Power Plant Gannt Chart

This document outlines a project plan for an 8 MW Dendro Power Project over 376 days from October 2016 to October 2017. It includes 32 tasks related to project development, financing, procurement, construction, installation, commissioning, and grid connection.

Uploaded by

Ruwan Wijemanne
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
38 views1 page

Power Plant Gannt Chart

This document outlines a project plan for an 8 MW Dendro Power Project over 376 days from October 2016 to October 2017. It includes 32 tasks related to project development, financing, procurement, construction, installation, commissioning, and grid connection.

Uploaded by

Ruwan Wijemanne
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

ID

Task Name

Duration

Start

Finish

Predecessors
Notes
Sep

1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32

8 MW Dendro Power Project Development


Project Progress Report Submission
Approval Phase
Approvals from SLSEA
PPA Extension From CEB
Generation Licence Extension from PUCSL
Project Financing
Bankable Feasibility report
Loan Appraisal
Loan Approval
Procurement
Finalysing detailed design and suppliers
Plant Machineries
Building Materfials
Fuel Supply Contracts
Civil Construction
Land preparation
Access roads
Plant house
Fuel wood storage
Machine Installation
Boiler and accessories
Turbine and Alternator
Other accessories
Electrical Evacuation
Inplant electrical works
Power line to SGS
Commissioning
Civil Structure
Machine Commissioning
Eelctrical Commissioning
Grid Connection

Project: MSProj11
Date: Oct 14

376 days
1 day
31 days
13 days
13 days
5 days
60 days
30 days
15 days
15 days
60 days
14 days
45 days
45 days
60 days
120 days
60 days
30 days
30 days
30 days
90 days
14 days
30 days
60 days
135 days
60 days
75 days
60 days
30 days
30 days
30 days
30 days

Oct 16
Oct 16
Oct 17
Oct 17
Oct 30
Nov 12
Oct 17
Oct 17
Nov 16
Dec 1
Dec 16
Dec 16
Dec 30
Dec 30
Dec 16
Dec 16
Dec 16
Feb 14
Mar 15
Dec 16
Apr 14
Apr 14
Apr 14
May 14
Apr 14
Apr 14
Jun 13
Aug 27
Aug 27
Aug 27
Aug 27
Sep 26

Oct 25
Oct 16
Nov 16
Oct 29 2
Nov 11 4
Nov 16 5
Dec 15
Nov 15 2
Nov 30 8
Dec 15 9
Feb 13 7
Dec 29 7
Feb 12 12
Feb 12 12
Feb 13 7
Apr 13
Feb 13 10
Mar 14 17
Apr 13 18
Jan 14 10
Jul 12
Apr 27 16
May 13 16
Jul 12 23
Aug 26
Jun 12 16
Aug 26 26
Oct 25
Sep 25 25
Sep 25 25
Sep 25 25
Oct 25 31

Qtr 4, 2015
Nov

Oct

Dec

Jan

Qtr 1, 2016
Feb

Mar

Apr

Qtr 2, 2016
May

Jun

Jul

Qtr 3, 2016
Aug

Sep

Oct

Qtr 4, 2016
Nov

10/16

10/25

Task

Progress

Summary

External Tasks

Split

Milestone

Project Summary

External Milestone