ATTS

The engineering for the PEB building is complete. The foundation bolts for the PEB building are being transported to the site and inspection of SF6 to air bushing has been finished. Inspections of CTs and surge arrestors will take place next week in Korea and Germany. The overall general arrangement of the GIS building has been finalized.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
38 views

ATTS

The engineering for the PEB building is complete. The foundation bolts for the PEB building are being transported to the site and inspection of SF6 to air bushing has been finished. Inspections of CTs and surge arrestors will take place next week in Korea and Germany. The overall general arrangement of the GIS building has been finalized.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 1

Status of

PEB Building engineering Completed.

Drawing & Design Tower Foundation & Control room Building


Foundation Bolts of PEB Building under transportation to site.
Inspection of SF6 to Air Bushing has been completed.
Inspections of CTs & Surge Arrestor are going to be held in next week in
Korea & Germany.
OGA of GIS Building has been finalised.