PPAP Manual
PPAP Manual
APPROVAL PROCESS
(PPAP)
Use of auditable language and a format consistent with QS-9000 to support third party auditing;
A reordering of the PPAP requirements aligned with the typical process flow;
Revision of Preliminary Process Capability Requirements, now called Initial Process Studies, to
provide for the use of either Cpk or Ppk, depending on the amount and type of data available, consistent
with our Statistical Process Control reference manual;
The actual changes of the previous PPAP text are minimal, and evolutionary. While the additions have
increased the size of the document, they provide greater clarification of PPAP requirements and allow
application of PPAP requirements to a broader community of users.
Current training modules sanctioned by DaimlerChrysler, Ford and General Motors have been revised to
incorporate these changes.
Acknowledgments are due to the DaimlerChrysler, Ford and GM Supplier Quality Requirements Task Force
(Hank Gryn, Dan Reid and Steve Walsh), Michael Schons from DaimlerChrysler, Carol Myers and Rudy
Pomper from General Motors, Paul Norkevicius from Ford, Patricia Messenger from the Chemical
Manufacturers Association, Joseph Muscedere from the AIAG Truck and Heavy Equipment Group, and
Steve Butcher from the Rubber Manufacturers Association.
The PPAP Third Edition obsoletes the Second Edition effective February 1, 2000 unless otherwise specified
by your customer.
September, 1999
ii
February, 1995
iii
iv
February, 1993
TABLE OF CONTENTS
Introduction................................................................................................................................... 1
Section I
I.1 General ................................................................................................................................................................... 2
I.2 PPAP Process Requirements ................................................................................................................................. 2
I.2.1
Significant Production Run ..................................................................................................................... 2
I.2.2
PPAP Requirements ................................................................................................................................. 2
I.2.2.1
Design Records ............................................................................................................................ 3
I.2.2.2
Engineering Change Documents ................................................................................................. 3
I.2.2.3
Engineering Approval .................................................................................................................. 3
I.2.2.4
Design Failure Mode and Effects Analysis (Design FMEA) ........................................................ 4
I.2.2.5
Process Flow Diagrams ............................................................................................................... 4
I.2.2.6
Process Failure Mode And Effects Analysis (Process FMEA) ..................................................... 4
I.2.2.7
Dimensional Results .................................................................................................................... 4
I.2.2.8
Records of Material/Performance Test Results ............................................................................ 5
I.2.2.8.1 Material Test Records .......................................................................................................... 5
I.2.2.8.2 Performance Test Records ................................................................................................... 5
I.2.2.9
Initial Process Studies .................................................................................................................. 6
I.2.2.9.1 General ................................................................................................................................ 6
I.2.2.9.2 Quality Indices ..................................................................................................................... 6
I.2.2.9.3 Acceptance Criteria ............................................................................................................. 7
I.2.2.9.4 Unstable Processes .............................................................................................................. 7
I.2.2.9.5 Processes With One-Sided Specifications or Non-Normal Distributions ........................... 7
I.2.2.9.6 Strategy When Acceptance Criteria Are Not Satisfied ........................................................ 8
I.2.2.10
Measurement System Analysis Studies ......................................................................................... 8
I.2.2.11
Qualified Laboratory Documentation .......................................................................................... 8
I.2.2.12
Control Plan ................................................................................................................................. 8
I.2.2.13
Part Submission Warrant (PSW) .................................................................................................. 9
I.2.2.13.1 Part Weight (Mass) .............................................................................................................. 9
I.2.2.14
Appearance Approval Report ....................................................................................................... 9
I.2.2.15
Bulk Material Requirements Checklist ....................................................................................... 10
I.2.2.16
Sample Production Parts ............................................................................................................ 10
I.2.2.17
Master Sample ........................................................................................................................... 10
I.2.2.18
Checking Aids ............................................................................................................................. 10
I.2.2.19
Customer-Specific Requirements ............................................................................................... 10
I.3 Customer Notification and Submission Requirements ...................................................................................... 11
I.3.1
Customer Notification ........................................................................................................................... 11
I.3.2
Submission to Customer ........................................................................................................................ 12
I.3.3
Situations Where Customer Notification Is Not Required .................................................................... 13
I.4 Submission To Customer - Levels Of Evidence .................................................................................................. 15
I.4.1
Submission Levels ................................................................................................................................ 15
I.5 Part Submission Status ........................................................................................................................................ 17
I.5.1
General ................................................................................................................................................... 17
I.5.2
Customer PPAP Status ........................................................................................................................... 17
I.5.2.1
Full Approval ............................................................................................................................. 17
I.5.2.2
Interim Approval ........................................................................................................................ 17
I.5.2.3
Rejected ..................................................................................................................................... 17
vi
Section II
II.1 DaimlerChrysler Corporation-Specific Instructions ......................................................................................... 19
II.2 Ford-Specific Instructions ................................................................................................................................... 24
II.3 General Motors-Specific Instructions ................................................................................................................ 34
II.4 Truck OEM-Specific Instructions ....................................................................................................................... 46
Appendices
Appendix A: Completion of the Part Submission Warrant ....................................................................................... 52
Part Submission Warrant ..................................................................................................................... 53
- Indexed Form ................................................................................................................................ 53
- Blank Form ................................................................................................................................... 54
Appendix B: Completion of the Appearance Approval Report ................................................................................. 56
Appearance Approval Report .............................................................................................................. 57
- Indexed Form ................................................................................................................................ 57
- Blank Form ................................................................................................................................... 58
Appendix C: Dimensional Report ............................................................................................................................. 61
Appendix D: Material Test Report ............................................................................................................................ 63
Appendix E: Performance Test Report ..................................................................................................................... 65
Appendix F: Bulk Material - Specific Requirements ............................................................................................... 67
Appendix G: Tire Industry - Specific Requirements ................................................................................................ 85
Glossary ....................................................................................................................................................................... 87
vii
viii
Introduction
INTRODUCTION
PURPOSE
Production Part Approval Process (PPAP) defines generic requirements for production part approval, including
production and bulk materials (See Glossary). The purpose of PPAP is to determine if all customer engineering
design record and specification requirements are properly understood by the supplier and that the process has the
potential to produce product consistently meeting these requirements during an actual production run at the
quoted production rate.
APPLICABILITY
PPAP shall apply to internal and external supplier sites (See Glossary) of bulk materials, production materials,
production or service parts. For bulk materials, PPAP is not required unless requested by your customer.
A supplier of standard catalogue production or service parts shall comply with PPAP unless formally waived by
the customer. Tooling shall be maintained for standard catalogue items as long as the items are offered or stated
as being available.
NOTE 1: See the customer-specific instructions in Section II for additional information. All questions
about PPAP should be addressed to the customer product approval activity (See Glossary).
NOTE 2: A customer can formally waive PPAP requirements for a supplier. Waivers for applicable items
will be documented by the customer.
APPROACH
The word shall indicates mandatory requirements. The word should indicates a mandatory requirement with
some flexibility allowed in compliance methodology.
Paragraphs marked NOTE are for guidance in understanding or clarifying the associated requirement. The
word should appearing in a NOTE is for guidance only.
The Glossary contains information that should be used for purposes of compliance to PPAP requirements.
SECTION I
I. 1
GENERAL
The supplier shall obtain full approval (See I.5.2.1) from the customer product approval activity for:
1. a new part or product (i.e., a specific part, material, or color not previously supplied to the specific customer).
2. correction of a discrepancy on a previously submitted part.
3. product modified by an engineering change to design records, specifications, or materials.
4. any situations required by Section I.3.
NOTE: If there is any question concerning the need for production part approval, contact the responsible customer
product approval activity.
I.2
I.2.1
For production parts, product for PPAP shall be taken from a significant production run. This production run shall be
from one hour to eight hours of production, and with the specific production quantity to total a minimum of 300
consecutive parts, unless otherwise specified by the authorized customer quality representative.
This run shall be manufactured at the production site using the tooling, gaging, process, materials, and operators from
the production environment. Parts from each unique production process, e.g. duplicate assembly line and/or work cell,
each position of a multiple cavity die, mold, tool or pattern, shall be measured and representative parts tested.
For bulk materials: No specific number of parts is required. If a sample is required to be submitted, it shall be taken
in a manner as to assure that it represents steady-state operation of the process.
NOTE: For bulk material, production histories of current products may often be used to estimate the initial
process capability or performance of new and similar products. In cases where no production history of a similar
bulk material product or technology exists, a containment plan may be put into effect until sufficient production
has demonstrated capability or performance.
I.2.2
PPAP Requirements
The supplier shall meet all specified requirements, e.g. design record, specifications, and for bulk material, the Bulk
Material Requirements Checklist (see I.2.2.15 and Appendix F). Any results that are outside specification are cause for
the supplier not to submit the parts, documentation and/or records. Every effort shall be made to correct the process so
that all design record requirements are met. If the supplier is unable to meet any of these requirements, the customer
shall be contacted for determination of appropriate corrective action.
Section I
Inspection and testing for PPAP shall be performed by a qualified laboratory (See QS-9000, Third Edition, cl. 4.10.6).
Commercial/independent test laboratories used shall be accredited facilities (see QS-9000, Third Edition, cl. 4.10.7,
and 4.11.2.b.1). When a commercial laboratory is used, the supplier shall submit the test results on the laboratory
letterhead, or the normal laboratory report format. The name of the laboratory that performed the tests, and the date (s)
of the tests, and the standards used to run the tests shall be indicated. Blanket statements of conformance are
unacceptable for any test results.
The supplier shall have the applicable items and records (See QS-9000, Third Edition, cl. 4.16), listed below, for each
part, or family of parts, regardless of the part submission level. These records (I.2.2.1 15 and 19 if any) shall be in a
PPAP part file, or referenced in such file and be readily available. The items below (I.2.2.16 - 18) shall be readily
available for customer use in PPAP.
The supplier shall obtain prior approval (see QS-9000, Third Edition, cl. 4.16) from the customer product approval
activity for exceptions or deviations to PPAP requirements.
NOTE 1: The supplier may, upon special arrangement, have tests performed by the customers laboratories.
NOTE 2: All I.2.2 items or records may not necessarily apply to every customer part number from every
supplier. For example, some parts do not have appearance requirements, and others do not have color
requirements. In order to determine with certainty which items must be included, consult the design record,
e.g. part print, the relevant Engineering documents or specifications, and your customer responsible part
approval activity.
I.2.2.4 Design Failure Mode and Effects Analysis (Design FMEA), if the supplier is design responsible. See
Potential Failure Mode and Effects Analysis reference manual.
The supplier shall have a Design FMEA developed in accordance with, and compliant to, QS-9000 Third Edition
requirements for parts or materials for which they are design-responsible. For bulk materials, a Design Matrix (See
Appendix F), when required by the Bulk Material Requirements Checklist (see I.2.2.15), shall be prepared prior to
developing the Design FMEA.
NOTE: For bulk materials, Design FMEA rankings (Severity, Occurrence, Detection) as discussed in Appendix
F, may be utilized to provide proper differentiation of risk factors.
I.2.2.6
Process Failure Mode and Effects Analysis (Process FMEA). See Potential Failure Mode and Effects
Analysis reference manual.
The supplier shall have a Process FMEA developed in accordance with, and compliant with QS-9000 Third Edition
requirements.
NOTE: A single Design or Process FMEA may be applied to a process manufacturing a family of similar parts
or materials. For bulk materials, see Appendix F for a severity, occurrence, and detection ranking system to
provide proper differentiation of risk factors.
Section I
NOTE 1: All dimensions (except reference dimensions), characteristics, and specifications as noted on the
design record and Control Plan should be listed in a convenient format with the actual results recorded. The
Dimensional Results form in Appendix C, or a checked print where the results are legibly written on a part
drawing including cross-sections, tracings, or sketches as applicable may be utilized for this purpose.
NOTE 2: Dimensional results typically do not apply to bulk materials.
General
The level of initial process capability or performance shall be determined to be acceptable prior to submission for
all Special Characteristics designated by the customer or supplier.
The supplier shall perform measurement system analysis to understand how measurement error is affecting the
study measurements. (See I.2.2.10 and Measurement Systems Analysis reference manual )
NOTE 1: The purpose of this requirement is to determine if the production process is likely to produce
product that will meet the customers requirements. The initial process study is focused on variables not
attributes data. Assembly errors, test failures, surface defects are examples of count time data, which is
important to understand, but is not covered in this initial study. To understand the performance of
characteristics monitored by attribute data will require more data collected over time.
NOTE 2: The index for estimating process capability or performance will be agreed upon by the customer
and supplier. Cpk and Ppk are described below. Other methods more appropriate for certain processes or
products may be substituted with prior customer approval.
NOTE 3: Initial process studies are short-term and will not predict the effects of time and variation in
people, materials, methods, equipment, measurement systems, and environment. Even for these short-term
studies, it is important to collect and analyze the data in the order produced using control charts.
NOTE 4: For those characteristics that can be studied using X-bar and R charts, a short term study should
be based on a minimum of 25 subgroups containing at least 100 readings from consecutive parts of the
significant production run (See I.2.1). The initial data requirements may be replaced by longer-term results
from the same or similar processes, with customer concurrence. For certain processes, alternative analytical
tools such as individual and moving range charts may be appropriate and permitted with prior customer
approval.
Section I
chronically unstable processes with output meeting specifications and a predictable pattern, Ppk should be
used. When not enough data is available ( <100 samples) contact the customer responsible part approval
activity to develop a suitable plan.
Refer to the Statistical Process Control reference manual for information on evaluating stability and a
detailed description of Ppk and Cpk.
NOTE 2: For bulk material, the supplier should obtain customer agreement regarding the appropriate
techniques for initial process studies, if required, in order to determine an effective estimate of capability.
Interpretation
I.2.2.9.4
Unstable Processes
Depending on the nature of the instability, an unstable process may not meet customer requirements. The supplier
shall identify, evaluate and, wherever possible, eliminate special causes of variation prior to PPAP submission.
The supplier shall notify the customer of any unstable processes that exist and shall submit a corrective action
plan to the customer prior to any submission.
NOTE: For bulk materials, if historical data shows that similar processes are chronically unstable, and
previous actions have been unable to achieve stability, corrective action plans may not be warranted.
NOTE 2: For bulk materials, non-normal distributions are generally found after routine plotting of
histograms of process data. Quality indices should not be computed because the values obtained may be
misleading.
I.2.2.12 Control Plan (See Advance Product Quality Planning and Control Plan reference manual and QS-9000,
Third Edition, cl. 4.2.3.7)
The supplier shall have a Control Plan that defines all controls used for process control and complies with QS-9000
(See QS-9000, Third Edition cl. 4.9).
NOTE 1: Control Plans for families of similar parts are acceptable if the new parts have been reviewed for
commonality.
NOTE 2: Certain customers require Control Plan approval, e.g. customer signature on the Control Plan, prior to
submission. See QS-9000, Third Edition, Section II, Customer-specific appendices.
Section I
I.2.2.15 Bulk Material Requirements Checklist (applies only to bulk material PPAP)
For bulk material, the Bulk Material Requirements Checklist (see Glossary) shall be jointly agreed upon by the customer
and supplier. All specified requirements shall be completed unless specifically indicated as Not Required (NR) on
the checklist.
NOTE: Additional requirements may be specified on the checklist.
Section I
I.3
I.3.1
Customer Notification
The supplier shall notify the responsible customer product approval activity of any design and process changes as
indicated in the table below. The customer may subsequently elect to require a submission for PPAP approval. (see
Table I.3.1)
Table I.3.1
Requirement
Clarification or examples
11
Requirement
Clarification or examples
I.3.2
Submission to Customer
The supplier shall submit for PPAP approval prior to the first production shipment in the following situations unless the
responsible product approval activity has waived this requirement (see Table I.3.2).
The supplier shall review and update, as necessary, all applicable items in the PPAP file to reflect the production
process, regardless of whether or not the customer requests a formal submission. The PPAP file shall contain the name
of the responsible customer product approval activity person granting the waiver and the date.
12
Section I
Table I.3.2
Requirement
Clarification or examples
I.3.3
Customer notification and submission (e.g. PSW) is not required for the situations described in the below table. The
supplier is responsible to track the changes and/or improvements and update any affected PPAP documentation. The
following examples are of manufacturing and quality systems situations and/or improvements.
NOTE: Customer notification is required any time customer product requirements for fit, form, function, durability
and performance are affected.
13
Table I.3.3
Requirement
Clarification or examples
14
Section I
I.4
Warrant only (and for designated appearance items, an Appearance Approval Report) submitted to the
customer.
Level 2 -
Warrant with product samples and limited supporting data submitted to the customer.
Level 3 -
Warrant with product samples and complete supporting data submitted to the
customer.
Level 4 -
Level 5 -
Warrant with product samples and complete supporting data available for review at the suppliers
manufacturing location.
See Retention/Submission Requirements Table I.4.1 for exact requirements for each level.
The supplier shall use level 3 as the default level for all submissions unless specified otherwise by the responsible
customer product approval activity. A supplier of bulk material only shall use level 1 as the default level for all bulk
material PPAP submissions unless specified otherwise by the responsible customer product approval activity.
NOTE 1: The customer will identify the submission level that will be used with each supplier, or supplier and
customer part number combination. Different customer locations may assign different submission levels to the
same supplier manufacturing location.
NOTE 2: All of the forms referenced in this document may be replaced by computer-generated facsimiles.
Acceptability of these facsimiles is to be confirmed with the responsible part approval activity prior to the first
submission. The Automotive Industry Action Group (AIAG) offers for sale a diskette with the PPAP/APQP/
FMEA forms.
15
Level 1
Level 2
Level 3
Level 4
Level 5
2.
3.
4.
5.
6.
Process FMEA
7.
Dimensional Results
8.
Material, Performance
Test Results
9.
10.
11.
12.
Control Plan
13.
14.
1.
15.
16.
Sample Product
17.
18.
Checking Aids
19.
Records of Compliance
With Customer-Specific Requirements
S = The supplier shall submit to designated customer product approval activity and retain a copy of records or documentation items at
appropriate locations, including manufacturing.
R = The supplier shall retain at appropriate locations, including manufacturing, and make readily available to the customer representative
upon request.
*
= The supplier shall retain at appropriate locations, and submit to customer upon request.
16
Section I
I.5
I.5.1
General
The supplier shall be notified by the customer of the disposition of the submission. After production part approval,
suppliers shall assure that future production continues to meet all customer requirements.
NOTE: For those suppliers that have been classified as self certifying by a specific customer, submission of
the required documentation showing supplier approval will be considered as customer approval unless the supplier
is advised otherwise.
I.5.2
I.5.2.1 Full Approval indicates that the part or material meets all customer specifications and requirements. The
supplier is therefore authorized to ship production quantities of the product subject to releases from the customer
scheduling activity.
I.5.2.2 Interim Approval permits shipment of material for production requirements on a limited time or piece quantity
basis. Interim Approval will only be granted when the supplier has:
- clearly defined the root cause of the non-conformities preventing production approval; and,
- prepared an interim approval action plan agreed upon by the customer. Re-submission to obtain full
approval is required.
Material covered by an interim approval that fails to meet the agreed-upon action plan either by the expiration date or
the shipment of the authorized quantity will be rejected. No additional shipments are authorized unless an extension of
the interim approval is granted.
For bulk materials, the supplier shall use the Bulk Material Interim Approval form, or its equivalent (See Appendix
F).
I.5.2.3 Rejected means that the submission, the production lot from which it was taken, and accompanying
documentation do not meet customer requirements. Corrected product and documentation shall be submitted and
approved before production quantities may be shipped.
I.6
RECORD RETENTION
Production part approval records (see I.2.2), regardless of submission level, shall be maintained for the length of time
that the part is active (See Glossary) plus one calendar year.
The supplier shall ensure that the appropriate PPAP records from a superseded part PPAP file are included, or referenced
in the new part PPAP file.
NOTE: An example of an appropriate document/record that should be carried forward from the old file to the
new part file would be a material certification from a raw material supplier for a new part that represents only a
dimensional change from the old part number. This should be identified by conducting a PPAP gap analysis
between the old and new part numbers.
17
18
SECTION II
II.1
Unless superseded by specific written direction from the DaimlerChrysler Corporation Procurement and Supply
representative or by engineering drawing and specification requirements the following instructions apply.
II.1.1
SUBMISSION LEVELS
Suppliers designated by DaimlerChrysler Corporation as self-certified are to follow the guidelines for Submission
Level 1. All others are to follow the guidelines for Submission Level 2 unless otherwise instructed by your Component
Procurement and Supplier Quality representative. When conducting a bulk material PPAP, use conventions as detailed
in Section I in this manual.
II.1.2 SUBMISSION
All suppliers submitting their PSWs for PRODUCTION PARTS designated for use at all DaimlerChrysler Corporation
facilities must follow the directions as found on the DaimlerChrysler Corporation Supply Partner Information Network,
(SPIN), on the World Wide Web. This information can be accessed from the PRISM Home Page. Click on PPAP
Business Processes.
II.1.3
All suppliers providing material for any DaimlerChrysler PILOT build must submit a PSW utilizing the directions
found in the DaimlerChrysler Corporation Supply Partner Information Network, (SPIN), on the World Wide
Web. This information can be accessed from the PRISM Home Page. Click on PPAP Business Processes.
Suppliers must submit their PSWs per table I.3.1 in this manual as required by DaimlerChryslers Forever
Requirements as well as PSWs for new and modified parts.
CHECKING AIDS
Checking aids must be submitted when required to perform the dimensional inspection of the part being submitted.
Contact your DaimlerChrysler Corporation part approval representative to determine if this requirement can be waived.
II.1.4
The supplier must complete the Appearance Approval Report if the design records include any appearance features
(e.g.. Color, Grain, Finish, Appearance Standards, or Mastering Standards). Prior to submission with the Warrant, the
supplier must obtain a DaimlerChrysler Corporation Design Office approval signature on the Appearance Approval
Report.
NOTE: Both Interior and Exterior parts are included in the Appearance Approval Report procedure.
Suppliers of external sheet metal body panels must follow DaimlerChrysler Corporate Procedure 90-57 for surface
appearance review.
19
17)
18)
19)
20)
21)
22)
23)
24)
25)
26)
27)
28)
End Item Number: Engineering released part number and engineering change level.
Supplier Name: Enter component and end item suppler.
Manufacturing Location: Location where part was manufactured or assembled.
Date: Date of submission.
Component Part Number: Engineering released component part number.
Supplier Contact: Supplier representative responsible for submission.
Supplier Phone Number: Supplier contact phone number.
Application (Vehicle): List model year(s) and vehicles in which part is used.
Component Name: Enter the component part name.
Supplier Code: DaimlerChrysler assigned code for supplier location where the part was manufactured or assembled.
Buyer Code: Enter the code for specific buyer of end item.
Customer Engineer: Enter the name of the DaimlerChrysler Release Engineer responsible for the part being submitted.
Texture ID: Enter DaimlerChrysler identification number of texture (when applicable).
Texture Source: Enter name and location of texturing source (when applicable).
Texture Location on Part: Enter area(s) of grain(s) delineation (when applicable).
Surface and Texture Evaluation (when applicable):
a) DaimlerChrysler Design Office manager (or designated representative) approval of pre-textured surface.
b) DaimlerChrysler Release / Product Engineer authorization to proceed with texture.
c) DaimlerChrysler Design Office mastering studios designated representative authorization to proceed, including a
signed part.
d) DaimlerChrysler Design Office mastering studios designated representative post texture approval
Note: Texturing can not proceed without authorized signatures in 16a, 16b, and 16c.
e) DaimlerChrysler Design Office manager (or designated rep.) decision as to ornamentation and graphics approval
requirements.
Base or Raw Material DaimlerChrysler Spec. # and Supplier / Supplier # / Lot # : Enter DaimlerChrysler material
specification code, supplier name, supplier product code, and lot number of the material used to make the submitted
part.
Paint or Colorant DaimlerChrysler Spec. # and Supplier / Supplier # / Lot # : Enter DaimlerChrysler Paint or
Colorant Spec. #, supplier name, supplier product code, and lot number of the material used to make the submitted part.
Master # and Color: Enter full master identification and color number as released by DaimlerChrysler. (Refer to Trim
Release).
Ref. Master Type and Date: Enter reference master type and date as supplied by DaimlerChrysler for visual direction.
Tristimulus and Gloss Part Data: List numerical (colorimeter) data of submission part as compared to the customerauthorized master. Enter gloss data using 60-degree geometry measuring equipment.
Customer Comments / Approval Status / Initials / Date: Customer comments regarding color and gloss disposition
and/or color direction. Customer will indicate whether the color and gloss are accepted (A) or rejected (R), initial and
date the form. Note: Final approval signature is still required.
Supplier Signature, Phone Number & Date: Supplier designated representative accountable for the certification that
the submitted parts and document information is accurate and meets all the requirements specified.
Type of Ornamentation, Graphics Required and Surface Tactility: Name / process type cluster graphics, badges,
labels, etc. / pad transfer, hot stamp, lithograph, heat transfer, silk screen, laser etch, soft touch feel, etc.
Customer Approval Signature & Date: Design Office designated rep. Approval of identified ornamentation, graphics
and surface tactility.
Comments: General comments of importance to be initialed and dated.
Customer Interim Approval Signature: DaimlerChrysler Design Office Interim approval of end item or component
part. Allows IAA usage at this submission level.
Customer Final Approval Signature: DaimlerChrysler Design Office Final approval of end item or component part.
ALL SIGNATURES AND DATES (areas 16 (if applicable), 22, 25 (if applicable) & 27)
MUST BE COMPLETED FOR FULL AAR APPROVAL.
THE AREAS INSIDE THE BOLD LINES ARE FOR CUSTOMER USE ONLY
20
13
TEXTURE
SOURCE
E/C
LEVEL
E/C
LEVEL
14
TEXTURE LOCATION
ON PART
21
January 1, 1999
AAR.doc
26
DL*
17
APPROVALS
16
ENGINEERING PRE-TEXTURE
CONCURRENCE
DESIGN STUDIO
PRE-TEXTURE SURFACE
Da*
Db*
De*
CMC
18
GLS
21
PHONE
b.
c.
d.
CUSTOMER COMMENTS
27
28
25
CUSTOMER APPROVAL
SIGNATURE
DATE
APPLICATION
(VEHICLE)
CUSTOMER
ENGINEER
12
4
8
22
REQD
APPROVAL
STATUS
e.
DATE
DATE
DATE
DATE
CUSTOMER
INITIALS / DATE
NOT REQD
COMMENTS:
24
DATE
TYPE OF ORNAMENTATION
AND GRAPHICS REQUIRED
TYPE
20
23
COLOR
REF. MASTER
SUPPLIER APPROVAL
SIGNATURE
19
15
11
MASTER
MANUFACTURING
LOCATION
SUPPLIER
PHONE
BUYER
CODE
10
TEXTURE
ID
END ITEM
NUMBER
COMPONENT
PART NUMBER
COMPONENT
NAME
DaimlerChrysler
22
TEXTURE
SOURCE
E/C
LEVEL
E/C
LEVEL
TEXTURE LOCATION
ON PART
COLOR
January 1, 1999
AAR.doc
TYPE
DATE
REF. MASTER
DL*
Da*
Db*
De*
CMC
PHONE
CUSTOMER COMMENTS
NOT REQD
DATE
DATE
DATE
CUSTOMER
INITIALS / DATE
APPROVAL
STATUS
DATE
REQD
CUSTOMER APPROVAL
SIGNATURE
DATE
APPLICATION
(VEHICLE)
CUSTOMER
ENGINEER
COMMENTS:
TYPE OF ORNAMENTATION
AND GRAPHICS REQUIRED
SUPPLIER APPROVAL
SIGNATURE
MASTER
DESIGN STUDIO
PRE-TEXTURE SURFACE
ENGINEERING PRE-TEXTURE
CONCURRENCE
APPROVALS
MANUFACTURING
LOCATION
SUPPLIER
PHONE
BUYER
CODE
TEXTURE
ID
END ITEM
NUMBER
COMPONENT
PART NUMBER
COMPONENT
NAME
DaimlerChrysler
II.1.5
The Supplier Request for Product Change (SRPC) provides suppliers the opportunity to obtain specification relief for
minor dimensional and/or standard variations that do not affect performance, assembly, quality, durability, warranty,
customer satisfaction or cost.
The SRPC is not a means to avoid making the parts to print. The supplier is expected to make every effort to resolve
discrepancies before resorting to an SRPC. All SRPCs should be written and approved prior to presenting the Warrant.
Contact the respective DaimlerChrysler Corporation part approval activity for copies of the SRPC form and complete
instructions on its use. Identify the approved SRPC (as SRPC#XXXX) in the Additional Engineering Change line of
the Warrant.
All references to customer pertain to the DaimlerChrysler Procurement and Supply representative. The customer
product approval activity pertains to DaimlerChrysler Corporation Powertrain, Stamping, and Component operation
receiving facilities.
II.1.8
When DaimlerChrysler Corporation specifies the use of a third party laboratory, that laboratory must be approved by
DaimlerChrysler Corporation or accredited through either an ILAC or APLAC member, e.g. American Association for
Laboratory Accreditation (A2LA), the Standards Council of Canada (SCC) or the Laboratory Accreditation Bureau (LA-B).
23
Part Approval Activity - For external suppliers this refers to the Ford Supplier Technical Assistance
Office (STA) of, or representing, the customer. Internal operations should contact their responsible approval activity or the FAO Quality Office.
II.2.2
ES (Engineering Specification) - This is the Ford designation for the performance tests referred to in the
body of this document.
II.2.3
Substance Use Restrictions - A statement indicating conformance with Ford Engineering Material Specification WSS-M99P9999-A1 is required on the material test report. (This specification is available from
Materials Engineering). This specification results from regulations of the countries where Ford does business. These regulations apply equally to Ford and its suppliers. Therefore, this specification does not add
any requirements, but does require the supplier to verify conformance with the specification and with
relevant regulations in the country of manufacture and the country of the Ford receiving location.
Suppliers self-certify conformance to this specification and are not required to provide supporting test
data.
NOTE: Plastic Parts Marking - suppliers of plastic parts are encourage to mark plastic (polymeric) parts
with the appropriate ISO symbols to designate the type of polymer and filler/reinforcer used to fabricate
the part (further information is provided in Ford material specification E-4 available on-line at https://
web.keyinfo.ford.com/manuals/index.html and https://web.keyinfo.ford.com/supply/docs/e4.pdf). Affected
suppliers are requested to indicate compliance on the PSW form, as appropriate.
II.2.4
Interim Approvals - When non-conformances on a production part submission are identified, the STA
engineer shall contact the buyer and product engineer following local procedures. If the product engineer
allows use of product affected by the non-conformance, product engineering shall initiate (and approve) an
alert in the WERS system, specifying the time period or quantity for which the non-conforming product
can be used. The supplier shall enter the alert number on the PSW form under Additional Engineering
Changes. Once parts are available from the permanent tooling/process, a new part submission warrant (PSW) is required. Should incomplete or in-process test data result in an alert, a new PSW is
required upon availability of completed test data.
II.2.5
Control Plans - Shall be developed by the supplier and be available for review by the customer as early as
possible and in any case prior to the production part submission date. Control Plans must include all
Critical and Significant characteristics. Product Engineering and Part approval activity signatory approval
is required on Control Plans for Control Item ( ) products and for products so designated by Product
Engineering (e.g., with an ES specifically requiring this approval). Some Ford quality activities may request that a copy of the approved Control Plan be attached to the Part Submission Warrant and forwarded
to the customer part approval activity.
II.2.6
Appearance Item Approvals - All parts having appearance criteria (*) shall be reviewed by the Ford
Design Quality Office. The completed Appearance Approval Report (form CFG01002) shall accompany
this submission. After approval signatures have been obtained from the designated Ford Design Quality
representative, the form shall be included with Warrant.
(*) NOTE: All interior, exterior, luggage compartment, and select underhood components which are
visible to the customer. Appearance approval included but is not limited to overall appearance, color,
texture, and gloss.
Refer to the Corporate Design Decorative Component Approval Process manual for detailed instructions.
24
For additional information, contact: Ford Design Quality, Ford Motor Company, Product Development
Center, Mail Drop 533, PO Box 2110, Dearborn, MI, 48123; fax: 313-594-7705.
II.2.7
Part Submission Level - For external suppliers, PPAP submission level is controlled by the Ford STA
Commodity Engineer based on Q1 status, correct PPAP usage/submittal, critical nature of components and
product concerns. When conducting a bulk material PPAP, use conventions as detailed in Section I in this
manual.
NOTE: It is important that suppliers designated as Level 2-5 account for any additional time that may
be required to obtain STA approval, when providing PSW promise date (If the STA Engineer is unavailable to approve the PPAP in a timely manner, the supplier should contact the STA Program Manager who may assign another engineer to disposition the PSW; for bulk materials, contact the Raw
Materials STA Manager).
Internal operations should contact their responsible approval activity or the FAO Quality Office regarding
PPAP submission level.
II.2.8
Manage the Change - The supplier shall develop and implement a process to manage change to ensure
that any product (either revised or new) affected by revisions in design and process shall continue to meet
all applicable specifications. A copy of the Supplier Checklist/Approval for Managing Change is provided
for guidance on page 30.
All design changes shall be clearly described and reference the WERS Engineering Notice number under
the Additional Engineering Changes on the PSW form. Questions regarding this requirement should be
reviewed with the using Ford facility.
The customer using facility may request full or partial PPAP documentation from the supplier in addressing specific product related concerns - supplier data shall be readily available upon request.
All post Job #1 changes (e.g., running changes, new supplier sourcing, revised supplier manufacturing
location, etc.) shall obtain functional approval from the customer using facility prior to shipping of production quantities.
NOTE: At Vehicle Operation facilities contact the Plant Vehicle Team (PVT) for functional approval.
If the component is used at multiple Ford facilities, then all using facilities must provide functional approval (a using facility may opt to waive functional approval in certain cases). Functional approval is
provided at the bottom of the PSW form under For Customer Use Only. Questions concerning the need
for functional approval should be directed to the using Ford facilities.
II.2.9
Family of Parts - Suppliers are permitted to submit multiple part numbers (same family of parts) on a
single PSW with all part specifics (e.g., prefix, base, suffix) clearly noted on the PSW.
II.2.10
Labeling Requirement - Suppliers to Ford European facilities are required to affix orange labels (Form
EU 3441, minimum A5 size) on all four sides of the packaging for all shipments of new or changed product
to each using Ford facility. Powertrain suppliers are required to include their unique supplier generated
PSW number on each label of the PSW shipment (ongoing shipments are excluded from this requirement).
II.2.11
Run at Rate - Run at rate is an integral part of the sample submission (PSW) for suppliers and which
provides the basis to extract capability data and inspection layout data. All production tooling shall be in
place and running at full production feeds and speeds, using all regular production direct and indirect
personnel and support systems (QS-9000, Section II, Ford-Specific Requirements)
25
II.2.12
II.2.13
Supplier Request for Engineering Approval (SREA) - The SREA procedure applies to all internal and
external suppliers without on-line WERS capability. Ford product engineering approval of a SREA is
required prior to implementing the change. Once Ford product engineering determines that the change is
feasible and a SREA is required, the supplier will complete and submit the SREA, Form 1638, to the
responsible product engineer.
Once approval is granted, a copy of the approved SREA shall be included in the PSW submission; powertrain
suppliers shall also provide a copy of the approved SREA to the using customer facility.
Process Changes
The supplier is empowered to implement process changes without issuing and obtaining SREA approval with the following exceptions:
- Change in heat treat, plating/coating and solderability.
- Changes to the manufacture of supplier-designed electronic components (capacitors, resistors, integrated circuits and similar components).
- Re-location of product to a different manufacturing location.
These exceptions will be waived once a supplier achieves Full Service Supplier status or is released
from the SREA requirement by the responsible design activity.
Changes to the process of control item ( ) parts or emission components always require issuance of
a SREA. No waivers apply for these components.
Ford reserves the right to require that additional process changes be subject to SREA submission based
on each suppliers performance in managing the change process. Suppliers are responsible for implementing this procedure with subcontractors.
Refer to the following flow diagram for the elements of the SREA process.
26
SUPPLIER WANTS TO
MAKE A DESIGN OR
PROCESS CHANGE
YES
PREDESIGNATED
PROCESS*
?
YES
NO
NO
SREA
WAIVED
?
NO
REVIEW WITH
ENGINEERING
FOR
APPROVAL IN
WERS
YES
YES
FULL
SERVICE
SUPPLIER
?
NO
SUPPLIER TO
MANAGE THE
CHANGE
ACCORDING TO
PPAP AND
ISSUE PSW
OBTAIN
FUNCTIONAL
APPROVAL
BLACK
BOX
DESIGN
?
FULL
SERVICE
SUPPLIER
?
NO
DESIGN
YES
(REQUIREMENT GUIDELINES)
CONTROL
ITEM OR
EMISSION
COMPONENT
?
YES
NO
SREA
WAIVED ?
YES
NO
SUPPLIER CONTACTS
FORD ENGINEERING TO
OBTAIN PRELIMINARY
FEASIBILITY APPROVAL
NO
FEASIBLE
?
YES
YES
ADDITIONAL
INFORMATION
REQUIRED
?
NO
YES
NO
SREA
APPROVED
?
27
YES
DO NOT IMPLEMENT
CHANGE
DISTRIBUTE TO
AFFECTED ACTIVITIES
AND SUPPLIER
II.2.14
PSW Submission Process - The following table sumarizes submission practices and methods for notifying the appropriate Ford system of completion of the PSW:
Suppliers on DDL (Direct Data Link) shall enter their PSW approval into appropriate Ford PSW
tracking system (EASI, CMMS Parts Progress, ELECT) per table below. Non-DDL suppliers shall
follow local practices required to accommodate differing Ford systems to facilitate proper entry.
PPAP
Level
Level 1
DDL
SUPPLIER
- Prepare PPAP data package/self
approve.
- Assign unique number to each PSW *
- Provide sample parts/PSW to using
Ford facilities for functional approval/
waiver.
- Fax copy of PSW to using powertrain
plant when parts are shipped *
- Enter approval in Ford System.
- Maintain the completed PPAP data
package on file.
Level 2-5
DDL
DATA ENTRY OF
APPROVAL
28
FAO Production
Purchasing enters
approval, per local
practice.
PPAP
Level
DATA ENTRY OF
APPROVAL
FAO Production
Purchasing enters
approval, per local
practice after STA
approval of PPAP data
package.
SUPPLIER
PTO
Vehicle Operations
All Operations
NON-DDL SUPPLIERS:
- Fax (or hand deliver to onsite drop box)
copy of the approved warrant to Timing
Analyst.
NON-DDL SUPPLIERS:
- Notify Material Follow-up Analyst when
PPAP data package is approved.
29
Part Name
Part Number
Change Description
ANY ITEMS NOT REQUIRED, PLEASE EXPLAIN:
Reqd.
Complete
Date
Comments
30
SUPPLIER TO COMPLETE
SUPPLIER NAME AND ADDRESS
FORD AND/OR SUPPLIER PART NAME AND PART NUMBER OF ASSEMBLY AND ITS COMPONENTS
EMISSION CONTROL
CODE NUMBER
(SEE FORM
74-107)
CONTROL ITEM
AFFECTED
YES
DESIGN
DESCRIPTION OF CHANGE:
COMPOSITION
WEIGHT
NO
PROCESSING
EFFECT OF CHANGE:
INTERCHANGEABILITY AFFECTED
ASSEMBLY
YES
NO
COMPONENTS
YES
NO
YES
NO
YES
NO
NO
SUPPLIER REPRESENTATIVE
BY
DATE
CONCURRED BY
SIGNATURE__________________________________
SIGNATURE __________________________________
BLANKET APPROVAL GRANTED FOR SUBSEQUENT CHANGES
WHICH ARE SAME AS DESCRIBED ABOVE
YES
YES
NO
REJECTED
DATE
NO
YES
NO
REVIEWED BY:
SQA ____________________________________ DATE ________________ PURCHASING____________________________________DATE __________________________
* This approval is granted upon the understanding that it is advisory in nature and in no manner changes the Sellers
original responsibility for insuring that all characteristics, designated in the applicable engineering specifications and/or
inherent in the samples as originally tested and approved, are maintained. Seller accepts full responsibility for the changes
or types of changes listed above; and should such changes result in less satisfactory performance than experienced with
the originally approved item, Seller will fully reimburse the Buyer for all expenses incurred to correct the deficiency.
CEG
JUL 92
FORD GLOSSARY
Critical ( )
Characteristics
SREA
The process that provides for two-way communication between the component supplier and
the responsible Ford product engineering activity through which the supplier requests
concurrence for certain process related changes.
32
33
GM
II.3
II.3.1
Applicability
This procedure is applicable to production, service, and unitized service parts, raw materials purchased by or contracted
to GM. It also applies to all commodities supplied by external independent suppliers, GM Allied and Affiliated suppliers,
plus all commodities supplied to these suppliers (e.g., subcontractors and third tier suppliers). Please note that for bulk,
raw, or indirect material, it is the Procuring Divisions decision whether PPAP is required. When conducting a bulk
material PPAP, use conventions as detailed in Section I in this manual.
II.3.2.1
1.
2.
3
4.
5.
6.
The supplier shall use one warrant per customer part number.
GM does not require the purchase order number (item #7).
Enter Buyer name, and/or Buyer Code, if known (item #15).
The Supplier Code referred to on the PSW and on the Appearance Approval Report is the full code assigned to the
manufacturing location on the purchasing order.
The PSW shall be complete, legible and accurate. Warrants will not be accepted that have the following fields in
error:
Part Number
item 2
Engineering Drawing Change Level
item 4
Weight
item 8
Supplier Code
item 11
Supplier Address
item 12
Reason for Submission
item 17
Supplier Authorized Signature
item 22
The supplier should include an EWO number with the engineering change level on the warrant.
II.3.2.2
1.
Appearance Approval Report (AAR) (CFG-1002) for parts with color, grain, gloss or textiles
NOTE: AAR is not required for surface quality of body in white (BIW) parts. Refer to the General Motors
North America Surface Buyoff Procedure for Surface Requirements of BIW parts.
2.
Appearance Approval may occur concurrently with part inspection and testing.
II.3.2.3
If submitting for Level 2 or 3, the supplier shall submit two sample parts unless otherwise specified by the procuring
Division. For multiple processes, two sample parts per process e.g. two parts per cavity, tool, cells, assembly lines are
required unless otherwise specified by the procuring division. The sample parts do not have to be the same part(s) that
34
were dimensionally measured and documented on the marked drawing or check sheet. All sample parts should be
labeled with part number, change level, and supplier name.
A marked drawing can be used for a full PPAP submission provided the drawing is signed by the product engineer,
has an EWO number and is dated.
All Supplier design records shall be GM approved.
The supplier shall furnish evidence of conformance to print specifications of each detail component when requested.
For CAD parts that are databanked, the current level in the GM design databank is the inspection referee. The
source of the data shall be provided with change level and date.
2.
3.
When Material, Validation, Performance, Durability, Reliability, or other engineering requirements are on the
design record, approval can occur in two ways.
a) The supplier gets approval prior to PPAP and submits evidence of approval.
b) The supplier submits the test data or results with the PPAP submission. Note that an additional drawing may
be required by the procuring division.
All Laboratory data shall be less than one year old at the time of initial submission. Previously approved test data
shall be updated (less than one year old) if part performance, material, reliability, durability or validation is affected
by an engineering change. The updated test data shall be included in the PPAP submission for the engineering
change.
A GM-E364 form is required where the note Engineering Approval required or the stamp Engineering source
approval for functional performance is checked yes and found on the drawing or design record (see I.2.2.3)
II.3.2.6
GM requires suppliers to document and submit (depending on submission level) their Pre-Launch Control Plan. For
information on the Pre-Launch Control Plan, see section 3.7 of the Chrysler, Ford, General Motors Advanced Product
Quality Planning and Control Plan reference manual. General Motors General Procedure GP-12 Early Production
Containment proceduralizes the Pre-Launch Control Plan. All parts requiring production part approval (PPAP) shall
also comply with GP-12 Early Production Containment.
Whenever a supplier is required to submit a Production Control Plan, they shall also submit a Pre-Launch Control
Plan, as defined by GP-12.
II.3.2.7
The minimum required acceptance criteria for the PPAP initial study shall be a Cpk or Ppk of 1.67.
II.3.3
35
GM
1.
2.
3.
4.
5.
The supplier shall review the proposed change with the procuring division prior to implementation to obtain
concurrence per the divisions local practice.
Sufficient information shall be provided to explain the detailed reason for the submission. Attachments are
encouraged.
Level 1 submission should be checked.
GM will review the warrant and determine if the warrant is acceptable. If the warrant is acceptable the supplier
shall receive the standard supplier notification authorizing shipment. If additional information or a higher submission
is required, the supplier shall be notified by the procuring division.
For submissions other than Initial Submission and Engineering Change(s) sufficient information shall be
provided to explain the detailed reason for the submission. Additional attachments are encouraged.
II.3.4
1.
2.
For item 1, table I.3.3, the supplier shall notify GM per II.3.3 Customer Notification of Supplier Initiated Changes.
Resubmission is not required for a design record update that reflects a change that was previously approved per a
dated marked print with an EWO number and engineering signature per section I.2.2.2 and/or I.2.2.3.
Suppliers are not required to maintain full documentation from their subcontractors if they have decision criteria
and a process in place to establish the level of evidence required from their subcontractors, and the appropriate
level of evidence on file at their location. Upon a Procuring Divisions request for Production Part Approval
Documentation, suppliers must comply within a reasonable period of time.
2.
ATTENTION SUPPLIERS TO GENERAL MOTORS EUROPE: Level 2 shall be the default level for all
submissions to General Motors Europe, unless specifically advised otherwise by the responsible part approval
activity.
Part meets all requirements as outlined on the GM approved drawing and in accordance with PPAP.
Drawing must be fully released or is a marked drawing accompanied by an EWO, product engineers signature
and date.
Multiple cavity tools can achieve full approval on individual cavities provided the cavity being submitted meets all
the requirements outlined in the PPAP manual. Each submission for a multiple cavity tool must specify the cavity
and/or cavities that are being submitted for full approval.
If a part is not a full approval, the Interim Approval will authorize the shipment to the customer. The status
Interim Approval indicates the customers decision to use the part without Full Approval.
All Interim Approvals require a corrective action plan. The Interim Recovery Worksheet (GM 1411), which has
been developed for this purpose, is to be completed with the supplier.
If an extension is required, the GM 1411 must be re-issued and the interim date changed.
All Interim Approvals require the part number to be classified A, B, C, D, or E as follows:
36
Class A: Parts are produced using 100% production tooling and meet design record specifications. However, not
all production approval requirements have been met.
Examples:
1. A capability study has been performed on less than 300 pieces and in the judgment of the SQE, satisfactory
stability and capability has not been achieved. The supplier shall implement temporary containment
actions until capability is achieved.
2. Documentation improvements required. Examples include DFMEA, PFMEA, Process Flow Diagram
and Process Control Plan.
3. Part only lacks formal PPAP processing for statusing. Parts and data have been reviewed by the SQE and
there is no indication of non-conformances.
4. Testing has not yet been completed and in the judgment of the appropriate engineer, usage of the parts
does not pose a significant risk to customer dissatisfaction e.g. Long term material tests, long term functional
test, environmental exposure etc. (Engineering signature is required).
5. Part and drawing do not match and a part change is not desired or anticipated. The interim worksheet
must specify the differences between the part and the specification. The interim worksheet must document
a commitment and date for the specification to be changed. (Engineers signature required.)
Class B: Parts are produced using 100% production tooling and require rework to meet design record specifications
as explained on the GM 1411 form.
Examples:
1. Parts have been produced not following the documented production process on the process flow diagram.
Examples include trimming, sanding, buffing, etc. The process flow diagram includes any temporary
operations except inspection. Added inspection alone should not be considered rework, but instead
documented in the GP-12 plan and/or the process flow diagram and process control plan.
Class C: Parts are not produced using 100% production tooling and/or production processes, but meet design
record specifications as explained on the GM 1411 form.
Examples:
1. Parts have been produced using additional, substitute or temporary tooling.
2. Parts have not been manufactured completely at the production site/environment.
NOTE: If low volume tools are intended to meet current production needs submit for full production
approval.
Class D: Parts do not meet design record specifications as explained on the GM 1411 form.
Examples:
1. Dimensional, material validation/functional testing or appearance characteristics that do not met design
record requirements but will not impact vehicle assembly or customer satisfaction. Product engineer
signature is required.
Class E: Parts do not meet design record specifications as explained on the GM 1411 form. Vehicles with Class
E parts require retrofit to make them saleable.
Examples:
1. Dimensional, material validation/functional testing or appearance characteristics that do not meet design
record requirements and will impact vehicle assembly or customer satisfaction. Product engineer signature
is required.
2.
Incomplete testing with high probability of failure and/or failed performance/functional material testing.
Parts require retrofit for saleable status. Product engineer signature required.
37
GM
3.
C.
The part or associated documentation does not meet specified requirements. A resubmission shall be required. Shipment
of parts is not permitted.
D.
2.
3.
II.3.7
Production approval status from one GM Division applies to all GM. Suppliers do not need to reevaluate the
part or resubmit documentation, solely because the part will be used by another GM location. A copy of the
warrant and the document signifying approval must be supplied to the new using division. The new using
division reserves the right to review the PPAP information upon request.
Parts may be requested for a production trial run (PTR).
Interim approval granted by one division does not automatically guarantee authorization to ship to other GM
locations.
Each sample submission to General Motors shall be packaged separately and identified with the General Motors
Sample Submission for Production Approval label, GM Form 1387. The information required on the label shall be
added by the supplier prior to shipment. When several submissions are to be shipped in one larger container, a Sample
Submission for Production Approval label, with only the To and From portion completed, shall be attached to the
container at the upper right hand corner, visible from two sides. Each sample submission inside the larger container
shall be packaged and labeled as specified. Parts and paperwork shall be packaged together.
38
INTERIM RECOVERY
WORKSHEET
(GM 1411)
39
GM
Supplier Name:
Supplier Code:
Resubmission date:
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
17.
18.
19.
20.
Status:
Brief Reasons:
21.
22.
GP-12:
23.
Supplier:
24.
Customer Approvals:
Attach Part Submission Warrant with Customer approvals in order to have interim processed and send to processing group. Interim Approvals can
be obtained in person, fax, mail or via E-mail.
40
Supplier
GM
PART NAME:
SUPPLIER CODE:
PART #:
RESUBMISSION DATE:
EWO#:
APPLICATION:
ECL:
SUBMISSION LEVEL:
SAMPLE #:
Customer
SUPPLIER NAME:
13
11
18 INTERIM CLASS
19 STATUS:
10
DATE:
12
KG Wt:
INSP/SQE:
14
ADD. SAMPLE:
15
PKG:
16
Interim#
17
DIM:
APP:
LAB:
PROCESS:
ENG:
Supplier
21 ISSUES:
22 WHERE APPLICABLE, ARE INTERIM ISSUES ADDRESSED ON THE GP-12 PLAN? (e.g. rework, temporary operations)
(Please explain below):
23
PHONE:
FAX:
PART SUBMISSION WARRANT MUST BE INCLUDED WITH CUSTOMER APPROVALS IN ORDER TO PROCESS YOUR REQUEST AND SEND TO THE PROCURING DIVISION.
Customer
24 CUSTOMER APPROVALS:
SIGNATURE
NAME (Print)
41
PHONE
DATE
GM
Supplier
GM
SUPPLIER NAME:
PART NAME:
SUPPLIER CODE:
PART #:
RESUBMISSION DATE:
INTERIM EXPIRE DATE:
EWO#:
APPLICATION:
ECL:
SUBMISSION LEVEL:
Customer
SAMPLE #:
KG Wt:
INSP/SQE:
ADD. SAMPLE:
PKG:
DATE:
Interim#
DIM:
APP:
LAB:
PROCESS:
ENG:
Supplier
ISSUES: (List DIM, APP, LAB, Process, tooling, capacity,o r start-up issues)
WHERE APPLICABLE, ARE INTERIM ISSUES ADDRESSED ON THE GP-12 PLAN? (e.g. rework, temporary operations)
(Please explain below):
PHONE:
FAX:
PART SUBMISSION WARRANT MUST BE INCLUDED WITH CUSTOMER APPROVALS IN ORDER TO PROCESS YOUR REQUEST AND SEND TO THE PROCURING DIVISION.
Customer
CUSTOMER APPROVALS:
SIGNATURE
NAME (Print)
42
PHONE
DATE
43
GM
Part number
2.
Supplier Name
3.
Part name
4.
Duns Code
5.
Application
6.
ECL
7.
EWO
8.
Drawing Number
9.
Revision Date
11. Comments
Parts that do not meet the requirements shall not use the GME364. The supplier shall clearly document the non
conformances on the GM 1411 and follow the interim approval
process. The Supplier shall obtain engineering signatures on the
GM 1411 form.
15. Signature
16. Date
17. Code
44
Supplier:
Part Name:
Duns Code:
Application:
ECL:
Drawing Number:
EWO:
Revision Date:
II. The Part Meets All Engineering Performance Requirements. (e.g., Sub System
Tech. Spec., Comp. Tech. Spec., Solar, Validation)
Yes 10
III. Comments:
11
IV. Part not meeting all engineering requirements specified above (section III).
Must be submitted on the GM1411 interim worksheet (the GM-E364 form
does not apply). 12
V. GM Product Engineer:
15
13
(Print)
Date:
Phone Number:
16
(Signature)
17
(Code)
45
14
GM
Supplier:
Part Name:
Duns Code:
Application:
ECL:
Drawing Number:
Revision Date:
EWO:
II. The Part Meets All Engineering Performance Requirements. (e.g., Sub System
Tech. Spec., Comp. Tech. Spec., Solar, Validation)
Yes
III. Comments:
IV. Part not meeting all engineering requirements specified above (section III).
Must be submitted on the GM1411 interim worksheet (the GM-E364 form
does not apply).
V. GM Product Engineer:
(Print)
Phone Number:
Date:
(Signature)
(Code)
46
The purpose of the production trial run is to ensure the effectiveness of the manufacturing process by running production
products off of production tools, materials, equipment, cycle times, and environments while using production operators,
gages, and other production methods. It is imperative that adequate quantities of parts be manufactured during this run
to sufficiently sample, test, and thoroughly try out the production process (at rate) prior to full production. Since parts
from the production trial run must be used to inspect and test for the initial sample submission, it is mandatory that
production processes and environments be used for this trial run. It is also mandatory to insure that sufficient quantities
of parts are run for preliminary process capability studies and for validation testing.
Since production trial runs in the truck industry are typically small, it is recommended that a maximum number of
production parts be run during the trial run to insure production has ample time to prove out the process, while yielding
sufficient quantities of parts to perform process capability studies. It is recognized that sample sizes as small as 30
pieces may be utilized for preliminary process capability studies. Sample sizes must be discussed and agreed to early
in the APQP process.
If projected volumes are so low that 30 samples are not attainable prior to production, interim PPAP approval may be
granted. A dimensional report with 100% inspection on special characteristics is required during the interim period.
Once the 30 production samples are produced, measured and the quality index calculated and accepted, then the interim
approval is changed to full approval.
II.4.2
Checked prints are not accepted within the truck industry. The supplier shall submit, as part of the PPAP package, a
copy of the drawing with each dimension, test, and or specification identified with a unique number. These unique
numbers shall be entered onto the dimensional or test results sheet as applicable, and actual results entered onto the
appropriate sheets. The supplier shall also identify print zone for each numbered characteristic as applicable.
II.4.3
Due to the fact that small production trial runs are common in the truck industry, the supplier shall use the guidelines
described in II.4.1 above to maximize the number of parts run during the production trial run in order to have as many
parts as possible available to inspect for capability studies. Truck manufacturers require a minimum of 30 production
pieces be studied for preliminary process capability.
47
When the customer specifies special characteristics and the estimated annual usage is less than 500 pieces, the supplier
shall document in their control plan that they will either:
conduct an initial process capability study with a minimum of 30 production pieces and maintain SPC control
charts of the characteristics during production.
For special characteristics that can be studied using variable data, the supplier shall utilize one of the following techniques
to study the stability of the process:
When performing the initial short term study, data shall be plotted from consecutive parts taken from the production
trial run. These studies could be augmented or replaced by long term results from the same or similar process run on
the same equipment with prior customer concurrence.
II.4.4
For initial process capability studies using 30 to 300 parts, the supplier shall use the following as acceptance criteria for
evaluating initial process study results for processes that appear stable:
For attribute features contact customer for appropriate sample size and statistical method.
II.4.5
1.00
1.33
1.67
1.33
1.79
2.24
The supplier shall have Measurement System Analysis studies, e.g. gage R&R, bias, linearity, stability studies, for all
gages and equipment used to measure special product characteristics or special process parameters. Measurement
System Analysis studies for gage families is not acceptable.
48
II.4.6
CUSTOMER
Freightliner
SYMBOL
Key Characteristics
Navistar
PACCAR
KCC
Kenworth
or Peterbilt
Western Star
[1] or [2]
CUSTOMER
Freightliner
TERM
SYMBOL
Key Characteristics
Mack Trucks
Navistar
KCC
PACCAR
Consequence Class
49
page for North American Truck Industry PSW Form). The North American Truck Industry PSW form is the same
as the automotive PSW except for the declaration statement, which is worded more properly for the truck industry.
Instructions for completing the form are the same as described on page 52.
Part Number
Safety and/or
Government Regulation
Yes
No
Dated
Dated
kg
Dated
SUBMISSION INFORMATION
11
Weight
10
Dimensional
13
Materials/Functional
Appearance
Customer Name/Division
12
Street Address
Buyer/Buyer Code
Application
14
15
16
City/State/Postal Code
Note:
Yes
No
Yes
No
18
Level 1 Warrant only (and for designated appearance items, an Appearance Approval Report) submitted to customer.
Level 2 Warrant with product samples and limited supporting data submitted to customer.
Level 3 Warrant with product samples and complete supporting data submitted to customer.
Level 4 Warrant and other requirements as defined by customer.
(Circle)
2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
Level 5 Warrant with product samples and complete supporting data reviewed at supplier's manufacturing location.
TS
SUBMISSION RESULTS
19
21
EXPLANATION/COMMENTS:
Print Name
Supplier Authorized Signature
Title
FAX No.
Phone No.
22
Date
FOR CUSTOMER USE ONLY (IF APPLICABLE)
Approved
Rejected
Customer Name
J u l y
1999
Approved
Waived
Interim Approval
Customer Signature
TAG-1001
50
Date
Part Number
Yes
No
Dated
Dated
kg
Weight
Dated
SUBMISSION INFORMATION
Dimensional
Materials/Functional
Appearance
Customer Name/Division
Street Address
Buyer/Buyer Code
Application
City/State/Postal Code
Note:
Yes
No
Yes
No
(Circle)
2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
Level 5 Warrant with product samples and complete supporting data reviewed at supplier's manufacturing location.
SUBMISSION RESULTS
The results for
dimensional measurements
material and functional tests
appearance criteria
statistical process package
These results meet all drawing and specification requirements:
Yes
NO
(If NO Explanation Required)
Mold / Cavity / Production Process
DECLARATION
I hereby affirm that the samples represented by this certification are representative of our parts, have been made to the applicable customer
drawings and specifications, and are made from the specified materials on regular production tooling with no operations other than the regular
production process. I also certify that documented evidence of such compliance is on file and available for review.
EXPLANATION/COMMENTS:
Print Name
Title
Phone No.
FAX No.
Date
FOR CUSTOMER USE ONLY (IF APPLICABLE)
Approved
Rejected
Customer Name
July
1999
Approved
Waived
Interim Approval
Customer Signature
TAG-1001
51
Date
Appendix A
Completion of the Part Submission Warrant
PART INFORMATION
1.
Part Name and 2. Customer part number: Engineering released finished end item part name and number.
3.
4.
Engineering Change Level & Approval Date: Show change level and date for submission.
5.
Additional Engineering Changes: List all authorized engineering changes not yet incorporated on the
drawing but which are incorporated in the part.
6.
Shown on Drawing Number: The design record that specifies the customer part number being submitted.
7.
Purchase Order Number: Enter this number as found on the purchase order.
8.
Part Weight: Enter the actual weight in kilograms to four decimal places.
9.
Checking Aid No. Enter the checking aid number, if one is used for dimensional inspection, and,
10.
Supplier Manufacturing Address: Show the complete address of the location where the product was
manufactured.
SUBMISSION INFORMATION
13. Submission type: Check box(es) to indicate type of submission.
14.
Customer Name: Show the corporate name and division or operations group.
15.
Buyer Name: and Buyer Code: Enter the buyers name and code.
16.
Application: Enter the model year, vehicle name, or engine, transmission, etc.
Appendices
D
aimlerChryslerFord
DaimlerChrysler
Part Name
General Motors
Safety and/or
Government Regulation
Yes
Part Number
No
Dated
Dated
7
10
Dated
SUBMISSION INFORMATION
11
Weight (kg)
Dimensional
13
Materials/Functional
Appearance
Customer Name/Division
12
Street Address
Buyer/Buyer Code
Application
City
State
Note:
14
15
16
Zip
Yes
No
Yes
No
18
Level 1 Warrant only (and for designated appearance items, an Appearance Approval Report) submitted to customer.
Level 2 Warrant with product samples and limited supporting data submitted to customer.
Level 3 Warrant with product samples and complete supporting data submitted to customer.
Level 4 Warrant and other requirements as defined by customer.
Level 5 Warrant with product samples and complete supporting data reviewed at supplier's manufacturing location.
SUBMISSION RESULTS
19
21
EXPLANATION/COMMENTS:
Print Name
Supplier Authorized Signature
Title
Phone No.
FAX No.
22
Date
FOR CUSTOMER USE ONLY (IF APPLICABLE)
Approved
Rejected
Customer Name
J u l y
1999
CFG-1001
Approved
Waived
Other
Customer Signature
The original copy of this document shall remain at the suppliers location
while the part is active (see Glossary).
53
Date
Optional: customer tracking
number: #
D
aimlerChrysler Ford
DaimlerChrysler
General Motors
Part Name
Safety and/or
Government Regulation
Part Number
Yes
No
Dated
Dated
Weight (kg)
Dated
SUBMISSION INFORMATION
Dimensional
Materials/Functional
Appearance
Customer Name/Division
Street Address
Buyer/Buyer Code
Application
City
State
Note:
Zip
Yes
No
Yes
No
Title
Phone No.
FAX No.
Date
FOR CUSTOMER USE ONLY (IF APPLICABLE)
Approved
Rejected
Other
Customer Name
J u l y
1999
CFG-1001
Approved
Waived
Customer Signature
The original copy of this document shall remain at the suppliers location
while the part is active (see Glossary).
54
Date
Optional: customer tracking
number: #
Appendices
55
Appendix B
2.
Drawing Number: Use the number of the drawing on which the part is shown if different from the
part number.
3.
Application: Enter the model year(s) and vehicle or other program on which the part is used.
4.
Part Name: Use the finished part name on the part drawing.
5.
6/7. E/C Level & Date: Engineering change level and E/C date for this submission.
8.
9.
10. Supplier Code: Customer-assigned code for supplier location where the part was manufactured or
assembled.
11. Reason for Submission: Check box(es) explaining the reason for this submission.
12. Supplier Sourcing & Texture Information: List all first surface tools, graining source(s), grain
type(s), and grain and gloss masters used to check part.
13. Pre-Texture Evaluation: To be completed by customer representative (not used by GM).
14. Color Suffix: Use alphanumeric or numeric color identification.
15. Tristimulus Data: List numerical (colorimeter) data of submission part as compared to the customerauthorized master.
16. Master Number: Enter alphanumeric master identification (not used by Ford).
17. Master Date: Enter the date on which the master was approved.
18. Material Type: Identify first surface finish and substrate (i. e.: paint/ABS).
19. Material Source: Identify first surface and substrate suppliers. Example: Redspot/Dow.
20. Color Evaluation, Hue, Value, Chroma, Metallic Brilliance & Gloss: Visual assessment by customer.
21. Color Shipping Suffix: Color part number suffix or color number.
22. Part Disposition: To be determined by customer (approved or rejected).
23. Comments: General comments by the supplier or customer (optional).
24.
Supplier Signature, Phone No. & Date: Supplier certification that the document information is
accurate and meets all requirements specified.
THE AREAS INSIDE THE BOLD LINES ARE FOR CUSTOMER USE ONLY.
56
PART
NAME
SUPPLIER
NAME
57
25
23
SUPPLIER
SIGNATURE
COMMENTS
Db*
DE*
CMC
TRISTIMULUS DATA
COLOR
SUFFIX
Da*
5
9
BUYER
CODE
MANUFACTURING
LOCATION
17
18
19
DATE
RED
YEL
BLU
LIGHT
DARK
VALUE
25
CLEAN
CHROMA
GRAY
20
CUSTOMER
REPRESENTATIVE SIGNATURE
GRN
HUE
COLOR EVALUATION
MATERIAL MATERIAL
SOURCE
TYPE
PHONE NO.
MASTER MASTER
DATE
NUMBER
16
HIGH
LOW
GLOSS
APPROVED TO
TEXTURE
CORRECT
AND PROCEED
CORRECT AND
RESUBMIT
PRE-TEXTURE
EVALUATION
21
HIGH
LOW
DATE
22
PART
DISPOSITION
CUSTOMER
REPRESENTATIVE
SIGNATURE AND DATE
10
COLOR
METALLIC SHIPPING
BRILLIANCE SUFFIX
13
OTHER
SUPPLIER
CODE
6/7 DATE
APPLICATION
(VEHICLES)
RE-SUBMISSION
ENGINEERING CHANGE
E/C LEVEL
12
APPEARANCE EVALUATION
SPECIAL SAMPLE
FIRST PRODUCTION SHIPMENT
DRAWING
NUMBER
15
11
14
DL*
REASON FOR
SUBMISSION
PART
NUMBER
Appendices
58
DL*
Da*
Db*
DE*
CMC
DATE
MATERIAL MATERIAL
SOURCE
TYPE
PHONE NO.
MASTER MASTER
DATE
NUMBER
RED
YEL
BLU
LIGHT
DARK
GRAY
CLEAN
CHROMA
CUSTOMER
REPRESENTATIVE SIGNATURE
GRN
HUE
COLOR EVALUATION
HIGH
LOW
GLOSS
APPROVED TO
TEXTURE
CORRECT
AND PROCEED
CORRECT AND
RESUBMIT
PRE-TEXTURE
EVALUATION
HIGH
LOW
DATE
PART
DISPOSITION
CUSTOMER
REPRESENTATIVE
SIGNATURE AND DATE
COLOR
METALLIC SHIPPING
BRILLIANCE SUFFIX
OTHER
SUPPLIER
CODE
DATE
APPLICATION
(VEHICLES)
RE-SUBMISSION
ENGINEERING CHANGE
E/C LEVEL
VALUE
APPEARANCE EVALUATION
SPECIAL SAMPLE
FIRST PRODUCTION SHIPMENT
TRISTIMULUS DATA
SUPPLIER
SIGNATURE
COMMENTS
COLOR
SUFFIX
REASON FOR
SUBMISSION
MANUFACTURING
LOCATION
BUYER
CODE
PART
NAME
SUPPLIER
NAME
DRAWING
NUMBER
PART
NUMBER
Appendices
59
60
Appendices
Appendix C
DaimlerChrysler
Production
Part
Production Part
Approval
Approval
DimensionalDimensional
Results
Results
SUPPLIER
PART NUMBER
PART NAME
ITEM
May
1995
DIMENSION/SPECIFICATION
CFG-1003
Page
of
SIGNATURE
61
TITLE
Pages
OK
DATE
NOT
OK
62
Appendices
Appendix D
DaimlerChrysler
Production Part
Approval
Approval
Production
Part
Material TestMaterial
Results Test Results
SUPPLIER
PART NUMBER
NAME OF LABORATORY
PART NAME
TYPE OF
TEST
May
1995
CFG-1004
Page
of
SIGNATURE
63
Pages
OK
TITLE
DATE
NOT
OK
64
Appendices
Appendix E
Daimler Chrysler
SUPPLIER
PART NUMBER
NAME OF LABORATORY
PART NAME
REF.
NO.
May
1995
REQUIREMENTS
CFG-1005
TEST QTY.
FREQ. TESTED
SIGNATURE
65
Page
of
OK
TITLE
DATE
Page
NOT
OK
66
Appendices
Appendix F
Bulk Material - Specific Requirements
F.1 Introduction
A supplier of bulk materials shall comply with the requirements in this Appendix or use guidance herein for clarification
of PPAP. This document is a minimum requirement and may be supplemented at the discretion of the supplier and/or
the customer.
F.2 Applicability
OEM PPAP approval of a bulk material eliminates the need to complete PPAP for that material at other levels in the
supply chain.
Suppliers are responsible for applying PPAP to their subcontractors of ingredients which have supplier-designated
special characteristics.
Examples of bulk material include, but are not limited to: adhesives and sealants (solders, elastomers); chemicals
(rinses, polishes, additives, treatments, colors/pigments, solvents); coatings (top coats, undercoats, primers, phosphates,
surface treatments); engine coolants (antifreeze); fabrics; film and film laminates; ferrous and non-ferrous metals
(bulk steel, aluminum, coils, ingots); foundry (sand/silica, alloying materials, other minerals/ores); fuels and fuel
components; glass and glass components; lubricants (oils, greases, etc.); monomers, pre-polymers and polymers (rubbers,
plastics, resins and their precursors); and performance fluids (transmission, power steering, brake, refrigerant).
PPAP does not require a Process FMEA or Control Plan for the customer process. Since the product is frequently two
products (bulk and finished), there is a shared responsibility for the final product attribute. For example, percent solids
and viscosity of a bulk coating which impacts the final coatings film build attribute, may be affected by the customers
mix room percent solvent reduction. The percent reduction process parameter may therefore be controlled to aid in
control of film build. The process steps at customer plants may be matrixed versus the Special Characteristics (determined
jointly by supplier and customer). Where high impact is evident, those process steps may be analyzed by the Process
FMEA methodology.
The Special Characteristics may then be determined, and be included in a Control Plan for the customer process. These
special control characteristic items may be monitored and continuously improved.
F.3.3 Customer Plant Connection - Guidelines
The following is a recommended set of guidelines for the customer plant when implementing process controls for bulk
materials.
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
Assemble cross-functional teams of customer personnel for each customer process area. Include appropriate
supplier representatives on each team.
Select Champions for each team - these are the customer process owners (i.e. chief process engineer, area
supervisor, etc.).
Define critical customer handling, application steps and process parameters in each area.
Review the suppliers Design Matrix and Design FMEA items for application functions which have been
designated as Special Characteristics. Also review the desired final product attributes for items needing
control.
From #4, develop a list of Special Characteristics and Attributes.
Construct a Customer Process Matrix, using #3 as the top, and #5 as the side of a matrix.
Perform a Customer Process FMEA, focusing on the high impact customer process areas which impact the
Special Characteristics. (Do the PFMEA per Appendix F).
Determine Special Characteristics from the Customer Process Matrix and PFMEA (e.g. paint fluid flow,
gun distance, etc.).
Prepare a Control Plan for each affected customer process area. The plan (utilize DaimlerChrysler, Ford,
GM APQP guidelines) might contain at a minimum all process steps containing Special Characteristics.
Monitor and record all Special Characteristics by appropriate means (control charts, checklists, etc.).
Ensure stability of Special Characteristics and continuously improve where possible.
Dirt Check
Film Build
Sags
Popping
Peel
Hiding
Adhesion
paint %
reduction
1
3
2
2
3
1
1
paint
fluid
flow
1
3
3
3
2
3
1
ance
2
2
2
3
3
1
1
2
2
2
2
2
1
1
3
2
1
1
2
1
1
68
1
3
3
2
2
3
1
box
3
1
1
1
1
1
1
bake
temp
idity
1
1
1
3
1
1
1
3
1
1
1
2
1
1
1
1
2
3
2
1
3
Appendices
69
70
over
under
1
3
250
275
70
110
UNITS
minutes
megaohms
#4 Ford Cup
%N.V. @ 110C
% Molar Comp.
Formula Wgt.
Formula Wgt.
Total Solids
Total Solids
Binder Solids
Binder Solids
Binder Solids
2
3
3
2
1
2
1
1
2
2
1
3
2
1
1
1
1
3
2
No Telegraphing
1
1
1
1
1
1
1
1
1
2
1
2
1
1
1
1
1
1
1
No Pinholing
1
1
3
2
1
1
1
1
1
1
1
1
1
1
1
1
1
2
1
No Mudcracking
1
1
2
1
1
1
2
1
0
1
1
1
1
1
1
1
1
2
1
1
1
2
3
1
1
0
1
1
1
1
1
3
1
1
1
1
Crater Free
0
1
1
1
2
3
1
1
2
2
1
2
1
1
2
1
1
2
1
2
3
2
2
1
1
0
2
3
0
1
0
1
1
1
0
1
1
1
1
2
1
1
0
1
1
1
1
1
1
1
1
1
1
1
1
1
2
1
1
0
1
1
1
1
2
2
1
1
1
1
1
1
1
1
1
1
0
1
1
1
1
2
3
1
1
1
1
1
1
1
2
1
1
0
1
1
1
1
2
3
1
1
1
1
1
1
1
1
1
1
0
1
1
1
1
2
2
1
1
1
1
1
1
1
1
1
1
0
1
1
1
1
2
2
1
1
1
1
1
1
1
2
1
1
0
1
1
1
1
2
3
1
1
1
1
3
2
1
1
2
2
1
3
2
1
1
1
1
1
1
1
3
Workable Visc/Atomization
0
0
0
0
1
1
2
2
3
3
3
2
3
1
1
1
1
2
2
0
0
3
3
2
3
1
2
1
2
2
1
1
3
1
1
1
0
0
2
1
2
2
1
3
3
2
1
1
1
3
1
1
2
Stable Rheology
0
0
0
0
3
3
2
2
1
2
1
2
3
1
1
2
1
2
2
Ne Edge Pull
1
1
2
1
1
1
2
2
1
3
1
1
1
1
1
1
1
2
3
1
1
1
1
1
1
1
1
0
1
1
1
1
0
0
1
1
0
0
PROCESSABILITY
PERFORMANCE
APPEARANCE
SP
under
over
0.15
Process Constraints
Batch Mixing Temp
0.01
over
Resistivity
61%
57%
over
under
30 sec
40 sec
over
under
% NV Solids
SP
under
30%
40%
1%
10%
2%
4%
5%
15%
Viscosity
Product Characteristics
Crosslinker-Imino (-NH) %
over
under
over
under
under
under
Alcohol Solvent
Ingredient Characteristics
Resign A-Viscosity
under
over
1.00%
2.00%
under
over
2.5%
30%
0.50%
under
over
over
35%
20%
over
under
25%
over
under
40%
50%
under
Solvent D
Color Dispersion-B
Formula Ingredients
FAILURE
SP
SP
SP
Crosslinker
Resin B
Resin A
CATEGORY /
CHARACTERISTICS
Project #: 00001
1
1
1
1
2
3
2
1
2
2
1
1
2
2
3
2
3
2
2
3
3
1
1
1
1
1
1
1
1
1
1
1
2
1
1
1
2
1
POTENTIAL CAUSES
ENVIRONMENTAL
Low/Acceptable VOC
1
2
1
2
1
1
3
1
1
1
1
1
1
0
1
1
2
1
3
Low/Acceptable Odor
1
3
1
1
0
1
1
1
1
0
0
0
0
0
1
1
2
1
2
1
1
0
0
1
1
1
1
1
1
1
1
1
0
1
1
3
1
3
HAPS Compliant
Appendices
Difference
Special Characteristics
and/or Key Product and
Key Control
Characteristics
Clarification
Example
71
Item B (Paint)
Item C (Sealant)
% Solids Resin A
Polymer Viscosity
Supplier (Tier I)
Bulk Product Characteristic
Supplier (Tier I)
Bulk Product Characteristic
Supplier (Tier I)
Bulk Product Characteristic
Paint Viscosity
% UVA intended
% Polymer in Sealant
Supplier (Tier I)
Mfg. Control Characteristic
Supplier (Tier I)
Mfg. Control Characteristic
Supplier (Tier I)
Mfg. Control Characteristic
Scale Calibration
Customer Transformation
Control Characteristic
Customer Transformation
Control Characteristic
Customer Transformation
Control Characteristic
% Solvent Reduction
Excellent Durability
Appendices
The goal for each of the items that multiply to arrive at the Risk Priority Number is to differentiate between the
items in that category. The following figure provides a guideline for severity rankings. If your situation only
uses a small portion of the scale then develop your own scale to improve the differentiation. If your situation
is greater than two tiers back from the final consumer, then the guideline figure should be adjusted to reflect
the effects that will be felt by your customers customer.
Effects of Failure and Severity Rankings:
Stakeholder
Effects of Failure
Severity
Consumer
(e.g. vehicle buyer)
10
8
6
4
Customer
(e.g. vehicle
manufacturer)
10
9
8
7
7
7
5
4
3
73
Occurrence Matrix:
Formulation Occurrence
Ranking
FREQUENCY
Type of Evidence
LOW
MODERATE
HIGH
Actual Experience
Similar Experience
Assumption
No Background
Actual Experience:
Similar Experience:
Assumption:
10
Obtained from appropriate experimentation on the specific final product
and the potential failure mode.
Based upon similar products or processes and the potential failure mode.
Based upon a clear understanding of the chemical impact of the material
and the potential failure mode.
Design controls identified by a number should be available so that the relevant content of that control can be understood.
F.7.5 Likelihood of Detection Rankings
The next step provides an alternate method for assigning Detection rankings.
Rank Detection - the ranking scale in the Potential Failure Mode and Effects Analysis manual is difficult to
relate to bulk materials and generally results in very low numbers with little differentiation in the ultimate risk.
The following matrix may be used. It evaluates the Detection as the ability of the current Design Control to
actually detect a cause of failure and/or failure mode based upon the assessed R&Rs percent of specification
range and the quality of evidence.
74
Appendices
Detection Matrix:
Detection by Design
Control
Quality of Evidence
< 30%
30% - 100%
> 100%
Screening Experiments
Assumption/Experience
No Evidence
DOE (Response Surface Analysis):
Screening Experiments:
Assumption/Experience:
10
Symmetric design space analyzed with appropriate statistical tools.
Screening design or ladder evaluation strategically set to develop DOE.
Information/data based upon similar products or processes.
NOTE: The above R&R limits are suggested unless otherwise agreed upon by the customer and the supplier.
R&R calculations can initially be based using design matrix thresholds.
Ranking
Very High: Potential failure mode may result in a field failure (9), or constitute a safety hazard or
noncompliance with a government regulation (10).
9 - 10
High: High degree of customer dissatisfaction due to the nature of the failure. May cause serious
disruption to subsequent processing of the product or result in the product failing to meet its sales
specifications. Will result in a customer complaint and product return. Failure is likely to be detected
during the customers final product testing.
7-8
Moderate: Failure causes some customer dissatisfaction and may result in a customer complaint or
limitation on shelf life. The customer may need to make modifications or adjustments to their process to
accommodate the material. The problem is likely to be detected as part of an incoming inspection or
prior to use (4). The problem will be detected during processing (5). The problem will be detected in
subsequent processing steps (6).
4-6
Low: Failure causing only a slight customer annoyance. Customer will notice only a slight deterioration
or inconvenience with the product or processing of the product.
2-3
Minor: Reasonable to expect that the minor nature of this failure would not cause any real effect on the
product or its processing by the customer. Customer will probably not even notice the failure.
75
OCCURRENCE RANKINGS
Frequency of Failure
Ranking
Very High: Failure is almost inevitable. Additional process steps are developed to deal with the failures.
9 - 10
High: Similar processes have experienced repeated failures. The process is not in statistical control.
7-8
Moderate: Similar processes have experienced occasional failures, but not in major proportions. Process
is in statistical control.
4-6
Very Low: Almost identical processes have experienced only isolated failures.
Remote: Failure is unlikely. No failures ever associated with almost identical processes. The process is in
statistical control.
DETECTION RANKINGS
Likelihood and Location in the Process the Defect is Detected
Ranking
Absolute Certainty of Non-Detection: Controls will not or cannot detect the existence of the defect.
10
Very Low: Supplier controls probably will not detect the existence of the defect, but the defect may be
detected by the customer.
Low: Controls may detect the existence of the defect, but detection may not occur until packaging is
underway.
7-8
Moderate: Controls likely to detect the existence of the failure, but not until lot acceptance testing has
been completed. Tests with a higher degree of variability will have the higher ranking.
5-6
High: Controls have a good chance of detecting the existence of the defect before the manufacturing
process has been completed. In-Process testing is used to monitor the manufacturing process.
3-4
Very High/Early: Controls will almost certainly detect the existence of the defect before the product
moves onto the next step in its manufacturing process. Important raw materials are controlled via
supplier specifications.
1 -2
Appendices
normal production.
Production - Documentation of the product/process control characteristics, process controls affecting Special
Characteristics, associated tests, and measurement systems employed during normal production. Additional
items may be included at the Suppliers discretion.
Pre-launch and production control plans may be applied to a family of products or specific processes.
77
Project:
Primary Responsibility
Customer
Supplier
Required /
Target Date
Product Design and Development Verification
Design Matrix
Design FMEA
Special Product Characteristics
Design Records
Prototype Control Plan
Appearance Approval Report
Master Sample
Test Results
Dimensional Results
Checking Aids
Engineering Approval
Process Design and Development Verification
Process Flow Diagrams
Process FMEA
Special Process Characteristics
Pre-launch Control Plan
Production Control Plan
Measurement System Studies
Interim Approval
Product and Process Validation
Initial Process Studies
Part Submission Warrant (CFG-1001)
Elements to be completed as needed
Customer Plant Connection
Change Documentation
Subcontractor Considerations
Company/Title/Date
78
Comments /
Conditions
Approved
by / date
Appendices
79
Batch
Number 1X97
Formula
Date: 1/18/97
TESTING INFORMATION
Name
Test Method
Specifications
Wt/Gallon
TM001
10.50 - 10.70
% Non Volatile
TM004
57 - 61%
Viscosity
TM003
30 - 40 Secs
Ingredients
Amt.
Date/Time
1000 Lbs.
999 Lbs.
AB345
12/5/97 9.35 AM
Resin B
500 Lbs.
501 Lbs.
CD678
12/5/97 10.00 AM
100 Lbs.
100 Lbs.
FILLING INSTRUCTIONS
Containers
Filtering
25 Micron Bag
Labeling
Per contract
80
AC250
Initials
12/5/97 10.25 AM
Operator
Initials
Appendices
12/5/97
Batch #
Gallons
Wt/Gallon
TM001
10.50 - 10.70
% non Volatile
TM004
57 - 61%
Viscosity
TM003
30 - 40 Secs
1000
10.59
59.6
34
Batch Size
1X97
Initials
Remarks
Ok
Certificate of Analysis
Material Name: Filmformer Resin
Lot/Batch #: AB345
Min.
Max.
Lot/Batch
57%
61%
58.8%
7.3
7.2
Result
% Non Volatile
(TM004)
pH
(TM005)
Certification Signature:
Date:
81
21.
22.
23.
24.
25.
26.
27.
28.
82
Appendices
PRODUCT NAME:
SUPPLIER CODE:
ENG. SPEC.:
MANUF. SITE:
PART #:
ENG. CHANGE #:
FORMULA DATE:
RECEIVED DATE:
RECEIVED BY:
10
SUBMISSION LEVEL:
11
EXPIRATION DATE:
12
TRACKING CODE:
13
RE-SUBMISSION DATE:
14
15
Design Matrix:
DFMEA:
Engineering Approval:
Control Plans:
PFMEA:
Test Results:
Process Studies:
Dimensional Results:
Master Sample:
17
18
19
21
22
PROGRESS REVIEW DATE:
DATE MATERIAL DUE TO PLANT:
WHAT ACTIONS ARE TAKING PLACE TO ENSURE THAT FUTURE SUBMISSIONS WILL CONFORM
TO BULK MATERIAL PPAP REQUIREMENTS BY THE SAMPLE PROMISE DATE?
23
24
PHONE:
(PRINT NAME)
DATE:
PHONE
25
(PRINT NAME)
MATERIALS ENG. (SIGNATURE)
26
(PRINT NAME)
QUALITY ENG. (SIGNATURE)
27
(PRINT NAME)
INTERIM APPROVAL NUMBER:
28
83
DATE
PRODUCT NAME:
SUPPLIER CODE:
ENG. SPEC.:
MANUF. SITE:
PART #:
ENG. CHANGE #:
FORMULA DATE:
RECEIVED DATE:
RECEIVED BY:
SUBMISSION LEVEL:
EXPIRATION DATE:
TRACKING CODE:
RE-SUBMISSION DATE:
DFMEA:
Engineering Approval:
Control Plans:
PFMEA:
Test Results:
Process Studies:
Dimensional Results:
Master Sample:
PHONE:
(PRINT NAME)
DATE:
PHONE
84
DATE
Appendices
Appendix G
TIRE INDUSTRY - SPECIFIC REQUIREMENTS
G.1 INTRODUCTION AND APPLICABILITY
A supplier of tires shall comply with the requirements of PPAP and use this appendix as guidance for clarification of
requirements. These guidelines are based on existing approved practices between the tire supplier and the OEM.
Design tests used by each OEM to select tire construction (technical approval), reduces the need to repeat all tests
during PPAP. Specific PPAP confirmation tests are specified by each OEM.
G.2 GUIDELINES FOR PPAP PROCESS REQUIREMENTS (REFERENCE SECTION I.2)
Significant Production Run (I.2.1)
Unless otherwise specified by the OEM, the size of the production run for the PPAP parts is to be determined by the
supplier. Current industry practice requires a minimum of 30 tires. The typical development of a new tire design
involves multiple builds of a small quantity of tires. Most designs are basic to the suppliers process. For the tire
industry, PPAP is typically completed with an initial mold or molds, and well in advance of customer requirements for
large volume production. PPAP is not required for additional molds that are brought on line in the approved production
process; however, for additional molds, the suppliers internal certification criteria and documentation are utilized.
The PPAP for the tire industry typically is derived from 1 to 8 hours of tire curing from the approved production
process as specified in the suppliers control plan. Subsequent parts from duplicate assembly lines for volume production
are not required to be represented in the PPAP sample, nor are additional PPAP submissions required.
The above definition for Significant Production Run applies to subsequent sections of I.2.
Tire industry practice defines tooling as a tire mold. This definition of tooling applies to all sections of PPAP.
Part Weight (Mass) (Reference I.2.2.13.1)
The tire industry practice is to weigh a specified number of PPAP tires to two (2) significant decimals (xx.xx). The
average is reported on the PSW to four (4) decimals (xx.xxxx).
Appearance Approval Report (AAR) (Reference I.2.2.14)
Tires are not an appearance item for the OEMs, consequently the AAR requirement is not applicable.
Material Test Results (Reference I.2.2.8.1)
Testing is applicable only to finished tires and not to raw materials. Tire industry practice does not require chemical,
physical or metallurgical testing.
Process Flow Diagrams (Reference I.2.2.5)
Process flow diagrams may be generic for families of similar parts.
Process Failure Mode and Effects Analysis (Reference I.2.2.6)
Tire industry practice is to have a generic process FMEA for a family of similar parts.
Design Failure Mode and Effects Analysis (Reference I.2.2.4)
Tire industry practice is to have a generic design FMEA for a family of similar parts.
85
86
Glossary
GLOSSARY
For additional related definitions, Refer to the Statistical Process Control reference manual, Measurement Systems
Analysis reference manual, and QS-9000, Third Edition.
ACCREDITED LABORATORY is one that has been reviewed and approved by a nationally-recognized accreditation
body [e.g. American Association for Laboratory Accreditation (A2LA) or the Standards Council of Canada (SCC)] for
test laboratory accreditation to ISO/IEC Guide 25 or its replacement, or national equivalent.
ACTIVE PART is one currently being supplied to the customer for original equipment or service applications. The
part remains active until tooling scrap authorization is given by the appropriate customer activity. For parts with no
customer-owned tooling or situations where multiple parts are made from the same tool, written confirmation from the
customer Purchasing activity is required to deactivate a part.
NOTE: For bulk material, active part refers to the bulk material contracted, not the parts that are subsequently
produced from that material.
AGREEMENT - used only for bulk material PPAP herein and refers to a situation where the customer and supplier
understand the boundaries of an issue without requiring signatures or records documenting the specifics.
APPEARANCE ITEM is a product that is visible once the vehicle is completed. Certain customers will identify
appearance items on the engineering drawings. In these cases, special approval for appearance (color, grain, texture,
etc.) is required prior to production part submission.
APPROVED is used in PPAP to mean that the parts, materials and/or related documentation or records submitted to,
or reviewed by, the customer meet all customer requirements. After full or interim approval, the supplier is authorized
to ship product as directed by the customer. For bulk material PPAP only: 1) approval requires a signature or record
of a verbal approval; 2) Any record of verbal approval shall include the date, scope of the approval, the name of the
customer representative granting the approval, and the name of the supplier representative involved; 3) The term
customer agreement does not require signatures or records.
APPROVED DRAWING is an engineering drawing signed by the engineer and released through the customers system.
APPROVED MATERIALS are materials governed either by industry standard specifications (e.g. SAE, ASTM,
DIN, ISO) or by customer specifications.
APPROVED SOURCE LIST is a list of suppliers and sub-suppliers that have been found to be acceptable to the
customer. Utilizing product from an approved sub-supplier does not relieve the direct supplier of responsibility for the
quality of that product.
ATTRIBUTES DATA are qualitative data that can be counted for recording and analysis. Examples include the
presence or absence of a required label, the installation of all required fasteners. Attributes data are not acceptable for
production part submissions unless variables data cannot be obtained.
BULK MATERIAL is a substance (e.g. non-dimensional solid, liquid, gas) such as adhesives, sealants, chemicals,
coatings, fabrics, lubricants, etc. A bulk material may become production material if issued a customer production part
number (PRODUCTION MATERIAL).
87
BULK MATERIAL REQUIREMENTS CHECKLIST defines the customer PPAP requirements for bulk material.
(See Appendix F).
CAD/CAM MATH DATA is a form of design record by which all dimensional information necessary to define a
product is conveyed electronically. When this design record is used, the supplier is responsible for obtaining a drawing
to convey results of dimensional inspection.
CALIBRATION is a set of operations which compare values taken from a piece of inspection, measuring and test
equipment or a gage to a known standard under specified conditions.
CAPABILITY is the total range of inherent variation in a stable process. (see Statistical Process Control reference
manual)
CHECKED PRINT is a released engineering drawing with actual measurement results recorded by the supplier
adjacent to each drawing dimension and other requirements.
CONFORMANCE means that the part or material meets the customers specifications and requirements.
CONTROL - see STATISTICAL CONTROL
CONTROL CHARTS - see Statistical Process Control reference manual.
CONTROL PLANS are written descriptions of the system for controlling production parts or bulk materials and
processes. They are written by suppliers to address the important characteristics and engineering requirements of the
product. Each part must have a Control Plan, but in many cases, family Control Plans can apply to a number of parts
produced using a common process. Refer to Advanced Product Quality Planning and Control Plan reference
manual and QS-9000 Section II for customer-specific requirements.
CRITICAL CHARACTERISTIC: Ford definition: Critical characteristics are those product requirements (dimensions,
performance tests) or process parameters that can affect compliance with government regulations or safe vehicle/
product function and which require specific supplier, assembly, shipping, or monitoring and inclusion on Control
Plans. Critical characteristics are identified with the inverted delta symbol.
CRITICAL CHARACTERISTIC: GM definition: See Key Product Characteristics.
CUSTOMER is the activity that has contracted to buy the product.
CUSTOMER PRODUCT APPROVAL ACTIVITY is the customer location assigned responsibility for supplier
PPAP approval.
NOTE: Some customers assign this responsibility geographically, while others use the procuring division.
DESIGN-INTENDED ROBUST RANGE are limits within which parameters may be allowed to vary while still
ensuring that a product complies with fitness for use requirements.
DESIGN RECORD is the part drawing, specifications, and/or electronic (CAD) data used to convey information
necessary to produce a product.
DOCUMENTATION is material (typically paper or electronic) defining the process to be followed, e.g. quality
manual, operator instructions, graphics, pictorials.
88
Glossary
ENVIRONMENT is defined as all of the process conditions surrounding or affecting the manufacture and quality of
a part or product. Environment will vary for each site, but generally includes: housekeeping, lighting, noise, HVAC,
ESD controls, and safety hazards relating to housekeeping. See Production Environment.
FAILURE MODE AND EFFECTS ANALYSIS (FMEA) is systematized technique which identifies and ranks the
potential failure modes of a design or manufacturing process in order to prioritize improvement actions. Refer to
Potential Failure Modes and Effects Analysis reference manual.
FULL APPROVAL used in PPAP to indicate that the part or production material meets all customer specifications and
requirements. The supplier is therefore authorized to ship production quantities of the part or material subject to
releases from the customer scheduling activity.
GAGE REPEATABILITY AND REPRODUCIBILITY (Gage R&R) - Refer to the Measurement System Analysis
reference manual.
INITIAL PROCESS STUDY is a short-term study conducted to obtain early information on the performance of new
or revised processes relative to internal or customer requirements. In many cases, preliminary studies should be conducted
at several points in the evolution of new processes (e.g., at the equipment or tooling subcontractors plant, after installation
at the suppliers plant). These studies should be based on as many measurements as possible. When utilizing X-Bar
and R charts, at least twenty-five subgroups (minimum of four pieces per subgroup) are required to obtain sufficient
data for decision making. When this amount of data is not available, control charts should be started with whatever data
is available. (Refer to the Statistical Process Control reference manual.)
INITIAL SAMPLE is a term previously used for production part submissions.
INTERIM APPROVAL used in PPAP to permit shipment of products for a specified time period or quantity. Since
not all customers allow interim approvals, consult your responsible customer product approval activity.
KEY CONTROL CHARACTERISTICS (KCCs) are those process parameters for which variation must be controlled
around a target value to ensure that a significant characteristic is maintained at its target value. KCCs require ongoing
monitoring per an approved Control Plan and should be considered as candidates for process improvement.
KEY DESIGN CHARACTERISTICS (DaimlerChrysler Corporation) - Toleranced and measurable characteristics
of a part, system, and/or assembly which may have an adverse or degrading effect on the function, quality, or reliability
of that part or system if an out of tolerance condition occurs. A Shield symbol is used to designate a key design
characteristic on components, systems or assemblies that have a safety or regulatory designation. On all other components
or systems, the key design characteristics are designated by the Diamond symbol. Good judgment should be used when
designating key design characteristics, as some designs have more robustness than others or the manufacturing process
may not be susceptible to variation.
KEY PROCESS CHARACTERISTICS (DaimlerChrysler Corporation) - Key Process characteristics are measurable
elements of the process used to manufacture or assemble a component or system that have significant impact on the
function, quality and/or reliability of that component or system. With a process characteristic, an actual element of the
process is measured, as opposed to a Key Design Characteristic where the measurement is taken at the component or
assembly.
KEY PRODUCT CHARACTERISTIC (KPC) are those product features that affect subsequent operations, product
function, or customer satisfaction. KPCs are established by the customer engineer, quality representative, and supplier
personnel from a review of the Design and Process FMEAs and must be included by the supplier in the Control Plan.
Any KPCs included in customer-released engineering requirements are provided as a starting point and do not affect
the suppliers responsibility to review all aspects of the design, manufacturing process, and customer application and to
determine additional KPCs.
89
LABORATORY is a test facility that may include chemical, metallurgical, dimensional, physical, electrical, reliability
testing or test validation.
LABORATORY SCOPE is quality record containing the following:
the specific tests, evaluations and calibrations a supplier laboratory has the ability and competency to perform
a list of the equipment which it uses to perform the above
a list of the methods and standards to which it performs the above.
MARKED PRINT is an engineering drawing modified, signed and dated by the customer engineer (the engineering
change number must be included).
MEASUREMENT SYSTEM ANALYSIS STUDIES - Refer to the Measurement System Analysis reference manual.
PART SUBMISSION WARRANT is an industry-standard document required for all newly-tooled or revised products
in which the supplier confirms that inspections and tests on production parts show conformance to customer requirements.
PERISHABLE TOOLS are drill bits, cutters, inserts, etc. used to produce a product and which are consumed in the
process.
PROCESS is a combination of people, equipment, methods, materials, and environment that produces output, a given
product or service. A process can involve any aspect of a business.
PROCESS FLOW DIAGRAM depicts the flow of materials through the process, including any rework or repair
operations.
PRODUCTION ENVIRONMENT is the manufacturing location within the production site which includes the
production tooling, gaging, process, materials, operators, environment, and process settings, e.g. feeds, speeds, cycle
times, pressures, temperatures, quoted line rate. Environment is defined as all of the process conditions surrounding or
affecting the manufacture and quality of a part or product. Environment will vary for each site, but generally includes:
housekeeping, lighting, noise, HVAC, ESD controls, and safety hazards relating to housekeeping.
PRODUCTION MATERIAL is material which has been issued a production part number by the customer and is
shipped directly to the customer.
PRODUCTION PART is manufactured at the production site using the production tooling, gaging, process, materials,
operators, environment, and process settings, e.g., feeds/speeds/cycle times/pressures/temperatures.
PRODUCTION PART APPROVAL SUBMISSION is based on specified quantities of production parts or production
materials taken from the significant production run made with production tooling, processes, and cycle times. These
parts or materials submitted for production part approval are to be verified by the supplier as meeting all specified
requirements from the design record.
QUALITY INDICES are defined herein as either Cpk or Ppk for purposes of PPAP. See the Statistical Process
Control reference manual.
QUALITY PLANNING is a structured process for defining the methods (i.e., measurements, tests) that will be used
in the production of a specific product or family of products (i.e., parts, materials). Quality planning embodies the
concepts of defect prevention and continuous improvement as contrasted with defect detection (see Advanced Product
Quality Planning and Control Plan reference manual).
90
Glossary
QUALITY RECORD is documented evidence that the suppliers processes were executed according to the quality
system documentation, e.g. test results, internal audit results, calibration data, and which records the results. See QS9000, cl. 4.16.
REGULAR PRODUCTION TOOLING is the tooling with which the manufacturer intends to produce production
product.
REJECTED used in PPAP to mean that the production part submission and/or documents did not meet the customers
requirements. The supplier must correct the production process and a make a new submission. (Advise the customers
Purchasing activity of the date when corrected parts will be available.) Do not ship production parts until the customer
approves the corrected parts. The customer may withhold tooling payments until part approval is obtained.
REMOTE LOCATION is a location at which production processes do not occur, e..g. does not fit the definition given
for Site, but which support such sites.
REPEATABILITY AND REPRODUCIBILITY (R&R) Refer to Measurement System Analysis reference manual.
SAFETY CHARACTERISTICS (DaimlerChrysler Corporation Definition) are specifications which require special
manufacturing control to assure compliance with DaimlerChrysler Corporation or government vehicle safety
requirements.
SALEABLE PRODUCT - generally refers to the product specified on the contract between the supplier and customer.
SELF-CERTIFYING SUPPLIER - is a supplier that an authorized customer representative has designated as selfcertifying, which means that the supplier submits the PSW (e.g. Level 1 PPAP) to the customer, but the response from
the customer is not necessary. This designation is to be documented. The PSW submittal from a self-certifying
supplier results in a simultaneous approval status by the customer for that submittal, which may not be a full
approval.
SIGNIFICANT PRODUCTION RUN is manufacture of a lot consisting of a minimum of 300 consecutive pieces, or
other quantity as agreed to by the customer product approval activity, and from a minimum of one hour of production
from the production environment.
SITE is defined as a supplier or subcontractor location at which value-added processes occur. Site also includes
distributors of parts manufactured by other companies. External locations which only stage material for onward shipment,
indirect material suppliers or assembly plants are not included. Providers of bulk or raw materials should contact their
procuring division buyer to determine if their material is considered to be production material.
SPECIAL CHARACTERISTICS - see Critical Characteristic or Key Product Characteristic. Reference individual
Truck Supplier Quality requirements for their definition. For bulk materials, see Appendix F.
SPECIFICATIONS are engineering requirements for judging the acceptability of a part or bulk material characteristic.
For the production part approval process, every feature of the product as identified by engineering specifications must
be measured. Actual measurement and test results are required. Specifications should not be confused with control
limits which represent the voice of the process.
STABLE PROCESSES are processes that are in statistical control. Variation in the output of a stable process arises
only from common causes. A stable process is predictable. For initial process studies performed prior to production
part submission, tests for stability may not be as rigorous as those used for ongoing processes.
91
SUBCONTRACTORS are defined as providers of production materials, or production or service parts, directly to a
supplier to DaimlerChrysler Corporation, Ford, General Motors or other customers requiring this document. Also
included are providers of heat treating, painting, plating or other finishing services.
SUPPLIERS are defined as providers of: a) production materials, b) production or service parts, or c) heat treating,
plating, painting or other finishing services, directly to DaimlerChrysler Corporation, Ford, or General Motors or other
customers requiring this document, e.g. Heavy Truck OEMs.
STATISTICAL CONTROL is the condition of a process from which all special causes of variation have been eliminated
and only common causes remain. Statistical control is evidenced on a control chart by the absence of points beyond the
control limits and by the absence of any non-random patterns or trends. (STATISTICAL CONTROL is a descriptive
term for a STABLE PROCESS.)
SUBMISSION LEVEL refers to the level of evidence required for production part submission (reference I.4.1 of this
document).
TOOL is defined as the portion of process machinery which is specific to a component or sub-assembly. Tools (or
tooling) are used in process machinery to transform raw material into a finished part or assembly.
TOOLING MAINTENANCE is the periodic sharpening, polishing, or other servicing of a tool. This maintenance
will not significantly affect the dimensions or other characteristics of the product produced by the tool. (contrasts with
TOOLING REFURBISHMENT)
TOOLING REFURBISHMENT is the major overhaul of a tool. Refurbishment can affect dimensions or other
characteristics of the product produced by the tool. Production part approval submission of product made with refurbished
tools is required before such product may be shipped to the customer.
VALIDATION is confirmation by examination and provision of objective evidence that the particular requirements for
specific intended use are fulfilled.
VARIABLES DATA are quantitative results where measurements are used for analysis. Examples include the diameter
of a bearing journal in millimeters, the closing effort of a door in newtons, the concentration of an electrolyte in
percent, and the torque of a fastener in newton-meters.
VERIFICATION is confirmation by examination and provision of objective evidence that specified requirements
have been fulfilled.
WARRANT - see Part Submission Warrant.
92