Design of Launching Aprons On U/S and D/s Side

This document provides design specifications for improvements to a road and construction of a minor bridge. For the road, it specifies launching aprons of 2.80 meters on the upstream side and 3.70 meters on the downstream side. For the bridge, it specifies launching aprons of 1.50 meters on the upstream side and 3.00 meters on the downstream side. Both projects require cutoff walls of 0.6 meters thick and 1.00-1.50 meters deep depending on location to support the structures.
Copyright
© © All Rights Reserved
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
36 views

Design of Launching Aprons On U/S and D/s Side

This document provides design specifications for improvements to a road and construction of a minor bridge. For the road, it specifies launching aprons of 2.80 meters on the upstream side and 3.70 meters on the downstream side. For the bridge, it specifies launching aprons of 1.50 meters on the upstream side and 3.00 meters on the downstream side. Both projects require cutoff walls of 0.6 meters thick and 1.00-1.50 meters deep depending on location to support the structures.
Copyright
© © All Rights Reserved
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
You are on page 1/ 3

N.W.

:- Improvements to Lakkavaram - Sankaraguptam road from km 0/0 to


3/0 in E.G.Dt. (Reconstruction of HLB across Sankaraguptam Major
Drain in km 2/2 of Lakkavaram - Sankaraguptam Road)
Design of Launching aprons on U/S and D/s side
dsm
HFL
SILL
Max scour depth
Max scour level
THICKNESS OF RAFT
top of raft level

=
=
=
=

1.145
0.58
-1.1
1.454
-0.874
=
0.6
=
-2.1
i.e.
say
Hence no scour below bed level
Appron on u/s
=
1.5X1.82
=
2.8
Appron on D/s
=
2X1.82
=
3.7

m
m
m
m
m
m
m
-1.826 m below bottom of raft
1.82 (means scour)
=
M
=
M

2.73
min
3.64
min

w
0.6
1.2

hence

PROVIDE APRONS OF

2.80 M ON U/S SIDE AND


3.70 M ON D/S SIDE
Cut off walls at bottom of ras per SP13 -86 article 14

TOP OF

(HFL--dsm)

(0.58--x1.145)

-0.565

-2.10

-2.14

RAFT LEVEL

cut off wall Depth


min cut off wall Depth on U/S

1.00 M

min cut off wall Depth on D/S

1.50 M

provide cut off wall depth

1.00 m

provide cut off wall depth

1.50 m

provide cut off wall Width

0.6 m

cut off wall bottom level on U/S

-3.70

cut off wall bottom level on D/S

-4.20
-2.10
0.6 m

-2.70

1.00 m
-3.70

1.50
0.6
m
-4.20
0.6 m

NABARD DPR PROPOSALS RIDF XIX Construction of Minor


Bridge Across Chuttu Gedda @ Km 6/0-2 of Cheedikada (R&B)
Road to Konam via Manchala in Visakhapatnam District

N.W

Design of Launching aprons on U/S and D/s side


dsm
HFL
SILL
Max scour depth
Max scour level
THICKNESS OF RAFT
top of raft level

=
=
=
=
=
=

Hence no scour below bed level


Appron on u/s
=
=
Appron on D/s
=
=

1.083 m
5.82
3.67
1.375 m
4.445
0.6 m
2.67
i.e.
1.775 m below MSL
(means no scour)
1.5X0 =
1.5
M
min
2X0
3
M
min

w
0.6
1.2

hence

PROVIDE APRONS OF
Cut off walls at bottom of raft

1.50 M ON U/S SIDE AND


3.00 M ON D/S SIDE
as per SP13 -86 article 14

(HFL--1.27dsm)

(5.82--1.27x1.083) =
TOP OF

RAFT LEVEL

cut off wall Depth

4.445

2.67

-2.37

min cut off wall Depth

on U/S

1.00 M

min cut off wall Depth

on D/S

1.50 M

provide cut off wall depth

1.00 m

provide cut off wall depth

1.50 m

provide cut off wall Width

0.6 m

cut off wall bottom level on U/S

1.07

cut off wall bottom level on D/S

0.57
2.67
0.6 m

2.07

1.00 m
1.07

1.50
0.6
m
0.57
Page 2

0.6 m

Page 3