Feb10 Throughput F5
Feb10 Throughput F5
throughput
and backflush RELEVANT to ACCA QUAlification paper F5
accounting
accounting
In Example 2, contribution is the goal unit. If that Throughput = selling price – material
is maximised, so is profit, which is the goal of a per unit per unit per unit
profit-seeking organisation.
The contribution approach is not wrong in Throughput = sales revenue – cost of materials
principle, but the assumptions it makes about
cost behaviour often do not accurately reflect the Throughput is generated only when a sale is made.
reality of a modern manufacturing business. In Increasing inventory does not increase throughput.
particular, the notion that there are significant See Table 1 in Example 3 below. Available hours:
variable labour and overhead costs is suspect. 5,000 machine hours, 6,000 labour hours, 2,500
Many of these businesses rely on sophisticated quality control hours.
automated systems that run continuously with The factory is modern and highly automated.
relatively little manual involvement. Even when Despite the presentation of the information, it
production is slack, provided the downturn is is considered that all costs, except material, are
expected to be short lived, most employees will effectively fixed. The first step in managing the
still be paid because it is expensive to dismiss performance of an organisation is to discover the
workers and then to rehire and retrain them. For limits to its performance. What is the bottleneck
short-term fluctuations in production it would be resource here?
more accurate to consider labour costs and all From the data we can identify the bottleneck
overheads to be fixed, leaving material as the only resource as seen in Table 2 opposite. So the
truly variable cost. bottleneck resource, the one which limits output,
If all costs except material are fixed, businesses is machine hours. There is more than enough of the
will become richer provided the sales revenue per other two resources.
unit exceeds material price per unit. In effect, sales If the company can’t make everything it wants
price less material price is the new contribution to, it has to decide on an optimum production plan.
per unit, but to make clear what we are talking Because the factory is highly automated and material
about this is not called ‘contribution’: it is called is the only truly variable cost, throughput will be the
‘throughput’. appropriate measure to use when calculating how
In fact, ‘throughput’ is sometimes usefully known much the manufacture and sale of each unit increases
as ‘throughput contribution’: the company’s wealth (see Table 3 opposite).
table 1, example 3
table 4, example 3
Product Throughput/unit Machine hours/unit Throughput/machine hour = Rank
($) return/factory hour ($/hour)
We can’t simply conclude from this that Product This shows that priority should be given to making
A must be best because it earns more per unit Product B, the highest earner per machine
than the other products. It is essential to take into hour, then to Product A, and finally to Product C.
account the use that each product makes of the The production plan would therefore be as seen in
bottleneck resource. Here, machine hours have been Table 5 on page 5.
identified as the bottleneck resource. These are
uniquely precious and must be used up in the best
possible way.
This can be done by calculating for each unit:
Throughput
Time in bottleneck resource
The throughput/machine hour (or return/factory Products A and B are clearly worth making and
hour) shows the rate at which throughput can be selling because their earning rates (return/factory
earned when making and selling each product. hour) exceed the factory spending rate on fixed
Similarly, if the total expected non-material costs costs (cost/factory hour). Product C is more difficult
are divided by the available machine hours then the to deal with. If the factory costs are truly fixed
cost per factory hour is obtained: then Product C is still worth making as it earns a
throughput amount of $317/factory hour – which
$1,624,000/5,000 = $324.80 is a lot better than earning nothing. However, if the
fixed costs identified with Product C ( $504,000)
So, for every hour the machine operates (which could actually be avoided, then Product C should
really means for every hour the factory operates be abandoned as it costs more to run the factory to
as nothing else matters if the machine is the make the product than the product can earn.
bottleneck resource), running costs accrue at the Instead of directly comparing return/factory hour
rate of $324.80/hour. The products the factory to costs/factory hour, it is common to express these
makes earn a net $388 for Product A, $400 for amounts as ratios, known as throughput accounting
Product B and £317 for Product C. ratios (TAR), as shown in Table 6 opposite.
student accountant issue 03/2010
06
The TAR tells us nothing that we have not worked In backflush accounting, costs are not associated
out already. Its interpretation is: with units until they are completed or sold.
1 The higher the better (but we already knew Backflush accounting is sometimes called delayed
Backflush accounting
Backflush accounting is a costing short cut. It
relies on a business having immaterial amounts
of work‑in-progress and is therefore particularly
suitable for businesses operating just-in-time
inventory management. If the amount of
work‑in‑progress is negligible, what is the point in
meticulously valuing it? Fretting that some products
might be 25% complete and others 60% complete,
and then adding carefully calculated labour
and overheads to these (immaterial) items, is a
complete waste of time and effort.
07 technical
work-in-progress must be negligible. It has only one set up so that costing records encourage managers
trigger point. to adopt this goal-orientated behaviour.
As before, the cost of labour and other
manufacturing expenses are initially debited to Ken Garrett is a freelance writer and lecturer
a conversion cost account and credited to cash
or creditors.
Entries into the finished goods inventory account
are made only when goods are completed, and the
journal entries will be:
Material
Materials account
Conversion costs
To cost
of sales
Costs in Costs out
to WIP
Material
Materials account
Conversion costs
To cost
of sales
Costs in Costs out to
finished goods