Chapter 9 - Allocating Resource To The Project Problems Problem 1
Chapter 9 - Allocating Resource To The Project Problems Problem 1
Problems
Problem 1:
a)
b)
c)
Figure 1
Problem 2:
Activit
y
Crash Days
Crash $
$200.00
200.00
$ 75.00
37.50
$150.00
50.00
$100.00
50.00
Crash $/Day
Figure 2
Problem 3:
Figure 9.3a converts the AOA
diagram into an AON
diagram.
Figure 9.3a answers
questions for problem 3a.
Activity
Figure 9.3a
Crash Days
Normal $
Crash $
Crash $/Day
500.00
$300.00
100.00
200.00
$150.00
150.00
500.00
$400.00
200.00
200.00
$300.00
150.00
300.00
250.00
$250.00
the
Activity
Crash Days
Normal $
Normal $
$ 1,700.00
Crash $
Crash $/Day
Net Cost $
Option 1
A=1, E = 1
$350.00
$ 2,050.00
Option 2
A=2, D=1
$350.00
$ 2,050.00