Conventional Building Construction
Conventional Building Construction
Contrary to IBS – New SPP stated that every government projects must use up to
70% of IBS components
In-situ / Cast-in-place concrete
Pre-cast
Helical
Spiral
Simple
Free standing/jack knife
FORMWORK
Definition
• Formwork: Formwork may be described as a mould or box
into which wet concrete can be poured and compacted so
that it will finally set to the inner profile of the mould or box.
• Necessity
– Formwork form a very important part of concrete construction. Most
permanent structures simply could not be built without formwork.
• Safety
– Failure of formwork could cause injuries or death at construction site.
Materials for Formwork
• Among the materials that can be used for construction of
formwork:
– Sawn timber – the most widely use
– Plywood – when fair face is necessary
– Steel form – the use of steel is largely confined to proprietary formwork system
– Plastic form – plastic sheets are normally used as liners to produce an almost
endless variety of patterns.
– Aluminium – Aluminium has many of the properties of steel but with
substantial weight savings.
– Rubber – Rubber materials are generally used as form liners when complex
shapes are required to be cast into the concrete.
– Glass fiber reinforced plastic (GFRP) – GFRP material is strong light weight
material manufactured from polyester or epoxy resin, reinforced with glass
fiber.
Concrete Formwork
• Forms are a type of temporary structure that provide containment for the
fresh concrete and support it until it can support itself.
• The period which should elapse before the formwork is struck will vary
from job to job and will depend on the concrete used. Formwork must
not be removed until the concrete is strong enough to be self-
supporting and able to carry imposed load. Time of striking is normally
related to the strength of the concrete, and obviously soffit forms to
beams and slabs must be left in place longer than is necessary for side
form.
• Striking must be carried out with care to avoid damages to arises and
projections, and it may be necessary to protect some of the work from
damage immediately after removing the form. Before the soffit forms
and props are removed, the concrete surface should be exposed
carefully to ascertain that the concrete has hardened sufficiently.
• Beam sides – 9 to 12 hours
• Beam soffit – 8 to 14 days (props left under)
• Beam props – 15 to 21 days
• Columns – 9 to 12 hours
Striking formwork
Striking formwork at for Ground Beam (Note the use of suspended slab)
Permanent Formwork
New York
Coliseum
Formwork
collapse,
where rapid
delivery of
concrete
introduced
lateral
forces at the top
of
high shoring.
Vibration
• Bar Setting
– Form design can permit the rebar to be pre assembled before
installation (more favorable condition)
Other Costs affected by FW - 2
• Concrete Placement
– High lifts in wall construction make placing and vibration difficult.
– Placing rate is limited by form design.
• Other Trades
– The plan should permit other trades to perform their work efficiently
and minimize interruptions in placing.
Among the precautions that can be taken to
ensure formwork function as it suppose to be
are as follow:
- Material used for the construction of formwork must fulfill the
specification.
- Formwork is fixed firmly & properly
- Construction area must be protected to prevent vandalism of formwork.
- Warning sign must be put up at the area where the formwork is fixed to
prevent entrance of people that may damage the formwork.
- The formwork must be inspected before the concrete is poured.
How to increase the speed of conventional
construction?
1. Use slipform techniques where possible especially when lift core
is present (in high rise). Cores control the vertical rise speed
2. Arrange for a large area pouring of floors (avoid cold joints),
continuous operation
3. Introduction of pre-cast elements where possible (especially in
horizontal locations)
4. Simplification of floor details – less varieties in bar size and
spacing
5. Prefabrication of slab reinforcement (especially when using
mesh reinforcement)
6. Use of straight bar reinforcement
7. Repetition as much as possible in formwork and falsework
allows less labour intensive method
Concrete Form Design
1. Wall and column forms
For vertical forms, design load consists of the lateral pressure of
the concrete against the form. ACI recommendation:
a. Vertical rate of placement 2.1 m/h or less
p = 7.2 + [785R/(T + 18)] where
p = lateral pressure (kPa)
R = rate of vertical placement
T = temperature (0C)
Maximum pressure ;
143.6 kPa for columns, 95.8 kPa for walls OR 150h (h = height of
form) whichever lesser
Minimum pressure;
28.7 kPa
Concrete Form Design
b. Vertical rate of placement 2.1 m/h – 3.0 m/h
p = 7.2 + [1154/(T + 18)] + [244R/(T + 18)]
Maximum pressure ;
95.8 kPa OR 150h (h = height of form) whichever lesser
Minimum pressure;
28.7 kPa
c. Vertical rate of placement more than 3.0m/h
p = 23.6h
Minimum pressure;
28.7 kPa
Concrete Form Design
Conditions ;
H = 0.02 x dl x ws where
H = lateral force applied along the edge of the
slab (kN/m)
dl = design dead load (concrete + formwork) (kPa)
ws = width of slab perpendicular to the form edge
(m)
Min pressure = 1.46 kN/m
Concrete Form Design
2. Lateral load for wall