Chapter 9 Inventory Management
Chapter 9 Inventory Management
N. D. Vohra
Quantitative
Techniques in
Management
© 2010
Chapter 9
Inventory
Management
Contents
1. Types of Inventory
2. Inventory Decisions and
Costs
3. Fixed Order Quantity
System
Classical EOQ Model
EOQ with Price Breaks
EOQ Model for
Production Runs
EOQ with Planned
Shortages
4. Determination of Safety
Stock
a)When Stock-out Costs
are Known
Contents
(…continued)
5. Periodic Review System
6. Ss System
7. One-period Model of
Inventory Management
8. Selective Approaches to
Inventory Control
ABC Analysis
VED Analysis
HML Analysis
SDE Analysis
S-OS Analysis
FSN Analysis
XYZ Analysis
In ven tory D ecision s
an d C osts
Basic Inventory Decisions
1. W h e n sh o u ld th e o rd e r b e
p la ce d ?
2. What is the quantity for
which the order be
placed?
3. What level of safety stock
be kept?
Inventory Costs
Ss System
Combines the features of P
and Q systems
Inventory Models:
Classical EOQ Model
Assumptions:
1. The annual demand is fixed and
uniformly distributed
2. The lead time is fixed
3. The ordering cost per order if
same irrespective of the
order quantity The holding
cost per unit per year is
fixed
4. The holding cost per unit per
year is fixed
5. The unit cost of the item is same
irrespective of the order
quantity. No discounts for
large orders
6. The units ordered for each time
arrive in a single lot
7. Shortages are not permitted
For this model,
Total Cost
Holding Cost
Order Size
EOQ
Inventory Profile:
Classical EOQ Model
Maximum Stock
Order Quantity
Q
Average Stock
Level
Time
Lead Time
Re-order Level Inventory
Cycle
Inventory Models: EOQ
with Price-breaks
Assumptions are the same as of
classical model, except No. 5
ELS = 2 AD
h
p
p −d
(
T (Q*) = 2 ADh 1 − dp )
Inventory Models:
Planned Shortages
Model
Used where back-ordering is
possible and planned
Based on same assumptions as
classical EOQ model except that
shortages are permitted
Back-ordering is possible and
shortages are in fact planned
EOQ determined where TC is minimum
and Ordering cost = Holding cost
+ Back-ordering cost
Q* = 2 AD
h
h +b
b
Maximum
T (QStock Q*×[
*) =, M 2=ADh b/(hbb++bh)]
Maximum Shortage Level, S = Q* - M
Safety Stock
Required when lead time and/or demand
rate are not fixed
When lead time and demand rate are
fixed, demand during lead time
(DDLT) can be determined . Deliveries
can be planned in such a manner
that there are no stock-outs
There is a risk of running out of
stock when lead time and demand
rate are variable, when provision
is made for only expected DDLT
The greater the variation in the two,
the greater the requirement of
safety stock
For a situation of never-out-of-
stock,
Safety Stock = Maximum DDLT –
Expected DDLT
where Max DDLT = Max Demand Rate ×
Max LT
For a smaller safety stock level,
there are chances of being out of
stock
Safety Stock
If the DDLT has a normal distribution,
with a given µ and σ then level of
service provided by a given safety
stock amount ss is equal to the area
under the curve to the left of X
(where X = µ + ss)
Re-order Level = Expected DDLT + Safety
Stock
leveL yrotnevnI
Re-order Level
Greater-than-average
Demand
Average Demand
SS
Re-order Level
leveL yrotnevnI
Demand
Lead Time
Extended Lead Time
SDE Availability
S-OS Seasonality
Percentage of Items
Multiple Choice
Questions
Φρ ο µ τ ηε
φ ο λ λ ο ω ι ν γ
σ τ α τ ε µ ε ν τ σ
ρ ε λ α τ ι ν γ τ ο
χ λ α σ σ ι χ αλ Ε ΟΘ
µ ο δ ε , µ αρ κ τ ηε
ι ν χ ο ρ ρ ε χ τ ο ν ε :
1.
2. Total Ordering Cost = Total
Holding Cost.
3.
4. Total Relevant Cost =
√2AOH.
5.
6. If annual demand doubles
with all other
parameters remaining
constant, the EOQ is
Multiple Choice
Questions
Mark the wrong statement:
1. Inventory cycle is the
time-period occurring
between successive
procurement actions.
2.
3. Shortage cost is the
penalty incurred for
being unable to meet a
demand as it occurs.
4.
5. Lead-time is the elapsed
time between the
initiation of an order
and the receipt of
replenishment stock.
6.
Multiple Choice
Questions
Mark the wrong statement:
1. In deterministic inventory
models, Re-order level
= Demand during lead
time (DDLT).
2.
3. In cases where demand is
probabilistic, ROL =
Expected DDLT +
Safety Stock.
4.
5. Greater the variation in
demand and/or lead-
time, greater the
amount of safety stock
needed.
Multiple Choice
Questions
If DDLT is known to be
distributed normally with a
variance of 6400, then a
safety stock of 160 units
will yield approximately
what level of service?
(Given: z = 2, Area = 0.4772)
1. 48%
2.
3. 98%
4.
5. 2%
6.
7. 52%
Multiple Choice
Questions
Fo r a 2 5 % in cre a se in o rd e r
q u a n tity ( u n d e r cla ssica l E O Q
m o d e l) th e to ta l re le va n t co st
w o u ld
1. Decrease by 2.5%
2.
3. Decrease by 0.25%
4.
5. Increase by 2.5%
6.
7. Increase by 1.025%
8.
Multiple Choice
Questions
M a rk th e w ro n g sta te m e n t:
1. The division of items into A,
B and C categories is
accomplished by
plotting the usage value
of items to obtain Pareto
curve.
2.
3. FNSD analysis represents
the speed classification
of items.
4.
5. XYZ analysis is based on
the classification of
items according to their
unit cost.
6.
7. SOS is the classification as