Time Management Plan PDF
Time Management Plan PDF
Site Establishment:
Temporary fencing
Temporary site office
Temporary lunch room
Ablution block
Electricity connection on site
Earthworks:
Top soil excavation and site clearance
Surveyor set out
Bored piles
Capping beams and safety rails installation
Excavation to basement level
Basement works:
Blinding
Rio + mesh
Engineer inspection of Rio + Mesh
Concrete slab pouring
Rio and formwork for columns
Concrete pouring in columns
Precast concrete walls for water tank room
Preparation for services (Rough)
Ground level works:
Condeck permanent formwork
Rio bars / shear studs / starter bars
Engineer inspection of bars
Concrete slab pouring
Rio and formwork for columns
Concrete pouring in columns
External pre cast concrete walls
Installation of doors and facades
Preparation for services (Rough)
Roof Structure:
Installation of steel trusses
Lattice girders
Purlins
Steel netting and roof insulation
Kliplok roof sheeting and flashing
Final installation for services: (fit-off)
Plumbing
Electrical
HVAC systems
Final fit out:
Internal plasterboard walls
Doors and windows internal installation
Shop fittings
Quality control
Days
Weeks
1
1
1
1
3
14
7
21
14
14
7
11
3
14
7
3
2
1
14
11
3
7
7
7
7
5
2
7
7
7
7
7
12
12
11
14
7
28
14
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51
52