The document discusses power and control cables used in electrical installations. Aluminum and copper cables insulated with XLPE and PVC are used for various applications like power supply and instrumentation. Separate cables are required for AC, DC, and different cores. Standard cable sizes are specified for different applications. Technical requirements include withstand capacities, temperature ratings, and marking. Cable installation details cover tagging, trenching, separation of cable types, bending radii, and termination lengths.
Download as PPT, PDF, TXT or read online on Scribd
0 ratings0% found this document useful (0 votes)
80 views
Power and Control Cables
The document discusses power and control cables used in electrical installations. Aluminum and copper cables insulated with XLPE and PVC are used for various applications like power supply and instrumentation. Separate cables are required for AC, DC, and different cores. Standard cable sizes are specified for different applications. Technical requirements include withstand capacities, temperature ratings, and marking. Cable installation details cover tagging, trenching, separation of cable types, bending radii, and termination lengths.
Download as PPT, PDF, TXT or read online on Scribd
You are on page 1/ 9
POWER AND CONTROL CABLES
ALUMINIUM CONDUCTOR XLPE ( CROSS LINKED POLY
EHELENE) INSULATED ARMOURED CABLES ARE USED FOR MAIN POWER SUPPLY FROM LT TRANSFORMER TO CONTROL ROOM, BETWEEN DISTRIBUTION BOARDS ( MCC ROOM TO FIREFIGHTING MCC AND MCC ROOM TO AC MCC), SUPPLY TO COLONY AND FROM DG SET TO CONTROL ROOM. ALUMINIUM CONDUCTOR PVC INSULATED ARMOURED WILL BE USED FOR VARIOUS APPLICATIONS IN SWITCHYARD AND CONTROL ROOM AREAS. FOR CONTROL/PROTECTION/INSTRUMENTATION PURPOSE PVC INSULATED ARMOURED CABLES OF MINIMUM 2.5 SQMMSIZE WITH STRANDED COPPER CONDUCTOR ARE USED. POWER AND CONTROL CABLES
SEPARATE CABLES WILL BE USED FOR AC AND DC
SEPARATE CABLES FOR DC1 & DC2
SEPARATE CABLES FOR DIFFERENT CORES OF CT & CVT
ATLEAST ONE CORE SHALL BE KEPT AS SPARE IN COPPER
CONTROL CABLES OF 4C,5C & 7C SIZES AND TWO CORES SHALL BE KEPT AS SPARE IN 10C OR HEIGHER SIZES. STANDARDISATION OF POWER CABLES
LT TRANSFORMER TO MAIN SWITCH BOARD : 2-1C X
630SQMM PER PHASE, 1-1C X 630SQMM FOR NEUTRAL, XLPE MSB TO ACDB : 2-3 1/2C X 300SQMM, XLPE MSB TO AIR COND.BOARD: 1-3 1/2C X 300SQMM, XLPE MSB TO OIL FILTRATION UNIT: 1-3 1/2C X 300SQMM, XLPE MSB TO COLONY LIGHTING: 1-3 1/2C X 300SQMM, XLPE MSB TO OIL FIRE FIFGT. BOARD: 1-3 1/2C X 300SQMM, XLPE MSB TO OIL LIGHTING TRANS.: 1-3 1/2C X 300SQMM, XLPE MSB TO OIL DG SET AMF: 1-3 1/2C X 300SQMM, XLPE MSB TO MAIN LIGHT. DB: 1-3 1/2C X 300SQMM, XLPE ACDB TO BAY MB : 1-3 1/2C X 35SQMM, XLPE DCDB TO BATTERY & CHARGER: 1-2C X 300SQMM, XLPE TECHNICAL REQUIREMENTS FOR CABLES
THE CABLES SHALL BE SUITABLE FOR LAYING IN
RACKS,DUCTS,TRENCHES,CONDUITS AND UNDER GROUND BURIED INSTALLATION WITH UNCONTROLLED BACK FILLING AND CHANCES OF FLOODING BY WATER. CABLES SHALL BE DESIGNED TO WITHSTAND ALL MECHANICAL, ELECTRICAL AND THERMAL STRESSES UNDER STEADY STATE AND TRANSIENT OPERATION CONDITION. THE XLPE/PVC POWER CABLES OF SIZES 240SQMM AND ABOVE SHALL BE WITHSTAND WITHOUT DAMAGE A 3 PH FAULT CURRENT OF AT LEAST 45KA FOR AT LEAST 0.12SEC. THE ARMOUR FOR THESE CABLES SHALL BE CAPABLE OF CARRYING 45KA FOR .12 SEC WITHOUT EXCEEDING THE MAXIMUM ALLOWABLE TEMP. OF PVC OUTER SHEATH. TECHNICAL REQUIREMENTS FOR CABLES
THE XLPE INSULATED CABLES SHALL BE CAPABLE OF WITHSTANDING A
CONDUCTOR TEMPERATURE OF 2500 C DURING A SHORT CIRCUIT WITHOUT ANY DAMAGE. THE PVC INSULATED CABLES SHALL BE CAPABLE OF WITHSTANDING A CONDUCTOR TEMPERATURE OF 160 DEG. C DURING A SHORT CIRCUIT. THE ALUMINIUM/COPPER WIRES USED FOR MANUFACTURING THE CABLES SHALL BE TRUE CIRCULAR IN SHAPE BEFORE STRANDING AND SHALL BE UNIFORMLY GOOD QUALITY, FREE FROM DEFECTS. PROGRESSIVE SEQUENTIAL MARKING OF THE LENGTH OF CABLE IN METERS AT EVERY ONE METER SHALL BE PROVIDED ON THE OUTER SHEATH OF THE CABLE. THE CABLE SHALL HAVE OUTER SHEATH OF A MATERIAL WITH AN OXYGEN INDEX OF NOT LESS THAN 29 AND A TEMPERATURE INDEX OF NOT LESS THAN 250 DEG. C ALLOWABLE TOLERANCE ON THE OVER DIA. OF THE CABLES SHALL BE +/- 2MM. CABLE TAGS AND MARKERS
EACH CABLE AND CONDUIT RUN SHALL BE TAGGED WITH
NUMBERS THAT APPEAR IN THE CABLE AND CONDUIT SCHEDULE. THE TAG SHALL BE ALUMINIUM WITH THE NUMBER PUNCHED ON IT AND SECURELY ATTACHED TO THE CABLE CONDUIT BY NOT LESS THAN TWO TURNS OF 20 SWG GI WIRE . CABLE TAGS SHALL BE RECTANGULAR IN SHAPE FOR POWER CABLES AND OF CIRCULAR SHAPE FOR CONTROL CABLES LOCATION OF CABLES LAID DIRECTLY UNDERGROUND SHALL BE CLEARLY INDICATED WITH CABLE MARKER MADE OF GALVANISED IRON PLATE. LOCATION OF UNDERGROUND CABLE JOINTS SHALL BE INDICATED WITH CABLE MARKER WITH AN ADDITIONAL INSCRIPTION “ CABLE JOINT” CABLE TAGS AND MARKERS
THE MARKER SHALL PROJECT 150MM ABOVE GROUND AND
SHALL BE SPACED AT AN INTERVAL OF 30 METERS AND AT EVERY CHANGE IN DIRECTION. THEY SHALL BE LOCATED ON BOTH SIDES OFROAD AND DRAIN CROSSINGS CABLE TAGS SHALL BE PROVIDED ON ALL CABLES AT EACH END, ON BOTH SIDES OF WALL OR FLOOR CROSSING, ON ECH DUCT/CONDUIT ENTRY AND AT EACH END & TURNING POINT IN CABLE TRAY/ TRENCH RUNS. CABLE TAGS SHALL BE PROVIDED INSIDE THE SWITCHGEAR, MOTOR CONTROL CENTRES, CONTROL AND RELAY PANELS ETC. WHEREVER REQUIRED FOR CABLE IDENTIFICATION, WHERE A NUMBER OF CABLES ENTER THROUGH A GLAND PLATE. INSTALLATION OF CABLES
CABLING IN CONTROL ROOM SHALL BE DONE ON LADDER
TYPECABLE TRAYS WHILE CABLING IN SWITCHYARD AREA SHALL BE DONE ON ANGLES IN TRENCH ALL CABLES FROM CABLE TRENCH TO EQUIPMENTS INCLUDING ALL INTERPOLE CABLE ( BOTH POWER AND CONTROL) FOR ALL EQUIPMENT, SHALL BE LAID IN PVC PIPES OF MINIMUM 50MM DIA., WHICH SHALL BE BURIED IN GROUND AT A DEPTH OF 250MM BELOW FINISHED FORMATION LEVEL. SEPARATE PVC PIPES SHALL BE LAID FOR CONTROL AND POWER CABLES POWER AND CONTROL CABLES IN THE CABLE TRENCH SHALL BE LAID IN SEPARATE TIERS.POWERCABLES ON TOP TIRES AND CONTROL & OTHER SERVICE CABLES IN BOTTOM TIERS. INSTALLATION OF CABLES
CABLE SHALL NOT BE BENT BELOW THE MINIMUM
PERMISSIBLE LIMIT. POWER CABLE 12D, CONTROL CABLE 10 D. D IS THE OVERALL DIAMETER OF CABLE. IN EACH CABLE RUN SOME EXTRA LENGTH SHALL BE KEPT AT A SUITABLE POINT TO ENABLE ONE ( FOR LT CABLES)/TWO (FOR HT CABLES) STRAIGHT THROUGH JOINTS TO BE MADE IN CASE THE CABLE DEVELOP FAULT AT A LATER DATE. CONTROL CABLE TERMINATION INSIDE THE EQUIPMENT ENCLOSURES SHALL HAVE SUFFICIENT LENGTHS SO THAT CHANGING OF TERMINATION IN TERMINAL BLOCKS CAN BE DONE WITHOUT REQUIRING ANY SPLICING.