Wbs Epc ProjectCCVBB

This document outlines a work breakdown structure (WBS) for the XYZ Project. It breaks the project down into levels from 0 to 3, with level 0 being the overall project, level 1 dividing it into phases (A-F), level 2 into disciplines/packages within each phase (A1-F3), and level 3 further dividing the level 2 items. The WBS provides a framework for tracking project costs and progress by assigning percentages to each level 2 and 3 item.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
415 views

Wbs Epc ProjectCCVBB

This document outlines a work breakdown structure (WBS) for the XYZ Project. It breaks the project down into levels from 0 to 3, with level 0 being the overall project, level 1 dividing it into phases (A-F), level 2 into disciplines/packages within each phase (A1-F3), and level 3 further dividing the level 2 items. The WBS provides a framework for tracking project costs and progress by assigning percentages to each level 2 and 3 item.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

XYZ Project

A%

B%

Project Management

Offsite Fabrication &


Transport

System / Area /
Package

Engineering (A.1.1%)

Acid Gas Removal (B.1.1%)

Bulks (C.1.1%)

PAU 1 (D.1.1%)

Area 1 (E.1.1%)

System 1 (F.1.1%)

HSE (A.1.2%)

TEG Dehydration (B.1.2%)

Equip. (Ex.PAU Scope) (C.1.2%)

PAU 2 (D.1.2%)

Area 2 (E.1.2%)

System 2 (F.1.2%)

Const. Coord. (A.1.3%)

Incineration (B.1.3%)

Speciality Item (C.1.3%)

PAU 3 (D.1.3%)

Area 3 (E.1.3%)

System 3 (F.1.3%)

PAU 4 (D.1.4%)

Area 4 (E.1.4%)

System 4 (F.1.4%)

Utility Systems (B.1.5%)

PAU 5 (D.1.5%)

Area 5 (E.1.5%)

System 5 (F.1.5%)

Seawater Pipelines (B.1.6%)

PAU 6 (D.1.6%)

Area 6 (E.1.6%)

Flare Package (B.1.7%)

PAU 7 (D.1.7%)

Flue Gas Treatment (B.1.4%)

F.1%

SVT Area /
Sub Package

Commissioning/ Start
up

E.1%

Pre-Assembled Units
(PAU's) Fab

F%

Installation /
Construction

D.1%

Procurement

C.1%

B.1%

Engineering
Packages

E%

D%

Procure/
Subcontract Award

Engineering

A.1%

Project Engineering

C%

System 6 (F.1.6%)
System 7 (F.1.7%)

Priority 1 (D.2.1%)

PAU Installation (C.2.2%)

Priority 2 (D.2.2%)

Constr. Contracts (C.2.3%)

Priority 3 (D.2.3%)

Document Control (A.2.3%)


Planning/Scheduling (A.2.4%)

Mechanical
Completion

Priority 4 (D.2.4%)

A.3%

Others

XYZ Project

PAU Fabrication (C.2.1%)

As Built Engg/Support (B.2.2%)

E.3%

Construction Support (B.2.1%)

Business Services (A.2.2%)

Inter-connects/
Interface

E.2%

Cost Control (A.2.1%)

D.2%

Subcontract Award

C.2%

Engineering Office
Support

B.2%

A.2%

Project Services

EPC Stage

System 8 (F.1.8%)
Transport/
Delivery

Legal & Admin

MC (E.3.1%)

Finance & Accounts

Area 2 (E.3.2%)

Revision Status

XYZ Project
Rev

Work breakdown Structure


WBS Structure

Level 0
(Project)

Level 1
(Phase)

Level 2
(Discipline)

Level 3
(Packages/PAU /Area/System)

Level 4 (Not included in this chart) :


Deliverables by Discipline/PAU/
Area/System

Prep. By

App. By

Date