spent through projects is inflated due to many exceeding their budget through
poor management. Furthermore, considering the impact that successful project
management has on fast-growing SMEs, we hope to see more project managers
getting the recognition they deserve in helping to make these organisations even
more innovative and successful."
Project management is a not-so-hi-tech concept that enables managers to
guide a project from point "A" to point "B" and do so in a way that demonstrates
efficiency, cost-savings and plain 'of ingenuity. That being said, the benefits
of project management are ten-fold: the manager actually gets to manage as
they lead their team and institute a strategy that will see said project reach
fruition. The client benefits because they are allowed to provide feedback, while
relishing in the knowledge that their input really means something. And finally,
Project Management Operations
the workers benefit because without the workers/team the project wouldn't get
finished. Additionally, the team members are able to take a stake in something,
work with it and see said project through from start to finish.
The benefits of project management contain all the elements of what
is a truly symbiotic relationship between manager, client and worker bee. In
fact, it's this very application of knowledge, skills, tools and techniques that
ultimately will meet or exceed a stakeholder's needs and/or expectations on any
given project.
Now that we've laid out the ground-rules, it's a lot easier to visualize
what some of the benefits of project management are. With apologies to David
Letterman, I've put together my own top-ten list of the benefits of project
management:
1.
2.
3.
4.
5.
Greater standing and competitive edge: This is not only a good benefit
of project management within the workplace but outside of it as well;
word travels fast and there is nothing like superior performance to secure
your place in the marketplace.
6.
7.
8.
Increased risk assessment: When all the players are lined up and your
strategy is in place potential risks will jump out and slap you in the face.
And that's the way it should be. Project management provides a red flag
at the right time: before you start working on project completion.
'
NOtes
Notes
9.
10.
Disadvantages
None, except when it's a very, very small project then project management
risks to be an overhead that is not paying.
2.
_-Activity Activity 1
Visit any nearby organisationand find the projects undertaken by them. List
the factors that they considered for the success of the project.
Risk: The risks involved in the project effecting its completion time are
high at the initial stages and low at the later stages of the project. Refer to
the characteristic chart.
Design changes: The project during the course of its progress may be
subjected to changes because of some external factors. The influence of
such external factors on the project may result in changes in the design of
the project though not very often. It is observed that such changes.
Stretched deadlines
Over-stressed team
Wasted resources
Overshot budget
Notes
Notes
2.
3.
Project Planning: Detailed plans of how the work will be carried out
including time, cost and resource estimates.
4.
5.
6.
Notes
There are other techniques for eliciting the requirements like use cases,
prototyping, data flow diagrams, and competitor analysis. It is essential
that the exact requirements of the stakeholders are established.
Build a prototype of the project to give an exact idea of the final results of
the product or project to stakeholders.
What requirements identify with the technical details needed for smooth
functioning?
List all the requirements with regard to priOrity and relevance to the
project.
Solve the ambiguous and conflicting details that have come up.
III,
.'
-.
Notes
document that will combine all the details and get it signed by all stakeholders/
end-users and the project manager. This will be the rulebook for the project.All
stakeholders, end-users, project personnel, and developers should be given a
copy to apprise them of the project goals.
An efficientlydone business requirements analysis will enable you to
pinpoint exactly what is wanted from the project and how you can achieve it.
Once this is done, there will be no ambiguity about the diverse requirements/
specifications connected with the project and there will be a focused and wellplanned execution of the project with no chance for a scope or function creep.
-
Initiation
Develop a Business Case
Undertake a Feasibility Study
Establish the Project
ChartAppoint the Project Team
Set up the Project Office
Perform Phase Review
38
Notes
Create a Project Plan
Create a Resource Plan
Create a Financial Plan
Create a Quality Plan
Create a Risk Plan
Create an Acceptance Plan
Create a Communications Plan
Create a Procurement Plan
Contract the Suppliers
Define the Tender Process
Issue a Statement of Work
Issue a Request for Information
Issue a Request for Proposal
Create Supplier Contract
Perform Phase Review
AP
Execution
Build Deliverable
Monitor and Control
Perform CommunicationsManagement
39
Closure
Perform
Project Closure
Review Project Completion
The Project Management process is unique, because
it:
Applies to all project types and industries
Is used to manage projects of any size
Gives you the complete set of project templates
Explains every step in the project lifecycle in depth!
The Project Management processhelps:
Project Managers to deliver projects Consultants
to manage client projects Trainers to teach project
management Students to learn how to manage
projects Project Offices to monitor and control
projects Senior Managers to improve the success of
projects.
2.
3.
Notes
b.
b.
c.
d.
e.
Execution plan of each module and integration of the same with the
rest.
f.
g.
h.
i.
j.
k.
1.
Define organisationstructure.
b.
c.
d.
e.
Clear plans to implement and monitor the activities as per the plan.
g.
41
Notes
h.
i.
4.
a.
b.
c.
Trial run of the live process with the help of customer for monitoring
the results as compared to the original expectations.
d.
e.
f.
The
2.
4AdivIIN
Activity 2
Visit a nearby project site and list down the steps taken by them for successful
. ._project management.
42
i.
Cost Management
ii.
Risk Management
iii.
Scope Management
iv.
Resource Management
v.
Communications Management
vi.
Quality Management
vii.
Time Management
Notes
Integration Management
2.
3.
43
Notes
Templates are used for the collection of the output of the process.
Activity 2
Activity 3
Activity 4
Document
Template
Discuss the project with the applications security manager and identify
what actions will be required to meet corporate standards
Review how the project will be affected by the new security standard
being introduced by architecture. This is best done in a workshop with
the following people. Talk with network administration and identify any
network security implications.
44
Using a Methodology
Any methodology is not the way all projects will operate. It is a best tit.
There will be variations for very good reasons. That is not to say it is variable
at the whim of each team. There needs to be some guidance provided as to what
is the sensible and pragmatic approach for each project. Gartner research found
that a methodology applied loosely could improve productivity by 30%. Applied
rigidly it improved product by only 10%. It should be a help to the project, not
a hindrance. If you want to have your organisation use a methodology, there
needs to be some champion who people have access to for help.
Objections to using a Methodology
The following are some objections that are encountered, and how to
address each objection:
It stifles my creativity?
Notes
Notes
My methodology is better
Secondly, it is cheaper and easier to throw away paper rather than code.
Implementing a Methodology
A methodology is not a series of templates. It is a process that needs to be
adapted to suit each situation. There needs to be someone who teams can talk
with someone who will mentor the teams in the use of the methodology.
They should have a full-time methodology coordinator who trains, works
with teams, and builds their feedback into the methodology.
Feedback is also important. The methodology will not stand still. It will
evolve and become more applicable to the organisation. As such, there needs to
be a mechanism in place to cater for "learning from experience".
Take it step by step. A massive change to the way people work is not as
likely to succeed as incremental change. If your goal is to have people produce
a plan for every phase, start by having them produce some sort of standard plan
for the whole project. If you decide to introduce three gates for approval of
funds, introduce them one at a time. You will probably
find after the first gate is in place, your experiences will indicate that you
need to slightly change the process for the other two gates.
Availability is another issue. Asking people to read a 400 page manual will
not work. Giving them some Iligh-level training, and presenting information in
a format where they can find the bit that is relevant to what they are doing right
now has more chance of success. A well-structured, web-based presentation is
46
a must. People need to be able to drill down in a few clicks to find out what is
relevant to them at the moment. Training them on the layout of a methodology
website is likely to have more impact than training them on the detail of the
methodology. Putting some templates in place is a nice first step, but it is not
a methodology. Make sure you understand the difference between templates
and process. Also understand the difference between a project management
methodology and other methodologies. To a lot of people methodology is a
dirty word. It means bureaucracy, paperwork and constriction. You need to
overcome this by providing support and flexibility in how it is applied.
Notes
2.
SULL.1
5Mrani
Many things can go wrong in project management. These things are often
called barriers. Here are some possible barriers: poor communication,
disagreement, misunderstandings, bad weather, union strikes, personality
conflicts, poor management, poorly defined goals and objectives.
A good project management discipline will not eliminate all risks, issues
and surprises, but will provide standard processes and procedures to deal
with them.
Some of the steps of a good project management are define the project,
reduce it to a set of manageable tasks, obtain appropriate and necessary
"
resources, build a team to perform the project work, plan the work and
allocate the resources to the tasks.
A project goes through six phases during its life: project definition,
project initiation, project planning, project execution, project monitoring
and control, project closure.
The Project Management Life Cycle has four phases: Initiation, Planning,
Execution and Closure.
16. Keywords
Triple constraint: The most important factors in project management are time, cost and scope.
Self-Assessment,Questions
1.
2.
3.
4.
5.
What is project life cycle? Explain the concept of project life cycle for
proper project management.
6.
7.
Notes
Time, cost and scope in project management are called triple constraint.
2.
False
2.
False
2.
2.
False
2.
True
Suggested Reading
1. Project Management Handbook. The Project Management Body of
Knowledge (PMBOK).
49
UNIT
51
Notes
Objectives
After going through this unit, you will be able to:
operating in a contractual network with each other that allocates risk in a way
that allows financing to take place. The various patterns of implementation are
sometimes referred to as "project delivery methods".
The financing of these projects must also be distributed among multiple
parties, so as to distribute the risk associated with the project while simultaneously
ensuring profits for each party involved.
A riskier or more expensive project may require limited recourse financing
secured by a surety from sponsors. A complex project finance structure may
incorporate corporate finance, securitisation, options, insurance provisions or
other types of collateral enhancement to mitigate unallocated risk.
Project finance shares many characteristics with maritime finance and
aircraft finance; however, the latter two are more specialised fields.
Basic scheme
Typical Structure of a Project Finance Scheme
Notei
Notes
54
Notes
Publicly funded projects may also use additional financing methods such
as tax increment financing or Private Finance Initiative (PFI). Such projects
are often governed by a Capital Improvement Plan which adds certain auditing
capabilities and restrictions to the process.
3.2 PROJECT COST
ANAL SIS
I_
uI-
1156..
Notes
1
p.AcwitY Activity 1
Consider any project you have done or you want to do. Do the cost benefit
analysis for the same.
\._
b.
The state remains responsible for delivery of public services or for the
public infrastructure responsibility for provision.
Potential suppliers of any ownership type have the right to compete for
the opportunity to deliver/produce the services to the public and to build
and maintain the necessary infrastructure.
1.
MA:es _
57
tap water of drinking quality may entail waste and misuse for all
sort of purposes (car wash, irrigation, cleaning walkways, etc.) and,
hence, lead to over-sized water works.
Notes
2.
Notes
59 , _
The method of funding the project, in part from the private sector,
sometimes by means of complex arrangements between the various
players. Nonetheless, public funds in some cases rather substantial may
be added to the private funds.
The roles of the partners who participate at different stages in the project
(design, completion, implementation, funding); the public partner
concentrates primarily on defining the objectives to be attained in terms
of public needs and outputs, quality of services provided and pricing
policy, and takes responsibility for monitoring the compliance with these
objectives.
However, a PPP does not necessarily mean that the private partner
assumes all the risks, or even the major share of the risks linked to the project,
the precise distribution of risks is determined case by case, according to the
respective ability of the concerned parties to assess, control and cope with this
risk.
The funding can be distinguished as follows:
Notes
61
Notes
63
Score Documentation
AB
10 4 Site A: 800m from
town centre, Site
B:5 km. Quite big
difference in the
distance.
3 12 9 Site A: 10' on foot, Site
B: You can't go on foot
but you could drive
(available parking)
IC1_ 6
6 B ath sites are serviced
bythe same public
Site B
,c,_
Accessibility
Services
provided
by public
transport
Position in
relatiaiito
inhabited
areas
a O
Accessibility
cost
4 GI
40
27
i(1_
TOTAL
transport.
Site A: Near to town
centre with population
of SO.D00. SiteB:5 km
away from inhabited
areas
Site A: No cost if you
walk or 60.60 if you
take the bus. SiteB: 61
by bus or 60. SO by
car (fuel cost). Site A
receives a higher score
because it lias lower
accessibility cost.
Notes
Score Documentation
A B
4
2 Site B requires
alienation of land from
individuals, where Site
A is totally owned by
dieMunicipality Site A
receives a higher score
because it lias fewer
legal restrictions.
6 12 Site A: Has no adequate
water resources and
problem with high
noise levels
Site B: Has mosquitoes'
problem but this
problem can easily be
solved, so it receives
higher score.
11
,1 15 6 No cost of land
SiteA: acquisition
(Municipality's
property)
Site B: 100.00 to
buy the land from the
individuals
6 15 Site A: The landscape
needs many
interventions to be
transformed into a
green park, Site B: The
morphology of the area
is identical for a green
park, since it is located
near a hill with many
trees and is also crossed
by a small stream.
6
6 Both Sites have
no problem with
the established
electricity and
telecommunication
networks.
37 39
Legal
restrictions
4 O
Specific
restrictions
(1_
Cost of land
acquisition
Landscape
morphology
Sufficiency
of networks
4 4
TOTAL
65
Notes
t Activity 3
law, environmental law, trade restrictions, tariffs and political stability. Political
factors may also include goods and services which the government wants to
provide or be provided (merit goods) and those that the government does not
want to be provided (demerit goods or merit bads). Furthermore, governments
have great influence on the health, education and infrastructure of a nation.
Notes
67
Notes
department of its company at a time with the PESTEL model, thus focusing on
the specific factors relevant to that one department. A company may also wish
to divide factors into geographical relevance, such as local, national and global
(also known as LONG PESTEL).
social forces
rseeffitcliticra
roAlir
1/4
txternal
analysis
objectives
Took dedicated
to external
analyses
ALL
Internal
analysis
objectives
Took dedicated
to internal
analyses
Assess ing
PESTEL analysis
resources
(Political,
Asesig the
Environmental,
nature of the
Socio-cultural,
,r
envi onment and
environment
Technological,
impacts
Econorrik andDrawing
Legal factors)
comparisons
SWOT analysis
Determining
external
opportunities and
threats
Resources audit
Analysis of best
practice
Determining
Internal strengths
and weaknesses
001ITICAl
SWOT analysIS
E C (1 kU M 1C
Government Type
Government Stability
Disposable Incomenistribution
vor,v learnmerketIna.not
Globalization
4. Economic Change
BAD Activity
Impact of Technology Transfer
Likely Technological Change
Lifestyle Choices
Likely Socio-Cultural Change
SOC10-CULTURAL
C 14NOLOG IC AL
Notes
2.
Activity 4
Consider any project that you are working on or you would have worked for
and do the PEST analysis of the same.
A strong currency may make exporting more difficult because it may raise
the price in terms of foreign currency.
Inflation may provoke higher wage demands from employees and raise
costs.
Higher national income growth may boost demand for a firm's products.
Social factors: Changes in social trends can impact on the demand for a firm's
products and the availability and willingness of individuals to work. In the UK,
for example, the population has been ageing. This has increased the costs for
firms who are committed to pension payments for their employees because their
Project Financing and Evaluation
169
Notes
staff is living longer. It also means some firms such as Asda have started to recruit
older employees to tap into this growing labour pool. The ageing population
also has impact on demand. For example, demand for sheltered accommodation
and medicines have increased ,whereas demand for toys is falling.
Technological factors: New technologies create new products and new
processes. MP3 players, computer games, online gambling and high-definition
TVs are all new markets created by technological advances. Online shopping,
bar- coding and computer aided design are all improvements to the way we do
business as a result of better technology. Technology can reduce costs, improve
quality and lead to innovation. These developments can benefit consumers as
well as the organisations providing the products.
Environmental factors: Environmental factors include the weather and
climate change. Changes in temperature can impact many industries including
farming, tourism and insurance. With major climate changes occurring due to
global warming and with greater environmental awareness this external factor
is becoming a significant issue for firms to consider. The growing desire to
protect the environment is having an impact on many industries such as the
travel and transportation industries (for example, more taxes being placed on
air travel and the success of hybrid cars) and the general move towards more
environmentally friendly products and processes is affecting demand patterns
and creating business opportunities.
Legal factors: These are related to the legal environment in which firms operate.
In recent years, in the UK, there have been many significant legal changes that
have affected firms' behaviour. The introduction of age discrimination and
disability discrimination legislation, an increase in the minimum wage and
greater requirements for firms to recycle are examples of relatively recent laws
that affect an organisation's actions. Legal changes can affect a firm's costs
(e.g., if new systems and procedures have to be developed) and demand (e.g.,
if the law affects the likelihood of customers buying the good or using the
service).
Different categories of law include:
7.0
Health and safety legislation: These laws are aimed at ensuring the
workplace is as safe as is reasonably practical. They cover issues such
as training, reporting accidents and the appropriate provision of safety
equipment.
Notes
Could include:
E.g., EU enlargement, the euro, international trade, taxation
policy
E.g., interest rates, exchange rates, national income, inflation,
unemployment, stock market
E.g., ageing population, attitudes to work, income distribution
E.g. innovation, new product development, rate of
technological obsolescence
E.g., global warming, environmental issues
E.g., competition law, health and safety, employment law
71
Notes
Global factors such as the opening up of new markets making trade easier.
The entry of Bulgaria and Romania into the European Union might make
it easier to enter that market in terms of meeting the various regulations
and provide new expansion opportunities. It might also change the labour
force within the UK and recruitment opportunities.
TECHNOLOGICAL
ENVIRONMENTAL
LEGAL
UK interest rates
UK law
GLOBAL
World trade
agreements, e.g.,
further expansion of
the EU
Overseas economic
growth
Migration flows
International
technological
breakthroughs
e.g., Internet
Global climate change
International
agreements on human
rights or environmental
policy
Notes
Summary
73
(costs and benefits) and technical (can it be built?) aspects are part of the
study. Results of the study determine whether the solution is feasible in
all the above aspects and thus should be implemented.
Notes
There are many factors in the macro environment that will affect the
decisions of the managers of any organisation. Tax changes, new laws,
trade barriers, demographic change and government policy changes are
all examples of macro change. To help analyse these factors managers
can categorise them using the PESTEL model. This classification
distinguishes between: Political factors, Economic factors, Social factors,
Technological factors, Environmental factors and Legal factors.
Keywords
Self-Assessment Questions
1.
2.
What are the different considerations for project financing? Explain with
suitable examples.
3.
4.
5.
6.
7.
Notes
2.
2.
False
2.
True
75
Notes
00 01
UNIT
Objectives
After going through this unit, you will be able to:
Top-down approach: Here the total time and costs mentioned for the
whole project is taken as reference and the same is not broken down to
the individual task level. This is also called macro estimation. Normally,
this approach is used during the project evaluation stage at the time of
selection and evaluation of the project by the top team. These estimates
are normally reasonably rough and are based on the experience of the
team who do it, and also the previous experience of the connected people
with similar activities. This process does not break down the project into
individual tasks or activities and therefore operates at gross top level. This
is normally substantiated by bottom up approach for the actual estimation.
2.
This process does give the estimate which is reasonably close to the
reality. This process is necessary for actual implementation of the project. In
most cases, this approach cannot be successfully deployed for estimation at the
beginning due to absence of detailed break up of project and deliverable designs.
The individual estimates are prepared by the functions and the individuals who
would eventually execute the tasks and are specialists in the respective fields.
78
Ratio method: Based on past experience, this method does not break
down the project into tasks. It uses experience to create a ratio which
represents average costs per unit variable of the project which bundles
all variables into one. For example, the construction costs of residential
buildings are calculated using a ratio of cost in rupees per square metre
of construction or cost of transport in terms of rupees per ton kilometer
travel. Obviously the ratio figures are created based on many such past
experiences.
2.
3.
4.
Notes
2.
Parametric method: The total costs of the project in the historical data
are directly related to one of the typical variable parameter which is most
representative. For example, elapsed time.
3.
79
activity the estimates are prepared from the likely members who actually
execute the said activity. Such data for all activities are generated to
arrive at a project estimate. This also helps in getting the support from the
same people when they actually execute the job because of the obviously
associated ownership.
Nbtes
4.
Adjusted Present Value (APV): Adjusted present value is the net present
value of a project if financed solely by ownership equity plus the present
value of all the benefits of financing.
2.
Payback Period: It measures the time required for the cash inflows to
equal the original outlay. It measures risk, not return.
3.
Cost Benefit Analysis: This includes issues other than cash, such as time
savings.
4.
5.
6.
7.
8.
9.
ActIv" f
Activity 1
Visit a nearby project site and find the methodology used by them for
time and cost estimation.
Enlist the tools used for economic analysis.
Notes
Single-period
a.
rarith = V.
rath is sometimes referred to as the yield. See also: effective interest rate,
effective annual rate (EAR) or annual percentage yield (APY).
b.
b.
1
n
vn rarith i = 1
(rarith 1, +
+ rarithn)
c.
II (1 + r arith.01/n
i=1
Estimates regarding the risk of the investment (e.g., how likely it is that
investors will receive regular interest/dividend payments and the return of
their full capital)
Notes
Notes
Whether or not the investors want the money available ("liquid") for other
uses.
The time value of money is reflected in the interest rates that banks offer
for deposits, and also in the interest rates that banks charge for loans such as
home mortgages. The "risk-free" rate is the rate on US Treasury Bills, because
this is the highest rate available without risking capital.
The rate of return which an investor expects from an investment is called
the Discount Rate. Each investment has a different discount rate, based on the
cash flow expected in future from the investment. The higher the risk, the higher
the discount rate (rate of return) the investor will demand from the investment.
Compounding or reinvesting
Compound interest or other reinvestment of cash returns (such as
interest and dividends) does not affect the discount rate of an investment, but
it does affect the Annual Percentage Yield, because compounding/reinvestment
increases the capital invested.
For example, if an investor put $1,000 in a 1 year certificate of deposit
(CD) that paid an annual interest rate of 4%, compounded quarterly, the CD
would earn 1% interest per quarter on the account balance. The account balance
includes interest previously credited to the account.
Compound Interest Example
1st
Quarter
$1,000
2nd
3rd
4th
Quarter
Quarter
Quarter
$1,010 $1,020.10 $1,030.30
84
Notes
1st Quarter
$1
$98
0.010204
1.010204
$99
-l%
2nd Quarter
$1.01
$101
0.01
1.020204
$103.04
4.08%
3rd Quarter
$1.02
$102
0.01
1.030204
$105.08
1.98%
4th Quarter
$1.03
$99
0.010404
1.040608
$103.02
-1.96%
$100. This is the compound yield, and this return can be considered to be
the return on the investment of $100.
85
Ps
Year 1
5%
5%
$105.00
$5.00
5%
Year 2
5%
5%
$110.25
$10.25
Year 3
5%
Year 4
5%
5%
5%
$115.76 $121.55
$15.76 $21.55
5.4%
Year 3
30%
16%
$156.00
Year 4
-40%
-1.6%
$93.60
($6.40)
-1.6%
Year 4
115%
-42.7%
$10.75
($89.25)
-22.3%
Notes
Dollar Return
ROI
Year 1
$100
10%
Year 2
$55
5.5%
Year 3
$60
6%
Year 4
$50
5%
ROI values typically used for personal financial decisions include Annual
Rate of Return and Annualised Rate of Return. For nominal risk investments such
as savings accounts or certificates of deposit, the personal investor considers the
effects of reinvesting/compounding on increasing savings balances over time.
For investments in which capital is at risk, such as stock shares, mutual fund
shares and home purchases, the personal investor considers the effects of price
volatility and capital gain/loss on returns.
Profitability ratios typically used by financial analysts to compare a
company's profitability over time or compare profitability between companies
include Gross Profit Margin, Operating Profit Margin, ROI ratio, Dividend
yield, Net profit margin, Return on equity, and Return on assets.
During capital budgeting, companies compare the rates of return of
different projects to select which projects to pursue in order to generate
maximum return or wealth for the company's stockholders. Companies do so
by considering the average rate of return, payback period, net present value,
profitability index, and internal rate of return for various projects.
89
Note's
A return may be adjusted for taxes to give the after-tax rate of return. This
is done in geographical aim or historical times in which taxes consumed or
consume a significant portion of profits or income. The after-tax rate of return
is calculated by multiplying the rate of return by the tax rate, then subtracting
that percentage from the rate of return.
A return of 5% taxed at 15% gives an after-tax return of
4.25% 0.05 x 0.15 = 0.0075
0.05 - 0.0075 = 0.0425 = 4.25%
A return of 10% taxed at 25% gives an after-tax return of
7.5% 0.10 x 0.25 = 0.025
0.10 - 0.025 = 0.075 = 7.5%
Investors usually seek a higher rate of return on taxable investment returns
than on non- taxable investment returns.
A return may be adjusted for inflation to better indicate its true value in
purchasing power. Any investment with a nominal rate of return less than the
annual inflation rate represents a loss of value, even though the nominal rate of
return might well be greater than 0%. When ROI is adjusted for inflation, the
resulting return is considered as an increase or decrease in purchasing power. If
an ROI value is adjusted for inflation, it is stated explicitly, such as "The return,
adjusted for inflation, was 2%."
Many online poker tools include ROI in a player's tracked statistics,
assisting users in evaluating an opponent's profitability.
110
--
IRR means
returns are often used by academics in their research
iketwits' Activity 3
Select a project of your choice and use IRR technique for the evaluation of
the project.
cash is the purchase price, the NPV is simply the PV of future cash flows minus
the purchase price (which is its own PV). NPV is a central tool in discounted
cash flow (DCF) analysis, and is a standard method for using the time value of
money to appraise long-term projects. Used for capital budgeting, and widely
throughout economics, finance, and accounting, it measures the excess or
shortfall of cash flows, in present value terms, once financing charges are met.
Notes
The NPV of a sequence of cash flows takes as input the cash flows and a
discount rate or discount curve and outputting a price; the converse process in
DCF analysis, taking as input a sequence of cash flows and a price and inferring
as output a discount rate (the discount rate which would yield the given price as
NPV) is called the yield, and is more widely used in bond trading.
Formula
Each cash inflow/outflow is discounted back to its present value (PV).
Then they are summed. Therefore, NPV is the sum of all terms,
where
Rt
(1 + i)t
t - the time of the cash flow
i - the discount rate (the rate of return that could be earned on an investment in
the financial markets with similar risk.)
Rt- the net cash flow (the amount of cash, inflow minus outflow) at time t (for
educational purposes, Ro is commonly placed to the left of the sum to emphasize
its role as (minus the) investment.
The result of this formula if multiplied with the Annual Net cash in-flows
and reduced by Initial Cash outlay will be the present value but in case where
the cash flows are not equal in amount then the previbus formula will be used to
determine the present value of each cash flow separately. Any cash flow within
12 months will not be discounted for NPV purpose.
The discount rate
The rate used to discount future cash flows to their present values is a key
variable of this process.
A firm's weighted average cost of capital (after tax) is often used, but
many people believe that it is appropriate to use higher discount rates to adjust
for risk or other factors. A variable discount rate with higher rates applied to
cash flows occurring further along the time span might be used to reflect the
yield curve premium for long-term debt.
Another approach to choosing the discount rate factor is to decide the
rate which the capital needed for the project could return if invested in an
alternative venture. If, for example, the capital required for Project can earn
five per cent elsewhere, use this discount rate in the NPV calculation to allow
a direct comparison to be made between Project A and the alternative. Related
Project Estimation and Economic Analysis
91
Notes
We compute the part or fraction of the next year's cash inflow need to
payback the initial cash outlay by taking the initial cash outlay less the
cumulative total in the last step then divide this amount by the next year's
cash inflow. E.g., ($10,000 - $ 9,000)/$3,000 = 0.334
To now obtain the payback period in years, we take the figure from the
last step and add it to the year from the step 2. Thus our payback period is
2 +.334 = 2.334 years
Summary
98
The time and cost estimation is the most daunting and challenging task
for success of the project. The estimates are the absolutely necessary
inputs for successful implementation of the project within the stipulated
resource constraints.
In the top-down approach, the total time and costs mentioned for the
whole project is taken as reference and the same is not broken down to
the individual task level. This is also called macro estimation.
Payback period: It measures the time required for the cash inflows
to equal the original outlay. It measures risk, not return.
Notes
Keywords
Self-Assessment Questions
1.
What is time and cost estimation? What is the importance of time and cost
estimation for project management?
99
Notes
2.
What are the different approaches to time and cost estimation? Give their
comparison.
3.
----------
5.
What is IRR technique? Explain the process and use of IRR for project
evaluation.
6.
What is ROI technique? Explain the process and use of ROI for project
evaluation.
7.
What is NPV technique? Explain the process and use of NPV for project
evaluation.
8.
What is EVA technique? Explain the process and use of EVA for project
evaluation.
9.
What is Payback technique? Explain the process and use of Payback for
project evaluation.
Ratio, Apportion, Function point and Learning Curve methods are macro
methods of project estimation.
2.
2.
100
1.
True
2.
True
Notes
2.
False
2.
True
2.
The EVA is a registered trademark by its developer, Stern Stewart and Co.
101
Notes
102 j
Organising Projects
Structure:
eal se io
UNIT
Organising Projects
103
gla Notes
Objectives
After going through this unit, you will be able to:
.......7,7
104
Notes
Decentralised reporting
Flat hierarchy
High transparency
Permanent monitoring
Rapid response
Shared reliability
Matrix hierarchy
Organising Projects
105
Notes
Post-bureaucratic
The term of post-bureaucratic is used in two senses in the organisational
literature: one generic and one much more specific. In the generic sense the
term post-bureaucratic is often used to describe a range of ideas developed
since the 1980s that specifically contrast themselves with Weber's ideal type
bureaucracy. This may include total quality management, culture management
and matrix management, amongst others. None of these however has left
behind the core tenets of bureaucracy. Hierarchies still exist, authority is still
Weber's rational, legal type, and the organisation is still rule bound. Heckscher,
arguing along these lines, describes them as cleaned up bureaucracies, rather
than a fundamental shift away from bureaucracy. Gideon Kunda, in his classic
study of culture management at 'Tech' argued that 'the essence of bureaucratic
control the formalization, codification and enforcement of rules and regulations
does not change in principle it shifts focus from organisational structure to the
organisation's culture'.
Another smaller group of theorists have developed the theory of the
Post-Bureaucratic Organisation provide a detailed discussion which attempts
to describe an organisation that is fundamentally not bureaucratic. Charles
Heckscher has developed an ideal type, the post-bureaucratic organisation, in
which decisions are based on dialogue and consensus rather than authority and
command, the organisation is a network rather than a hierarchy, open at the
boundaries (in direct contrast to culture management); there is an emphasis
on meta-decision-making rules rather than decision-making rules. This sort
of horizontal decision-making by consensus model is often used in housing
cooperatives, other cooperatives and when running a non-profit or community
organisation. It is used in order to encourage participation and help to empower
people who normally experience oppression in groups.
Still other theorists are developing a resurgence of interest in complexity
theory and organisations, and have focused on how simple structures can be
used to engender organisational adaptations. For instance, Miner et al. (2000)
studied how simple structures could be used to generate improvisational
outcomes in product development. Their study makes links to simple structures
and improvises learning. Other scholars such as Jan Rivkin and Sigglekow, and
Nelson Repenning revive an older interest in how structure and strategy relate
in dynamic environments.
Darwin's natural selection is a great thing. The shape of every species
is crafted over thousands of years, to get the functions it needs to survive in
the environment it operates. If it does not have the .necessary skills, it just dies
and is doomed with extinction. All the beautiful, blonde, long legged creatures
survive.
The Homo Projectus is an ugly thing. It survives in extreme situations,
where dirt has to be shoved. In this case it has the aspects of a hog. But to get
the right features to have a party of hogs operating in such a way the pack
will survive is something completely different. We cannot wait until nature has
106
killed all unsuccessful project organisations (the hog party), so the software
project manager has to help nature a little bit, tinkering with the organisation,
so it might have a chance to survive in the corporate jungle.
Notes
Organising Projects
107
Notes
Project
Head of the
Implementing Agency
Coordination
i
Head of the Department
(Functional manager)
r
Head of the Department
(Functional Manager)
(blue boxes represent staff of the Departments engaged in the project activities)
contains all the necessary resources and functions within it. Divisions can be
categorised from different points of view. A distinction can be made on the basis
of geographical basis (a US division and an EU division) or on product/service
basis (different products for different customers: households or companies).
Another example, an automobile company with a divisional structure might
have one division for SUVs, another division for subcompact cars, and another
division for sedans. Each division would have its own sales, engineering and
marketing departments.
The projectised organisation or divisional structure, shown in Figure 5.2
is a structure where the focus is on teams with cross-functional expertise. Most
of the organisation's resources are involved in project work team's mission to
complete the project. All team members working for a specific project have one
clear superior, the project manager and they all refer to him/her.
Project
Coordinadon
Project Manager ij
Head of the
Implementing Agency
Project Manager
staff
staff
Project Manager
4H
staff
stett
staff
staff
Notes
Notes
Market Structure
Market structure groups employees together based upon specific markets
in which the company sells.
Geographic structure
Geographic structure groups employees together based upon specific
geographic location. This is often used by large companies that operate in many
areas throughout the United States or in both the US and overseas.
Matrix structure
This structure is a blend of functional and projectised organisations. In
the matrix structure (Figure 5.3), the personnel engaged in the project activities
belong to one or more functional units (departments). For project related
issues the project team members (staff) report to the Project Manager, who
is responsible for the timely completion of the project activities. For business
related issues the project team members report to the corresponding functional
managers. Once the implementation of the project or part of their work has
been completed, they are returned to the control of the functional manager for
reassignment. The person who is assigned to play the role of Project Manager
for a specific project is not necessarily one of the functional managers, but it can
be a single staff member possessing the appropriate skills and competencies.
The Project Manager in the matrix structure cooperates with the functional
manager to establish the resource requirements and plan their utilisation on
the project as well as to make the necessary revisions during the project's
implementation progress.
Heed of the
Implementing Agency
Prated
(blue boxes represent staff engaged in the project act Woes)
Cocandlcu
The main advantage of the matrix organisation is that it retains the benefits
of both functional and projectised structures. It also facilitates the effective
resource allocation to different projects.
Notes
For these reasons, the matrix structure is considered as the most effective
structure for implementing and managing projects and therefore is widely used.
The main disadvantage of the matrix structure is the potential for conflict
between the project manager and the functional manager regarding the resource
assignment, since the functional manager has to staff multiple projects with the
same experts.
The matrix organisation is an attempt to combine the advantages of the
pure functional structure and the product organisational structure. This form is
identically suited for companies, such as construction, that are "project-driven".
The figure below shows a typical matrix organisation.
In a matrix organisation, each project manager reports directly to the vice
president and the general manager. Since each project represents a potential
profit centre, the power and authority used by the project manager come directly
from the general manager.
Information sharing is mandatory in such an organisation, and several
people may be required for the same piece of work. However, in general, the
project manager has the total responsibility and accountability for the success
of the project. The functional departments, on the other hand, have functional
responsibility to maintain technical excellence on the project. Each functional
unit is headed by a department manager whose prime responsibility is to ensure
that a unified technical base is maintained and that all available information can
be exchanged for each project.
The basis for the matrix organisation is an endeavour to create synergy
through shared responsibility between project and functional management. Other
advantages of a pure matrix organisational form, to project management, include:
Conflicts are minimal, and those requiring hierarchical referrals are more
easily resolved.
111
Notes
The matrix structure groups employees by both function and product. This
structure can combine the best of both separate structures. A matrix organisation
frequently uses teams of employees to accomplish work, in order to take
advantage of the strengths, as well as make up for the weaknesses, of functional
and decentralised forms. An example would be a company that produces two
products, "product a" and "product b". Using the matrix structure, this company
would organise functions within the company as follows: "product a" sales
department, "product a" customer service department, "product a" accounting,
"product b" sales department, "product b" customer service department,
"product b" accounting department. Matrix structure is amongst the purest
of organisational structures, a simple lattice emulating order and regularity
demonstrated in nature.
Notes
113
Notes
into the projects, and, since each of the project managers originates and reports
back to the directive PMO, it guarantees a high level of consistency of practice
across all projects. This is effective in larger organisations that often matrix out
support in various areas, and where this setup would fit the culture.
The best type is very specific to the organisation, culture, and history of
what works and what does not. But the objectives are more or less to:
Standardise terminology
Being aware of these types can help you and your organisation more
easily accomplish this.
In a well-run project there is a lot going on. The routine project management
processes require a combination of special skills and administrative resource.
Rarely is it enough just to appoint a project manager. To do the job properly
requires time and resources.
It is common to pint in place a small project office team to deal with
the administrative tasks of the project, freeing up the project leadership and
project resources to get on with their jobs. A project office team might comprise
roles such as project manager, project planner, progress tracker, financial
controller, process administrator (change control, risks, issues, configuration,
documentation management), quality controller, communications manager,
organisational change manager, and administrative support.
It may be beneficial to use an integrated set of support tools. Project
information can be shared among the team members from a single data source.
Modern tools enable effective communication of project information through
existing user interfaces such as web browsers and email. Typical uses would be
to:
Manage the workflow for submitting and handling changes, risks, and
issues
Enforce controls, for example in the "checking in" and "checking out" of
documentation
Put in place the project management people, processes and technology. Few
organisations get the most out of their programmes and projects. Intelligently
adapting a company's current approach to adopt the features of best-practice
114
Am I certain this is the best investment we can make with our limited
resources?
Notes
Activity t Activity 1
1..
1.
The project manager must define the project, reduce it to a set of manageable
tasks, obtain appropriate resources and build a team to perform the work.
2.
The project manager must set the final goal for the project and motivate
his/her team to complete the project on time.
3.
4.
The project manager must assess and monitor risks to the project and
mitigate them.
Organising Projects
I
.- MI II
Notes
5.
116
The Project Manager is also the main focal point for liaison with other
departments, projects and initiatives within the organisation, taking into
account the needs and contributions of other internal groups.
The Project Manager is equally the main point of contact for aspects
requiring co-operation and co-ordination with external parties such as
the project's suppliers and contractors, customers, suppliers, regulatory
bodies, and other third parties making sure everything is in place to
guarantee success.
Project Management Operations
The Project Manager has direct responsibility for the activities of all
project participants, all project tasks and all deliverables.
Notes
Leadership Team
Steering Group
\ Project Dilutor
ti Sponsors
Internal Liaison Project' ExtemalLialon
Line De part/news Manager Trading Pariners
Othe z Projec is
Suppliers
IT /
Contractors
Project Team
Participant s
Deliverables
Tasks
Organising Projects
-117
Notes
Project Concept & Delude n
Pito or Stagg
Mar"runt
Plannirg
Projec t'
End
.
& Mugs&
001
11131
Bildiurvere
Ali
Sole & arm Ceti
Onionda Mowed
Cecueggis Cattel
Tam hi* abeam el Merl Coma do
Orgriatimpal Chug Hewed
tying Comisiall
Prg wood & howitirg
Sionateeir HIMIONSI
118
A project will pass through several stages or phases, each with a different
objective and deliverable. Typically the phases will require different
skills, structures and resource levels. It is normal to plan, estimate and
resource each phase separately (albeit overlapping the preliminary work
to avoid stoppages).
Risks will be assessed at the start of the project. Contingency plans and
avoiding action will be defined as appropriate. The risk management
process will pro-actively monitor risks throughout the project. Risk
assessments and plans will be modified as appropriate.
The issues management process will ensure they are considered and
addressed.
The scope of the project and specific changes to the solution will be
controlled through a management process with appropriate balances and
controls focused on achieving optimum overall benefit.
The needs to communicate outside the team with other parts of the
organisation, customers, suppliers, and other parties will be assessed. A
course of communications will be defined and actioned.
At the end of the project, there will be several activities to transition work,
processes and deliverables to line operation. The team also need to ensure
filing and documentation is in good order, leaving behind sufficient detail
for the operation of the system, audits concerning the project, and as a
baseline for future maintenance and development. People, equipment and
facilities need to be demobilised.
After the live solution has settled down, it is normal to organise a PostImplementation Review to measure the success of the project, to see what
further improvements can be made, and to learn lessons for the future.
Notes
Organising Projects
119
Organization Type
Matrix
Project
Oriente
-------PM Authority
011101111011bn
Coordinate project plan development. execute the plan, and manage the
change control process to ensue that all aspects of the project are
_ woildno together.
Establish project scope at the start. Develop and impiement plans and
Scope
procedures to verify that scope Is achieved and maintained. Define and
Management
oversee the process for controlling chances to the scope.
identify potential risks Mitigate large risks and plan how to deal with
Risk Management
smaller risks Monitor the project to detect and resolve problems.
Time and Schedule Estimate the duration of project activities. trie proper sequence of these
activities, and develop and control the project schedule.
Management
Estimate project costs and develop and control the project budget.
Cost and Budget
Management
..
Establish and control processes to ensure project goals are met to the
Quality
stakeholders' satisfaction. This includes quality planning. quality
Management
1 assurance. and quality control.
Define methods and lines of reporting and inforrnauon distnbution: Who
Communications
gets reports and project information? How often? What is the content?
Oversee procurement and delivery of materials, equipment, and services
Procurement
needed for the project This includes planning, solicitation, source
Management
selection. and contract administration.
Develop good leadership qualities Plan learn organization. obtain the
Human Resources
right people to staff the positions, and develop thew skills as Individuals
Management
and as a team.
Develop a systematic approach to project control integrating cost and
Earned Value
schedule control with performance control.
Management
Bear in mind that the Project Manager needs to achieve this without direct
control over the participants. The Project Manager will not have power over the
leadership, nor the internal and external contributors. Even in the project team
there may be loaned staff, part-timers and sub-contractors who will have their
prime loyalties elsewhere.
Notes
2.
P41"
Activity 2
Organising Projects
121
Notes
Stage I
Team membership is an important determinant of team performance. In
many cases it is possible to predict the outcome of a project, its possible success
or failure, from the group of people assigned to the team. Unless the team is
selected carefully and unless the leader is convinced that that team members
can do the job, project success may be jeopardized.
It is not necessarily true that all team members must be stars in their
own right. Many high performance teams are comprised of competent but not
necessarily outstanding team members. What makes the difference? Leadership!
Given the right leadership, a group of competent individuals can be developed
into a high-performing team.
Stage II
Stage II requires that a team culture must be established or if an appropriate
culture already exists, the culture must be reinforced. What is important is
that effective team culture cannot be assumed nor can the active process of
developed a team culture be ignored. An excellent example of this is the Boeing
777 team approach, which was established before the design project began and
communicated clearly to project team members. It was an open team culture
that encouraged constructive criticism and to a large extent it was this culture
that contributed to a very successful project outcome.
There are many ways to create a team culture. Consider the process of
spring training in professional baseball. In the US, teams start training in midFebruary and continue for about six weeks. Every day they work on individual
and team skills in preparation for the Major League season beginning in early
April. Wouldn't it be unthinkable for the Major League season to start without
spring training? Unthinkable for the team to meet for the first time moments
before the first game of the season
Yet most of our projects begin this way there is no period during which
we work with individuals and teams to build the kind of team culture capable of
achieving high performance results.
Perhaps we need spring training sessions before each project begins.
Stage III
The Boeing case example underscores the importance of deliberate team
management throughout the project. This is especially true when a new culture,
as was true in the Boeing case, was established. What we have learned is that it
is unlikely for a team to perform at its full potential without constant monitoring
and feedback. If left on its own team behavior may not be in the best interest of
the project.
Team selection
There are two variants of the team selection process. In the first variant,
there is little leeway in choosing team members because there may be few if
any choices. There may be, for example, a software design team that is routinely
122
used for a specific software project. Consider also a large joint project where
team members come from several organisations. It may not be possible to use
the same criterion when screening members.
In the second there may be considerable leeway in selecting members.
The project leader may have the option of interviewing several people to fill
each spot on the team.
Fiat Group in Italy, for example, maintains a database of employees, their
skill levels, training, evaluations, and availability. They have found this to be a
very effective way to assign team members to projects.
When there is choice in choosing team members, the process should
involve those who are positively predisposed toward the project and those who
have achieved a successful track record. But isn't this usually how selection
proceeds? No, not always. In some situations team members are chosen because
they or their supervisors may insist they be included. Sometimes including these
individuals may have a hidden agenda.
These issues, like many other management issues that need to be resolved
at the beginning of a project, are deferred in the hope that the issue will resolve
itself or go away.
Sometimes it does and sometimes it doesn't. One reason that issues of
team composition are resolved expeditiously is because the negotiation process
to solve them in another way takes time, and most leaders are anxious to get
busy with the project.
Network
Another modern structure is network. While business giants risk becoming
too clumsy to be proactive (such as), act and react efficiently, the new network
organisations contract out any business function that can be done better or more
cheaply. In essence, managers in network structures spend most of their time
coordinating and controlling external relations, usually by electronic means.
Some organisations are outsourcing its clothing to a network of 700 suppliers,
more than two-thirds of which are based in low-cost Asian countries. Not owning
any factories, H&M can be more flexible than many other retailers in lowering
its costs, which aligns with its low-cost strategy. The potential management
opportunities offered by recent advances in complex networks theory have been
demonstrated including applications to product design and development, and
innovation problem in markets and industries.
Virtual
A special form of borderless organisation is virtual. It works in a
network of external alliances, using the Internet. This means while the core
of the organisation can be small but still the company can operate globally
and be a market leader in its niche. According to Anderson, because of the
unlimited shelf space of the Web, the cost of reaching niche goods is falling
dramatically. Although none sell in huge numbers, there are so many niche
Organising Projects
Notes
Notes
products that collectively they make a significant profit, and that is what made
highly innovative Amazon.com so successful.
Notes
2.
SCIM,
141Py
Summary
Organising Projects
125
The best type is very specific to the organisation, culture, and history of what
works and what does not. But the objectives are more or less to implement
a common methodology, standardise terminology, introduce effective
repeatable project management processes, provide common supporting
tools and to improve levels of project success within the organisation.
Conflict that forces us to reframe a problem and take another view may
improve the outcome or lower the risk of failure. But there is also conflict
that is dysfunctional and serves only to sidetrack the team, waste time,
cost money, and threaten group process.
Project Management Operations
4Keywords
Notes
t S 7i.- -
"''roti
estios
1.
2.
3.
4.
5.
6.
7.
8.
2.
Project manager has direct responsibility for the activities of all project
participants, all project tasks and all deliverables.
False
2.
True
Organising Projects
127
Notes
128
Project Planning
Structure: ow
6.1 Project Life Cycle
UNIT
Project Planning
129
Notes
Objectives
After going through this unit, you will be able to:
K..
Activity
Closing
Tiovd
Fin sh
130
Planning Processes
Notes
Controlling Processes
Controlling processes are ongoing throughout most of the project. They
include verifying that the project is proceeding according to plan or determining
where and how much a deviation is occurring. They are absolutely essential to
the progress and success of the project. They include the following:
Schedule control
Cost control
Quality control
Project Planning
131
Notes _
Figure 6.2 illustrates an example of a very generic project life cycle with its
phases and major deliverables.
De fi n tio n )0(Project Rules
These project rules are written in three documents: the project statement
of work (PSOW), the project responsibility matrix, and the project
communication plan. The PSOW establishes the scope of the project and
documents what is to be accomplished. For an internal project, the PSOW
becomes the primary requirements document. However, the PSOW is not
the same as a contract statement of work (SOW). For a project where much
of the work is contracted, the SOW is a binding, contractual agreement.
Notes
WO* Ph41s,
Determine goals, scope.
and project constraints.
11 Announces Project
- States Purpose
- Identifies Project Manager
I Stateraent of Support
1/4c."
ri--
Responstiltty Matrix
Define communications
channels. methods,
frequency. and content.
Communications Plan
The project has specific goals to accomplish, and you understand the
reasoning behind them.
You understand the level of authority you have been granted in relation
to the project and the rest of the organisation, and the level of authority is
appropriate.
You understand what you are responsible for delivering at both a macro
and a micro level.
The
phase begins when upper management creates a
project charter that defines the project's purpose and identifies the
PM.
PSOW stands for
Notes
Again, a manager can control any three of these four constraints. For
example, if one chooses to control schedule, cost, and quality, the functional
capability of the product may have to be reduced. Likewise, if one attempts to
expand functional capability (i.e., requirements bloat) while maintaining cost
and quality, the schedule may have to be relaxed to maintain the balance.
Other planning processes include the following:
Sequence activities.
Estimate costs.
Major risks.
Notes
I-
. uglesi "
"-- i
Elements
Objectives
Activities
Schedule
Budget
Organisation
138
Notes
Ectiattoitfiftaitik.
Product or Goal
LProjoct Plan
Feedback
What your project's expenditures are to date and any difference between
those and the budget?
The status of project activity completion along the critical path and any
difference between that and the schedule.
Any issues or problems with quality or performance that may impact the
critical path.
Project Planning
139
Notes
Closeout Phase
Product Is
delivered or
goals are met. ;
....
Stakeholders Satisfied
Complete contractual
obligations (contract
closeout).
Contract Closed
Project History
2.
time and has multiple activities rolled in it. This process can easily be used for
project monitoring also with very good results.
Notes
The relationship of the said activity with other activities in the project
This database itself creates a very handy footprint for monitoring the
activities of the project.
If we apply the concept of PERT to the project (which anyway is
necessary), what we additionally get is the range of time limits for each activity
within which the same is to be completed. The range is defined by using the
probability method from statistics and is therefore pretty reliable. These time
estimate ranges could be also used to estimate the value ranges for other
resources of the project.
When we combine this with the database mentioned above, what we have
in hand is a clear complete database for monitoring the project from "Start to
Finish".
The Monitoring Process
A. The management process
Define the monitoring and review process. Also define the review
calendar for each activity.
Define the reporting process two-way reporting, one for the team
and the other for the top management team.
Define the mechanism which will enable the project team to raise
the red flag to draw the attention of the people before it's too late.
Project Planning
141
Notes
B. Working process
Prepare/refer to a format for each activity that defines the activity as
mentioned above. This formatted document is a pre-requisite for CPM
process. As mentioned above, it clearly gives all the information for each
activity.
Ideal way is to use the activity format from CPM process as also the
network diagram which makes the variables relevant to the project
activity flow.
Here the review process starts taking the PDCA route and could be
made three pronged (Trishul)
First pointer looks at the part of the work that should have happened
at the time of review. The process checks whether same has been completed
within the planned parameters. If there are deviations, it takes.note of them and
analyses the reasons for deviations and the CAPA strategy for the deviations. It
also evaluates the impact of the deviations on overall project parameters and the
subsequent activities.
Second pointer tries to look at the activities that are already underway
or are planned for initiation in the immediate future. For the activities already
underway, it monitors the progress with respect to the plan and identifies for
additional needs (if any) to ensure the plan compliance. It also factors the inputs
coming from the first pointer for their possible effects on the activities on hand
and the necessary CAPA strategy. With the second pointer, we are actually
trying to be proactive so as to build the first pointer leanings into the working of
subsequent project activities.
Third pointer actually tries to look at the immediately succeeding
activities from the perspective of the experience from the first pointer. This is a
completely proactive step to build the learning into all subsequent activities.
Every time the review is made as per the calendar, all three activities are
carried out. With this approach, we achieve the continuity in the monitoring
process. With the second and third pointers we have already created a process
for monitoring the activities which were underway or were about to begin.
In the subsequent review process this data becomes the data base for review
and thus reduces the review efforts as well as eliminates many of the possible
failures.
A typical integrated planning, monitoring and control system for a
major project starts with development of master control network which forms
14.2
the base of overall planning and monitoring of the projects. Based on this
network, engineering schedule, tender schedule and procurement schedule
are finalised and based on these schedules overall construction schedule of
the project is formulated. This overall construction schedule is further broken
up into contractor's schedule, monthly construction programme, and weekly
programmes. Based on frequency of reviews, weekly progress report, monthly
progress report and exception report are formulated. Exception report forms the
basis for various action plan of the project.
Detailing:
(SoW, WBS)
Notes
Scheduling:
I PERT, CPM etc.
udgets
Feedback
Management
Decision making
Reports
(Time, cost,
Performance)
Tracking:
Time/Cost/
Performance
2.
Project Planning
443
Notes
Notes
Activity 1
Level 1
Air
Vehicle
Training
Peculiar
Support
Equipment
Level 2
1
Receiver
Fire
Control
Communication
Equipment
Services
Depot Level 3
11147
Notes
tasks, subtasks, and work packages) which include all steps necessary to achieve
the objective.
The work breakdown structure provides a common framework for the
natural development of the overall planning and control of a contract and is the
basis for dividing work into definable increments from which the statement of
work can be developed and technical, schedule, cost, and labour hour reporting
can be established.
A work breakdown structure permits summing of subordinate costs
for tasks, materials, etc., into their successively higher level "parent" tasks,
materials, etc. For each element of the work breakdown structure, a description
of the task to be performed is generated. This technique (sometimes called a
System Breakdown Structure) is used to define and organize the total scope of
a project.
The WBS is organised around the primary products of the project (or
planned outcomes) instead of the work needed to produce the products (planned
actions). Since the planned outcomes are the desired ends of the project, they
form a relatively stable set of categories in which the costs of the planned actions
needed to achieve them can be collected. A well-designed WBS makes it easy
to assign each project activity to one and only one terminal element of the
WBS. In addition to its function in cost accounting, the WBS also helps to map
requirements from one level of system specification to another, for example, a
requirements cross-reference inatrix mapping functional requirements to high
level or low level design documents.
WBS Design Principles
One of the most important Work Breakdown Structure design principles
is called the 100% Rule. It has been defined as follows:
The 100% Rule states that the WBS includes 100% of the work defined
by the project scope and captures all deliverables internal, external and interim
in terms of the work to be completed, including project management. The
100% rule is one of the most important principles guiding the development,
decomposition and evaluation' of the WBS. The rule applies at all levels within
the hierarchy the sum of the work at the "child" level must equal 100% of the
work represented by the "parent" and the WBS should not include any work
that falls outside the actual scope of the project, that is, it cannot include more
than 100% of the work. It is important to remember that the 100% rule also
applies to the activity level. The work represented by the activities in each work
package must add up to 100% of the work necessary to complete the work
package.
Mutually Exclusive Elements
In addition to the 100% Rule, it is important that there is no overlap
in scope definition between two elements of a work breakdown structure.
This ambiguity could result in duplicated work or miscommunications about
responsibility and authority. Likewise, such overlap is likely to cause confusion
Project Management Operations
regarding project cost accounting. If the WBS element names are ambiguous,
a WBS dictionary can help clarify the distinctions between WBS elements.
The WBS Dictionary describes each component of the WBS with milestones,
deliverables, activities, scope, and sometimes dates, resources, costs, quality.
Notes
The first is the "80-hour rule" which means that no single activity or group
of activities to produce a single deliverable should be more than 80 hours
of effort.
The last heuristic is "if it makes sense" rule. Applying this rule of thumb,
one can apply "common sense" when creating the duration of a single
activity or group of activities necessary to produce a deliverable defined
by the WBS.
Project Planning
149 .-
Notes
WBS LEVEL 2:
I. Maid*
1.1 Fraia. $ol
WBS LEVEL 1:
I. Mold* 1s
ucruk 641_
*Ude_
1.4 Orals. %Vim_
LS nide' trim _
1i1r4w11144_
t7 FIciect Sys
(16'
.$
1.1.4 Soot
1.2 Crank
1.3 141$.4.
1.11 Fred Vtrumi
1.32 Rw Wheel
1$
1.4 &akin Systm
6,
1.4 Shitii Systaln
100 \ lertsvit144
111 Co-440_
1.0.2 Design_
1./13 Portably.
1.14 Teeing
1.7 Proiest Ito
27
3
3
13
17
6
3
5
10
I/
100
150
The WBS construction technique employs the 100% rule during WBS
construction. The figure on the right shows a work breakdown structure
construction technique that demonstrates the 100% rule and the "progressive
elaboration" technique. At WBS level 1 it shows 100 units of work as the total
scope of a project to design and build a custom bicycle. At WBS level 2, the
100 units are divided into seven elements. The number of units allocated to
each element of work can be based on effort or cost it is not an estimate of task
duration.
Notes
The three largest elements of WBS level 2 are further subdivided at level
3. The two largest elements at Level 3 each represent only 17% of the total
scope of the project. These larger elements could be further subdivided using
the progressive elaboration technique.
WBS design can be supported by software (e,g., a spreadsheet) to allow
automatic rolling up of point values. Estimates of eff9rt or cost can be developed
through discussions among project team members. This collaborative technique
builds greater insight into scope definitions, underlying assumptions, and
consensus regarding the level of granularity required to manage the project.
Pitfalls and Misconceptions
A work breakdown structure is not an exhaustive list of work. It is instead
a comprehensive classification of project scope.
A WBS is neither a project plan, a schedule, nor a chronological listing.
It is considered poor practice to construct a project schedule (e.g., using project
management software) before designing a proper WBS. This would be similar
to scheduling the activities of home construction before completing the house
design. Without concentrating on planned outcomes, it is very difficult to follow
the 100% rule at all levels of the WBS hierarchy.
AWBS is not an organisational hierarchy. Some practitioners make the
mistake of creating a WBS that shadows the organisational chart. While it is
common for responsibility to be assigned to organisational elements, a WBS
that shadows the organisational structure is not descriptive of the project scope
and is not outcome-oriented.
WBS updates, other than progressive elaboratiOn of details, require formal
change control. This is another reason why a WBS should be outcome-oriented
and not be prescriptive of methods. Methods can, and do, change frequently, but
changes in planned outcomes require a higher degree of formality. If outcomes
and actions are blended, change control may be to rigid for actions and too
informal for outcomes. A WBS is not a logic model. Nor is it a strategy map.
:;',ctvity
Activity 2
Prepare a work breakdown structure to minimum three levels for making tea
starting from collecting the resources.
Project Planning
151
Notes
List the major activities of the project: Only the major project activities
should be listed. Detailed task assignments should be made in the project
plan. Because the responsibility matrix shows interaction between
organisations, it needs to emphasize the different roles required for each
task. In highlighting the roles of various stakeholders involved in the
project's major activities, the responsibility matrix should usually use
the same level of detail as the scope statement. On very large projects it
can be useful to develop multiple responsibility matrixes, with differing
levels of detail. These matrixes will define subprojects within the larger
project.
2.
3.
4.
that the project manager is always left with a written document to refer to
in the event of a dispute.
Notes
# 4 Standards
Listed for each
task
This is the skilled role of the planner, viz., to determine the nature
and objectives of each phase.
Project Planning
153
Notes
154
Summary
Projects, like products, have life cycles and are usually performed in
phases. Each phase accomplishes specific work toward reaching the
project goal and produces one or more deliverables. These are tangible,
real items used in attaining the final goal of the project, and could include
plans, studies, designs, or software or hardware prototypes. The end of a
phase is defined by completing its deliverable.
The planning phase uses the project rules as a foundation and defines
the path to achieve the project goals. It is performed by the PM and
the core project team, which interfaces with appropriate elements of
the organisation, and identifies the actual work to be done. It includes
estimating schedule, cost, and resources required to perform the work,
and produces plans to serve as a baseline and direct the work. A key part
of schedule planning is :identifying the critical path. This is the chain of
interdependent, sequential project activities that takes the longest time
to complete, and thus determines the minimum schedule for the project.
Planning also includes risk identification and risk reduction efforts. The
results of the planning phase become the project plan.
Project Execution Phase is the phase where project goals are achieved.
The execution phase entails directing the various work groups in their
activities, monitoring their progress, solving problems and resolving
issues that will certainly come up, making changes to the plan, and
coordinating these changes. This phase is complete when the product is
complete, the project goals are reached, or the project is terminated.
of tying up loose ends. Any unresolved issues from the contract or SOW
are resolved in this phase. The contract is signed off as fulfilled and all
other paperwork is completed. A very important activity of this phase
is assembling the project history. This is a summary of all that has been
accomplished.
One of the major reasons for project failure is the failure to monitor it
when it is being executed. We have already seen that project management
is substantially different than the normal work management. The primary
differentiating factor is the diverse nature of activities and the fact that
the project has a strong time pressure on it. Also, there is a tremendous
management focus on projects for obvious reasons.
Responsibility matrix lays out the major activities in the project and
precisely details the responsibilities of each stakeholder involved in
a project. It is an important project communication tool because all
stakeholders can see clearly who to contact for each activity.
Notes
Keywords
Project Planning
.155
3.
4.
5.
6.
7.
8.
9.
2.
True
2.
False
.156
1.
2.
Notes
The project closeout phase begins with the delivery of the product or
completion of the project goals or project termination.
2.
False
2.
True
() Suggested Reading
1.
Project Planning
157
Notes
--- , -------
158
UNIT
Structure:
7.1 Project Scheduling
7.2 Project Networks
7.3 Critical Path Method
7.4 Critical Path Calculations
7.5 Project Floats
7.6 Program Evaluation and Review Technique (PERT)
Summary
Key Words
Self-Assessment Questions
Answers to Check your Progress
Suggested Reading
159
Notes
Objectives
After going through this unit, you will be able to:
Activity A
Activity B
Activity C
i
Activity D
Days
This way the PM can draw up all the activities in a structured manner so
as to capture everything. This chart is known as Gantt chart, named after the
person who first used it for project scheduling work.
A Gantt chart is a type of bar chart that illustrates a project schedule. Gantt
charts illustrate the start and finish dates of the terminal elements and summary
PIM
Notes
Activity A
Activity B
Activity C
Activity D
161
Notes
75% complete
START-TO-START
67% complete:
FINISH-TO-START
50% complete
FINI81-140FINISH4,
J0% complete
111
1111 0% complete
0%
C clple
te
0% complete
0% complete
A Gantt chart lays out the order in which the tasks need to be carried out.
Early Gantt charts did not show dependencies between tasks but modern
Gantt chart software provides this capability.
A Gantt chart lets you see immediately what should have been achieved
at any point in time.
A Gantt chart lets you see how remedial action may bring the project back
on course.
Most Gantt charts include "milestones" which are technically not available
on Gantt charts. However, for representing deadlines and other significant
events, it is very useful to include this feature on a Gantt chart.
more than about 30 activities. Larger Gantt charts may not be suitable for most
computer displays. A related criticism is that Gantt charts communicate relatively
little information per unit area of display. That is, projects are often considerably
more complex than can be communicated effectively with a Gantt chart.
Notes
Gantt charts only represent part of the triple constraints (cost, time and
scope) of projects, because they focus primarily on schedule management.
Moreover, Gantt charts do not represent the size of a project or the relative size
of work elements, therefore the magnitude of a behind-schedule condition is
easily miscommunicated. If two projects are the same number of days behind
schedule, the larger project has a larger impact on resource utilization, yet the
Gantt does not represent this difference.
Although project management software can show schedule dependencies
as lines between activities, displaying a large number of dependencies may
result in a cluttered or unreadable chart.
Because the horizontal bars of a Gantt chart have a fixed height, they can
misrepresent the time-phased workload (resource requirements) of a project,
which may cause confusion especially in large projects. In the example shown
here, Activities E and G appear to be the same size, but in reality they may be
orders of different magnitude different. A related criticism is that all the activities
of a Gantt chart show planned workload as constant. In practice, many activities
(especially summary elements) have front-loaded or back- loaded work plans,
so a Gantt chart with percent-complete shading may actually miscommunicate
the true schedule performance status.
163
Notes
2.
Any activity that occurs before the given activity is called as preceding
activity.
Project Management Operations
3.
Any activity that occurs after the given activity is called as succeeding
activity.
4.
5.
6.
Closed loops within the network are normally avoided by following the
relationships and dependencies carefully and with the use of dummy activity.
7.
Dummy activities are used only when it's an absolute must for dependency
conformance.
Notes
There are different methods depending upon format of the network used.
There are two types of networks: Activity-On-Node (AON) and Activity-onArrow (AOA). Results are same in both the cases.
Arrow Diagram
The arrow diagram shows the required order of tasks in a project or
process, the best schedule for the entire project, and potential scheduling and
resource problems and their solutions.
Difference between AOA and AON
Method for constructing a unique AOA net with a node for each precedence
constraint of its corresponding AON network (yielding small number of dummy
arcs).
AON
165
AOA
Sometimes, dummy activities (dotted lines) are used for linking two
activities.
Air
WV
AIL
MIL
Situations in network diagram Given below are the situations which indicate
the construction possibilities of a network diagram.
a.
A
C
b. Both A and B must finish before C can start
B
c.
A
N,Dummy
4
C
CSC
-11111-0
Notes
Lay foundation
Lay
foundation
*. Dummy
1
Order material
Order material
(b) Correct precedence
relationship
Concurrent Activities
Network example
Illustration of network analysis of a minor redesign of a product and its
associated packaging.
Activity
number
1
2
3
4
5
6
7
8
9
10
11
Completion
time (weeks)
6
Redesign product
2
Redesign packaging
.
3
Order and receive components for redesigned product
2
Order and receive material for redesigned packaging
4
Assemble products
1
Hake up packaging
1
Package redesigned product
6
Test market redesigned product
S
Revise redesigned product
1
Revise redesigned packaging
1
Present results to the Board
8
9,10
Activity
number
can start
3
4
6
7
a
9
10
11
167
Notes MI
7(1)
0IWO 10'0
6(1)
4(2)
2(2)
1.
2.
The inputs of the project planning phase include Project Charter and
the Concept Proposal.
muvo Activity 1
Select any project and prepare a Gantt chart for the same.
of using CPA within the planning process is to help you develop and test your
plan to ensure that it is robust. Critical Path Analysis formally identifies tasks
which must be completed on time for the whole projdct to be completed on time.
It also identifies which tasks can be delayed if resource needs to be reallocated
to catch up on missed or overrunning tasks. The disadvantage of CPA, if you use
it as the technique by which your project plans are communicated and managed
against, is that the relation of tasks to time is not as immediately obvious as with
Gantt charts. This can make them more difficult to understand.
Notes
Earliest start
Week 0
Length
1 week
Type
Sequential
Dependent
on
Week 1
1 day
Sequential
Week 1.2
2 weeks Parallel
,
Week 1
2 weeks Sequential
Week 3
2 weeks Sequential
Week 3
2 weeks Sequential
Week 5
3 weeks Sequential
169
Notes
..... . . ,::-
Task
H. Quality assurance of
core modules
I.
Quality assurance of
supporting modules
Core module training
J.
Development and QA of
K.
accounting reporting
Development and
L.
QA of management
reporting
M. Development
of Management
Information System
Detailed training
N.
Earliest start
Week 5
Length
1 week
Type
Sequential
Dependent
F
Week 8
1 week
Sequential
Week 6
Week 5
1 day
1 week
Parallel
Parallel
C,H
E
Week 5
1 week
Parallel
Week 6
1 week
Sequential
Week 9
1 week
Sequential
I, J, K, M
Step 2 Plot the activities as a circle and arrow diagram. Critical Path Analyses
are presented using circle and arrow diagrams.
In these, circles show events within the project, such as the start and finish
of tasks. The number shown in the left-hand half of the circle allows you to
identify each one easily. Circles are sometimes known as nodes.
An arrow running between two event circles shows the activity needed
to complete that task. A description of the task is written underneath the arrow.
The length of the task is shown above it. By convention, all arrows run left to
right. Arrows are also sometimes called arcs.
An example of a very simple diagram is shown below:
Figure 2: Simple Circle and Arrow Diagram
I Week
-4 2
This shows the start event (circle 1), and the completion of the 'High
Level Analysis' task (circle 2). The arrow between them shows the activity of
carrying out the High Level Analysis. This activity should take 1 week.
Where one activity cannot start until another has been completed, we
start the arrow for the dependent activity at the completion event circle of the
previous activity. An example of this is shown below.
Figure 3: Circle and Arrow Diagram showing two activities that cannot be
started until the first activity has been completed.
1 Week
High Level Analysis.
Ftr
2 Weeks
(3
Core Module Anolviu
Activities are not drawn to scale. In the diagram above, activities are
1-week long, 2-week long and 1-day long. Arrows in this case are all the
same length.
In the example above, you can see a second number in the top, right- hand
quadrant of each circle. This shows the earliest start time for the following
activity. It is conventional to start at 0. Here units are whole weeks.
Notes
1 Week
supporting
(DOA atmodules
1 Week
Detailed Training
yoo 0
,046 too
0,64:004
it/ 4-
8vP
Here activities 6 to 7 cannot start until the other four activities (11 to 6, 5
to 6, 4 to 6, and 8 to 6) have been completed.
171
Notes
Critical Path: The longest path (time) determines the project duration.
Critical Activities: All of the activities that make up the critical path.
Earliest finish time (Ey): Earliest time an activity can finish = earliest
start time plus activity time.
EF= ES + t
Latest Start Time (LS): Latest time an activity can start without delaying
critical path time
LS= LF - t
Latest finish time (LF):, Latest time an activity can be completed without
delaying critical path time.
LS = minimum LS of immediate predecessors
c''de
Preceding
Activity
Duration (Days) 6
d, e h, i, j
13
15
17 19
12
Activity
Figure 1 represents the network diagram for the project activities as per above.
o917
h,0
0 Dpo
Figure 2 below shows calculation of duration for activities a, b and c. The square
indicates earliest start time and earliest finish time.
Notes
Notes
Figure 3 indicates time durations for all the activities in the project.
Project's EF = 33
:3
I
I b
b, 8
d, 13
IP
t
1)
j, 12 "If
2.
3.
It is not necessary that the critical path has maximum number of activities
on it.
4.
There can be more than one critical path for tbe same project.
5.
Any impact on any activity lying on critical path directly affects the
project completion immediately.
6.
The PM should focus on all activities on critical path as the first priority
to ensure compliance to schedules.
7.
Activities that lie on critical path are called critical activities. The total
project duration cannot be less than the total time required for completing
the critical path activities.
Notes
Shows the time available even if an activity' has a late start and early
finish.
It is the most adverse type of float and often results in a negative figure.
Also called Normal Float, it shows time for which an activity can be
delayed without delaying the early start of successor activity/activities.
If there are more than one succeeding activities, minimum of the floats
would be taken as free float.
It shows time for which an activity can be delayed from its ES without
delay in project completion. (In FF, when one activity was delayed, the
succeeding activity was started on time as per its ES and not delayed.)
175
Note _---
2.
3.
In case of free float, the formula is: Early Start of Successor Activities
minus Early Finish of Existing Activity. Naturally, if we can finish an activity
early but the next will start sometime later, we have a free float to delay our
activity.
Calculation of float under AOA - In case of AOA formulae are:
a)
b)
FF(i,j) = EF(j) - ES(i) - D(i,j), (If there are more than one activities,
minimum thereof)
c)
TF(i,j) = LF(j) - ES(i) - D(i,j) (If there are more than one activities,
minimum thereof)
......
176
a, 6
06
tb, 6
0,8
27 33
d, 93
8 21
c,5
9, 9
5 14
Step II: The diagram below shows the EST, EFT, LST and LFT for all the
activities.
Notes
f, 15
Step III: The diagram below shows the floats associated with each activity.
F, 15
A, 6
6
9
B, 8
0
4 23'29
27 33
J, 12
It is clear from the diagram that the float is nil for the critical path activities
177
Notes
1.
Activity 2
Prepare a network diagram for making tea starting from collecting resources
ending at making and serving the same and find critical path by assuming
\..t.ife estimates for each activity.
Pessimistic time (to - the time the activity would take if things did
not go well
Most likely time (tm) - the consensus best estimate of the activity's
duration
Optimistic time (to) - the time the activity would take if things did go
well
So every activity has the above 3 time estimates based on past experiences
and judgment of the project team. The activity time is calculated by the
following formula
T=
t +p
t
e to + 4 m
6
The concept of 3 time estimates as mentioned above clearly underlines the factor
of uncertainty involved in the estimation of times for the project activities.
The concept Te is developed based on the statistical concept of probability of
occurrence of a particular event. This is also based on the statistical concept
of normal distribution of events when you conduct the analysis of actual
experimental data.
This formula clearly shows the fact that the probability of the activity getting
carried in realistic estimated time of tmis 4 times more than the probability of
Project Management Operations
Notes
If the difference between the values of t., tp on one side and tn, on the other
side is substantially small, then it can be said that the activities are more likely
to be carried out in the given estimated time as also the project completion.
On the contrary hand, if these differences are large it can be safely said
that the probability of the activities and the project getting completed in time is
much smaller.
These deviations are evaluated based on 2 parameters namely:
1.
Variance
2.
Standard deviation
Both of these parameters try to capture the difference between the mean
time t1 and the two other extreme times t., tp frequency of their occurrence. More
is the difference and more is the frequency more so is the probability of project
getting completed in actual time different from the CPM time estimate.
Variance 62 = ((tp to)/6)2
Standard deviation = v (G)2 = (tp to)/6
One can observe from the CPM process that the schedule along the critical
path has the highest probability and therefore lowest variance amongst all the
paths.
As you compare the other paths with CPM path they would have lower
probability and therefore higher variance signifying larger possibilities of
deviations and delays.
In any recurring type of events it is known that the event need not
necessarily complete itself in the same amount of time since it depends on so
many variables.
Every activity is an event of this type and can normally be completed in
a range of time values from minimum time to maximum time. Somewhere in
between lies the most likely time or the realistic time value also known as the
mean value.
The project consists of many such activities and therefore would follow a
similar behavioural pattern having range of completion time values and a mean
realistic time.
The activity and the project are dependent on many independent variables.
The completion of activity (and project) will follow a pattern which is called
normal distribution pattern.
The possibility of completing the activity in minimum or maximum time
is much smaller as compared to the realistic mean time value ().
We know what standard deviation is (")
Frequency of occurrence around realistic mean time value (p) is always
'179
Notes
maximum. As you move away from (u) in either direction, the frequency of
occurrence reduces substantially.
The standard deviation C) defines this concept numerically. More is the
value of ('), lower is the frequency of occurrence and vice versa.
As a manager, we can have the values of (-) and () for each activity and
also for the whole project. These values help identify the activities that have
high values of C).
These activities are the ones which will have higher probability of
deviating from the mean time value ().
As such they become the target activities for the manager to focus and
work upon to avoid issues of delays and cost overruns.
One C) of deviation on either side of the mean value covers a probability
spectrum of little over 68%, two 0 covers little over 95% and three 0 covers
little over 99% of the probability.
Steps in PERT
Draw the network.
Analyse the paths through the network and find the critical path.
The length of the critical path is the mean of the project duration probability
distribution which is assumed to be normal
X -
Notes
Probabi I ity
PERT Example
Let us consider an example for time estimation using PERT. For this consider
the data as per following table.
Immed. Optimistic Most Likely Pessimistic
Activity Predec. Time (Hr.) Time (Hr.)
A
B
C
D
E
F
G
H
I
J
K
A
A
A
B,C
B,C
E,F
E,F
D,H
G,I
4
1
3
4
0.5
3
1
5
2
2.5
3
6
4.5
3
5
1
4
1.5
6
5
2.75
5
Time (Hr.)
8
5
3
6
1.5
5
5
7
8
4.5
7
----- -
..11111
Notes
For this network, the expected time and variance is calculated and shown
as follows:
Activity Expected Time Variance
A
B
C
D
E
F
G
H
I
4/9
4/9
0
1/9
1/36
1/9
4/9
1/9
1
1/9
4/9
6
4
3
5
1
4
2
6
5
3
5
K
The paths in the n
Path No.
1
2
3
4
5
6
7
8
9
Path activities
ADJ
AEHJ
ACFHJ
AEIK
ACGK
ACFIK
BGK
BFHJ
BFI-K
Path Duration
6+5+3
6+1+6+3
6+3 + 4 +6+3
6+1+5+5
6+3+2+5
6+3 + 4 +5 +5
4+2+5
4+4+6+3
4+4+5+5
Total Time
14
16
22
17
16
23
11
17
18
182
Advantages
PERT facilitates identification of the critical path and makes this visible.
PERT facilitates identification of early start, late start, and slack for each
activity.
Disadvantages
The network charts tend to be large and unwieldy require several pages to
print and special size paper.
When the PERT/CPM charts become unwieldy, they are no longer used to
manage the project.
Activity 3
Select any project and prepare a network diagram and estimate time using
PERT for the same.
The scheduling activity starts by first listing all the activities in a structured
manner.
Notes
184
Bar chart is one of the simplest methods to capture all the activities in a
graphical manner. It uses 2-axis method, the X axis is used to indicate
the time required for each activity and the Y axis indicates the various
activities.
This way the PM can diaw up all the activities in a structured manner so
as to capture everything. This chart is known as Gantt chart named after
the person who first used it for project scheduling work.
The most popular form of the project network is activity on node, the
other one is activity on arrow. The condition for a valid project network
is that it doesn't contain any circular references. Project dependencies
can also be depicted by a predecessor table. Although such a form is very
inconvenient for human analysis, project management software often
offers such a view for data entry.
For complex projects the most commonly used process is the "Networking
process". This was developed in 1957 by planners of DuPont and
Remington Rand companies. The process is known as Critical Path
Method or simply CPM, Another method was developed in 1958 by US
Navy and is known as Program Evaluation and Review Techniques or
simply PERT.
For both the methods, it is necessary to define every activity of the project
in specific way and assign the resources needed for the same. It is also
necessary to define the dependency relationship of each activity before
we embark on the project plan. Dependency clearly specifies as to when
the particular activity can start with respect to other activities (before or
after them).
Project Management Operations
Critical path method is used to find the path which is most critical
and needs focus on priority. It is defined as the longest path (time). It
determines the project duration. Critical activities are all of the activities
that make up the critical path.
Notes
Pessimistic time is the time, the activity would take if things did not go
well. Most likely, time is the consensus best estimate of the activity's
duration. Optimistic time is the time the activity would take if things did
go well.
So every activity has the above three time estimates based on past
experiences and judgment of the project team. The activity time is
calculated by the following formula:
T= te + 40 tm + t p
Pe Keywords!
Critical path: The longest path (time), it determines the project duration.
Earliest start time: Earliest time an activity can start and is equal to the
maximum earliest finish time of immediate predecessors.
Earliest finish time: Earliest time an activity can finish and is equal to
the earliest start time plus activity time.
Latest start time: Latest time an activity can start without delaying
critical path time.
1185
Notes
Free float: It shows time for which an activity can be delayed without
delaying the early start of successor activity/activities.
Total float: It shows time for which an activity can be delayed from its
ES without delay in project completion.
11 1
1
Self-Assessment Questions
1.
What is project scheduling? What are the tools used for project scheduling?
2.
What is the use of Gantt chart? How Gantt chart can be used for project
scheduling and tracking?
3.
4.
5.
6.
7.
What is PERT? How PERT can be used for project time estimation?
8.
For the following data, prepare the network diagram and find critical path.
Activity
Preceding Activity
AB
A
C
B
D
E
C
D
F
G
E,F
H
G
I
G
J
H,I
186
9.
Most likely
Duration (Days)
12
8
9
10
18
9
8
7
6
6
7
9
Pessimistic
Duration (Days)
16
10
10
12
21
12
9
9
10
8
8
12
10. Prepare network diagram and find floats and critical path.
Activity
A
B
C
D
E
F
G
H
I
J
Preceding Activity
A
A
B
C
D
E, F
G
G
H,I
2.
False
2.
True
Notes
Notes
Critical Path Analysis helps to identify the minimum length of the time
needed to complete a project.
2.
ClSuggested Reading
1.
444
UNIT
Notes
Objectives
After going through this unit, you will be able to:
Notes
191
Notes
to the project resource requirements the project plan should be refined when
necessary so that it is practical. The process of refining the plan to effectively
manage and schedule resources (sometimes referred to as resource modeling)
comprises of four major stages: resource definition, resource allocation, resource
aggregation, and resource leveling (which includes resource smoothing). In the
subsequent sections we will discuss of these major stages.
Resource Definition
The first step in resource modeling is to decide exactly what resources
are considered important enough to be modeled. While most resource
modeling is concerned with people or workers (such as welders or computer
programmers), it may also include other resources such as machines (such as
a computer of a particular specification), or space on a project where space is
restricted and where this restriction limits the amount of other resources which
can be deployed at any one time. Often resources are specified in terms of the
number of units of resource required, e.g., four mechanics or two computer
programmers. Alternatively, resources may be specified in terms of the hours
or days that a specific resource is required, e.g., 32 mechanic hours or 16
computer programmer days. Resources may be considered as consumable, such
as materials that may be used once and once only, or non-consumable, such as
people, which may be used again and again. The way in which consumable
resources are used is not critical as long as they are used efficiently. However,
the way in which non-consumable resources are used can have a significant
impact on the project. For example, there is a significant difference between
requiring 16 units of a non-consumable resource for one week, thus requiring
16 units to be made available at that time, and requiring one non-consumable
unit for 16 weeks, thus only requiring one unit which can be reused 16 times.
Resource modeling is therefore mainly concerned with non-consumable
resources with an important caveat. It should never be assumed that the quantity
of resources deployed and the task duration are inversely related. Thus, one
should never automatically assume that the work that can be done by one man
in 16 weeks can actually be done by 16 men in one week. Furthermore, there
are many situations in which tasks may have to be carried out in a serial fashion,
while in other situations only one or two persons can be usefully employed due
to a limited number of workers. Understanding the nature of the job and the
size of the work team needed to do the job is an essential aspect of resource
modeling. Resource definition may also include the creation of resource
profiles which show how many units of each resource are available for use
in the project at any given time. In multi-project situations, this is not an easy
matter, as resources may be required to work on several projects simultaneously
and there, determination of the resources required for one project must also
consider the use of the same resources for other projects.
Resource Allocation
Resource allocation, also called resource loading, is concerned with
assigning the required number of those resources identified in the previous step
to each activity identified in the plan. More than one type of resource may be
Project Management Operations
attributed to a specific activity. For example, fixing the plates on a ship's hull
may require 10 fitters, 20 welders, 15 labourers and a certain type of welding
machine. From a practical standpoint, resource allocation does not have to
follow a constant pattern some activities may initially require fewer resources
but may require more of the same resources during the later stages of the project.
At this stage, the impact of any resource allocation decision is not known and
we cannot yet answer questions such as:
Notes
to
Resource aggregation
Resource leveling
v.
Resources cost cutting
vi. Resource controlling
State True or False.
1.
2.
193
An example is shown in Figure 8.1 below, where, for a particular resource, the
required resource units for each time period are annotated on the bar chart. The
total number of resource units for each time period can then be summed and a
resource aggregation or load chart can be produced.
Notes
10
10
10
10
Activity
REMINIail,
tip
D
E
Total resource
units requirement
.
......
10
18
10
12
10
10
14
El
....
15
Resource
unit
aggregation
chart
10
5
%-
Fig. 8.1: Resource Unit Aggregation Chart derived from a Bar Chart
However, when a network is used for planning, the resource aggregation
procedure is not so simple or straightforward. As the network is not drawn to
a time-scale, there is not a direct link between the network and the demand for
resources. Therefore, a schedule must be prepared which tabulates activities
in terms of time. However, this highlights another difficulty, namely that those
activities which are not on the critical path do not have fixed starting and
finishing times but are constrained by the earliest and latest starting and finishing
times. However, this seeming difficulty offers the planner considerable scope
for adjusting the demand for resources. This will be discussed in more detail
later, but the limits, within which resources can be adjusted, without extending
the overall project duration, are the resource requirements between the earliest
starting times and the latest starting times. This is illustrated in Figure 8.2, which
shows the differing resource requirements that arise when both earliest and
latest start times are considered and also highlights the resource requirements
for those activities which are on the critical path.
Notes
Resource units
ET
rt
2'
n
112 1
- I-
41
14
12
10
Weeks
,.....
Resource
Demand
- Over demand of
,z resources
10
9 Resource availability
..
.....____
7
6
5
...
r.
4
3
2
1
1
5
Week
10
195
Notes
Resource leveling is the process that ensures resource demand does not
exceed resource availability. The ideal scenario would be a buildup of resource
usage at the beginning of the project and a reduction at the end of the project.
However, the approach to resource leveling will also depend on whether
resources are dedicated to a particular project or shared across several projects
and whether there is a need to ,keep all resources fully utilised.
We will begin by analysing the issues involved in resource leveling for a
situation where a bar chart has been used as the primary planning technique for
a simple project. The reason for this is that resource leveling must be considered
within a time framework and bar charts are drawn to a time scale while networks
are not. Examine Figure 8.1. In this figure, the time-scale for the activities
comprising the project are shown in a bar chart, which also shows resource
requirements for one particular resource unit. An examination of the bar chart
and its associated resource chart in Figure 8.1 shows that improvements can be
made to the level of resource requirements by:
We will now examine situations where networks are used as the primary
planning method. Generally, there are two approaches to leveling and smoothing
the resources required:
Notes
In this case the project must be completed with the resources available
even if this means extending the project duration. If the total resource demand
exceeds the resource availability at any time then some of the activities must be
delayed until there is sufficient resource availability.
For both of the above approaches, information concerning the earliest and
the latest start times and slack will be used to level resources.
Resource Smoothing
Resource smoothing is part of the resource leveling process. In itself,
resource smoothing is the process that, not withstanding any constraints imposed
during the leveling process, attempts to determine a resource requirement that
is "smooth" and where peaks and troughs are eliminated. For example, even
if 7 units of a given resource are available at any one time, utilising 5 of these
units each week is preferable to 4 one week, 7 the next, 2 the next and so on.
Even if there is no limit to the amount of any one resource available, it is still
desirable that resource usage is as smooth as possible. Given that the resource
requirements of those activities on the critical path are fixed, some order or
priority should be established for selecting which activity and which particular
resource associated with this activity should be given priority in the smoothing
process. In determining which activity should be given priority, a subjective
judgment should be made about the type of resource (or resources) associated
with each activity priority should be given to the activities whose resources
are considered to be the most important. Beyond this consideration, activities
should be ranked in order of total work content and total float or slack available
for that activity. A useful device for prioritising is to consider the ratio of total
work content/total float remaining and give priority to activities with the highest
value of this ratio.
Solving the resource scheduling problem for optimal solutions is extremely
complex, particularly for large project networks with many different resource
types. However, several heuristics are available to solve such problems. These
heuristics allocate resources to activities to minimise project delay based on
certain priority rules. The two most commonly used heuristics are the serial
197
and the parallel methods. In the serial method of resource allocation, activities
are sorted into a list and resources are allocated to each of these activities one
at a time until resources are allocated to all activities. In the parallel method,
however, resources are allocated on a period by period basis rather than each
activity. In this method, only those activities whose preceding activities have
been completed will be considered. If two or more activities compete for the
same resources, then allocation of resources is based on certain prescribed
priority rules. Compared to the serial method, the parallel method has been the
most widely used heuristic. The following priority rules, in the order presented,
have been found to be the most effective in minimising project delay.
Minimum slack
Smallest duration
Regardless of the scheduling heuristic used, the primary impact of the resource
constrained scheduling is the loss of flexibility due to the reduction in slack.
Furthermore, the reductiOn in slack also increases the number of critical or
near-critical activities.
1.
This next example has several parts. We will discuss each of them in some
detail.
Notes
LEGEND
ID
ES
0 2
61
SL Resource
EF
SL
LS Duration LF
5
LEGEND
4 1 4 ; 10
0
0 1 ! 0
4
1
1
416
10
ES
LS
5
2 1
6 4 10
ID
EF
SL Resource SL
Duration LF
Minimum slack
Smallest duration
199
Notes
ID RES DUR ES
2
'2
0,1,2,3
1,,
0
-1.-2
.1
4
10
5,6,7,8
10
-1 -2
10,11,12 13
9 10 11 12 13 14 15
6 7
LF SL 0 1 2 3 4 5
. ..
1 ". 1
,.,.
10,
,
0,1,
-2
Resources Scheduled
Resources Available
Fig. 8.7: Scheduled Resource Load Chart with ES and Slack Updates
Note: The parallel method schedules resources to various activities through
leveling and smoothing. This is accomplished in the above problem by delaying
and reducing the slack on activities 3, 5 and 6. Using the load profiles presented
above, graphical resource aggregation charts, similar to the ones presented
earlier in this lesson, can be developed.
Next, keep a log of each activity change and the update you make for
each period, e.g., period 0-1, 1-2, 2-3, etc. The log should include any changes
or updates in ES and slack times each period, activities scheduled and activities
delayed. (Hint: Remember to maintain the technical dependencies of the
network.) The log is shown in Table 8.1 below.
Table 8.1 Log of the Parallel Method of Scheduling
PERIOD ACTIVITY CHANGES
Schedule activity 2 first by the minimum slack rule
2
0-1
Schedule activity 1
1
3
Delay activity 3 ES to period 1. Reduce slack to 0.
Delay activity 5 ES to period 6. Reduce slack to 0.
5
Delay activity 3 ES to period 2. Reduce slack to -1.
1-2
3
Delay activity 5 ES to period 7. Reduce slack to -1.
5
Delay activity 6 ES to period 11. Reduce slack to -1.
6
Delay activity 3 ES to period 3. Reduce slack to -2.
3
2-3
Delay activity 5 ES to period 8. Reduce slack to -2.
5
Delay activity 6 ES to period 12. Reduce slack to -2.
6
Schedule activity 3
3
3-4
Schedule activity 4
4
4-5
No changes
5-6
No changes
6-7
No changes
7-8
Schedule activity 5
8-9
5
No
changes
9-10
No changes
10-11
No changes
11-12
Schedule activity 6
12-13
6
Proj ect Management Operations
2.
3.
ik
Activity 1
Visit any project site or any organisation and prepare the network for the
project carried out there. Find the resources required and see how the
\.._resource levelling can be done.
Notes
Notes
Ted 1911.
iv..., :1,9.
imerntria
4-4
."IneI
1 Wro
Fig. 8.10: Only Critical Path can shorten the Project Duration
Crashing the project isn't as simple as finding all the tasks on the critical
path and wildly assigning resources to them. Some tasks cost more per week to
crash than others. Figure 8.11 shows a crash table that uses the cost of crashing
a task and the number of weeks it reduces the schedule to calculate the crash
cost per week.
From your Microsoft Office Project Professional 2003 schedule, you can
export the tasks on the critical path, their durations, and their original costs.
Then, by importing that information onto a Microsoft Office Excel 2003
worksheet, you can calculate the crash cost per week for each task. Sorting the
tasks by the crash cost per week quickly shows you the least costly tasks for
crashing.
This worksheet is sorted by using three columns. Column A identifies the
tasks on the critical path, so the sort begins by separating the critical path tasks
from the rest of the schedule. Then, the "Crash Cost per Week" column is sorted
in ascending order to find the least costly tasks. Finally, the "Crash Duration"
column is sorted in descending order to find the cheapest tasks that shorten the
schedule the most. By looking for the largest reduction at the lowest price, you
crash the fewest tasks.
Telt Name
NO Cruse
5 Assemble Coreponerts
1 Design Step
6 Test SNP
2 &mkt Imorob4t.ily Orme
4 6okt Shap ltdrastruclue
3 Teti VornrottabOtie nil Yll
ID
CP
Cl
CP
CP
Crash
Gash
COSI tx.e'
DINB000 DUr9[109
Cr aS#1
Original
Clash
Week
(Wks)
(ttrk0 Reduchon Cost ISW Cost 51,41 LSI.1)
20
26
25
50
40
16
16
18
19
45
36
14
4
8
6
5
4
2
12
20
74
56
26
6
16
32
33
100
42
16
100
150
1 50
10 00
3 50
4 09
Crew
IlesuN
121
117
109
103
96
96
99
Notes
The Build Improbability Drive task costs $10 million for every week
that we cut from the schedule. Therefore, it will cost $50 million to reduce the
schedule by five weeks. Build Improbability Drive engineers are, well, pretty
improbable to come by, so hiring a second one for the project comes at a steep
price. On the other hand, if you start by crashing the ,least costly task, Assemble
Components, you can shorten the schedule by four weeks for only $4 million.
Crashing a task can change the critical path on the project, even adding a
task to the critical path that wasn't there before. For example, if you reduced the
"Build Improbability Drive" task to less than 40 weeks, the status of the "Build
Ship Infrastructure" task would be elevated to the critical path. To accurately
evaluate your crash decisions, you should review the critical path after every
task crash.
If you look closely at the worksheet in Figure 8.11, you'll notice that the
"Build Ship Infrastructure" task and the "Test Improbability Drive" task cost
less per week to crash than the "Build Improbability Drive" task. Why aren't
they crashed earlier? The answer lies in the "Crash Result" column. These two
tasks aren't on the critical path. Although crashing those tasks costs money,
their shorter durations don't shorten the overall project schedule one bit.
Figure 8.12 illustrates the benefit of crashing the least costly tasks first.
As you can see, the initial reductions shorten the schedule significantly without
much of an increase in overall cost. But, as you dig deeper for more reductions,
each additional week comes at a higher and higher price.
Total Cost
$250 -
$200
$150
$100
$50
SO
98
103
109
117
121
Weeks
205
Notes .
Crash tables are simple to create. Here are the basic steps that are required
to be performed:
A.
Export the work package tasks (ID and Task Name fields), the original
duration (Duration field), and the original cost (Original Cost field) from
your Project Professional 2003 schedule, and open that file in Excel 2003.
B.
You must calculate the potential crash duration for each critical path task
and the cost to crash each task.
C.
D.
Add another column to calculate the crash cost per week, which is the
crash cost divided by the crash reduction value.
The
schedule.
The minimum possible duration of the activity is its crash duration, when
its cost is the highest.
206
Notes
Direct
cost of
job
Crash
Normal
Job duration
Labour costs
The indirect costs are the administrative costs and not related to the
activities directly.
These are fixed expenses incurred on daily basis during the project.
Project Indirect Costs include overhead costs such as:
Managerial services
Indirect supplies
Equipment rentals
Thus, this cost will be directly proportional to the project duration and
it will reduce with the reduction in the project duration and increase with the
duration of the project. This is shown in the figure below.
Indirect
cost of
project
Direct
cost of
job
Crash
Normal
Project duration
207
Notes
11
12
113
14
15
P1
1
16
Project
Duration
increment
800
700
600
500
400
300
200
100
5201
Crash D by 2 Days
32Q
P2
160
P1
Proj ect
Duration
11
12
14
15
16
Project Cost: The figure below indicates the total cost of crashing and
combining all the stages.
210
Direct
cost
increment
_780
800
700
5 20
600
500
400
120
300
200
100
Notes
Crash B,D,F by 1 day
Crash F,G by 1 clay
_ _ _ 1)5
Crash A ,0
2d0
relax D by 1 day
Project
Duration
200
Crash D by 2 Days
160
11
Project Total Costs: In case project has indirect cdst of Rs. 100 per Day, The
total project cost will be as indicated in figure beloW.
Project Indirect costs = Rs 100 1 day'
Total
Jar
Cost
Indirect
cost
Direct cost
Duration
Activity 2
Select any project and prepare a network diagram and estimate time using
CPM for the same. Find the possibility of crashing, looking at the cost and
the duration of each activity.
""',.',,,, Summary
211
Notes
212
The most important resources that project managers have to plan and
manage on day-to-day basis are people, machines, materials and working
capital. Depending on the type of resources, the costs of providing an
abundance of such resources to accelerate project completion time can be
very high.
Resource leveling is the process that ensures resource demand does not
exceed resource availability. The ideal scenario would be a buildup of
resource usage at the beginning of the project and a reduction at the end
of the project. Resource leveling improvements can be made to the level
of resource requirements by:
The project has direct and indirect costs. The direct costs are directly
proportional to the activities. As the duration reduces, these costs increase
as we may have to put additional resources.
Notes
/OKeywords
Resource leveling: The last stage in the process. In this stage, we attempt
to ensure that the demand for resources does not exceed availability.
Self-Assessment Questions
1.
What is project scheduling? What are tools used for project scheduling?
2.
3.
4.
5.
6.
7.
What is the direct cost in project? How it is different from indirect cost?
8.
What is cost slope? What is the use of cost slope in project management?
9.
A
1
2
B
2
1
CD
A
1
2
1
1
E
B
3
1
F
G
CD
2
1
1
1
If only 3 persons are available, do the resource leveling, find the project
duration.
213
Notes .
10. Prepare network diagram and find minimum duration of the project and
minimum cost if the fixed cost is Rs. 2000 per day.
Activity Preceding
Activity
A
B
C
D
E
F
G
H
I
J
A
A
B
B
C
E,F
G
G
H,I
Normal
Duration
(Days )
10
6
8
8
12
6
7
5
4
4
Crash
days
8
5
6
6
9
5
5
4
6
3
Normal cost
12000
6000
6400
6400
8400
4800
4900
5500
5600
4000
Crash Cost
16000
7500
7800
7200
9900
6000
5500
6000
7200
4500
Resource definition
ii.
Resource allocation
iii.
Resource aggregation
iv.
Resource leveling
False
2.
True
Resource levelling is the process that ensures resource demand does not
exceed resource availability.
2.
2.
Notes
The critical path is the place to look when you want to shorten a schedule.
True
2.
True
n
i Suggested Reading
1.
215
Notes
216
UNIT
217
Notes
Objectives
After going through this unit, you will be able to:
Do activity scheduling
Input
Project Management
41111
Output
Mechanisms
Fig. 9.1: The Project Management Process
A good project management discipline will not eliminate all risks, issues
and surprises, but will provide standard processes and procedures to deal with
them and help prevent the following:
218
Project management seen as not adding value and as a waste of time and
money
Notes
The first step of this approach is to list the main activities. In order
to do this use as basis the WBS we have developed. Identify all the
activities required to create the products or develop the deliverables
that have been identified and presented in level 1 and then list them.
The list of activities should normally include management activities
as well.
.2 1-9
Notes
2.
When using the WBS to identify which activities are needed, the
project manager may find out that has forgotten to incorporate one
deliverable in the WBS or that the deliverable descriptions have to
be corrected to indicate the exact outputs of the project. In this case
the WBS must be updated.
It is noted that as has already been described the WBS and the
activity list are being prepared sequentially first the WBS and then
the activity list. nowever, sometimes it is convenient to develop
them simultaneously.
Notes
According to this method, the Activities are presented as boxes and their
dependencies as arrows. There are four types of dependencies but only
one is the most commonly used, the finish to start. More specifically, the
types of dependencies are:
Finish to Start (FS): In this case the work of the successor cannot start
until the work of the predecessor has finished.
Finish to Finish (FF): In this case the completion of the work of the
successor depends on the completion of the work of the predecessor.
Start to Start (SS): In this case the initiation of the work of the
successor depends on the initiation of the work of the predecessor.
Start to Finish (SF): In this case (it is rarely used) the completion
of the work of the successor depends on the initiation of the
predecessor.
I Start
--+ Finish
221
are more familiar with the nature of the specific activity and those who
have the necessary technical knowledge or experience (by participating or
managing similar activities/projects in the past) should be consulted. The
inputs that are necessary for the activity duration estimation are:
Notes
4.
Notes
MEd
Milestones: Milestones are the key events that provide the basis by
which the project implementation will be monitored and managed.
The simplest milestones are the dates estimated for completion of
each Activity, for submission of deliverables, or for getting approval
by the client (acceptance of the product produced).
Time leads and lags: There are cases that a dependency between
two activities may require specification of a lead or lag to accurately
define the relationship.
There are many different approaches to scheduling. The steps can either be
done manually or a computer tool (software) can be used. Project Management
Software (like Microsoft Project, Primavera, etc.) is widely used to assist with
schedule development.
The project schedule includes at least the start and finish dates of each
activity and their duration (in days, weeks, months, etc.). It can also include
information concerning the responsible for the implementation of each action. It
may be presented in summary form or in detail graphically or in a tabular form.
ii.
iii.
iv.
v.
vi.
223
Notes
it- 3
f: Activity 1
:'t1/400v"v
Select any project and prepare a list of activities for the same and prepare
the activity schedule.
__e ,
Rosourco
Schodulo
resources
project
activities!
2.
b.
c.
d.
e.
Notes
.225
Material: We have to list the material that will be used for the
production of the ideliverables. For example, in case of a building
construction project, materials like bricks, cement, steel, cables,
paints will be used. Or in case of a training delivery project,
materials like paper for printing the training material and blank CDs
for distributing the training material to participants will be used.
In addition, material that will be used for project management and
procurement management activities should also be listed (e.g., paper
for printing the tender documents, posters to be used for publicity
actions of the project, etc.)
The quantity of material resources is defined using the appropriate
measurement units for each material. For example, 50 m of cable, 5
to of cement, 50 kg of plastic paint, 5000 sheets of printing paper,
100 blank CD-Rs, etc.
f.
226
Get expert's judgement. Once you have identified the types and
quantities of resources you should present the resource requirements
to an individual expert or a group of experts in order to assess
them and advise you for their suitability and appropriateness. Such
expertise and specialised knowledge may be acquired either from
other units within the agency (e.g., technical unit, HR unit) or/
and by external consultants or/and by professional and technical
associations or/and by industry groups.
Project Management Operations
g.
3.
Notes
227
Notes
4.
b.
c.
d.
Use under allocated resources to help relieve the over allocated ones.
e.
g.
Use the resources with the higher quality or the more effective resources
on high-risk tasks or tasks that require the highest level of quality.
iii.
iv.
v.
vi.
Notes
Notes
Pdiw Activity 2
Select any project and prepare a list of resources required for the project
along with the quantity and type of resources.
Development of Cost Plan: The Cost Plan is usually prepared after the
development of the Activities Schedule and the Resource Plan, since it
requires input from both of them. Based on the information now known
about the project as a result of Project Planning activities (i.e., more detail
and greater accuracy regarding project activities, tasks and durations, a
more detailed understanding of the resources required to perform the
work and their associated costs), the Project Manager can refine the
budget required to complete the project. This is particularly important
when a project or some of its components are planned to be performed
under contract (i.e., through a tendering process), since in this case
the value of the contract should be accurately estimated in order to be
included in the relative tender documents. The cost planning is also very
important in case that the project is implemented with own resources (inhouse production), since the establishment of a realistic and accurate cost
plan will help you to effectively monitor costs during the execution and
monitoring phase in order to stay within budget.
In order to develop the Cost Plan, the following steps should be followed:
Development of
Cost Schedule
Estimation of
cost per
activity/ task
Fig. 9.4: Steps to be followed for the Development of the Cost Plan
For simple projects the development of a Cost Plan may be limited to
entering only the overall cost against the project activity on the Activities
Schedule. However, for larger and more complex projects, a detailed Cost
Plan should be completed to ensure that the overall expenditure is both
accurate and appropriate.
There are various software packages in the market, such as MS Project and
Primavera Project Planner (P3), which can be used to develop, monitor
and control a detailed cost plan.
230
2.
iv.
Travel costs: They are costs associated with any travelling that may be
required in the scope of the project. They include transportation costs
(e.g., flight tickets, taxi fees, car fuel, parking fees, etc.), accommodation
costs (e.g., hotel rooms, apartments, etc.) and any daily allowances (e.g.
lunch/ dinner, entertainment).
v.
vi.
Contingency costs: These are the costs which, based on past experiences,
are known to be regularly encountered but difficult or impossible to
estimate at the time the plan is prepared. These costs may result from
incomplete design, unforeseen and unpredictable conditions, risks
or uncertainties within the defined project scope. The reason that they
are included in the Cost Plan is to reduce the risk of budget overrun.
Contingency costs may be either built into the above costs or listed as a
separate category.
Notes
After identifying the various costs it is time to estimate the value of each
cost. Depending on the way that they are estimated/calculated the resource costs
can be distinguished into three categories:
Project Implementation and Monitoring
231
Notes
Fixed costs: They are costs that remain constant regardless of the
task duration, the work performed by a resource, or the number of
assigned resource. units. A rate-based resource cost may increase
when a task takes more time, but a fixed cost does not. For example,
if a consultant is paid hourly and is scheduled to complete a task in
five days, but the task takes seven days, the consultant will be paid
more than planned. If the consultant is paid a fixed amount for the
work, then the cost will be the same no matter how long the task
takes.
Fixed costs can be assigned to a task in addition to rate-based
resource costs. For example, if the performance of a task requires
a machine that has to be purchased, the cost of purchasing that
machine is a fixed, cost, while the operating cost of this machine is
a rate-based cost.
For the estimation of the'rest costs (except from the costs of resources) we
can apply the following general guidelines:
232
Notes
Once all the elements of costs have been estimated, we can easily
estimate the overall cost of the project by summing up all the individual
costs. It should be noted that the estimated overall cost of the project
should not exceed in any case the approved budget. Any refinements of
the budget as a result of the cost estimating process are allowed only if
they don't cause an overrun of the budget. For example, the review of cost
estimates may bring up the need to make adjustments to the cost totals or/
and reallocations of costs between activities. These adjustments of cost
estimates should be done with respect to the overall budget of the project.
3.
233
Notes
Time
The above graph represents the cumulative project costs in the time. In
order to prepare this graph we need to create an intermediate table that will sum,
for each time period of our schedule (week or month), the planned costs, and
calculate the cumulative cost for each period (week or month). A simple Excel
graph will then enable us to generate our Cost Baseline Graph. For cost schedule
estimate and monitoring we can use the concept of Earned value analysis.
f'CtV"si
Notes
Activity 3
2.
3.
235
Notes
236
Notes
SPI BCWP
BCWS
In the example above, the task's SPI is about 0,80 or 80%.
One common way of visualising the key values of earned value analysis
is to use a chart. The following figure presents a snapshot of a typical EVA
chart and explains in graphic format the various key values of the earned value
analysis.
Ciiimilalive Cosi
ACWP
Cosi)
(Aducil
1\
CV
BCWS
(Planned Value)
SV
Time Now
Tune
Ratios, such as the Cost Performance Index (CPI) and the Schedule
Performance Index (SPI), can be greater than 1 or less than 1.
A value that's greater than 1 indicates that the project is ahead of schedule
or under budget
A value that's less than 1 indicates that you're behind schedule or over
budget.
For example, an SPI of 1.5 means that you've taken only 67 per cent of
the planned time to complete a portion of a task in a given time period, and a
CPI of 0.8 means that we are spending 1,25 for every 1,00 of budgeted work
accomplished.
Project Implementation and Monitoring
237
Notes
Review the baseline, actual and remaining costs to identify whether the
project will or will not stay within budget.
Review cost variances per type of cost or per task to find out when and
where the actual costs exceed or are less than the budgeted ones.
Find which types of costs are already over budget. Perform the same
exercise with the tasks' cost to find out if you need to make any reallocation
of resources (or costs) to stay within budget.
After we have identified cost variances that occur over time, we should
take corrective actions to keep costs within budget. Before we make any major
changes, it is recommended that we save a backup copy of the initial cost
schedule, so that we can refer to it as we are making changes that may affect
costs of other resources or tasks.
In order to get an overview of options that are available keep costs under
control, we have to consider how quality affects costs. The changes that we will
make in our schedules to stay within budget depend mainly on our priorities.
For instance, we could choose to sacrifice quality by using less expensive
resources (e.g., people with less experience and skills, equipment with less
operational power, materials of lower quality, etc.) or by removing some of
the tasks we meant to accomplish. Alternatively, we could choose to spend a
little more money on quality resources, under the thought that those resources
will complete the task or project in significantly less time and probably with
less total cost. Regardless of the actions we decide to take to reduce costs, we
have to examine their effects on tasks, resources and quality of the deliverables.
We may also need to discuss the effect of these actions on quality with the
appropriate stakeholders. In order to keep costs within budget we can take the
following actions:
Reduce rates of resources (if this is possible), who are assigned to tasks
that are in danger of exceeding their budget. This can be possible only if
you have included profit or overhead in the cost rate.
Assign per-use costs more efficiently. This can be achieved, for instance,
by combining tasks (i.e., let them run together), which involve the use of
a resource with a per-use cost.
Reduce unnecessary fixed costs. For example, you can cancel a travel that
is not so important for the progress of the work or reduce the number of
project staff that was scheduled to travel.
Notes
Critical path to verify that the adjustments you made didn't affect it
adversely.
Project dates and costs to verify that the adjustments you made do not
adversely affect important dates or other costs
Resource allocation to verify that the adjustments you made do not cause
any over allocations or under allocations.
t ,
L t Activity 4
3.
239
Notes
Summary
240
the difference between the current progress and the scheduled progress of
a task, in terms of cost, Cost Performance Index (CPT), which is the ratio
of budgeted costs to actual costs, and Schedule Performance Index (SPI),
which is the ratio of work performed to work scheduled.
Notes
3/ Keywords
Actual cost of work performed: The total 'actual cost incurred while
performing work on a task during a given period.
Cost variance: The difference between a task's estimated cost and its
actual cost.
Schedule variance: The difference between the current progress and the
scheduled progress of a task, in terms of cost.
Self-Assessment Questions
1.
What is project management process? Explain' with the help of inputs and
outputs.
2.
3.
4.
5.
6.
7.
8.
How is cost estimation done for projects? What are the different types of
costs required to be considered for cost estimation?
241
Notes
ii.
iii.
iv.
ii.
iii.
iv.
Suggested Reading
1.
Controlling Projects
Structure:
up
WI
UNIT
10
Controlling Projects
243
Notes
244
Cost Management: It is the process during which the actual costs are
tracked against estimates and if needed corrective actions are taken to
keep costs within budget.
Notes
Issue
Manigement // I
Conduction of
ProOct
Evaluation
Review
_Po
sit
r NNW,
Controlling Projects
245
Notes
Identify and resolve schedule problems that may affect the project's
finish date.
> Record
progress of
activities &
tasks
Update the
Activities
Schedule
Identify and
resolve
schedule
problems
Notes
\..
i.
ii.
iii.
iv.
v.
vi. Managerial/Management decisions
Actv"Y Activity I
With an example from Infrastructural Projects, write how would you manage
your main resources deployed in the Project.
Controlling Projects
247
11.5M-1
The steps that are undertaken to control costs are the following:
Update the Cost Schedule on a regular basis to ensure that the financial
progress is on track.
Identify and resolve cost problems to ensure that the project stays within
budget.
Record actual
costs (or
expenses)
Update the
Cost
Schedule
Identify and
resolve cost
problems
3.
by
I:ga
re (ow
or
Examine the Peer Review Report that normally has to be attached to the
Deliverable concerned and check whether all the information needed are
included.
Use a checklist to ensure that all the quality assurance activities defined in
the Contractor's offer (and consequently in the Contract and in the Project
Kick off document (or Inception Report) are being implemented.
This process helps the Project Manager to monitor what is being done
well, to identify real or potential issues and to suggest ways of improvement. It
is recommended to perform this process regularly during Project Execution and
Control Phase and of course at the end of the project.
Checklist for Contractor's Quality Assurance activities
The questions listed below are indicative of what the Project Manager
may ask to check is the consistency between what the Contractor promised and
what actually performs
Project management process and deliverables
Does the Contractor produce progress reports on the agreed intervals that
contain all the recommended components from the Tender Documents?
Is the project scope clear in the Project Inception Report? (Is it clear as to
what is "in" and "out" of the scope?
Has the Contractor described at the Inception Report the quality standards
for the project and the quality assurance and control activities he is going
to perform?
Controlling Projects
249
Notes
Has the Contractor identified and prioritized possible risks of the project?
If any risks events have occurred to date, was the risk mitigation plan
executed successfully?
Deliverables
Do the deliverables produced so far meet the objectives set in the Project
Fiche and in the Tender Documents?
Have you identified and assigned the appropriate resources for the
performance of project management activities?
Does the project organisation ensure that decisions are taken in the
appropriate 'management level?
Are there any quality reviews being performed according to the plan?
Notes
c) Follow up
Controlling Projects
251
__L
Activity 2
Q,52 I
To raise a project risk if the issue is likely to impact the project in the
future, or
To raise a change request (or ask the Contractor to raise a change request)
if the issue results in the need for a change to the project/contract, or
Notes
The Project Manager registers the change request in the Change Log and
assigns to it an ID.
He/she then analyses the request, examines its complexity and whether
the change is feasible or not. He/she also assesses the full impact of the
change to the project and defines in detail the change requirements, costs,
additional resources needed and risks.
In case that the change request has been approved, the Project Manager
must incorporate the effect of the change into the appropriate Plan (e.g.,
in the Activities Schedule and the Resources Plan if the whole duration of
the project is prolonged, in the Cost Plan if the budget has been changed,
etc.) and update the Change Log.
Controlling Projects
253
Notes
The Departmental Committee for Variations and Claims and the central
committee for variations & claims.
. .. --------
Risk Monitoring
Risk Control
NN,
Risk
Monitoring
Risk Control
254
Determine if identified risks have occurred and risks responses have been
implemented as planned
Identify if the risk probabilities have changed the expected level of impact
is different or the date of impact may be sooner or later than the original
anticipated
Determine if risk exposure has changed from its prior state and then
analyse the new trends
Project Management Operations
Identify if new risks that were not previously identified have arisen or
even worse occurred
Notes
The risk occurs as expected and the risk control actions defined in the
Risk Management Plan are proven adequate for dealing with it.
The risk occurs in a different manner and consequently the risk control
actions must be modified appropriately
It should be noted that during the entire risk management process, the
Project Manager should be especially vigilant regarding the effect on the
project's scope, cost, schedule and quality. With the appropriate contingency
plans established, many risks may not affect the above-mentioned basic
parameters of the project. However, when a risk event occurs that threatens one
or more of these parameters, the Project Manager must determine the actions to
be implemented in order to protect the project's integrity. In this perspective, a
change request may be issued which has to be managed formally according to
the predefined Change Management process.
povity Activity 3
Enlist with example from Projects, factors affecting risk management.
Controlling Projects
255
Notes
Reporting
Prolat's
Performance
Notes
Variance analysis which is about comparing actual project results (in terms
of schedule, resources, cost, scope, quality and risk) against planned or
expected ones.
Controlling Projects
Notes.
ii.
Project Title
iii.
iv.
v.
Date of submission
vi.
vii.
viii. Work programme for the following reporting period (i.e., activities/tasks
to be executed, deliverables to be submitted, schedule estimates for key
milestones, etc.)
ix.
Notes
In case of small projects with only few team members, the Progress
Report can be substituted by personal judgment and observations of the Project
Manager or by day-to-day discussions with the team members on the progress
of the deliverables. On the contrary, in case of large and complex projects, where
progress reporting is an important aspect of communication management, the
Progress Reports should be formally submitted to the Project Manager by the
Team Manager(s) (or by the Contractor), who have to prepare them by collecting
the relative progress information from individual team members.
The use of a Project Status Report
The project status report is a document prepared by the Project Manager
using the information provided by the progress reports to present the status of
the project to key stakeholders, including the project steering committee, the
project owner and the funding agency. Depending on the duration and the size
of the project, as well as on specific communication requirements of the project
owner or/and the funding agency, the status report can be prepared monthly,
quarterly or biannually. Usually, status reports are prepared with the same or
less frequency than progress reports since they require input from them. The
aim of the project status report is to:
Ensure that the key stakeholders are regularly informed on the progress of
the project
Inform the key stakeholders about issues that require immediate action or
resolution
Generally, a project status report should include the following information:
Status of Risks
Status of Issues
Other documents that can be attached to the Status Report are: Status Gantt
Chart, Notes of meetings, Quality Review Reports, Deliverable Acceptance
Forms, Risk Log, etc.
Controlling Projects
259
Note's I
260
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
17.
18.
19.
20.
21.
22.
23.
24.
Cost Management
Are the actual costs (expenses) being recorded?
Is the Cost Schedule being updated on a regular basis?
Is the Cost Schedule being reviewed to identify and
resolve cost problems?
Quality Management
Are the quality assurance activities implemented during
the execution of the project being monitored?
Are the deliverable quality reviews being organised and
conducted regularly?
Are the results of the deliverable quality reviews being
documented?
Issue Management
Are the project issues being formally identified and
raised?
Is issue management process being applied when
necessary?
Change Management
Are changes to project's scope, cost, deliverables,
timescales or resources being formally identified and
requested?
Is change control process being applied when necessary?
Risk Management
Are the risks being monitored according to the processes
defined in the Risk Plan?
Are the risk mitigation actions being evaluated in terms
of their effectiveness?
Are the preventive or contingency actions defined in
the Risk Plan being applied?
Acceptance Management
Are the produced deliverables being reviewed and
accepted according to the Acceptance Plan?
Communication Management
Is information being distributed according to the
Communication Plan?
Are Project Status Reports being prepared regularly by
the Project Manager?
Are Project Progress Reports being prepared and
submitted regularly to the Project Manager?
Is the project's progress and performance being
communicated?
`milm = Activity 4
Prepare a checklist for reviewing the performance of the contractor.
Controlling Projects
Notes
Notes
rev! ow
Ensure that all the deliverables of the project have been produced, accepted
and approved by the appropriate organization structure (e.g., Acceptance
Committee, Project Ste&ing Committee, etc.)
Complete and archive all project information, notify all involved parties
that the project is to be closed and therefore the resources committed are
being disbanded
Update the CVs of the human resources involved in the project and
evaluate their performance.
Identifying
follow - on
actions
Ensuring that el
lho deliverables
have been
accepted
Completing 8.
archiving all
project
information
Disbanding the
-, resources
/ used In the
project
Notes
Controlling Projects
' 263
Notes
Project Material
ii.
Business Case
iii.
iv.
v.
Project Fiche
vi.
x.
xi.
Risk Plan
264
Notes
During this step the Project Manager recommends to the Project Steering
Committee that the resources that were working for ,the project can be released
and that the support infrastructure can also be withdrawn. He/she also prepares
notification to any parties identified in the Communication Plan as needing to
be told about the project closure. Before sending the project closure notification
the Project Manager needs confirmation by the Steering Committee.
Updating the CVs of the Human Resources involved in the Project
During the course of the project, Project Team members most likely
improved their skills and qualifications or obtained,new ones. The investment
made in improving an individual's skills should not be lost. The Project Manager
is responsible to ensure that the CVs of the project team members have been
updated to include the reference of the project they participated, description of
their exact role and finally any skills newly developed. As it is obvious, up-todate CVs may become invaluable to future Project Managers when attempting
to staff appropriately their projects.
Finally, the Project Manager in cooperation with Team Managers (if the
project organisation includes this role) must evaluate the performance of each of
the project team members and then document their judgement by completing a
relative form. This evaluation form can then be submitted to each Project Team
Member's supervisor in order to be used as input to performance appraisals.
Conduction of Project Evaluation Review
During this process, the Project Manager evaluates the product produced,
the project management processes and in addition he/she gathers accumulated
experience, best practices and performance trends in order to communicate
them via the Project Evaluation Report.
In order to conduct the Project Evaluation Review, the Project Manager
has to:
Prepare the
Project
Evaluation
Report
265
Notes
the administrative costs have been reduced and the productivity has been
increased. Similarly, when we run a project for the expansion of the railway
network we have to wait a year or more in order to realise whether the number
of passengers served by it is increased and the traffic in the respective highways
and roads has been diminished.
If this is the case, a recommended date should be defined for conducting
the post project review. Besides a plan should be prepared which should define
the following:
Who will carry out the' measurements? (It is not necessary to name certain
individuals but you could describe the required skills.)
7.
8.
9.
10.
11.
12.
13.
266
Yes No N/A
Administrative Closure
Have any follow-on actions been identified?
Have all the project deliverables been accepted?
Is all the project information collected and archived?
Have all parties that were involved in the project been
notified about the project closure?
Have the resources that were utilised during the
implementation of the project been released?
Have the CVs of the project team members been updated
with their role in the project and the skills they obtained?
Project Evaluation Review
Has a project evaluation review been performed?
Has a Project Evaluation Report been prepared?
Has the Project Evaluation Report been distributed to the
appropriate stakeholders?
Have lessons learned been identified and documented?
Post-roject Review
Is a post-project review necessary to identify if the
expected benefits have been achieved?
Have the benefits to be measured been defined?
Has the methodology/technique to be used for measuring
the achievement of the expected benefits been determined?
Project Management Operations
Note's
i:f\ctvm
Activity 5
4 L
Prepare a checklist for reviewing the performance of the project.
Summary
To ensure that the project's requirements are met, the project manager
monitors and controls the activities, resources and costs that are required
for the production of the deliverables throughout the execution phase.
In this phase all the plans, schedules, procedures and templates that
were prepared during the planning phase are utilised to ensure that
the project proceeds as planned. In this perspective, the following
management processes are undertaken: schedule management, resource
management, cost management, quality management, issue management,
change management, risk management, acceptance management and
communication management.
During Project Closure, the Project Manager should examine whether the
correspondence exchanged, the project management documentation, the
project related material, the deliverables, change request forms, approvals
and decisions taken have been indexed. If any of the above-mentioned
material is missing, the Project Manager should try to find and file it. The
archive must be in both: electronic and hard copy forms.
Keywords
Cost management: The process during which the actual costs are tracked
against estimates and if needed corrective actions are taken to keep costs
within budget.
Controlling Projects
267
Notes
Administrative closure: The process during which all project records are
collected and archived and all the resources provided to the project are
being released.
411
6
268
Self-Assessment Questions 1
1.
What is project scheduling? What are tools used for project scheduling?
2.
3.
4.
5.
6.
7.
8.
What is cost slope? What is the use of cost slope in project management?
9.
A
Preceding activity
Duration
1
Manpower Required 2
B
2
1
D
A
1
1
2
1
B
3
1
F
C
2
1
G
D
1
1
If only 3 persons are available, do the resource leveling and find the
project duration.
10. Prepare network diagram and find minimum duration of the project and
minimum cost if the fixed cost is Rs. 2000 per day.
Activity Preceding Normal Duration
Activity
(Days)
A10
B
A
6
C
8
A
D
B
8
E
B
12
F
C
6
G
E,F
7
5
H
G
I
4
G
J
H,I
4
Crash
days
8
5
6
6
9
5
5
4
6
3
2.
ii.
Labour
2.
Controlling Projects
Notes
3.
rl Suggested Reading
1.
UNIT
11
Notes
Objectives
After going through this unit, you will be able to:
Explain contracts
Prepare bids
Evaluate bids
Totally in-house where all the activities are performed by the employees
within the organisation.
Partly in-house and partly outsourced where some activities are done in
house and some activities are outsourced.
Capacity to contract
Consideration
Legal purpose
Legality of form
Consent to contract
Notes
Notes
275 ill
Notes
remark is that more frauds have been committed through the application of the
Statute of frauds than have ever been prevented. Contracts that do not meet the
requirements of common law or statutory Statutes of frauds are unenforceable,
but are not necessarily thereby void. However, a party unjustly enriched by
an unenforceable contract may be required to provide restitution for unjust
enrichment. Statutes of frauds are typically codified in state statutes covering
specific types of contracts, such as contracts for the sale of real estate.
Notes
Ali
4 Negotioflo
Potential
Contractor
B
5 Contract award
277
Notes
Contact potential vendors and request examples of their work and request
references.
Using the above information, determine those vendors who have the
capability to produce the materials you want to get developed. Include in
your decision such variables as geographical location, industry experience,
reputation, size of staff, and quality/level of work.
Step 3 In step 3, Request for Proposal (RFP) is floated to the prospective
Project Contractors (Bidders) for submission of Technical and Price bids which
contains:
Scope of work
Technical information/specifications
2.
3.
4.
Notes
RFP Specifications
An RFP typically involves more than a request for the price. Other
requested information may include basic corporate information and history,
financial information (can the company deliver without risk of bankruptcy),
technical capability (used on major procurements of services, where the item
has not previously been made or where the requirement could be met by varying
technical means), product information such as stock availability and estimated
completion period, and customer references that can be checked to determine a
company's suitability.
In the military, an RFP is often raised to fulfill an Operational Requirement
(OR), after which the military procurement authority will normally issue a
detailed Technical Specification against which tenders will be made by potential
contractors. In the civilian use, an RFP is usually part of a complex sales process,
also known as enterprise sales.
RFPs often include specifications of the item, project or service for which
a proposal is requested. The more detailed the specifications, the better the
chances that the proposal provided will be accurate. Generally RFPs are sent to
an approved supplier or vendor list.
The bidders return a proposal by a set date and time. Late proposals may or
may not be considered, depending on the terms of the initial RFP. The proposals
are used to evaluate the suitability as a supplier, vendor or institutional partner.
Discussions may be held on the proposals (often to clarify technical capabilities
or to note errors in a proposal). In some instances, all or only selected bidders
may be invited to participate in subsequent bids, or may be asked to submit their
best technical and financial proposal, commonly referred to as a Best and Final
Offer (BAFO).
RFP Variations
Other variations in RFP include request for quotation, request for pricing,
request for qualification, request for tender and request for information.
'279 .
Notes
A Request for Quotation (RFQ) is used when discussions with bidders are
not required (mainly when the specifications of a product or service are already
known) and when price is the main or only factor in selecting the successful
bidder. An RFQ may also be used as a step prior to going to a full-blown RFP to
determine general price range. In this scenario, products, services or suppliers
may be selected from the RFQ results to bring in to further research in order to
write a more fully fleshed out RFP.
An RFQ is a standard business process whose purpose is to invite suppliers
into a bidding process to bid on specific products or services. RFQ generally
means the same thing as Invitation for Bid (IFB).
An RFQ typically involves more than the price per item. Information
like payment terms, quality level per item or contract length are possible to be
requested during the bidding process.
To receive correct quotes, RFQs often include the specifications of the
items/services to make sure all the suppliers are bidding on the same item/
service. Logically, the more detailed the specifications, the more accurate the
quote will be and comparable. to the other suppliers. Another reason for being
detailed in sending out an RFO is that the specifications could be used as legal
binding documentation for the suppliers.
The suppliers have to return the bidding by a set date and time to be
considered for an award. Discussions may be held on the bids (often to clarify
technical capabilities or to note errors in a proposal). The bid does not have
to mean the end of the bidding. Multiple rounds can follow or even a Reverse
auction can follow to generate the best market price.
RFQs are best suited to products and services that are as standardised and
as commoditised as possible, as this makes each suppliers' quotes comparable.
In practice, many businesses use a RFQ where an RFT or RFP would be more
appropriate.
An RFQ allows different contractors to provide a quotation, among which
the best will be selected. It also makes the potential for competitive bidding a
lot higher, since the suppliers could be quite certain that they are not the only
ones bidding for the products..
Requests for quotations are most commonly used in the business
environment but can also be found being applied to domestic markets.
A Request for Information (RFI) is a proposal requested from a potential
seller or a service provider to determine what products and services are
potentially available in the marketplace to meet a buyer's needs and to know the
capability of a seller in terms of offerings and strengths of the seller. RFIs are
commonly used on major procurements, where a requirement could potentially
be met through several alternate means. An RFI, however, is not an invitation
to bid, is not binding on either the buyer or sellers, and may or may not lead to
an RFP or RFQ.
280
Price section in which the vendor must detail the time and costs that
will be required to complete the project. Price section includes all the
pricing terms which include basic prices, taxes and duties, costs related
to transportation, packaging, loading unloading, installation, erection,
testing commissioning, etc.
Notes
Notes
B.
C.
282
Revised Technical Proposals that are needed to meet the agreed technical
standard and to prepare the Supplementary Price Proposals that reflect
these changes.
The Price Proposals, Supplementary Prices Proposals, and Revised
Technical Proposals are evaluated, and following approval, the Contract is
awarded to the Bidder whose Bid is determined to be the lowest evaluated
substantially responsive Bid.
D.
Notes _All
Notes
Price
Trying to fit all the parameters (in the previous slide) together can lead
to 'subjectivity' and low transparency in decision-making for selection.
A method commonly adopted for "objectivity in decision-making" is the
"Keppner-Treggo" matrix which uses weighted rating of the different
parameters. Constructing the decision matrix has the following phases:
Step 1: Define all the parameters that are relevant to the decision
Step 6: Compute the weighted average marks for each bidder per
parameter and compute the totals
Step 7: The contractor with the highest score is the "best choice"
2841 .-'
Evaluation Parameter
Weightage
7
5
4
3
3
2
Score out of 10
ABC XYZ NEW
LTD. CO. CO.
6
8
7
6
7
8
8
6
7
8
5
6
8
7
7
7
5
9
Notes
STEP 6 Negotiations
285
Notes
286
of the contract value. If the contractor fails to perform as per the terms
agreed, Customer can invoke the Bank Guarantee and encash it. Banks
charge a commission from Contractors to issue Guarantee
A performance BG (also called performance bond) states that in the event
of failure to perform an agreed task the beneficiary can raise a claim on the
bank. Example: Party A wins a tender to supply party B with equipment
for US$ 1 billion. Party A submits a performance bond. Thereafter, party
A backs out because it feels it cannot deliver on the agreed price and will
incur a loss. The beneficiary (party B) will claim against the performance
bond for failure to perform the contract.
A financial guarantee is a very broad and general guarantee that can be
issued by a bank to ensure that party A fulfils its financial obligations to
party B. Typical example is party B is a manufacturer and seller of goods
and party A is a newly established buyer & distributor of those goods and
requests a credit limit of USD 1 million. Party B will request party A to
arrange a Financial Guarantee stating that Party B will receive payment
of up to USD 1 million upon submission of proof of delivery of goods by
party B to party A (typically Invoice and signed Goods Receipt Note).
A performance bond is a surety bond issued by an insurance company or
a bank to guarantee satisfactory completion of a project by a contractor.
For example, a contractor may cause a performance bond to be issued in
favor of a client for whom the contractor is constructing a building. If the
contractor fails to construct the building according to the specifications
laid (most often due to the bankruptcy of the contractor), the client is
guaranteed compensation for any monetary loss up to the amount of the
performance bond.
Performance bonds are commonly used in the construction and
development of real property, where an owner or investor may require
the developer to assure that contractors or project managers procure such
bonds in order to guarantee that the value of the work will not be lost in
the case of an unfortunate event (such as insolvency of the contractor). In
other cases, a performance bond may be requested to be issued in other
large contracts besides civil construction projects.
The term is also used to denote a collateral deposit of "good faith money",
intended to secure a futures contract, commonly known as margin.
Performance bonds are generally issued as part of a 'Performance and
Payment Bond', where a Payment Bond guarantees that the contractor
will pay the labour and material costs they are obliged to.
H. STEP 8 Payments to Contractors
Last step is finalising the payment formalities for the contractor which
may include any of the following processes:
Notes
.. .......
Notes
Running bills: Payments are made as per the progress of the project,
measured in terms of percentage completion or on achieving certain
milestones agreed upon.
4.
term sheet or
List the parameters that you would use for evaluating a potential contractor
\...for a project.
288
Notes
289
Note
I
r Prime
Contractor
2.
Selected Sellers: The selected sellers are sellers that the buyer deems the
best candidates for the project and that have negotiated a draft contract.
Notes
Notes
292
_I
Nctisi"
Activity 2
Notes
I Notes
Fixed Price (FP or FFP - firm fixed price)/Lump Sum: The simplest
type of contract. The owner specifies the work and the contractor gives
a price. In this case the contractor assumes almost all of the risk and as a
result reaps whatever profit there is. A fixed price or lump sum contract
is an agreed price for the performance of work, supply of labor, or supply
or goods at a designated time. The scope of the contract defines the
expectations of both parties. This type of contract provides a degree of
certainty for both parties because the contract scope clearly spells out
what is involved. They can be short term or ongoing in duration.
Fixed price contracts are often used in governmental contracting as they
give an easy way to compare competitive bids and to budget for the work
as all the uncertainty in actual price becomes the responsibility of the
contractor. On the other hand, this may not be the cheapest way to get
the work done. Aside effect of the fixed price contract is the Change
Order which modifies the initial contract for unforeseen conditions and
changes. Some contractors are highly skilled at generating change orders
which can boost profits on the job. In some cases change orders can equal
the size of the original contract. Litigation is often more expensive than
construction, so arbitration and settlement are typical in these cases.
294
B.
C.
Cost Plus Fixed Fee (CPFF or sometimes just Cost Plus): This type of
contract shifts most of the risk to the owner, but also allows the owner a
high degree of flexibility. The contractor under this form of contract has
profit at risk and will seek to minimize cost/duration to return a higher
proportional profit margin. This type of contract is more common on
projects which have high amounts of risk and uncertainty which would
scare contractors into giving impossibly high bids, or where the owner
just needs resources to work on a project.
Project Management Operations
Cost Plus Percentage of Costs (CPPC): This is very similar to the cost
plus fixed fee contract except that the contractor bears even less risk.
Their fee is calculated based on a percentage of actual costs. It is generally
believed that having a fee at risk is a motivating factor for contractors, so
this approach is not allowed for federal government contracts (though
there may be loopholes) It is very similar to T&M.
E.
Cost Plus Incentive Fee (CPIF): This type of contract uses an incentive
fee for motivating better performance than you would get with percentage
or fixed fee. In addition to a fee, an incentive is paid for beating a schedule
or cost target. Like having the fee at risk, is intended to motivate the
contractor to minimise costs and duration. Determining the appropriate
incentive is one difficulty, another is that once the target has been missed,
the incentive is no longer a motivating factor, Often the incentive fee is
calculated as a percentage of savings and is shared by the owner and the
contractor. The flip-side of incentive fees are liquidated damages.
F.
G.
Fixed Price Incentive Fee (FPIF): Similar to Fixed Price but with an
incentive fee. Motivation to perform is the reason.
H.
Unit Rate: Unit rate contract types are an agreed to rate for the
performance of specified work. Monetary exchange takes place when
work is performed and is directly proportional to the volume and range of
295
work. These types of contract are most prevalent in the building industry.
An example of a unit rate contract would be the supply of timber where
the monetary amount would be defined by the volume of units supplied.
The terms of this type of contract often accommodates flexibility for
price adjustment. The agreed to value may be subject to amendment if the
volume is reduced or exceeds the original negotiated terms and price.
Notes
I.
So those are the most common contract types. Of course, a contract can
take any form that two parties can agree to (and which is not prohibited by law)
so hybrids of these forms are possible. Another way of classifying the contracts
is as per following:
Hard Contract: A hard contract is the type of contract most widely used
by project management consultants. This concept identifies a clear set of
deliverables that the Project Manager is expected to complete and submit
to the client. These deliverables typically have a set timetable for when
they must be completed. The other key aspect of the hard contract is that
there is a set fee associated with the contract. In essence, it says "here is
what we need", "this is when we need it" and "this is how much you get
paid".
A.
Using hard contracts requires the ability to accurately forecast the costs of
the project, as well as the ability to make sure the project comes in under
budget. Because the fee paid to the Project Manager is fixed, anything
that runs over budget ultimately translates into money out of the Project
Manager's pocket.
Soft Contract: A soft contract offers a significant degree of flexibility
on the part of the client and the Project Manager alike. In case of a soft
contract, the fee is flexible according to the needs of the project, which
are reassessed frequently as the project is executed.
B.
AcotY Activity 3
Prepare a checklist for including the terms in contract for construction
project.
Prepare a checklist for including the terms in contract for a software
development and installation project.
296
Summary
Negotiations
Contract award
Payments to contractors
Force majeure (French for "superior force"), also known as cas fortuit
(French) or casus fortuitous (Latin), is a common clause in contracts
that essentially frees both parties from liability or obligation when an
extraordinary event or circumstance beyond the control of the parties,
such as a war, strike, riot, crime, or an event described by the legal term
"act of God" (e.g., flood, earthquake, volcanic eruption), prevents one or
both parties from fulfilling their obligations under the contract.
Notes
Notes
The tools and techniques for the Contract Administration process are:
Contract Change Control. System, Buyer-conducted Performance Review,
Inspections and Audits, Performance Reporting, Payment System,
Claims Administration, Records Management System and Information
Technology.
QdKeywords
298
Notes
Self-Assessment Questions
1.
2.
3.
4.
What are the different terms required to be looked at for project contracts?
5.
6.
7.
8.
9.
10.
What are liquidated damages? Explain the use of liquidated damages for
projects.
11.
12.
13.
PQR Ltd., STP Co. and RTS Co. are the three bidders who have submitted
their bids.
The company has decided to evaluate the bid on six parameters as per
following table. They have decided the weightages as per following table. Now
based on the bid submitted by the three contractors, the points are given to the
contractors which are shown in the following table. Find which bidder should
be selected.
Projects Contracts Management
299
Evaluation Parameter
Notes
---
RTS
CO.
6
7
7
6
6
9
2.
3.
4.
False
2.
False
300
40
UNIT
12
Notes
Objectives
After going through this unit, you will be able to:
Assess risk
Do risk mitigation
Scope Risk: The scope risk arises for improper understanding of scope
or insufficient definition of scope. This risk includes Scope gap (illdefined scope), Dependency change (unexpected legal, regulatory, etc.)
and Integration defect (change due to unexpected behaviour). There are
variety of methods for arriving at and defining deliverables and hence,
defining the scope. He suggests using the "is/is not" method of bounding
the scope. The scope risk includes Risk Framework, Risk Complexity
Index and Risk Assessment Grid. Risk Framework looks at the project's
technology, the market and the manufacturing effects and uses the relative
change to each of these to determine the risk level of the project. Risk
Complexity Index looks at the technical aspects of the project (technology,
architecture and system) and generates a number from 0-99 to quantify
risk. Risk Assessment creates a grid of technology, structure and size to
estimate the risk.
Scope risk is introduced into a project when the Work Breakdown Structure
WBS is not fully defined and understood. A WBS at too high a level can
leave scope ill-defined not allowing for proper estimates or definition of
work to be performed. Often WBS elements that are defined at too high
a level indicate work that is not understood and indicates significant risk
due to uncertainty on the project. The scope risk can be avoided by
302
2.
Notes
Schedule Risk: Schedule risk is the second level of risks affecting project
duration which is due to
Parts delays, which are due to delay in the activities which are part
of the project.
Decision delay wherein the delay in the activities occurs due to time
lost in waiting for the decisions to carry out the activities.
To assist in reducing these risks, the process should start with the WBS
and apply estimates for effort and resources. This is an iterative process.
A number of things should be kept in mind:
If the durations are greater than two weeks they should be broken
down further.
Historical data
Prior experience
_ ' .130'
Notes
3.
Resource Risk: The final category of risks is the resource risks which
include:
Outsourcing delays
Lack of funds
Attrition of resources
Scarcity of skills
'
When planning one must determine the skill set required and to identify
and reserve the people with those skills. To ensure proper resource
utilisation, computerised tools can be used to properly look at staff
loading. The loading will need to be compared to other project's needs
and resource availability. Conflicts need to be resolved and documented
since this also indicates inherent risk in the project.
Outsourcing is mitigated best by thorough planning, proper Request for
Proposal (RFP) generation, a clear and succinct contract and monitoring
the subcontractor for progress. Funding issues can be addressed by
defining and planning financial outlays early in the project planning cycle.
To ensure avoidance of resource risk we must take following actions:
All skills required to finish the project must have a named resource.
When managing project risk it must be understood that only two of the
three constraints can be defined, the third will be determined by the other two.
It should be determined which of the three (resource, scope or schedule) is the
controlling constraint and which is the most acceptable to change. Determining
this and insuring the stakeholders understand and consequence of this is of
utmost importance.
If scope is the least important, determine methods to achieve the most
for the customer while using fewer resources, trim low priority scope, suggest
alternative solutions to the problem being addressed, and look for reusable
components from other projects.
For resource constraints look at cross-training staff or training new people.
Outsourcing is an option but it introduces significant risk.
If schedule constraints are an issue, it is possible to use schedule float.
Also carefully analyse the schedule for tasks that can overlap. If they exist, look
at defining the tasks with more granularities. Lastly, if the funds are available,
add more resources to try to compress the schedule. All of these introduce their
own risk. Moreover to avoid risks in general, we must take following actions:
ii.
iii.
iv.
v.
vi.
r
:,, ActwAy
Activity 1
1.
2.
305
Notes
Problem analysis: Risks are related to the identified threats. For example,
the threat of losing money, the threat of abuse of privacy information or
the threat of accidents and casualties. The threats may exist with various
entities, most important with shareholders, customers and legislative
bodies such as the government.
When either source or problem is known, the events that a source may
trigger or the events that can lead to a problem can be investigated.
For example: stakeholders withdrawing during a project may endanger
funding of the project; privacy information may be stolen by employees
even within a closed network; lightning striking a Boeing 747 during
takeoff may make all people onboard immediate casualties.
The chosen method of identifying risks may depend on culture, industry
practice and compliance. The identification methods are formed by
templates or the development of templates for identifying source, problem
or event. Common risk identification methods are:
Notes
307
Notes
0
500
1000
Risk Likelihood %
20
10
40
30
30
10
60
20
A
B
C
D
E
F
G
H
Risk
Impact
Days
Risk
Impact
USD
0
4
3
0
2
1
0
4
1000
0
2000
1000
0
500
1000
0
Risk
Likelihood
%
20
10
40
30
30
10
60
20
TOTAL
Risk
Consequence
Days
Risk
Consequence
USD
0 X 0.2 = 0
4 X 0.1=0.4
3 X 0.4 = 1.2
0 X 0.3 = 0
2 X 0.3 =0.6
1 X 0.1 = 0.1
0 X 0,1 = 0
4 X 0.2 =0.8
3.1
Notes
Avoidance
Reduction
Sharing
Retention
Ideal use of these strategies may not be possible. Some of them may
involve trade-offs that are not acceptable to the organisation or person making
the risk management decisions. Some sources call these categories ACAT, for
Avoid, Control, Accept or Transfer.
Risk mitigation measures are usually formulated according to one or
more of the following major risk options, which are:
Risk avoidance (eliminate, withdraw from or not become involved)
This includes not performing an activity that could carry risk. An example
would be not buying a property or business in order to not take on the Legal
liability that comes with it. Another would be not being flying in order to not
take the risk that the airplane was to be hijacked. Avoidance may seem the
answer to all risks, but avoiding risks also means losing out on the potential gain
that accepting (retaining) the risk may have allowed. Not entering a business to
avoid the risk of loss also avoids the possibility of earning profits.
Type of risk avoidance is hazard prevention. Hazard prevention refers
to the prevention of risks in an emergency. The first and most effective stage
of hazard prevention is the elimination of hazards. If this takes too long, is too
costly, or is otherwise impractical, the second stage is mitigation.
Management Risk in Projects
r ViT971
Notes
Risk reduction
Risk reduction or "optimisation" involves reducing the severity of the
loss or the likelihood of the loss from occurring. For example, sprinklers are
designed to put out a fire to reduce the risk of loss by fire. This method may
cause a greater loss by water damage and therefore may not be suitable. Fire
suppression systems may mitigate that risk, but the cost may be prohibitive as a
strategy.
Acknowledging that risks can be positive or negative, optimising risks
means finding a balance between negative risk and the benefit of the operation
or activity; and between risk reduction and effort applied. By an offshore
drilling contractor effectively applying HSE Management in its organisation, it
can optimise risk to achieve levels of residual risk that are tolerable.
Modern software development methodologies reduce risk by developing
and delivering software incrementally. Early methodologies suffered from
the fact that they only delivered software in the final phase of development;
any problems encountered in earlier phases meant costly rework and often
jeopardized the whole project. By developing in iterations, software projects
can limit effort wasted to a single iteration.
Outsourcing could be an example of risk reduction if the outsourcer can
demonstrate higher capability at managing or reducing risks. For example, a
company may outsource only its software development, the manufacturing
of hard goods, or customer support needs to be done by another company,
while handling the business management itself. This way, the company can
concentrate more on business development without having to worry as much
about the manufacturing process, managing the development team, or finding a
physical location for a call center.
Risk sharing
Briefly defined as "sharing with another party the burden of loss or the
benefit of gain from a risk, and the measures to reduce the risk."
The term of 'risk transfer' is often used in place of risk sharing in the
mistaken belief that you can transfer a risk to a third party through insurance
or outsourcing. In practice, if the insurance company or contractor go bankrupt
or end up in court, the original risk is likely to still revert to the first party. As
such in the terminology of practitioners and scholars alike, the purchase of an
insurance contract is often described as a "transfer of risk." However, technically
speaking, the buyer of the contract generally retains legal responsibility for the
losses "transferred", meaning that insurance may be described more accurately
as a post-event compensatory mechanism. For example, a personal injuries
insurance policy does not transfer the risk of a car accident to the insurance
company. The risk is still with the policy holder namely the person who has
been in the accident. The insurance policy simply provides that if an accident
(the event) occurs involving the policy holder then some compensation may be
payable to the policy holder that is commensurate to the suffering/damage.
,319
Some ways of managing risk fall into multiple categories. Risk retention
pools are technically retaining the risk for the group, but spreading it over the
whole group involves transfer among individual members of the group. This is
different from traditional insurance, in that no premium is exchanged between
members of the group up front, but instead losses are assessed to all members
of the group.
Notes
Risk retention
Involves accepting the loss, or benefit of gain, from a risk when it occurs.
True self-insurance falls in this category. Risk retention is a viable strategy for
small risks where the cost of insuring against the risk would be greater over
time than the total losses sustained. All risks that are not avoided or transferred
are retained by default. This includes risks that are so large or catastrophic that
they either cannot be insured against or the premiums would be infeasible. War
is an example since most property and risks are not insured against war, so the
loss attributed by war is retained by the insured. Also any amount of potential
loss (risk) over the amount insured is retained risk. This may also be acceptable
if the chance of a very large loss is small or if the cost to insure for greater
coverage amounts is so great it would hinder the goals of the organisation too
much.
1P..t.tw t. Activity 2
..Enlist the different techniques of risk management in construction projectsi)
12.6 RISK MANAGEMENT PLANNING
The procedure used to manage risks is defined in the planning stage,
documented in the project risk management plan, and then executed through the
life of the project. Risk Management is the process of thinking systematically
about all potential undesirable outcomes before they happen and determining
procedures that will avoid them, minimise their impact, or cope with their
impact.
Risk management planning is the identification, assessment, and
prioritisation of risks followed by coordinated and economical application of
resources to minimise, monitor, and control the probability and/or impact of
unfortunate events or to maximise the realisation of opportunities. Risks can
come from uncertainty in financial markets, project failures, legal liabilities,
credit risk, accidents, natural causes and disasters as well as deliberate attacks
from an adversary. Several risk management standards have been developed
including the Project Management Institute, the National Institute of Science
and Technology, actuarial societies, and ISO standards. Methods, definitions
and goals vary widely according to whether the risk management method is in
the context of project management, security, engineering, industrial processes,
financial portfolios, actuarial assessments, or public health and safety.
Management Risk in Projects
311
Notes
Create value.
Be part of decision-making.
Be tailored.
ineffective operational procedures are applied. These risks directly reduce the
productivity of knowledge workers, decrease cost effectiveness, profitability,
service, quality, reputation, brand value, and earnings quality. Intangible risk
management allows risk management to create immediate value from the
identification and reduction of risks that reduce productivity.
Notes
2.
313
Notes
Planning how risk will be managed in the particular project. Plan should
include risk management tasks, responsibilities, activities and budget.
Maintaining live project risk database. Each risk should have the
following attributes: opening date, title, short description, probability and
importance. Optionally a risk may have an assigned person responsible
for its resolution and a date by which the risk must be resolved.
Preparing mitigation plans for risks that are chosen to be mitigated. The
purpose of the mitigation plan is to describe how this particular risk will
be handled what, when, by who and how will it be done to avoid it or
minimise consequences if it becomes a liability.
314
1.
Notes
Mitigative Controls
41
ro 1141.
I I I '
Hazards
Controls
.i--rijs
Controls
315
Notes
1.
A main goal of
decision-making.
Supplier power: Here you assess how easy it is for the suppliers to
drive up prices. This is driven by the number of suppliers of each
key input, the uniqueness of their product or service, their strength
and control over you, the cost of switching from one to another, and
so on. The fewer the supplier choices you have, and the more you
need suppliers' help, the more powerful your suppliers are.
2.
Buyer power: Here you ask yourself how easy it is for buyers to
drive prices down. Again, this is driven by the number of buyers,
the importance of each individual buyer to your business, the cost
Project Management Operations
4.
5.
Notes
These forces can be neatly brought together in a diagram like the one below:
Porter's Five Forces
threat of New Enity:
tens and cosi of naive
SiValallst know4odge
- Iconornicas of seek,
Cot, ochiontogos
Inchriolegy orotrAcren
Bailors ks onify
oic
N
N
Supplier
Power
Threat of
New
Entry
CornoetilMiRh,olry:
Nemo, of c:OrTipOriforr.
;Duddy offoroncos
Olhor dlifortricos
Swift:frog costs
Customer lOyilly
Costs or 110t-hil'iq mote;
/
/Competitive r
Rivalry
Buyer
Power
_
Supplier Power:
Nernixit of stiprecils
Sizo of 51.101-*01$
- UricitoOnesS of service
Ycra obely to 9ubstitula
- Cosi of crionryng
-etc
Threat of Substitution:
- Sr Lzlindo ixof art I 'arc-9
CoS1 Of crango
\
Threat of
Substitution
layer Power
Numboi of customers
Silo of colon:Sol
Wolof/COS ootwoon
ccmoofifors
Puce sertseivity
- ALAN to sUbstifulo
Cost of charging
otc-
317
To use the tool to understand the situation, we will have to look at each of
these forces one-by-one and write our observations.
Notes
We will have to brainstorm the relevant factors for our market or situation,
and then check against the factors listed for the force in the diagram above.
Then, we will have to mark the key factors on the diagram and summarise
the size and scale of the force on the diagram. An easy way of doing this
is to use, for example, a single "+" sign for a force moderately in your
favour, or "" for a force strongly against us.
Then we need to look at the situation we find using this analysis and think
through how it affects us. Bear in mind that few situations are perfect;
however, looking at things in this way helps you think through what you
could change to increase your power with respect to each force. What's
more, if you find yourself in a structurally weak position, this tool helps
you think about what you can do to move into a stronger one.
B.
Notes
mascot reaction
InOdtittrIO
of
Dap,
Once we have done this, review your tree diagram. We have to challenge
each square and circle to see if there are any solutions or outcomes we have
not considered. If there are, we need to draw them in. If necessary, we have to
redraft our tree if parts of it are too congested or untidy.
Evaluating Decision Tree
Now we need to see which option has the greatest worth to us. For this we
need to start by assigning a cash value or score to each possible outcome. We
need to make our best assessment of how much we think it would be worth to
us if that outcome came about.
Next look at each circle (representing an uncertainty point) and estimate
the probability of each outcome. If you use percentages, the total must come
to 100% at each circle. If you use fractions, these must add up to 1. If you
have data on past events you may be able to make rigorous estimates of the
probabilities. Otherwise write down your best guess.
319
Notes
This will give you a tree like the one shown in Figure 2:
rigure
Example Ciecison Tree:
Should we develop a new
product or consolidate?
market reaction
$1,000.000
$-50.000
$2,000
$ I ,000,00C
$50,000
$2,000
$400 000
$20.000
$6,000
.11700
-7
_
'
$2,000
320
Notes
market reaction
$1,0001)O1)
1-4--]
.A 100
WO 0
$50000
$2.000
420.400
$1,000,000
11,4001
$50,000
i>00,
0 1 x 1.000 COO= 100.000
0 2 x 50 CCO = 10.0c0
07x
Mee = 1,4C0
111,400
$2,000
$400,000
LLIEXA
fi
c.L.
C 1-131eze,--0
modemgo
$20.000
Q
>40".
Poo,.
0.3 x 400.000 = 120,000
0,4 x 20.000 = 8,000
0.3 x 4.000 =
1,800
129,800
4600,,j.
$6,000
$20 OCO
112,8001
04
04
Door
$2,000
0 d x 20.000 = 12,000
0,4 x 2.000 =
80(1
12 800
Note that the values calculated for each node are shown in the boxes.
Calculating the Value of Decision Nodes
When you are evaluating a decision node, write down the cost of each
option along each decision line. Then subtract the cost from the outcome value
that you have already calculated. This will give you a value that represents the
benefit of that decision.
Note that amounts already spent do not count for this analysis. These are
`sunk costs' and (despite the emotional cost) should not be factored into the
decision.
When you have calculated these decision benefits, choose the option that
has the largest benefit, and take that as the decision made. This is the value of
that decision node.
321
Notes
tnrroloIt.1141$ Weer
:00tio we Ovvolork aeow
n itelOtconsovcs7kv
'P KC tr.
Clearly lay out the problem so that all options can be challenged.
outside your control could delay your project. But formal risk analysis and risk
management can help you to assess these risks and decide what actions to take
to minimise disruptions to your plans. They will also help you to decide whether
the strategies you could use to control risk are cost-effective.
IM Notes
Firstly, run through a list such as the one above, to see if any apply.
323 11
Notes
2.
Estimate risk: Once you have identified the threats you face, the next
step is to work out the likelihood of the threat being realised and to assess
its impact. One approach to this is to make your best estimate of the
probability of the event occurring, and to multiply this by the amount it
will cost you to set things right if it happens. This gives you a value for
the risk.
3.
Managing risk: Once you have worked out the value of risks you face,
you can start to look at ways of managing them. When you are doing this,
it is important to choose cost-effective approaches. In most cases, there is
no point in spending more to eliminate a risk than the cost of the event if
it occurs. Often, it may be better to accept the risk than to use excessive
resources to eliminate it. Risk may be managed in a number of ways:
Once you have carried out a risk analysis and management exercise, it
may be worth carrying out regular reviews. These might involve formal reviews
of the risk analysis, or may involve testing systems and plans appropriately.
Risk analysis allows you to examine the risks that you face or your
organisation faces. It is based on a structured approach to thinking through
threats, followed by an evaluation of the probability and cost of events occurring.
As such, it forms the basis for risk management and crisis prevention. Here
the emphasis is on cost-effectiveness. Risk management involves adapting the
use of existing resources, contingency planning and good use of new resources.
Contingency Planning
Fires, floods, tornadoes these are the things we often connect with
contingency planning. But what if your main supplier suddenly goes bankrupt?
Or, what if your entire sales force gets sick with food poisoning at your annual
Project Management Operations
sales conference? Or, your payroll clerk simply calls in sick on payroll day?
These things can all cause confusion and disorder if you haven't prepared for
them properly. Contingency planning is a key part of this preparation.
Notes
2.
Since all projects involve some degree of risk, a project risk management
plan is necessary to define and document those procedures that will be used
to manage risk throughout the life of the project. Risk can be understood
as any factor that may potentially interfere with successful completion of
the project. Therefore, it follows that by recognising potential problems
the project manager and core team members can avoid most, if not all, of
these problems through proper actions. The potential problems arise from
the constraints in projects which are: Scope risk, Schedule risk, Resource
Risk.
When managing project risk it must be understood that only two of the
three constraints can be defined, the third will be determined by the
other two. It should be determined which of the three (resource, scope or
schedule) is the controlling constraint and which is the most acceptable
,325
Notes
Once risks have been identified and assessed, all techniques to manage
the risk fall into one or more of these four major categories: Avoidance,
Reduction, Sharing and Retention. Some of them may involve tradeoffs that are not acceptable to the organisation or person making the risk
management decisions.
There are various tools which help in proper risk management in project.
The two tools which are very helpful in this are Porter's Five Forces
Model and Decision Tree Analysis.
Keywords
326
Risk: Any factor that may potentially interfere with successful completion
of the project.
Scope risk: The scope risk arises for improper understanding of scope or
insufficient definition of scope.
Schedule risk: The second level of risks effecting project duration which
is due to project dependencies, parts delay, estimation errors, decision
delay, hardware delay.
Resource risk: The risk which arises due to outsourcing delays, lack of
funds, attrition of resources, people joining the team late, scarcity of skills
and material shortage.
Project Management Operations
Risk sharing: Sharing with another party the burden of loss or the benefit
of gain, from a risk, and the measures to reduce a risk.
Risk retention: Involves accepting the loss, or benefit of gain, from a risk
when it occurs.
Notes
What is risk? What are the various types of risks that can occur in projects?
2.
What are the sources of risk in projects? Explain with suitable examples.
3.
4.
5.
6.
7.
8.
What are risk impact, risk likelihood and risk consequence? Explain with
suitable examples.
9.
What are the tools that can be used for risk management? Explain with
examples.
10.
11.
What is the importance of Porter's Five Forces model for project risk
management?
12.
13. ABC Ltd. has forecasted total cost of USD 10,000 for the project and
expects to complete the project in 10 days. They have identified risks and
made an assessment as per following table. Find the revised estimate.
Risk
A
B
C
D
E
F
G
H
327
Notes
2.
False
2.
True
2.
Suggested Reading
1.
328
UNIT
13
329
Notes
Objectives
After going through this unit, you will be able to:
2.
Notes
The ultimate judge for quality is the beneficiary, and represents how
close the project outputs and deliverables come to meeting the beneficiaries'
requirements and expectations. How a beneficiary defines quality may be
completely subjective, but there are many ways to make quality objective by
defining the individual characteristics and determine one or more metrics that
can be collected to mirror the characteristic. For instance, one of the features
of a quality product may be that it has a minimum amount of errors. This
characteristic can be measured by counting errors and defects after the product
is used.
Quality management is not an event it is a process, a consistently high
quality product or service cannot be produced by a defective process. Quality
management is a repetitive cycle of measuring quality, updating processes,
measuring, updating processes until the desired quality is achieved.
The Purpose of Management of Quality
The main principle of project quality management is to ensure the project
will meet or exceed stakeholder's needs and expectations. The project team
must develop a good relationship with key stakeholders, specially the donor and
the beneficiaries of the project, to understand what quality means to them. One
of the causes for poor project evaluations is the project focuses only in meeting
the written requirements for the main outputs and ignores other stakeholder
needs and expectations for the project.
Quality must be viewed on an equal level with scope, schedule and budget.
If a project donor is not satisfied with the quality of how the project is delivering
the outcomes, the project team will need to make adjustments to scope, schedule
and budget to satisfy the donor's needs and expectations. To deliver the project
scope on time and on budget is not enough, to achieve stakeholder satisfaction
the project must develop a good working relationship with all stakeholders and
understand their stated or implied needs. Project management consists of four
main processes:
Quality Definition
Quality Control
Quality Assurance
Quality Improvements
331
Notes
332
Quality Characteristics
Notes
Completeness, the quality that the service is complete and includes all
the entire scope of services. Training sessions should be complete and
include all the material needed to build a desired skill or knowledge
Consistency, services are delivered in the same way for every beneficiary.
Clinical tests need to be done using the same procedure for every patient.
333
Notes
Quality plan
Part of defining quality involves developing a quality plan and a quality
checklist that will be used during the project implementation phase. This check
list will ensure the project team and other actors are delivering the project
outputs according to the quality requirements. Once the project has defined the
quality standards and quality characteristics, it will create a project quality plan
that describes all the quality definitions and standards relevant to the project,
it will highlight the standards that must be followed to comply to regulatory
requirements setup by the donor, the organisation and external agencies such as
the local government and professional organisations (health, nutrition, etc.)
The quality plan also describes the conditions that the services and
materials must possess in order to satisfy the needs and expectations of the
project stakeholders, it describes the situations or conditions that make an
output fall below quality standards, this information is used to gain a common
understanding among the project team to help them identify what is above and
what is below a quality standard.
The quality plan also includes the procedure to ensure that the quality
standards are being followed by all project staff. The plan also includes the
steps required to monitor and control quality and the approval process to make
changes to the quality standards and the quality plan.
2
3.
- ActIvtY ^:
Activity 1
b.
Rework: It is the action taken to bring the rejected product or service into
compliance with the requirements, quality specifications or stakeholder
expectations. Rework is expensive, that is why the project must make
every effort to do a good job in quality planning and quality assurance to
avoid the need for rework. Rework and all the costs associated with it may
not refundable by the donor and the organisation may end up covering
those costs.
c.
Notes
335
Notes
One of the most powerful aspects of a scatter plot, however, is its ability
to show non-linear relationships between variables. Furthermore, if the
data is represented by a mixture model of simple relationships, these
relationships will be visually evident as superimposed patterns.
A_
B.
c.
1
D.
E.
336 .
symptoms of the problem, or other topics that digress from the intent of
the session. It also displays a real-time 'snap-shot' of the collective inputs
of the team as it is updated. The possible causes are presented at various
levels of detail in connected branches, with the level of detail increasing
as the branch goes outward, i.e., an outer branch is a cause of the inner
branch it is attached to. Thus, the outermost branches usually indicate the
root causes of the problem. This is indicated in the diagram as below:
Insullkionl
hardness
Noornnforonwo
dellWry
Unlink
motion,
Wrong.. .cif on a-
Latent
Wrong
5lock keeping
Fa.uro 'offing
.4 tiCIAlaluf
H.C.,41
II 1.1krtvirig
Ercorn or
loohnology
Influence
Tolson drIbing
UncopobrIfIly
of machine
probteral
Ignorance
Doloollvo lowly
Faun of
%on ng WOloof
Notes
Inahr011m
Wrong rocord
337
Notes
Why? - The alternator belt was well beyond its useful service life
and has never been replaced. (fourth why)
The questioning for this example could be taken further to a sixth, seventh,
or even greater level. This would be legitimate, as the "five" in 5 Whys
is not gospel, rather, it is postulated that five iterations of asking why is
generally sufficient to get to a root cause. The real key is to encourage the
troubleshooter to avoid assumptions and logic traps and instead to trace
the chain of causality in direct increments from the effect through any
layers of abstraction to a root cause that still has some connection to the
original problem.
Typical categories of causes are: The original 4 Ms
Machine (Equipment)
Method (Process/Inspection)
Manpower
More categories
Measurement (Inspection)
Maintenance
Money Power
Management
338
People
Process
Policies
Procedures
Price
Promotion
Place/Plant
Product
Surroundings
Suppliers
Systems
Skills
Notes
Thus, the aim of Ishikawa diagram is to arrive at the root cause of the
problems.
3.
2.
3.
4.
5.
Check list: The items to be performed for a task are listed so that, as
each is accomplished, it can be indicated as having been completed.
339
Notes
Sheet No:
1532
Operator: Mw4,
Date:
2 at, (.9
Lathe number: 3 2 1 4 15
Remarks:
Cutter type:
332
Lowere...c LiraM
upper spec. LUTA
mm.
1 0 1 1 1 21,31.4151 6(1.71.8 1.9 2.0 21 2.2 2.3 2.4 2.5 2.6 2.7 2.8 2.9 3.0 3.1 3 2 3.3 3 4
25
20
,
15
----
10
--- -,
. -_
-_ --
-- -- --. __
-__ --- __ -- _
5
0
Total:
Pareto charts: These charts are based on Pareto's rule, which states that
80 per cent of the problems are often due to 20 per cent of the causes. The
assumption is that most of the results in any situation are determined by a
small number of causes and helps identify the vital few contributors that
account for most of the quality problems. The chart is a form of histogram
that orders the data by frequency of occurrence.
It shows how many defects were generated by a type of category of
identified cause. For example, to determine the errors in the collection of
beneficiary data the project team identified five causes and for each cause,
the measured frequency of errors. The data is plotted as shown in the
chart below. The bars represent each category and the line represents the
cumulative percentage of the errors, the chart allows to identify that 80
per cent of the errors coUld be reduced just by improving the collection of
data in two categories instead of focusing efforts to correct all categories.
5.
items that were outside the control limits. This helps the project determine
actions to help the beneficiaries improve the quality of their work.
NQtes
Control charts can also be used to the project management areas, such as
schedule and budget control, to determine whether the costs variances or
schedule variances are outside the acceptable limits set by the donor.
6. Histogram: The most commonly used graph for showing frequency
distributions, or how often each different value in a set of data occurs is
the histogram. In statistics, a histogram is a graphical display of tabulated
frequencies, shown as bars. It shows what proportion of cases fall into
each of several categories: it is a form of data binning The categories
are usually specified as non-overlapping intervals of some variable.
The categories (bars) must be adjacent. The intervals (or bands, or bins)
are generally of the same size. Histograms are used to plot density of
data, and often for density estimation: estimating the probability density
function of the underlying variable. The total area of a histogram used for
probability density is always normalised to 1. If the length of the intervals
on the x-axis is all 1, then a histogram is identical to a relative frequency
plot. An alternative to the histogram is kernel density estimation, which
uses a kernel to smooth samples. This will construct a smooth probability
density function, which will in general more accurately reflect the
underlying variable.
600 500
O
6.
400
300
200
100
0
Fig.13.4: Histogram
13.4 QUALITYASSURANCE
Assurance is the activity of providing evidence to create confidence
among all stakeholders that the quality-related activities are being performed
effectively and that all planned actions are being done to provide adequate
confidence that a product or service will satisfy the stated requirements for
quality.
Quality assurance is a process to provide confirmation based on evidence
to ensure to the donor, beneficiaries, organisation management and other
stakeholders that product meet needs, expectations, and other requirements. It
Project Quality Management
341
assures the existence and effectiveness of process and procedures tools, and
safeguards are in place to make sure that the expected levels of quality will be
reached to produce quality outputs.
Quality assurance occurs during the implementation phase of the project
and includes the evaluation of the overall performance of the project on a regular
basis to provide confidence that the project will satisfy the quality standards
defined by the project.
One of the purposes of quality management is to find errors and defects as
early in the project as possible. Therefore, a good quality management process
will end up taking more effort hours and cost upfront.
The goal is to reduce the chances that products or services will be of poor
quality after the project has been completed. Quality assurance is done not only
to the products and services delivered by the project but also to the process and
procedures used to manage the project, that includes the way the project uses
the tools, techniques and methodologies to manage scope, schedule, budget and
quality. Quality assurance also includes whether the project meets any legal or
regulatory standards.
Quality Audits
Quality audits are structured reviews of the quality management activities
that help identify lessons learned that can improve the performance on current
or future project activities. Audits are performed by project staff or consultants
with expertise in specific areas. The purpose of quality audit is to review how
the project is using its internal processes to produce the products and services
it will deliver to the beneficiaries. Its goal is to find ways to improve the tools,
techniques and processes that create the products and services.
If problems are detected during the quality audits, corrective action will
be necessary to the tools, processes and procedures used to ensure quality
is reestablished. Part of the audit may include a review of the project staff
understanding of the quality parameters or metrics, and skills, expertise and
knowledge of the people, lin charge of producing or delivering the products or
services. If corrective actions are needed, these must be approved through the
change control processes.
The PDCA Cycle
The most popular tool used to determine quality assurance is the PDCA
Cycle. This cycle for quality assurance consists of four steps - Plan, Do, Check,
and Act. These steps are commonly abbreviated as PDCA. The four quality
assurance steps within the PDCA model stand for:
Notes
PDCA CYCLE
PDCA is an effective method for monitoring quality assurance because
it analyses existing conditions and methods used to provide the product or
service to beneficiaries. The goal is to ensure that excellence is inherent in every
component of the process. Quality assurance also helps determine whether the
steps used to provide the product or service is appropriate for the time and
conditions. In addition, if the PDCA cycle is repeated throughout the lifetime of
the project helping improve internal efficiency.
The PDCA cycle is shown below as a never-ending cycle of improvement.
This cycle is sometimes referred to as the Shewart/Deming cycle since it
originated with Shewart and was subsequently applied to management practices
by Deming.
7343
Notes
Quality assurance is something that must be planned for from the earliest
stages of a project, with appropriate measures taken at every stage. Unfortunately,
far too many development projects are implemented with no quality assurance
plan, and these projects often fail to meet quality expectations of the donor and
beneficiaries. To avoid problem the project must be able to demonstrate the
consistent compliance with the quality requirements for the project.
phase of the
344
Identify what you want to improve in the project using the data found in
the quality control process. Identify the areas that need improvement.
Analyze the problem or system. The team then investigates the causes for
the problem and its implications to the project, the causes may be internal
or external to the project.
Test and implement the solutions. The team may decide to test the solution
on a small scale to verify that it is capable of fixing the problem. It testes
for the initial assumptions made about the problem and once it confirms
that the solution is a viable alternative, it then proceeds to implement it in
a full scale solution.
Cost of Quality
Notes
The cost of quality is the sum of costs a project will spend to prevent poor
quality and any other costs incurred as a result of outputs of poor quality. Poor
quality is the waste, errors, or failure to meet stakeholder needs and project
requirements. The costs of poor quality can be broken down into the three
categories of prevention, appraisal, and failure costs.
Failure costs: A project incurs these costs because the product or service
did not meet the requirements and had to be fixed or replaced, or the
service had to be repeated.
Leadership
Joseph M. Juran, one of the leading experts in Quality management said
that "it is most important that management be quality-minded. In the absence
of sincere manifestation of interest at the top, little will happen below." What
this means is the main cause of quality problems is a lack of leadership. In
order to establish and implement effective quality projects, senior management
must lead the way. A large percentage of quality problems are associated with
management, not technical issues, it is the responsibility of the development
organisations senior management to take responsibility for creating, supporting,
and promoting quality programs.
Quality problems should be taken as an opportunity for improvement.
Problems can help identify more fundamental or systemic root causes and help
develop ways to improve the process. Unfortunately, projects do not have a
culture that promotes the identification of problems for the fear that making
improvements is an admission that the current way of doing things is flawed or
that those responsible are poor performers. Improved performance cannot occur
unless the project team feels comfortable that they can speak truthfully and are
confident that their suggestions will be taken seriously.
Maturity Models
Another approach to improve quality is the use of maturity models, which
are frameworks for helping organisations and projects improve their processes.
Project Quality Management
-345
Notes
The model includes a method for assessing the projects maturity levels as a
first step to determine the improvements needed to increase the capacity of the
project to deliver the project outputs as promised.
The use of the word "maturity" implies that capabilities must be grown
over time in order to produce repeatable success in project management. The
Random House College Dictionary defines "maturity" as full development or
perfected condition. "Maturity" also indicates understanding or visibility into
why success occurs and ways to correct or prevent common problems. "Model"
implies change, a progression, or steps in a process.
Project management maturity is the progressive development of an
organisations project management approach, methodology, strategy and
decision-making process. The appropriate level of maturity can vary for each
organisation based on specific goals, strategies, resource capabilities, scope and
needs.
The proper level of maturity to which an organisation should strive is
determined during a detailed assessment conducted by a professional project
management consulting team. The organisation has achieved full project
management maturity when it has met the requirements and standards for project
management effectiveness and it is capable of demonstrating improvements
such as on-time project delivery, cost reductions, organisational efficiency and
quality outcomes.
A project quality maturity usually consists of five levels:
Level 2: Defined level, the organisation has defined some basic quality
standards and project quality policies that are being adopted. But not all
projects are using it in a consistent manner.
Level 4: Controlled level, all projects are required to use quality planning
standard processes. The organisation has a unit or roles that coordinate
quality standards and assurance and quality audits are done on a regular
basis.
The model helps an organisation identify where they stand and where
they should strive to reach. It is a simple way to determine the level of maturity
346
Notes
Continuous Improvement
Quality is not something that is done at the end of a phase or at the end
of the project. It is a continuous process to ensure quality is performed in all
aspects of the project. The goal is to continuously improve based on the lessons
learned and new insights provided by the project. To be effective it should
happen during all the activities of the project. Continuous improvement, in
regard to project quality always focuses on improving stakeholder satisfaction
through continuous and incremental improvements to processes, including the
removal of any unnecessary activities. By applying a process that continuously
improves every element of the project can achieve better results than trying
to wait until the end of a phase or a mid-term evaluation to start making
adjustments and improvements to the work. It requires little effort and by doing
small incremental improvements the project can reach significant levels of
quality.
To implement continuous improvements, it is necessary to have a culture
of reflection that allows the project team to learn from mistakes and apply the
lesson at the next phase or cycle and not spend time and effort trying to put
blame; otherwise, the team will fear reporting any problems with quality and it
will be too late to do anything once the donor or the beneficiaries find out.
Check your Progress 3
Fill in the blanks.
1.
2.
347
Notes
1.
(ii)
(iii) Give trouble-free service over its life span (reliability requirements).
(iv) Be repaired, in case of malfunction, with ease and without aid of
too many special tools (maintainability requirements).
(v)
11 ;
Notes
Procurement of materials and parts at the right time and at the right
price.
2.
349
Notes
Good quality of design does not automatically guarantee high quality of the
product. It is the good design coupled with a good execution (conformance)
which results in good quality of product. Poor conformance, on the contrary,
can easily debase a good design.
Quality of conformance demands a system approach and control of every
item that goes into the product and control of every activity that is required
for the production of the product: the material, the tools, the equipment, the
processes, the preservatives, the packaging and packing, etc. Quality control
is the watch-dog which ensures that every element of production and activities
linked to it which could affect the quality of the end-product are regulated to the
extent desirable.
Quality of
Notes
Quality standards should also be reasonable and achievable, i.e., they must
be economically viable. Absolute uniformity (i.e., to produce each item to
exact dimension) is not only impossible to obtain in production but also
costly to approach. The quality standards, therefore, must take into account
permissible amount of variation from the ideal. In an engineering drawing,
specification gives the basic dimension called nominal size which is
theoretically the perfect dimension and the permissible variations around
it called design tolerance which depends on the functional requirements
of the part.
Activm r Activity 2
Select project activities and use QC tools for measuring quality performance
of project activities.
LuMM
Summary
.6
Quality management is the process for ensuring that all project activities
necessary to design, plan and implement a project are effective and
efficient with respect to the purpose of the objective and its performance.
Project quality management (QM) is not a separate, independent process
that occurs at the end of an activity to measure the level of quality of
the output. It is not purchasing the most expensive material or services
available in the market. A product may be of good quality (no defects) and
be of low grade (few or no extra features).
W5.1
The first step on the quality management is to define quality. The project
manager and the team must identify what quality standards will be used in
the project, it will look at what the donor, beneficiaries, the organisation
and other key stakeholders want to come up with a good definition of
quality. Identifying quality standards is a key component of quality
definition that will help identify the key characteristics that will govern
project activities and ensure the beneficiaries and donor will accept the
project outcomes.
Quality control is the use of techniques and activities that compare actual
quality performance with goals and define appropriate action in response
to a shortfall. It is the process that monitors specific project results to
determine if they comply with relevant standards and identifies different
approaches to eliminate the causes for the unsatisfactory performance.
Notes
0Keywords
Quality management: The process for ensuring that all project activities
necessary to design, plan and implement a project are effective and
efficient with respect to the purpose of the objective and its performance.
Pareto charts: These charts are based on Pareto's rule, which states that
80 per cent of the problems are often due to 20 per cent of the causes.
The chart is a form of histogram that orders the data by frequency of
occurrence.
353
Notes
Cost of quality: The sum of costs a project will spend to prevent poor
quality and any other costs incurred as a result of outputs of poor quality.
Self-Assessment Questions
1.
2.
3.
4.
What are the quality, control tools? Explain the different types of quality
control tools.
5.
6.
7.
8.
9.
What is PDCA cycle? Explain the application of PDCA cycle for quality.
354 S
1.
2.
3.
Notes
PDCA cycle for quality assurance consists of four steps - Plan, Do, Check
and Act.
2.
The four steps of quality improvement are identify, analyse, develop and
test.
2.
Cost of poor quality can be broken into three categories prevention cost,
appraisal cost and failure cost.
2.
355
Notes
UNIT
14
357
Notes
Do software maintenance
Notes
Planning
The important task in creating a software product is extracting the
requirements or requirements analysis. Customers typically have an abstract idea
of what they want as an end-result, but not what software should do. Incomplete,
ambiguous, or even contradictory requirements are recognised by skilled and
experienced software engineers at this point. Frequently demonstrating live
code may help reduce the risk that the requirements are incorrect.
Once the general requirements are gathered from the client, an analysis of
the scope of the development should be determined and clearly stated. This is
often called a scope document.
Certain functionality may be out of scope of the project as a function
of cost or as a result of unclear requirements at the start of development. If
the development is done externally, this document can be considered a legal
document so that if there are ever disputes, any ambiguity of what was promised
to the client can be clarified.
Implementation, testing and documenting
Implementation is the part of the process where software engineers
actually program the code for the project.
Software testing is an integral and important part of the software
development process. This part of the process ensures that defects are recognised
as early as possible.
Documenting the internal design of software for the purpose of future
maintenance and enhancement is done throughout development. This may also
include the writing of an API, be it external or internal. It is very important to
document everything in the project.
Deployment and maintenance
Deployment starts after the code is appropriately tested, is approved for
release and sold or otherwise distributed into a production environment.
Software Training and Support is important and a lot of developers fail
to realise that it would not matter how much time and planning a development
team puts into creating software if nobody in an organisation ends up using it.
People are often resistant to change and avoid venturing into an unfamiliar area,
so as a part of the deployment phase, it is very important to have training classes
for new clients of your software.
Maintaining and enhancing software to cope with newly discovered
problems or new requirements can take far more time than the initial
development of the software. It may be necessary to add code that does not fit
359
Notes
,360 . .
Notes
NoteS
Agile Development
Agile software development uses iterative development as a basis
but advocates a lighter and more people-centric viewpoint than traditional
approaches. Agile processes use feedback, rather than planning, as their primary
control mechanism. The feedback is driven by regular tests and releases of the
evolving software.
There are many variations of agile processes.
XP (Extreme Programming)
In XP, the phases are carried out in extremely small (or "continuous")
steps compared to the older, "batch" processes. The (intentionally incomplete)
first pass through the steps might take a day or a week, rather than the months or
years of each complete step in the Waterfall model. First, one writes automated
tests to provide concrete goals for development. Next is coding (by a pair of
programmers), which is complete when all the tests pass, and the programmers
can't think of any more tests that are needed. Design and architecture emerge
out of refactoring, and come after coding. Design is done by the same people
who do the coding. (Only the last feature merging design and code is common to
all the other agile processes.) The incomplete but functional system is deployed
or demonstrated for (some subset of) the users (at least one of which is on the
development team). At this point, the practitioners start again on writing tests
for the next most important part of the system.
r
Check your Progress 1
11#
Fill in the blanks.
1.
3.
362
Waterfall Model
Notes
2.
Software Design
3.
4.
Integration
5.
6.
7.
Maintenance
2.
3.
4.
- 3E3
...Notes
2.
If the implementation of risk analysis will greatly affect the profits of the
project, then risk analysis is meaningless. Therefore, spiral model is only
suitable for large-scale software projects.
3.
364
Critical
High: The bug or issue affects a crucial part of a system, and must be
fixed in order for it to resume normal operation.
Medium: The bug or issue affects a minor part of a system, but has some
impact on its operation. This severity level is assigned when a non-central
requirement of a system is affected.
Low: The bug or issue affects a minor part of a system, and has very little
impact on its operation. This severity level is assigned when a non-central
requirement of a system (and with lower importance) is affected.
Cosmetic: The system works correctly, but the appearance does not
match the expected one. For example, wrong colours, too much or too
little spacing between contents, incorrect font sizes, typos, etc. This is the
lowest priority issue.
Notes
The purpose of
is to keep the team and management up to
date on the project's progress.
2.
365
Notes
System Analysis
and Control
(Balance
Requirements
Analysis
Requirements
Loop
Il
Verification
Functional Analysis
and Allocation
A
Design
i
Loop
Design Synthesis
it_
V
PROCESS OUTPUT
modern techniques include prototyping, and use cases. Where necessary, the
analyst will employ a combination of these methods to establish the exact
requirements of the stakeholders, so that a system that meets the business needs
is produced.
Notes
Requirements engineering
Systematic requirements analysis is also known as requirements
engineering. It is sometimes referred to loosely by times such as requirements
gathering, requirements capture or requirements specification. The term
requirements analysis can also be applied specifically to the analysis proper, as
opposed to elicitation or documentation of the requiiements, for instance.
Requirement engineering according to Laplante (2007) is "a subdiscipline of systems engineering and software engineering that is concerned
with determining the goals, functions, and constraints of hardware and software
systems." In some life cycle models, the requirement engineering process
begins with a feasibility study activity, which leads to a feasibility report.
If the feasibility study suggests that the product should be developed, then
requirement analysis can begin. If requirement analysis precedes feasibility
studies, which may foster outside the box thinking, then feasibility should be
determined before requirements are finalised.
Functional specification
A functional specification (also, functional spec, specs, functional
specifications document (FSD), or Program specification) in systems
engineering and software development is the documentation that describes the
requested behaviour of an engineering system. The documentation typically
describes what is needed by the system user as well as requested properties of
inputs and outputs.
System
Concept
P
Requirements
Integrated and
Qualified System
System Specification
uu
c t
Product
output
System
Spec
P
r
o
d
10,
Item Performance Specifications
ct
dor p
r Ho.
.g,jit4
t:
i
to u
t I
511)tpeeetmo:i.
l
=
Drawings
Product
Output Process
and
Material
Specs
Drawings
Product
Output
367
Notes
Notes
" 369
involved in each such user's specialty area and interest, e.g., the stakeholders
of software systems, the software developer, the software system operational
support group, the software maintenance specialists, the deployer, the tester
and also the business end-user. In this sense, software architecture is really
the amalgamation of the multiple perspectives a system always embodies. The
fact that those several different perspectives can be put together into software
architecture stands as the vindication of the need and justification of creation
of software architecture before the software development in a project attains
maturity.
Software design
Software design is a process ofproblem-solving and planning for a software
solution. After the purpose and specifications of software are determined,
software developers will design or employ designers to develop a plan for a
solution. It includes low-level component and algorithm implementation issues
as well as the architectural view.
The software requirements analysis (SRA) step of a software development
process yields specifications that are used in software engineering. If the
software is "semi-automated" or user-centred, software design may involve user
experience design yielding a storyboard to help determine those specifications.
If the software is completely automated (meaning no user or user interface), a
software design may be as simple as a flow chart or text describing a planned
sequence of events. There Are also semi-standard methods like Unified
Modeling Language and fundamental modeling concepts. In either case some
documentation of the plan is usually the product of the design.
A software design may be platform-independent or platform-specific,
depending on the availability of the technology called for by the design.
Notes
Notes
Algorithmic complexity
The academic field and the engineering practice of computer programming
are both largely concerned with discovering and implementing the most
efficient algorithms for a given class of problem. For this purpose, algorithms
are classified into orders using so-called Big 0 notation, 0 (n), which expresses
resource use, such as execution time or memory consumption, in terms of the size
of an input. Expert programmers are familiar with a variety of well-established
algorithms and their respective complexities and use this knowledge to choose
algorithms that are best suited to the circumstances.
Methodologies
The first step in most formal software development projects is requirements
analysis, followed by testing to determine value modeling, implementation, and
failure elimination (debugging). There exist a lot of differing approaches for
each of those tasks. One approach popular for requirements analysis is Use
Case Analysis.
Popular modeling techniques include Object-Oriented Analysis and
Design (GOAD) and Model-Driven Architecture (MDA). The Unified Modeling
Language (UML) is a notation used for both the GOAD and MDA.
A similar technique used for database design is Entity-Relationship
Modeling (ER Modeling). Implementation techniques include imperative
languages (object-oriented or procedural), functional languages and logic
languages.
Notes
Notes
and
Ndmtv Activity 1
List at least six quality requirements of any software project development.
a&
------
Meets the business and technical requirements that guided its design and
development
Works as expected
Notes
13'
Notes
2.
Verification: Have we built the software right? (i.e., Does it match the
specification?)
Validation: Have we built the right software? (i.e., Is this what the
customer wants?)
The terms verification and validation are commonly used interchangeably.
Notes
2.
3.
4.
377
Notes
5.
6.
Built-in: Mechanisms for installing updates are built into some software
systems.
Automation of these update processes ranges from fully automatic to
user- initiated and controlled. Norton Internet Security is an example of a
system with a semi-automatic method for retrieving and installing updates
to both the antivirus definitions and other components of the system.
Other software products provide query mechanisms for determining
when updates are available.
7.
Version tracking: Version tracking systems help the user find and install
updates to software systems installed on PCs and local networks. Webbased version tracking systems notify the user when updates are available
for software systems installed on a local system. For example, Version
Tracker Pro checks software versions on a user's computer and then
queries its database to see if any updates are available.
Local version tracking system notifies the user when updates are available
for software systems installed on a local system. For example, Software
Catalog stores version and other information for each software package
installed on a local system. One click of a button launches a browser
window to the upgrade web page for the application, including autofilling of the user name and password for sites that require a login.
Browser-based version tracking systems notify the user when updates are
available for software packages installed on a local system. For example,
wfx-Versions is a Firefox extension which helps the user find the current
version number of any program listed on the web.
8.
9.
378
3.
4.
5.
6.
Finally, the last maintenance process, also an event which does not occur
on a daily basis, is the retirement of a piece of software.
Notes
There are a number of processes, activities and practices that are unique
to maintainers. For example:
Transition: A controlled and coordinated sequence of activities during
which a system is transferred progressively from the developer to the maintainer.
Service Level Agreements (SLAs) and specialised (domain-specific)
maintenance contracts negotiated by maintainers.
Modification Request and Problem Report Help Desk: A problemhandling process used by maintainers to prioritise, documents and route the
requests they receive.
Modification Request Acceptance/Rejection: Modification request work
over a certain size/effort/complexity may be rejected by maintainers and
rerouted to a developer.
A common perception of maintenance is that it is merely fixing bugs.
However, studies and surveys over the years have indicated that the majority,
over 80 per cent of the maintenance effort is used for non-corrective actions
(Pigosky 1997). This perception is perpetuated by users submitting problem
reports that in reality are functionality enhancements to the system.
Software maintenance and evolution of systems was first addressed by
Meir M. Lehman in 1969. Over a period of twenty years, his research led to
the formulation of eight laws of evolution (Lehman 1997). Key findings of his
research include that maintenance is really evolutionary developments and that
maintenance decisions are aided by understanding what happens to systems
379
Notes
(and software) over time. Lehman demonstrated that systems continue to evolve
over time. As they evolve, they grow more complex unless some action such as
code refactoring is taken to reduce the complexity.
The key software maintenance issues are both managerial and technical.
Key management issues are: alignment with customer priorities, staffing,
which organisation does maintenance, estimating costs. Key technical issues
are: limited understanding, impact analysis, testing, and maintainability
measurement.
Activity 2
\---v Summary
380
Once the general requirements are gathered from the client, an analysis
of the scope of the development should be determined and clearly stated.
This is often called a scope document.
Notes
)Keywords
381
Notes
Self-Assessment Questions
382
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
Notes
2.
Bug tracking system tools are often deployed to allow development teams
to interface with customer/field teams testing the software to identify any
real or perceived issues.
3.
4.
The purpose of project monitoring and control is to keep the team and
management up to date on the project's progress.
2.
2.
(
114' Suggested Reading
1.
383
384
UNIT
15
385
Notes
Objectives
After going through this unit, you will be able to:
2.
3.
386
Notes
387
As in everyday life, there is little value in having laws if they are not
enforced. With the support of senior management, the governance
process is more likely to receive the required resources to be
effective. While it can be anticipated that some Project Managers
may not embrace the idea of governance, fearing that they are being
unnecessarily policed, the project management purists are likely
to accept governance by recognising it as value rather than as a
constraint.
Notes
38.8
2.
Notes
389
Notes
3.
Notes
391
Notes
activities are all the same in two different cultures, but two different meanings,
two different interpretations.
When a person from one cultural background, meets, interacts with,
understands and deals with a person from other cultural background, it is crosscultural management.
Some people are in favour of the world which is converging, all things are
going to be same. They are right. Some people are arguing still the world has
divergence. They are also right.
We shouldn't fight over this issue. We need to learn how to manage both
the convergence and divergence. That is the key to success.
Let us take an example. In USA, it is performance that counts, based
on which higher assignments and promotions are given. In Indian companies,
performance is not the main criteria. It is "organisational compatibility" that
counts, that is, the employee "fit" in to the organisation that counts. India is
a high-context society. The "fit" into the organisation has to be interpreted in
Indian way.
The business has different interpretation. In USA, doing business means
creating organisation wealth. In India doing business means "Individual
wealth". On recruitment, in USA it is the process of selection, in India it is the
process of rejection and the difference goes on...
Certainly, the differences are innumerable. Increasing an individual's or
an organisation's cultural intelligence is not an easy task.
One of the very important accomplishments of developing project
management as a field is that it is increasingly being informed by Project
Managers across the world. And while we can say that, on a fundamental level,
projects across the world see similar classes of threats and opportunities, we can
agree that the expression of those opportunities and threats are often different,
depending on where you happen to be.
The reason for this difference is not technical; it is cultural. What do we
mean here? Well, for example, some cultures tend to emphasise individual
performance, while others evaluate success based on team performance. Some
cultures invite very direct speech, while others tend to invite a reading between
the lines. Some cultures follow a very formal chain of command in terms of
project communications, while other cultures promote a more horizontal flow
of information. As a Project Manager, our project will work within a particular
cultural environment, and will necessarily thus reflect that.
Cultural influences are, of course, nothing new. Any of us who have
travelled even to a neighbouring country have likely encountered some form of
cultural influence different than their own. However, because project life is so
mobile, there's a good chance that if you venture into the field, you will either
find yourself working in a variety of cultures, or working with people who
reflect an array of multicultural perspectives. Being aware of these different
392
cultural horizons will not only make you a more successful Project Manager,
but much more importantly, it will make you a much better communicator and
listener, which will make our work both satisfying and meaningful.
Notes
Small vs. Large Power Distance: We find that some cultures have a steep
hierarchy where people do not communicate between levels much higher
or lower then themselves. In Slovakia someone would not communicate
directly with a project manager, they would talk to their supervisor and
relay the information up the hierarchy. As for leadership in these cultures
the leader is not questioned and consensus is not a tactic to be used. A
natural inclusive leader would have to become much more of a dictator
in leadership style. In small power distance countries as Denmark lower
down workers freely express question and concerns with much higher
project managers. Leaders are questioned in this culture and so may
have to be ready to defend reasons for doing something better than with
`because I'm the boss and I say so' which would be expected out of a
leader in the large power distance cultures.
393
Notes
2.
3.
4.
5.
6.
Notes
8.
But clinging to this perception of the other side can lead to a self-fulfilling
prophecy. In other words, just thinking this way can make it seem that attempting
to engage the other side in creating a better relationship is futile and a waste of
time. So the attempt is not made and this leads to an increase in tension between
both sides.
For starters, it might be appropriate to accept the other side's preference
for maintaining an arms-length relationship. At the same time, however, it might
be appropriate to take small but concrete steps to improve the relationship. To
do this requires attention to language, culture and trust building. These steps
might begin by asking the other side questions that uncover common interests
or it might begin by actively listening to the other side and then asking for
clarification. They will not always work, but when they do succeed the payoff
can well worth the effort.
As we can see from these examples cross-cultural issues have a large
importance in project management. Different cultures must be taken into
account throughout the life of the project to avoid everything from added stress
to outright failure. The best way to deal with anything is to gather as much
information as possible. There are many online sources that give overviews of
working in specific cultures. Take these differences into SERIOUS account as
they are not to be underestimated!
Issues in Project Management
395
Notes
v iv
Att;
Activity 1
Select any two countries and list at least five cross-cultural differences
between them.
' 1396 7
Notes
Is this realistic? Yes. It happens over and over again. Both sides sit down
at the table with instructions from top management not to give in. No one at
the bargaining table has the authority to bargain! As a result, the negotiation
degenerates into a competitive debate where one party tries to persuade the
other. They get nowhere and unless one side capitulates, the dispute is referred
to as arbitration.
There is, of course, a major downside to arbitration. It can be a costly
process, it can take time, and above all it can erode the relationship and trust
between parties. Furthermore, arbitration is risky because one party may end up
with much less than what could have been achieved had a negotiated settlement
been reached.
So, what can be done in these situations? EvFry effort must be made to
ensure that the decision-makers for both sides sit at the negotiation table. If this
is not possible, then every effort must be made to bring the decision-makers
into a later negotiating session, even for a short period of time. If this is still
not possible, then it might be possible to hold informal or special meetings with
the decision maker present. None of these may work, but they are worth a try.
Without a decision-maker, negotiators have one hand tied behind their back!
When a project conflict occurs between two parties, separated by distance
and culture, resolving that conflict is a challenge that can often end up in
arbitration or the courts. Following are the reasons why this breakdown occurs.
1.
397
Notes
2.
3.
But situations like this are often characterised as win-lose negotiations and
are certainly not preferred, especially when they have the potential to damage
the working relationship between both parties and especially if the potential for
follow-on business between them is jeopardized.
A much better strategy is to shift the focus from an adversarial mode in
which positions are argued to a cooperative mode that explores the interests of
both sides. Consider this example. A client insists that only those vendors on
the original approved vendor list can be used to provide products and services.
The contractor, however, insists that they should have the option of using other
vendors. The argument over approved or non-approved vendors can go on and
on, but the real interests of both parties are to successfully complete the project,
on time and on budget. Shifting the discussion to common interests has a better
chance of expanding the vendor list than an argument in which both sides
simply argue positions.
Note's
11,
AGWAY
Activity 2
Enlist the reasons for a project conflict between two parties, separated by
distance and culture.
When the negotiations are at an impasse and relationships are tense, the
status quo may have to be challenged. The goal is to improve working
relationships.
Yet every one of these steps is difficult to take. The fear is that the side
taking these steps will be seen as abandoning their own position and capitulating
to the other side. By opening the negotiation process some would see it as
`giving in'. But to the contrary, it is actually a deliberate move in the interest
of reaching a mutually acceptable solution to the problem. In international
projects, where the project is managed by a company in one country for a client
in another, contracts serve at least three purposes as:
Marketing Tool
Blueprint
Legal Document
399
used when conflicts or disputes occur. Each purpose is different and that is
where the problem begins.
.1
Notes
401
Notes
3.
Evidence
402
Naturally multi-user
Project information not available when the user (or server) is offline
Some solutions allow the user to go offline with a copy of the data
4.
5.
6.
Notes
403
Notes
7.
404
Focuses primarily on the planning phase and does not offer enough
functionality for project tracking, control and in particular plan adjustment.
There may be excessive dependency on the first paper printout of a project
plan, which is simply a snapshot at one moment in time. The plan is
dynamic as the project progresses the plan must change to accommodate
tasks that are completed early, late, re-sequenced, etc. Good management
software should not only facilitate this, but assist with impact assessment
and communication of plan changes.
Does not make a clear distinction between the planning phase and
post-planning phase, leading to user confusion and frustration when
the software does not behave as expected. For example, shortening the
duration of a task when an additional human resource is assigned to it
while the project is still being planned.
Some people may achieve better results using simpler technique, (e.g., pen
and paper), yet feel pressured into using project management software by
company policy (discussion).
When there are multiple larger projects, project management software can
be very useful. Nevertheless, one should probably not use management
software if only a single small project is involved, as management
software incurs a larger time-overhead than is worthwhile.
Notes
activity Activity 4
List at least six activities that should be taken care of by any project
management software.
15.7 PROJECT PORTFOLIO MANAGEMENT
Project Portfolio Management (PPM) is a term used by project managers
and Project Management (PM) organisations to describe methods for analysing
and collectively managing a group of current or proposed projects based on
numerous key characteristics. The fundamental objective of the PPM process is
to determine the optimal mix and sequencing of proposed projects to best achieve
the organisation's overall goals typically expressed in terms of hard economic
measures, business strategy goals, or technical strategy goals while honoring
constraints imposed by management or external real world factors. Typical
attributes of projects being analysed in a PPM process include each project's
total expected cost, consumption of scarce resources (human or otherwise)
expected timeline and schedule of investment, expected nature, magnitude and
timing of benefits to be realised, and relationship or inter-dependencies with
other projects in the portfolio.
The key challenge for implementing an effective PPM process is typically
securing the mandate to do so. Many organisations are culturally inured to an
informal method of making project investment decisions, which can be compared
to political processes observable in the US legislature. However this approach to
make project investment decisions has led many organisations to unsatisfactory
results, and created demand for a more methodical and transparent decisionmaking process. That demand has in turn created a commercial marketplace for
tools and systems which facilitate such a process.
Issues in Project Management
405
Notes
406
Notes
407
Notes
of the specifications, as you will be the one to make sure the work fulfills your
obligation to your client. Ask for a price that allows you to make a profit without
driving the price too high or beyond what the market will bear for your client.
This is often referred to as a preferred customer rate or wholesale rate.
Managing Subcontractors
The following is a list of suggestions for managing subcontractors. These
depend on your relationship with your subcontractor, and many are understood
amongst experienced contractors.
Never let the subcontractor deal directly with your client without your
approval. These protocols should be specified in your subcontractor
agreement.
Payment Terms
Terms of payment should always be agreed upon prior to any project
work. Smaller projects may only require an invoice from the subcontractor
larger projects may warrant full agreements with task completion and payment
schedules. Whatever method you deem appropriate, the most important item is
that a consensus on the agreement exist prior to starting any work. There should
be no question of intent or any other potential misunderstandings. Typical
models for payment terms with subcontractors are shown here.
A great deal of value can be gained in trading services with subcontractors
on projects, loyalty and trust among the most valuable. Trading services and
products usually applies to smaller tasks or portions of a project that would
not justify the work to establish a formal agreement, and are often collected
as payback for a favor from other projects. When proposing projects that rely
on this form of subcontracting, always have a backup plan, and if possible,
get a commitment for the trade. Never rely on large portions of a project to be
completed in trade with a subcontractor. It is better to exchange the money and
avoid any issues with the IRS or worse yet, potentially ruining a relationship
with a long-time associate due to informal agreements run amok.
408
Notes
with subcontractors on
Activity 5
List at least eight criteria that you would look at while selecting a subcontractor.
Summary
For any project to be successful, we can follow the past practices which
have resulted in successful completion of projects. The skills sets for this
are Organisational Practices, Team Practices and Individual Practices.
The areas in which differing cultures will play a large part in project
management are small vs. large power distance, uncertainty avoidance,
long vs. short-term orientation, individualism vs. collectivism, language;
culture, trust etc.
409
Notes
It is not enough just to identify these challenges. Some of the steps that can
be taken to address these are: assigning the role of process monitor, to ask
the other side for clarification at several points in the discussion, to bring
an additional person into the session, one with fluent language skills, to
request that the decision-maker is present at the time of discussion, look
towards to improve working relationships.
7 4Keywords
410
nr Self-Assessment Questions
1.
Explain the best practices that can be used in projects for ensuring success.
2.
3.
4.
5.
6.
7.
8.
9.
Notes
False
2.
True
411
Notes
2.
Suggested Reading
1.
'41)2