0% found this document useful (0 votes)
207 views

Deliverables and Schedule

This transmittal log tracks documents submitted for the Red Line Project between December 2009 and August 2010. It lists 63 transmittals between ICS-NETT and Ansaldo regarding equipment specifications, design packages, and resubmittals for different segments of the project. Resubmittals were made to address review comments and questions. Segments included Rhode Island Ave, New York Ave, Judiciary Square, and Union Station.

Uploaded by

neelureddy
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
207 views

Deliverables and Schedule

This transmittal log tracks documents submitted for the Red Line Project between December 2009 and August 2010. It lists 63 transmittals between ICS-NETT and Ansaldo regarding equipment specifications, design packages, and resubmittals for different segments of the project. Resubmittals were made to address review comments and questions. Segments included Rhode Island Ave, New York Ave, Judiciary Square, and Union Station.

Uploaded by

neelureddy
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 26

Transmittal Log

Red Line Project - FQ8143


Updated: 6/3/2010
Transmittal Log
Rejection
Comments Comments Response Rejection Response Approval
ID Date Sender Recipient Subject Date Response Date Date Date Date Date Date
FQ8143-001 9-Dec-2009 [email protected] SOLID STATE RELAYS
FQ8143-002 18-Dec-2010 [email protected] JODI VASALINI -ANSALDO PRELIMINARY SUBMITTALS 30% PACKAGE
FQ8143-003 12-Feb-2010 [email protected] JODI VASALINI -ANSALDO RHODE ISLAND DESIGN SUBMITTAL
FQ8143-004 12-Feb-2010 [email protected] JODI VASALINI -ANSALDO RHODE ISLAND PRODUCT DATA SUBMITTAL
FQ8143-005 12-Feb-2010 [email protected] JODI VASALINI -ANSALDO RHODE ISLAND CCTV PRODUCT DATA SUBMITTAL
FQ8143-006 12-Feb-2010 [email protected] JODI VASALINI -ANSALDO RHODE ISLAND CCTV TEST SHEETS SUBMITTAL
FQ8143-007 12-Feb-2010 [email protected] JODI VASALINI -ANSALDO RHODE ISLAND PA TEST SHEET SUBMITTAL
FQ8143-008 12-Feb-2010 [email protected] JODI VASALINI -ANSALDO VIDEO ANALYTIC OVERVIEW SUBMITTAL
FQ8143-009 [email protected] JODI VASALINI -ANSALDO
FQ8143-010 [email protected] JODI VASALINI -ANSALDO
FQ8143-011 [email protected] JODI VASALINI -ANSALDO
FQ8143-012 8-Mar-2010 [email protected] JODI VASALINI -ANSALDO RHODE ISLAND PRODUCT DATA RE-SUBMIT
FQ8143-013 8-Mar-2010 [email protected] JODI VASALINI -ANSALDO RHODE ISLAND DESIGN PACKAGE RE-SUBMIT
FQ8143-014 8-Mar-2010 [email protected] JODI VASALINI -ANSALDO CCTV TEST PROCEDURE-RESUBMIT
FQ8143-015 8-Mar-2010 [email protected] JODI VASALINI -ANSALDO RHODE ISLAND PRODUCT DATA -RE-SUBMIT
FQ8143-016 16-Mar-2010 [email protected] JODI VASALINI -ANSALDO NEW YORK AVE PA PRODUCT DATA SUBMITTAL
FQ8143-017 17-Mar-2010 [email protected] JODI VASALINI -ANSALDO NEW YORK AVE CCTV PRODUCT DATA SUBMITTAL
FQ8143-018 18-Mar-2010 [email protected] JODI VASALINI -ANSALDO NEW YORK AVE CCTV AND PA DESIGN SUBMITTAL
FQ8143-019 19-Mar-2010 [email protected] JODI VASALINI -ANSALDO NEW YORK AVE CCTV TEST SHEET SUBMITTAL
FQ8143-020 20-Mar-2010 [email protected] JODI VASALINI -ANSALDO NEW YORK AVE PA TEST SHEET SUBMITTAL
PRELIMINARY SUBMITTAL: ETS CABINET PRODUCT
FQ8143-021 12-Apr-2010 [email protected] JODI VASALINI -ANSALDO DATA 30-Apr-10

PRELIMINARY SUBMITTAL: ETS CABINET PRODUCT


DATA; Response & supporting documents to
REV 1 10-May-2010 [email protected] JODI VASALINI -ANSALDO questions
FQ8143-022 10-May-2010 [email protected] JODI VASALINI -ANSALDO ETS STATEMENT OF WORK

ETS / SCADA REVIEW PACKAGE : ETS Design Dwgs;


SCADA Design Dws; ETS Cabinet Layout: Switch &
Controller; ETS Relay Cabinet Layout; Material Data
Sheets:ETS Cabinet: Switch & Controller; ETS Relay
Cabinet; Federal Signal Lights-Blue & Amber;
Guardian Telephone for ETS; ETS Kill Switch;
Protected Terminal Blocks; Terminal Blocks; ETS
Relays; DIO Module; Digital Trace Recorder; HMI;
FQ8143-023 15-Apr-2010 [email protected] JODI VASALINI -ANSALDO Network Switch; Current Sensor & Relays
FQ8143-023 8-Jul-2010 [email protected] JODI VASALINI -ANSALDO REV 1 ETS/SCADA REVIEW PACKAGE
FQ8143-024 23-Apr-2010 [email protected] JODI VASALINI -ANSALDO UNION STATION CCTV PRODUCT DATA SUBMITTAL
FQ8143-025 23-Apr-2010 [email protected] JODI VASALINI -ANSALDO UNION STATION CCTV TEST SHEETS SUBMITTAL
FQ8143-026 23-Apr-2010 [email protected] JODI VASALINI -ANSALDO UNION STATION CCTV SYSTEM DESIGN SUBMITTAL
ETS SCHEDULE FOR DESIGN P1-4 & CONSTRUCTION
FQ8143-027 26-Apr-2010 [email protected] JODI VASALINI -ANSALDO FOR P1

ETS SCHEDULE FOR DESIGN P1-4 & CONSTRUCTION


REV 1 4-May-2010 [email protected] JODI VASALINI -ANSALDO FOR P1 (Revised with Training)
FQ8143-028 10-May-2010 [email protected] JODI VASALINI -ANSALDO ETS DESIGN DRAWINGS
FQ8143-029 10-May-2010 [email protected] JODI VASALINI -ANSALDO ETS TRIP SCHEME
FQ8143-029 30-Jun-2010 [email protected] JODI VASALINI -ANSALDO ETS TRIP SCHEME REV 2
FQ8143-030 4/XX/2010 [email protected] JODI VASALINI -ANSALDO SCADA DESIGN DRAWINGS
FQ8143-031 4/XX/2010 [email protected] JODI VASALINI -ANSALDO ETS LABEL CATALOG SHEETS
FQ8143-032 4/XX/2010 [email protected] JODI VASALINI -ANSALDO ETS CABLE TYPES & LENGTHS
ETS RELAY CABINET WITH TERMINAL BLOCK
FQ8143-033 10-May-2010 [email protected] JODI VASALINI -ANSALDO (TYPICAL)
FQ8143-034 10-May-2010 [email protected] JODI VASALINI -ANSALDO ETS PROPOSED PATHWAYS UTILIZATION
FQ8143-035 4/XX/2010 [email protected] JODI VASALINI -ANSALDO ETS TRACTION POWER EQUIPMENT LOCATIONS

ETS WIRE BLOCK AND TERMINALS LAYOUT (KILL


FQ8143-036 4/XX/2010 [email protected] JODI VASALINI -ANSALDO SWITCH CABINET & CONTROLLER CABINET)
FQ8143-037 4/XX/2010 [email protected] JODI VASALINI -ANSALDO SCADA STATEMENT OF WORK

ETS ENHANCED DESIGN DRAWINGS / SEGMENT:


FQ8143-038 10-May-2010 [email protected] JODI VASALINI -ANSALDO JUDICIARY SQUARE - RHODE ISLAND AVENUE
FQ8143-039 4/XX/2010 [email protected] JODI VASALINI -ANSALDO ETS/SCADA CUTOVER PLAN
FQ8143-040 11-May-2010 [email protected] JODI VASALINI -ANSALDO JUDICIARY SQUARE CCTV TEST SHEETS
FQ8143-041 11-May-2010 [email protected] JODI VASALINI -ANSALDO JUDICIARY SQUARE CCTV PRODUCT DATA
FQ8143-042 29-Apr-2010 [email protected] JODI VASALINI -ANSALDO CCTV TEST PROCEDURE-RESUBMIT
FQ8143-043 29-Apr-2010 [email protected] JODI VASALINI -ANSALDO PA TEST PROCEDURE-RESUBMIT
FQ8143-044 11-May-2010 [email protected] JODI VASALINI -ANSALDO JUDICIARY SQUARE CCTV SYSTEM DESIGN

ETS ENHANCED DESIGN DRAWINGS / SEGMENT:


FQ8143-045 13-May-2010 [email protected] JODI VASALINI -ANSALDO UNION STATION - RHODE ISLAND AVENUE
FQ8143-046 [email protected] JODI VASALINI -ANSALDO RESERVED FOR CCTV / PA
FQ8143-047 14-Jun-2010 [email protected] JODI VASALINI -ANSALDO 90% RHODE ISLAND AVE CCTV DESIGN
FQ8143-048 14-Jun-2010 [email protected] JODI VASALINI -ANSALDO 90% RHODE ISLAND AVE PA DESIGN
FQ8143-049 24-Jun-2010 [email protected] JODI VASALINI -ANSALDO 90% RHODE ISLAND PA PRODUCT DATA
FQ8143-050 24-Jun-2010 [email protected] JODI VASALINI -ANSALDO 90% RHODE ISLAND CCTV PRODUCT DATA
FQ8143-051 24-Jun-2010 [email protected] JODI VASALINI -ANSALDO RHODE ISLAND GARAGE PLANS
FQ8143-052 25-Jun-2010 [email protected] JODI VASALINI -ANSALDO NEW YORK AVENUE PA DESIGN
FQ8143-053 25-Jun-2010 [email protected] JODI VASALINI -ANSALDO NEW YORK AVENUE CCTV DESIGN
FQ8143-054 25-Jun-2010 [email protected] JODI VASALINI -ANSALDO NEW YORK AVENUE PA 90% PRODUCT DATA
FQ8143-055 25-Jun-2010 [email protected] JODI VASALINI -ANSALDO NEW YORK AVENUE CCTV 90% PRODUCT DATA
FQ8143-056 12-Jul-2010 [email protected] JODI VASALINI -ANSALDO PA SYSTEM SPARE PARTS LIST
FQ8143-057 12-Jul-2010 [email protected] JODI VASALINI -ANSALDO CCTV SYSTEM SPARE PARTS LIST
DUPONT CIRLCE & NEW YORK AVE VIDEO
FQ8143-058 12-Jul-2010 [email protected] JODI VASALINI -ANSALDO ANALYTICS OVERVIEW
FQ8143-059 27-Jul-2010 [email protected] JODI VASALINI -ANSALDO ETS DESIGN-RESUBMIT RI TO JUDICIARY SQUARE
FQ8143-060 27-Jul-2010 [email protected] JODI VASALINI -ANSALDO ETS DISCONNECT SWITCH
FQ8143-061 27-Jul-2010 [email protected] JODI VASALINI -ANSALDO LETTER -FEDERAL SIGNAL CLARIFICATION
FQ8143-062 28-Jul-2010 [email protected] JODI VASALINI -ANSALDO JUPITER- PRODUCT DATA
FQ8143-063 2-Aug-2010 [email protected] JODI VASALINI -ANSALDO AXIS 233D CAMERA FOR RI PARKING LOT
FQ8143-064 3-Aug-2010 [email protected] JODI VASALINI -ANSALDO 100% RI PA DESIGN
FQ8143-065 3-Aug-2010 [email protected] JODI VASALINI -ANSALDO 100% RI CCTV DESIGN
FQ8143-066 25-Aug-2010 [email protected] JODI VASALINI -ANSALDO SQUARE 4" SPEAKER ENCLOSURE
FQ8143-067 25-Aug-2010 [email protected] JODI VASALINI -ANSALDO MEZZANINE SPEAKER ENCLOSURE
FQ8143-068 25-Aug-2010 [email protected] JODI VASALINI -ANSALDO ETS SIMULATION TEST PROCEDURE
FQ8143-069 9-Sep-2010 [email protected] JODI VASALINI -ANSALDO OUTDOOR PYLON SPEAKER-ENCL-GRILL SUBMITTAL
FQ8143-070 27-Sep-2010 [email protected] JODI VASALINI -ANSALDO NY AVENUE SOUND STUDY
Estimated Estimated Estimated
WBS Task Name start date end date duration
1 REDLINE PA & CCTV DESIGN AND INSTALLATION
1.1 PHASE 1
1.1.1 RHODE ISLAND AVENUE STATION
1.1.1.1 STATION DESIGN
1.1.1.1.1 Start Redline CCTV and PA Design Project 18JAN10A 0
1.1.1.1.2 Rhode Island Ave. 60% Design 18JAN10A 12FEB10A 40
1.1.1.1.3 Rhode Island Ave. 60% Submit 15MAR10A 0
1.1.1.1.4 Rhode Island Ave. 60% Review 15MAR10A 28APR10A 21
1.1.1.1.5 Rhode Island Ave. 90% Design 01JUN10A 14JUN10A 15
1.1.1.1.6 Rhode Island Ave. 90% Submit 14JUN10A 0
1.1.1.1.7 Rhode Island Ave. 90% Review 15JUN10A 03AUG10A 21
1.1.1.1.8 Rhode Island Ave. IFC Set 04AUG10A 12AUG10 6
1.1.1.1.9 Rhode Island Ave. 100% Submit 12AUG10 0
1.1.1.2 STATION REHABILITATION
1.1.1.2.1 RIA - Procurement of Materials 28JUN10A 03AUG10A 30
1.1.1.2.2 RIA - Start/Mobilize Station Rehabilitation 18AUG10 19AUG10 2
1.1.1.2.3 RIA - PA/CCTV Field Device Installation 30AUG10 24SEP10 20
1.1.1.2.4 RIA - PA/CCTV Head End Installation 27SEP10 15OCT10 15
1.1.1.2.5 RIA - PA Field Device Testing 18OCT10 19OCT10 2
1.1.1.2.6 RIA - CCTV Field Device Testing 20OCT10 21OCT10 2
1.1.1.2.7 RIA - PA & CCTV Final Accpt. Testing & Commision 22OCT10 26OCT10 3
1.1.1.2.8 STATION CLOSE-OUT
1.1.1.2.9 RIA - Station Close-Out 27OCT10 0
1.1.1.2.10 RIA - Substantial Completion Inspection (SCI) 27OCT10 28OCT10 2
1.1.1.2.11 RIA - As-Built Pkg & Final O&M Pkg Submittal 29OCT10 02NOV10 3
1.1.2 NEW YORK AVENUE STATION
1.1.2.1 STATION DESIGN
1.1.2.1.1 New York Ave. 60% Design 15FEB10A 17MAR10A 20
1.1.2.1.2 New York Ave. 60% Submit 17MAR10A 0
1.1.2.1.3 New York Ave. 60% Review 15APR10A 17MAY10A 21
1.1.2.1.4 New York Ave. 90% Design 18MAY10A 25JUN10A 15
1.1.2.1.5 New York Ave. 90% Submit 11AUG10 0
1.1.2.1.6 New York Ave. 90% Review 17AUG10 23AUG10 5
1.1.2.1.7 New York Ave. IFC Set 24AUG10 30AUG10 5
1.1.2.1.8 New York Ave. 100% Submit 30AUG10 0
1.1.2.2 STATION REHABILITATION
1.1.2.2.1 NYA - Start/Mobilize Station Rehabilitation 24AUG10 25AUG10 2
1.1.2.2.2 NYA - PA/CCTV Field Device Installation 26AUG10 22SEP10 20
1.1.2.2.3 NYA - PA/CCTV Head End Installation 23SEP10 13OCT10 15
1.1.2.2.4 NYA - PA Field Device Testing 14OCT10 15OCT10 2
1.1.2.2.5 NYA - CCTV Field Device Testing 18OCT10 19OCT10 2
1.1.2.2.6 NYA - PA & CCTV Final Accpt. Testing & Commision 20OCT10 22OCT10 3
1.1.2.3 STATION CLOSE-OUT
1.1.2.3.1 NYA - Station Close-Out 25OCT10 0
1.1.2.3.2 NYA - Substantial Completion Inspection (SCI) 25OCT10 26OCT10 2
1.1.2.3.3 NYA - As-Built Pkg & Final O&M Pkg Submittal 27OCT10 29OCT10 3
1.1.3 UNION STATION
1.1.3.1 STATION DESIGN
1.1.3.1.1 Union Station 60% Design 17MAR10A 13APR10A 20
1.1.3.1.2 Union Station 60% Submit 23APR10A 0
1.1.3.1.3 Union Station 60% Review 26APR10A 21JUN10A 21
1.1.3.1.4 Union Station 90% Design 12AUG10A 01SEP10 15
1.1.3.1.5 Union Station 90% Submit 01SEP10 0
1.1.3.1.6 Union Station 90% Review 02SEP10 30SEP10 21
1.1.3.1.7 Union Station IFC Set 01OCT10 07OCT10 5
1.1.3.1.8 Union Station 100% Submit 07OCT10 0
1.1.3.2 STATION REHABILITATION
1.1.3.2.1 US - Start/Mobilize Station Rehabilitation 01OCT10 04OCT10 2
1.1.3.2.2 US - CCTV Field Device Installation 05OCT10 14OCT10 8
1.1.3.2.3 US - CCTV Head End Installation 18OCT10 22OCT10 5
1.1.3.2.4 US - CCTV Field Device Testing 25OCT10 26OCT10 2
1.1.3.2.5 US - CCTV Final Accpt. Testing & Commision 27OCT10 29OCT10 3
1.1.3.3 STATION CLOSE-OUT
1.1.3.3.1 US - Station Close-Out 01NOV10 0
1.1.3.3.2 US - Substantial Completion Inspection (SCI) 01NOV10 02NOV10 2
1.1.3.3.3 US - As-Built Pkg & Final O&M Pkg Submittal 03NOV10 05NOV10 3
1.1.4 JUDICIARY SQUARE STATION
1.1.4.1 STATION DESIGN
1.1.4.1.1 Judiciary Square 60% Design 23APR10A 11MAY10A 20
1.1.4.1.2 Judiciary Square 60% Submit 11MAY10A 0
1.1.4.1.3 Judiciary Square 60% Review 12MAY10A 21JUN10A 21
1.1.4.1.4 Judiciary Square 90% Design 19AUG10 08SEP10 15
1.1.4.1.5 Judiciary Square 90% Submit 08SEP10 0
1.1.4.1.6 Judiciary Square 90% Review 15SEP10 13OCT10 21
1.1.4.1.7 Judiciary Square IFC Set 14OCT10 20OCT10 5
1.1.4.1.8 Judiciary Square 100% Submit 20OCT10 0
1.1.4.2 STATION REHABILITATION
1.1.4.2.1 JSS - Start/Mobilize Station Rehabilitation 14OCT10 15OCT10 2
1.1.4.2.2 JSS - CCTV Field Device Installation 18OCT10 27OCT10 8
1.1.4.2.3 JSS - CCTV Head End Installation 28OCT10 03NOV10 5
1.1.4.2.4 JSS - CCTV Field Device Testing 04NOV10 05NOV10 2
1.1.4.2.5 JSS - CCTV Final Accpt. Testing & Commision 08NOV10 10NOV10 3
1.1.4.3 STATION CLOSE-OUT
1.1.4.3.1 JSS - Station Close-Out 11NOV10 0
1.1.4.3.2 JSS - Substantial Completion Inspection (SCI) 11NOV10 12NOV10 2
1.1.4.3.3 JSS - As-Built Pkg & Final O&M Pkg Submittal 15NOV10 17NOV10 3
1.2 PHASE 2
1.2.1 GALLERY PLACE STATION
1.2.1.1 STATION DESIGN
1.2.1.1.1 Gallery Place 60% Design 26AUG10 22SEP10 20
1.2.1.1.2 Gallery Place 60% Submit 22SEP10 0
1.2.1.1.3 Gallery Place 60% Review 22SEP10 20OCT10 21
1.2.1.1.4 Gallery Place 90% Design 21OCT10 10NOV10 15
1.2.1.1.5 Gallery Place 90% Submit 10NOV10 0
1.2.1.1.6 Gallery Place 90% Review 03NOV10 01DEC10 21
1.2.1.1.7 Gallery Place IFC Set 02DEC10 08DEC10 5
1.2.1.1.8 Gallery Place 100% Submit 08DEC10 0
1.2.1.2 STATION REHABILITATION
1.2.1.2.1 GPS - Start/Mobilize Station Rehabilitation 02DEC10 03DEC10 2
1.2.1.2.2 GPS - CCTV Field Device Installation 06DEC10 24DEC10 15
1.2.1.2.3 GPS - CCTV Head End Installation 27DEC10 31DEC10 5
1.2.1.2.4 GPS - CCTV Field Device Testing 03JAN11 04JAN11 2
1.2.1.2.5 GPS - CCTV Final Accpt. Testing & Commision 05JAN11 07JAN11 3
1.2.1.3 STATION CLOSE-OUT
1.2.1.3.1 GPS - Station Close-Out 10JAN11 0
1.2.1.3.2 GPS - Substantial Completion Inspection (SCI) 10JAN11 11JAN11 2
1.2.1.3.3 GPS - As-Built Pkg & Final O&M Pkg Submittal 12JAN11 14JAN11 3
1.2.2 METRO CENTER STATION
1.2.2.1 STATION DESIGN
1.2.2.1.1 Metro Center 60% Design 23SEP10 20OCT10 20
1.2.2.1.2 Metro Center 60% Submit 20OCT10 0
1.2.2.1.3 Metro Center 60% Review 21OCT10 18NOV10 21
1.2.2.1.4 Metro Center 90% Design 19NOV10 01DEC10 15
1.2.2.1.5 Metro Center 90% Submit 01DEC10 0
1.2.2.1.6 Metro Center 90% Review 24NOV10 22DEC10 21
1.2.2.1.7 Metro Center IFC Set 23DEC10 29DEC10 5
1.2.2.1.8 Metro Center 100% Submit 29DEC10 0
1.2.2.2 STATION REHABILITATION
1.2.2.2.2 MCS - Start/Mobilize Station Rehabilitation 23DEC10 24DEC10 2
1.2.2.2.2 MCS - CCTV Field Device Installation 27DEC10 14JAN11 15
1.2.2.2.3 MCS - CCTV Head End Installation 17JAN11 21JAN11 5
1.2.2.2.4 MCS - CCTV Field Device Testing 24JAN11 25JAN11 2
1.2.2.2.5 MCS - CCTV Final Accpt. Testing & Commision 26JAN11 28JAN11 3
1.2.2.3 STATION CLOSE-OUT
1.2.2.3.1 MCS - Station Close-Out 31JAN11 0
1.2.2.3.2 MCS - Substantial Completion Inspection (SCI) 31JAN11 01FEB11 2
1.2.2.3.3 MCS - As-Built Pkg & Final O&M Pkg Submittal 02FEB11 04FEB11 3
1.2.3 FARRAGUT NORTH STATION
1.2.3.1 STATION DESIGN
1.2.3.1.1 Farragut North 60% Design 21OCT10 17NOV10 20
1.2.3.1.2 Farragut North 60% Submit 17NOV10 0
1.2.3.1.3 Farragut North 60% Review 18NOV10 16DEC10 21
1.2.3.1.4 Farragut North 90% Design 17DEC10 06JAN11 15
1.2.3.1.5 Farragut North 90% Submit 06JAN11 0
1.2.3.1.6 Farragut North 90% Review 06JAN11 03FEB11 21
1.2.3.1.7 Farragut North IFC Set 04FEB11 10FEB11 5
1.2.3.1.8 Farragut North 100% Submit 10FEB11 0
1.2.3.2 STATION REHABILITATION
1.2.3.2.1 FNS - Start/Mobilize Station Rehabilitation 04FEB11 07FEB11 2
1.2.3.2.2 FNS - CCTV Field Device Installation 08FEB11 17FEB11 8
1.2.3.2.3 FNS - CCTV Head End Installation 18FEB11 24FEB11 5
1.2.3.2.4 FNS - CCTV Field Device Testing 25FEB11 28FEB11 2
1.2.3.2.5 FNS - CCTV Final Accpt. Testing & Commision 01MAR11 03MAR11 3
1.2.3.3 STATION CLOSE-OUT
1.2.3.3.1 FNS - Station Close-Out 04MAR11 0
1.2.3.3.2 FNS - Substantial Completion Inspection (SCI) 04MAR11 07MAR11 2
1.2.3.3.3 FNS - As-Built Pkg & Final O&M Pkg Submittal 08MAR11 10MAR11 3
1.2.4 DUPONT CIRCLE STATION
1.2.4.1 STATION DESIGN
1.2.4.1.1 Dupont Circle 60% Design 18NOV10 15DEC10 20
1.2.4.1.2 Dupont Circle 60% Submit 15DEC10 0
1.2.4.1.3 Dupont Circle 60% Review 16DEC10 13JAN11 21
1.2.4.1.4 Dupont Circle 90% Design 14JAN11 03FEB11 15
1.2.4.1.5 Dupont Circle 90% Submit 03FEB11 0
1.2.4.1.6 Dupont Circle 90% Review 03FEB11 03MAR11 21
1.2.4.1.7 Dupont Circle IFC Set 04MAR11 11MAR11 6
1.2.4.1.8 Dupont Circle 100% Submit 11MAR11 0
1.2.4.2 STATION REHABILITATION
1.2.4.2.1 FNS - Start/Mobilize Station Rehabilitation 04MAR11 07MAR11 2
1.2.4.2.2 FNS - CCTV Field Device Installation 08MAR11 17MAR11 8
1.2.4.2.3 FNS - CCTV Head End Installation 18MAR11 24MAR11 5
1.2.4.2.4 FNS - CCTV Field Device Testing 25MAR11 28MAR11 2
1.2.4.2.5 FNS - CCTV Final Accpt. Testing & Commision 29MAR11 31MAR11 3
1.2.4.3 STATION CLOSE-OUT
1.2.4.3.1 FNS - Station Close-Out 01APR11 0
1.2.4.3.2 FNS - Substantial Completion Inspection (SCI) 01APR11 04APR11 2
1.2.4.3.3 FNS - As-Built Pkg & Final O&M Pkg Submittal 05APR11 07APR11 3
1.3 PHASE 3
1.3.1 BROOKLAND STATION
1.3.1.1 STATION DESIGN
1.3.1.1.1 Brookland 60% Design 16DEC10 12JAN11 20
1.3.1.1.2 Brookland 60% Submit 12JAN11 0
1.3.1.1.3 Brookland 60% Review 13JAN11 10FEB11 21
1.3.1.1.4 Brookland 90% Design 11FEB11 03MAR11 15
1.3.1.1.5 Brookland 90% Submit 03MAR11 0
1.3.1.1.6 Brookland 90% Review 03MAR11 31MAR11 21
1.3.1.1.7 Brookland IFC Set 01APR11 07APR11 5
1.3.1.1.8 Brookland 100% Submit 07APR11 0
1.3.1.2 STATION REHABILITATION
1.3.1.2.1 BLS - Start/Mobilize Station Rehabilitation 01APR11 04APR11 2
1.3.1.2.2 BLS - PA/CCTV Field Device Installation 05APR11 02MAY11 20
1.3.1.2.3 BLS - PA/CCTV Head End Installation 03MAY11 23MAY11 15
1.3.1.2.4 BLS - PA Field Device Testing 24MAY11 25MAY11 2
1.3.1.2.5 BLS - CCTV Field Device Testing 26MAY11 27MAY11 2
1.3.1.2.6 BLS - PA & CCTV Final Accpt. Testing & Commision 30MAY11 01JUN11 3
1.3.1.3 STATION CLOSE-OUT
1.3.1.3.1 BLS - Station Close-Out 02JUN11 0
1.3.1.3.2 BLS - Substantial Completion Inspection (SCI) 02JUN11 03JUN11 2
1.3.1.3.3 BLS - As-Built Pkg & Final O&M Pkg Submittal 06JUN11 08JUN11 3
1.3.2 FORT TOTTEN STATION
1.3.2.1 STATION DESIGN
1.3.2.1.1 Fort Totten 60% Design 13JAN11 09FEB11 20
1.3.2.1.2 Fort Totten 60% Submit 09FEB11 0
1.3.2.1.3 Fort Totten 60% Review 10FEB11 10MAR11 21
1.3.2.1.4 Fort Totten 90% Design 11MAR11 31MAR11 15
1.3.2.1.5 Fort Totten 90% Submit 31MAR11 0
1.3.2.1.6 Fort Totten 90% Review 31MAR11 28APR11 21
1.3.2.1.7 Fort Totten IFC Set 29APR11 09MAY11 7
1.3.2.1.8 Fort Totten 100% Submit 09MAY11 0
1.3.2.2 STATION REHABILITATION
1.3.2.2.1 FTS - Start/Mobilize Station Rehabilitation 29APR11 02MAY11 2
1.3.2.2.2 FTS - PA/CCTV Field Device Installation 03MAY11 30MAY11 20
1.3.2.2.3 FTS - PA/CCTV Head End Installation 31MAY11 20JUN11 15
1.3.2.2.4 FTS - PA Field Device Testing 21JUN11 22JUN11 2
1.3.2.2.5 FTS - CCTV Field Device Testing 23JUN11 24JUN11 2
1.3.2.2.6 FTS - PA & CCTV Final Accpt. Testing & Commision 27JUN11 29JUN11 3
1.3.2.3 STATION CLOSE-OUT
1.3.2.3.1 FTS - Station Close-Out 30JUN11 0
1.3.2.3.2 FTS - Substantial Completion Inspection (SCI) 30JUN11 01JUL11 2
1.3.2.3.3 FTS - As-Built Pkg & Final O&M Pkg Submittal 04JUL11 06JUL11 3
1.4 PHASE 4
1.4.1 SILVER SPRING STATION
1.4.1.1 STATION DESIGN
1.4.1.1.1 Silver Spring 60% Design 10FEB11 09MAR11 20
1.4.1.1.2 Silver Spring 60% Submit 09MAR11 0
1.4.1.1.3 Silver Spring 60% Review 10MAR11 07APR11 21
1.4.1.1.4 Silver Spring 90% Design 08APR11 28APR11 15
1.4.1.1.5 Silver Spring 90% Submit 28APR11 0
1.4.1.1.6 Silver Spring 90% Review 28APR11 26MAY11 21
1.4.1.1.7 Silver Spring IFC Set 27MAY11 02JUN11 5
1.4.1.1.8 Silver Spring 100% Submit 02JUN11 0
1.4.1.2 STATION REHABILITATION
1.4.1.2.1 SSS - Start/Mobilize Station Rehabilitation 27MAY11 30MAY11 2
1.4.1.2.2 SSS - PA/CCTV Field Device Installation 31MAY11 27JUN11 20
1.4.1.2.3 SSS - PA/CCTV Head End Installation 28JUN11 18JUL11 15
1.4.1.2.4 SSS - PA Field Device Testing 19JUL11 20JUL11 2
1.4.1.2.5 SSS - CCTV Field Device Testing 21JUL11 22JUL11 2
1.4.1.2.6 SSS - PA & CCTV Final Accpt. Testing & Commision 25JUL11 27JUL11 3
1.4.1.3 STATION CLOSE-OUT
1.4.1.3.1 SSS - Station Close-Out 28JUL11 0
1.4.1.3.2 SSS - Substantial Completion Inspection (SCI) 28JUL11 29JUL11 2
1.4.1.3.3 SSS - As-Built Pkg & Final O&M Pkg Submittal 01AUG11 03AUG11 3
1.4.2 TAKOMA PARK STATION
1.4.2.1 STATION DESIGN
1.4.2.1.1 Takoma Park 60% Design 01APR11 28APR11 20
1.4.2.1.2 Takoma Park 60% Submit 28APR11 0
1.4.2.1.3 Takoma Park 60% Review 29APR11 27MAY11 21
1.4.2.1.4 Takoma Park 90% Design 30MAY11 17JUN11 15
1.4.2.1.5 Takoma Park 90% Submit 17JUN11 0
1.4.2.1.6 Takoma Park 90% Review 17JUN11 15JUL11 21
1.4.2.1.7 Takoma Park IFC Set 18JUL11 22JUL11 5
1.4.2.1.8 Takoma Park 100% Submit 22JUL11 0
1.4.2.2 Design Complete - Redline CCTV and PA Design 22JUL11 0
1.4.2.2.1 STATION REHABILITATION
1.4.2.2.2 FTS - Start/Mobilize Station Rehabilitation 18JUL11 19JUL11 2
1.4.2.2.3 TPS - PA/CCTV Field Device Installation 20JUL11 16AUG11 20
1.4.2.2.4 TPS - PA/CCTV Head End Installation 17AUG11 06SEP11 15
1.4.2.2.5 TPS - PA Field Device Testing 07SEP11 08SEP11 2
1.4.2.2.6 TPS - CCTV Field Device Testing 09SEP11 12SEP11 2
1.4.2.2.7 TPS - PA & CCTV Final Accpt. Testing & Commision 13SEP11 15SEP11 3
1.4.2.3 STATION CLOSE-OUT
1.4.2.3.1 TPS - Station Close-Out 16SEP11 0
1.4.2.3.2 TPS - Substantial Completion Inspection (SCI) 16SEP11 19SEP11 2
1.4.2.3.3 TPS - As-Built Pkg & Final O&M Pkg Submittal 20SEP11 22SEP11 3
1.4.2.3.4 Project Complete - Redline CCTV and PA 22SEP11 0
2 REDLINE ATC DESIGN
2.1 PHASE 1
2.1.1 RHODE ISLAND AVENUE STATION
2.1.1.1 STATION DESIGN
2.1.1.1.1 Start Redline CCTV and PA Design Project 18JAN10A 0
2.1.1.1.2 Rhode Island Ave. 60% Design 18JAN10A 12FEB10A 40
2.1.1.1.3 Rhode Island Ave. 60% Submit 15MAR10A 0
2.1.1.1.4 Rhode Island Ave. 60% Review 15MAR10A 28APR10A 21
2.1.1.1.5 Rhode Island Ave. 90% Design 01JUN10A 14JUN10A 15
2.1.1.1.6 Rhode Island Ave. 90% Submit 14JUN10A 0
2.1.1.1.7 Rhode Island Ave. 90% Review 15JUN10A 03AUG10A 21
2.1.1.1.8 Rhode Island Ave. IFC Set 04AUG10A 12AUG10 6
2.1.1.1.9 Rhode Island Ave. 100% Submit 12AUG10 0
2.1.2 NEW YORK AVENUE STATION
2.1.2.1 STATION DESIGN
2.1.2.1.1 New York Ave. 60% Design 15FEB10A 17MAR10A 20
2.1.2.1.2 New York Ave. 60% Submit 17MAR10A 0
2.1.2.1.3 New York Ave. 60% Review 15APR10A 17MAY10A 21
2.1.2.1.4 New York Ave. 90% Design 18MAY10A 25JUN10A 15
2.1.2.1.5 New York Ave. 90% Submit 11AUG10 0
2.1.2.1.6 New York Ave. 90% Review 17AUG10 23AUG10 5
2.1.2.1.7 New York Ave. IFC Set 24AUG10 30AUG10 5
2.1.2.1.8 New York Ave. 100% Submit 30AUG10 0
2.1.3 UNION STATION
2.1.3.1 STATION DESIGN
2.1.3.1.1 Union Station 60% Design 17MAR10A 13APR10A 20
2.1.3.1.2 Union Station 60% Submit 23APR10A 0
2.1.3.1.3 Union Station 60% Review 26APR10A 21JUN10A 21
2.1.3.1.4 Union Station 90% Design 12AUG10A 01SEP10 15
2.1.3.1.5 Union Station 90% Submit 01SEP10 0
2.1.3.1.6 Union Station 90% Review 02SEP10 30SEP10 21
2.1.3.1.7 Union Station IFC Set 01OCT10 07OCT10 5
2.1.3.1.8 Union Station 100% Submit 07OCT10 0
2.1.4 JUDICIARY SQUARE STATION
2.1.4.1 STATION DESIGN
2.1.4.1.1 Judiciary Square 60% Design 23APR10A 11MAY10A 20
2.1.4.1.2 Judiciary Square 60% Submit 11MAY10A 0
2.1.4.1.3 Judiciary Square 60% Review 12MAY10A 21JUN10A 21
2.1.4.1.4 Judiciary Square 90% Design 19AUG10 08SEP10 15
2.1.4.1.5 Judiciary Square 90% Submit 08SEP10 0
2.1.4.1.6 Judiciary Square 90% Review 15SEP10 13OCT10 21
2.1.4.1.7 Judiciary Square IFC Set 14OCT10 20OCT10 5
2.1.4.1.8 Judiciary Square 100% Submit 20OCT10 0
2.2 PHASE 2
2.2.1 GALLERY PLACE STATION
2.2.1.1 STATION DESIGN
2.2.1.1.1 Gallery Place 60% Design 26AUG10 22SEP10 20
2.2.1.1.2 Gallery Place 60% Submit 22SEP10 0
2.2.1.1.3 Gallery Place 60% Review 22SEP10 20OCT10 21
2.2.1.1.4 Gallery Place 90% Design 21OCT10 10NOV10 15
2.2.1.1.5 Gallery Place 90% Submit 10NOV10 0
2.2.1.1.6 Gallery Place 90% Review 03NOV10 01DEC10 21
2.2.1.1.7 Gallery Place IFC Set 02DEC10 08DEC10 5
2.2.1.1.8 Gallery Place 100% Submit 08DEC10 0
2.2.2 METRO CENTER STATION
2.2.2.1 STATION DESIGN
2.2.2.1.1 Metro Center 60% Design 23SEP10 20OCT10 20
2.2.2.1.2 Metro Center 60% Submit 20OCT10 0
2.2.2.1.3 Metro Center 60% Review 21OCT10 18NOV10 21
2.2.2.1.4 Metro Center 90% Design 19NOV10 01DEC10 15
2.2.2.1.5 Metro Center 90% Submit 01DEC10 0
2.2.2.1.6 Metro Center 90% Review 24NOV10 22DEC10 21
2.2.2.1.7 Metro Center IFC Set 23DEC10 29DEC10 5
2.2.2.1.8 Metro Center 100% Submit 29DEC10 0
2.2.3 FARRAGUT NORTH STATION
2.2.3.1 STATION DESIGN
2.2.3.1.1 Farragut North 60% Design 21OCT10 17NOV10 20
2.2.3.1.2 Farragut North 60% Submit 17NOV10 0
2.2.3.1.3 Farragut North 60% Review 18NOV10 16DEC10 21
2.2.3.1.4 Farragut North 90% Design 17DEC10 06JAN11 15
2.2.3.1.5 Farragut North 90% Submit 06JAN11 0
2.2.3.1.6 Farragut North 90% Review 06JAN11 03FEB11 21
2.2.3.1.7 Farragut North IFC Set 04FEB11 10FEB11 5
2.2.3.1.8 Farragut North 100% Submit 10FEB11 0
2.2.4 DUPONT CIRCLE STATION
2.2.4.1 STATION DESIGN
2.2.4.1.1 Dupont Circle 60% Design 18NOV10 15DEC10 20
2.2.4.1.2 Dupont Circle 60% Submit 15DEC10 0
2.2.4.1.3 Dupont Circle 60% Review 16DEC10 13JAN11 21
2.2.4.1.4 Dupont Circle 90% Design 14JAN11 03FEB11 15
2.2.4.1.5 Dupont Circle 90% Submit 03FEB11 0
2.2.4.1.6 Dupont Circle 90% Review 03FEB11 03MAR11 21
2.2.4.1.7 Dupont Circle IFC Set 04MAR11 11MAR11 6
2.2.4.1.8 Dupont Circle 100% Submit 11MAR11 0
2.3 PHASE 3
2.3.1 BROOKLAND STATION
2.3.1.1 STATION DESIGN
2.3.1.1.1 Brookland 60% Design 16DEC10 12JAN11 20
2.3.1.1.2 Brookland 60% Submit 12JAN11 0
2.3.1.1.3 Brookland 60% Review 13JAN11 10FEB11 21
2.3.1.1.4 Brookland 90% Design 11FEB11 03MAR11 15
2.3.1.1.5 Brookland 90% Submit 03MAR11 0
2.3.1.1.6 Brookland 90% Review 03MAR11 31MAR11 21
2.3.1.1.7 Brookland IFC Set 01APR11 07APR11 5
2.3.1.1.8 Brookland 100% Submit 07APR11 0
2.3.2 FORT TOTTEN STATION
2.3.2.1 STATION DESIGN
2.3.2.1.1 Fort Totten 60% Design 13JAN11 09FEB11 20
2.3.2.1.2 Fort Totten 60% Submit 09FEB11 0
2.3.2.1.3 Fort Totten 60% Review 10FEB11 10MAR11 21
2.3.2.1.4 Fort Totten 90% Design 11MAR11 31MAR11 15
2.3.2.1.5 Fort Totten 90% Submit 31MAR11 0
2.3.2.1.6 Fort Totten 90% Review 31MAR11 28APR11 21
2.3.2.1.7 Fort Totten IFC Set 29APR11 09MAY11 7
2.3.2.1.8 Fort Totten 100% Submit 09MAY11 0
2.4 PHASE 4
2.4.1 SILVER SPRING STATION
2.4.1.1 STATION DESIGN
2.4.1.1.1 Silver Spring 60% Design 10FEB11 09MAR11 20
2.4.1.1.2 Silver Spring 60% Submit 09MAR11 0
2.4.1.1.3 Silver Spring 60% Review 10MAR11 07APR11 21
2.4.1.1.4 Silver Spring 90% Design 08APR11 28APR11 15
2.4.1.1.5 Silver Spring 90% Submit 28APR11 0
2.4.1.1.6 Silver Spring 90% Review 28APR11 26MAY11 21
2.4.1.1.7 Silver Spring IFC Set 27MAY11 02JUN11 5
2.4.1.1.8 Silver Spring 100% Submit 02JUN11 0
2.4.2 TAKOMA PARK STATION
2.4.2.1 STATION DESIGN
2.4.2.1.1 Takoma Park 60% Design 01APR11 28APR11 20
2.4.2.1.2 Takoma Park 60% Submit 28APR11 0
2.4.2.1.3 Takoma Park 60% Review 29APR11 27MAY11 21
2.4.2.1.4 Takoma Park 90% Design 30MAY11 17JUN11 15
2.4.2.1.5 Takoma Park 90% Submit 17JUN11 0
2.4.2.1.6 Takoma Park 90% Review 17JUN11 15JUL11 21
2.4.2.1.7 Takoma Park IFC Set 18JUL11 22JUL11 5
2.4.2.1.8 Takoma Park 100% Submit 22JUL11 0
2.4.2.1.9 Project Complete - Redline ATC DESIGN 22SEP11 0
3 REDLINE ETS DESIGN
3.1 PHASE 1
3.1.1 JUDICIARY TO RHODE ISLAND AVENUE
3.1.1.1 STATION DESIGN
3.1.1.1.1 Start Redline ETS Design Project 18JAN10A 0
3.1.1.1.2 Judiciary to Rhode Island Ave. 60% Design 18JAN10A 12FEB10A 40
3.1.1.1.3 Judiciary to Rhode Island Ave. 60% Submit 15MAR10A 0
3.1.1.1.4 Judiciary to Rhode Island Ave. 60% Review 15MAR10A 28APR10A 21
3.1.1.1.5 Judiciary to Rhode Island Ave. 90% Design 01JUN10A 14JUN10A 15
3.1.1.1.6 Judiciary to Rhode Island Ave. 90% Submit 14JUN10A 0
3.1.1.1.7 Judiciary to Rhode Island Ave. 90% Review 15JUN10A 03AUG10A 21
3.1.1.1.8 Judiciary to Rhode Island Ave. IFC Set 04AUG10A 12AUG10 6
3.1.1.1.9 Judiciary to Rhode Island Ave. 100% Submit 12AUG10 0
3.2 PHASE 2
3.2.1 DUPONT TO GALLERY PLACE
3.2.1.1 STATION DESIGN
3.2.1.1.1 Dupont to Gallery Place 60% Design 18JAN10A 12FEB10A 40
3.2.1.1.2 Dupont to Gallery Place 60% Submit 15MAR10A 0
3.2.1.1.3 Dupont to Gallery Place 60% Review 15MAR10A 28APR10A 21
3.2.1.1.4 Dupont to Gallery Place 90% Design 01JUN10A 14JUN10A 15
3.2.1.1.5 Dupont to Gallery Place 90% Submit 14JUN10A 0
3.2.1.1.6 Dupont to Gallery Place 90% Review 15JUN10A 03AUG10A 21
3.2.1.1.7 Dupont to Gallery Place IFC Set 04AUG10A 12AUG10 6
3.2.1.1.8 Dupont to Gallery Place 100% Submit 12AUG10 0
3.3 PHASE 3
3.3.1 FORT TOTTEN TO BROOKLAND
3.3.1.1 STATION DESIGN
3.3.1.1.1 Fort Totten to Brookland 60% Design 18JAN10A 12FEB10A 40
3.3.1.1.2 Fort Totten to Brookland 60% Submit 15MAR10A 0
3.3.1.1.3 Fort Totten to Brookland 60% Review 15MAR10A 28APR10A 21
3.3.1.1.4 Fort Totten to Brookland 90% Design 01JUN10A 14JUN10A 15
3.3.1.1.5 Fort Totten to Brookland 90% Submit 14JUN10A 0
3.3.1.1.6 Fort Totten to Brookland 90% Review 15JUN10A 03AUG10A 21
3.3.1.1.7 Fort Totten to Brookland IFC Set 04AUG10A 12AUG10 6
3.3.1.1.8 Fort Totten to Brookland 100% Submit 12AUG10 0
3.2 PHASE 4
3.2.1 TAKOMA PARK TO SILVER SPRING
3.2.1.1 STATION DESIGN
3.2.1.1.1 Start Redline ETS Design Project 18JAN10A 0
3.2.1.1.2 Takoma Park to Silver Spring 60% Design 18JAN10A 12FEB10A 40
3.2.1.1.3 Takoma Park to Silver Spring 60% Submit 15MAR10A 0
3.2.1.1.4 Takoma Park to Silver Spring 60% Review 15MAR10A 28APR10A 21
3.2.1.1.5 Takoma Park to Silver Spring 90% Design 01JUN10A 14JUN10A 15
3.2.1.1.6 Takoma Park to Silver Spring 90% Submit 14JUN10A 0
3.2.1.1.7 Takoma Park to Silver Spring 90% Review 15JUN10A 03AUG10A 21
3.2.1.1.8 Takoma Park to Silver Spring IFC Set 04AUG10A 12AUG10 6
3.2.1.1.9 Takoma Park to Silver Spring 100% Submit 12AUG10 0
2.4.2.1.9 Project Complete - Redline ETS DESIGN 22SEP11 0
Remaining Actual start Actual end Actual
Duration date date duration % Complete Resources

0 18JAN10A 0 100
0 18JAN10A 12FEB10A 40 100
0 15MAR10A 0 100
0 15MAR10A 28APR10A 21 100
0 01JUN10A 14JUN10A 15 100
0 14JUN10A 0 100
0 15JUN10A 03AUG10A 21 100
1 04AUG10A 12AUG10 TBD 83
0 TBD 0

0 28JUN10A 03AUG10A 30 100


2 TBD 0
20 TBD 0
15 TBD 0
2 TBD 0
2 TBD 0
3 TBD 0
TBD
0 TBD 0
2 TBD 0
3 TBD 0

0 15FEB10A 17MAR10A 20 100


0 17MAR10A 0 100
0 15APR10A 17MAY10A 21 100
0 18MAY10A 25JUN10A 15 100
0 TBD 0
5 TBD 0
5 TBD 0
0 TBD 0

2 TBD 0
20 TBD 0
15 TBD 0
2 TBD 0
2 TBD 0
3 TBD 0
0 TBD 0
2 TBD 0
3 TBD 0

0 17MAR10A 13APR10A 20 100


0 23APR10A 0 100
0 26APR10A 21JUN10A 21 100
15 TBD 0
0 TBD 0
21 TBD 0
5 TBD 0
0 TBD 0

2 TBD 0
8 TBD 0
5 TBD 0
2 TBD 0
3 TBD 0
TBD
0 TBD 0
2 TBD 0
3 TBD 0

0 23APR10A 11MAY10A 20 100


0 11MAY10A 0 100
0 12MAY10A 21JUN10A 21 100
15 TBD 0
0 TBD 0
21 TBD 0
5 TBD 0
0 TBD 0

2 TBD 0
8 TBD 0
5 TBD 0
2 TBD 0
3 TBD 0

0 TBD 0
2 TBD 0
3 TBD 0
20 TBD 0
0 TBD 0
21 TBD 0
15 TBD 0
0 TBD 0
21 TBD 0
5 TBD 0
0 TBD 0

2 TBD 0
15 TBD 0
5 TBD 0
2 TBD 0
3 TBD 0

0 TBD 0
2 TBD 0
3 TBD 0

20 TBD 0
0 TBD 0
21 TBD 0
9 19NOV10 01DEC10 TBD 10
0 TBD 0
21 TBD 0
5 TBD 0
0 TBD 0

2 TBD 0
15 TBD 0
5 TBD 0
2 TBD 0
3 TBD 0

0 TBD 0
2 TBD 0
3 TBD 0

20 TBD 0
0 TBD 0
21 TBD 0
15 TBD 0
0 TBD 0
21 TBD 0
5 TBD 0
0 TBD 0

2 TBD 0
8 TBD 0
5 TBD 0
2 TBD 0
3 TBD 0

0 TBD 0
2 TBD 0
3 TBD 0

20 TBD 0
0 TBD 0
21 TBD 0
15 TBD 0
0 TBD 0
21 TBD 0
6 TBD 0
0 TBD 0

2 TBD 0
8 TBD 0
5 TBD 0
2 TBD 0
3 TBD 0

0 TBD 0
2 TBD 0
3 TBD 0

20 TBD 0
0 TBD 0
21 TBD 0
15 TBD 0
0 TBD 0
21 TBD 0
5 TBD 0
0 TBD 0
2 TBD 0
20 TBD 0
15 TBD 0
2 TBD 0
2 TBD 0
3 TBD 0

0 TBD 0
2 TBD 0
3 TBD 0

20 TBD 0
0 TBD 0
21 TBD 0
15 TBD 0
0 TBD 0
21 TBD 0
7 TBD 0
0 TBD 0

2 TBD 0
20 TBD 0
15 TBD 0
2 TBD 0
2 TBD 0
3 TBD 0

0 TBD 0
2 TBD 0
3 TBD 0

20 TBD 0
0 TBD 0
21 TBD 0
15 TBD 0
0 TBD 0
21 TBD 0
5 TBD 0
0 TBD 0

2 TBD 0
20 TBD 0
15 TBD 0
2 TBD 0
2 TBD 0
3 TBD 0

0 TBD 0
2 TBD 0
3 TBD 0

20 TBD 0
0 TBD 0
21 TBD 0
15 TBD 0
0 TBD 0
21 TBD 0
5 TBD 0
0 TBD 0
0 TBD 0

2 TBD 0
20 TBD 0
15 TBD 0
2 TBD 0
2 TBD 0
3 TBD 0

0 TBD 0
2 TBD 0
3 TBD 0
0 TBD 0

0 18JAN10A 0 100
0 18JAN10A 12FEB10A 40 100
0 15MAR10A 0 100
0 15MAR10A 28APR10A 21 100
0 01JUN10A 14JUN10A 15 100
0 14JUN10A 0 100
0 15JUN10A 03AUG10A 21 100
1 04AUG10A 12AUG10 TBD 83
0 TBD 0
0 15FEB10A 17MAR10A 20 100
0 17MAR10A 0 100
0 15APR10A 17MAY10A 21 100
0 18MAY10A 25JUN10A 15 100
0 TBD 0
5 TBD 0
5 TBD 0
0 TBD 0

0 17MAR10A 13APR10A 20 100


0 23APR10A 0 100
0 26APR10A 21JUN10A 21 100
15 TBD 0
0 TBD 0
21 TBD 0
5 TBD 0
0 TBD 0

0 23APR10A 11MAY10A 20 100


0 11MAY10A 0 100
0 12MAY10A 21JUN10A 21 100
15 TBD 0
0 TBD 0
21 TBD 0
5 TBD 0
0 TBD 0

20 TBD 0
0 TBD 0
21 TBD 0
15 TBD 0
0 TBD 0
21 TBD 0
5 TBD 0
0 TBD 0

20 TBD 0
0 TBD 0
21 TBD 0
9 19NOV10 01DEC10 TBD 10
0 TBD 0
21 TBD 0
5 TBD 0
0 TBD 0

20 TBD 0
0 TBD 0
21 TBD 0
15 TBD 0
0 TBD 0
21 TBD 0
5 TBD 0
0 TBD 0

20 TBD 0
0 TBD 0
21 TBD 0
15 TBD 0
0 TBD 0
21 TBD 0
6 TBD 0
0 TBD 0

20 TBD 0
0 TBD 0
21 TBD 0
15 TBD 0
0 TBD 0
21 TBD 0
5 TBD 0
0 TBD 0

20 TBD 0
0 TBD 0
21 TBD 0
15 TBD 0
0 TBD 0
21 TBD 0
7 TBD 0
0 TBD 0

20 TBD 0
0 TBD 0
21 TBD 0
15 TBD 0
0 TBD 0
21 TBD 0
5 TBD 0
0 TBD 0

20 TBD 0
0 TBD 0
21 TBD 0
15 TBD 0
0 TBD 0
21 TBD 0
5 TBD 0
0 TBD 0
0 TBD 0

0 18JAN10A 0 100
0 18JAN10A 12FEB10A 40 100
0 15MAR10A 0 100
0 15MAR10A 28APR10A 21 100
0 01JUN10A 14JUN10A 15 100
0 14JUN10A 0 100
0 15JUN10A 03AUG10A 21 100
1 04AUG10A 12AUG10 TBD 83
0 TBD 0

0 18JAN10A 12FEB10A 40 100


0 15MAR10A 0 100
0 15MAR10A 28APR10A 21 100
0 01JUN10A 14JUN10A 15 100
0 14JUN10A 0 100
0 15JUN10A 03AUG10A 21 100
1 04AUG10A 12AUG10 TBD 83
0 TBD 0

0 18JAN10A 12FEB10A 40 100


0 15MAR10A 0 100
0 15MAR10A 28APR10A 21 100
0 01JUN10A 14JUN10A 15 100
0 14JUN10A 0 100
0 15JUN10A 03AUG10A 21 100
1 04AUG10A 12AUG10 TBD 83
0 TBD 0

0 18JAN10A 0 100
0 18JAN10A 12FEB10A 40 100
0 15MAR10A 0 100
0 15MAR10A 28APR10A 21 100
0 01JUN10A 14JUN10A 15 100
0 14JUN10A 0 100
0 15JUN10A 03AUG10A 21 100
1 04AUG10A 12AUG10 TBD 83
0 TBD 0
0 TBD 0
Deliverables & Delivery Method
System
Design Deliverable PA & CCTV ATC ETS
RHODE ISLAND AVENUE STATION
60% Design - 3 copies in .dgw on CD - 3 copies in .dgw on CD *thru Judiciary Square Station
- 3 copies in pdf on CD - 3 copies in pdf on CD - 3 copies in .dgw on CD
- 3 hardcopy - 3 hardcopy - 3 copies in pdf on CD
- 3 hardcopy

90% Design - 3 copies in .dgw on CD - 3 copies in .dgw on CD - 3 copies in .dgw on CD


- 3 copies in pdf on CD - 3 copies in pdf on CD - 3 copies in pdf on CD
- 3 hardcopy - 3 hardcopy - 3 hardcopy

IFC Set - 3 copies in .dgw on CD - 3 copies in .dgw on CD - 3 copies in .dgw on CD


- 3 copies in pdf on CD - 3 copies in pdf on CD - 3 copies in pdf on CD
- 3 hardcopy - 3 hardcopy - 3 hardcopy

NEW YORK AVENUE STATION


60% Design - 3 copies in .dgw on CD - 3 copies in .dgw on CD
- 3 copies in pdf on CD - 3 copies in pdf on CD
- 3 hardcopy - 3 hardcopy

90% Design - 3 copies in .dgw on CD - 3 copies in .dgw on CD


- 3 copies in pdf on CD - 3 copies in pdf on CD
- 3 hardcopy - 3 hardcopy

IFC Set - 3 copies in .dgw on CD - 3 copies in .dgw on CD


- 3 copies in pdf on CD - 3 copies in pdf on CD
- 3 hardcopy - 3 hardcopy

RHODE ISLAND AVENUE STATION


60% Design - 3 copies in .dgw on CD - 3 copies in .dgw on CD
- 3 copies in pdf on CD - 3 copies in pdf on CD
- 3 hardcopy - 3 hardcopy
Phase 1

90% Design - 3 copies in .dgw on CD - 3 copies in .dgw on CD


- 3 copies in pdf on CD - 3 copies in pdf on CD
- 3 hardcopy - 3 hardcopy

IFC Set - 3 copies in .dgw on CD - 3 copies in .dgw on CD


- 3 copies in pdf on CD - 3 copies in pdf on CD
- 3 hardcopy - 3 hardcopy

UNION STATION
60% Design - 3 copies in .dgw on CD - 3 copies in .dgw on CD
- 3 copies in pdf on CD - 3 copies in pdf on CD
- 3 hardcopy - 3 hardcopy

90% Design - 3 copies in .dgw on CD - 3 copies in .dgw on CD


- 3 copies in pdf on CD - 3 copies in pdf on CD
- 3 hardcopy - 3 hardcopy

IFC Set - 3 copies in .dgw on CD - 3 copies in .dgw on CD


- 3 copies in pdf on CD - 3 copies in pdf on CD
- 3 hardcopy - 3 hardcopy

JUDICIARY SQUARE STATION


60% Design - 3 copies in .dgw on CD - 3 copies in .dgw on CD
- 3 copies in pdf on CD - 3 copies in pdf on CD
- 3 hardcopy - 3 hardcopy

90% Design - 3 copies in .dgw on CD - 3 copies in .dgw on CD


- 3 copies in pdf on CD - 3 copies in pdf on CD
- 3 hardcopy - 3 hardcopy

IFC Set - 3 copies in .dgw on CD - 3 copies in .dgw on CD


- 3 copies in pdf on CD - 3 copies in pdf on CD
- 3 hardcopy - 3 hardcopy
Deliverables & Delivery Method
System
Design Deliverable PA & CCTV ATC ETS
GALLERY PLACE STATION
60% Design - 3 copies in .dgw on CD - 3 copies in .dgw on CD *thru Dupont Circle Station
- 3 copies in pdf on CD - 3 copies in pdf on CD - 3 copies in .dgw on CD
- 3 hardcopy - 3 hardcopy - 3 copies in pdf on CD
- 3 hardcopy

90% Design - 3 copies in .dgw on CD - 3 copies in .dgw on CD - 3 copies in .dgw on CD


- 3 copies in pdf on CD - 3 copies in pdf on CD - 3 copies in pdf on CD
- 3 hardcopy - 3 hardcopy - 3 hardcopy

IFC Set - 3 copies in .dgw on CD - 3 copies in .dgw on CD - 3 copies in .dgw on CD


- 3 copies in pdf on CD - 3 copies in pdf on CD - 3 copies in pdf on CD
- 3 hardcopy - 3 hardcopy - 3 hardcopy

METRO CENTER STATION


60% Design - 3 copies in .dgw on CD - 3 copies in .dgw on CD
- 3 copies in pdf on CD - 3 copies in pdf on CD
- 3 hardcopy - 3 hardcopy

90% Design - 3 copies in .dgw on CD - 3 copies in .dgw on CD


- 3 copies in pdf on CD - 3 copies in pdf on CD
- 3 hardcopy - 3 hardcopy

IFC Set - 3 copies in .dgw on CD - 3 copies in .dgw on CD


- 3 copies in pdf on CD - 3 copies in pdf on CD
Phase 2

- 3 hardcopy - 3 hardcopy

FARRAGUT NORTH STATION


60% Design - 3 copies in .dgw on CD - 3 copies in .dgw on CD
- 3 copies in pdf on CD - 3 copies in pdf on CD
- 3 hardcopy - 3 hardcopy

90% Design - 3 copies in .dgw on CD - 3 copies in .dgw on CD


- 3 copies in pdf on CD - 3 copies in pdf on CD
- 3 hardcopy - 3 hardcopy

IFC Set - 3 copies in .dgw on CD - 3 copies in .dgw on CD


- 3 copies in pdf on CD - 3 copies in pdf on CD
- 3 hardcopy - 3 hardcopy

DUPONT CIRCLE STATION


60% Design - 3 copies in .dgw on CD - 3 copies in .dgw on CD
- 3 copies in pdf on CD - 3 copies in pdf on CD
- 3 hardcopy - 3 hardcopy

90% Design - 3 copies in .dgw on CD - 3 copies in .dgw on CD


- 3 copies in pdf on CD - 3 copies in pdf on CD
- 3 hardcopy - 3 hardcopy

IFC Set - 3 copies in .dgw on CD - 3 copies in .dgw on CD


- 3 copies in pdf on CD - 3 copies in pdf on CD
- 3 hardcopy - 3 hardcopy
Deliverables & Delivery Method
System
Design Deliverable PA & CCTV ATC ETS
BROOKLAND STATION
60% Design - 3 copies in .dgw on CD - 3 copies in .dgw on CD *thru Fort Totten Station
- 3 copies in pdf on CD - 3 copies in pdf on CD - 3 copies in .dgw on CD
- 3 hardcopy - 3 hardcopy - 3 copies in pdf on CD
- 3 hardcopy

90% Design - 3 copies in .dgw on CD - 3 copies in .dgw on CD - 3 copies in .dgw on CD


- 3 copies in pdf on CD - 3 copies in pdf on CD - 3 copies in pdf on CD
- 3 hardcopy - 3 hardcopy - 3 hardcopy

IFC Set - 3 copies in .dgw on CD - 3 copies in .dgw on CD - 3 copies in .dgw on CD


- 3 copies in pdf on CD - 3 copies in pdf on CD - 3 copies in pdf on CD
Phase 3

- 3 hardcopy - 3 hardcopy - 3 hardcopy

FORT TOTTEN STATION


60% Design - 3 copies in .dgw on CD - 3 copies in .dgw on CD
- 3 copies in pdf on CD - 3 copies in pdf on CD
- 3 hardcopy - 3 hardcopy

90% Design - 3 copies in .dgw on CD - 3 copies in .dgw on CD


- 3 copies in pdf on CD - 3 copies in pdf on CD
- 3 hardcopy - 3 hardcopy

IFC Set - 3 copies in .dgw on CD - 3 copies in .dgw on CD


- 3 copies in pdf on CD - 3 copies in pdf on CD
- 3 hardcopy - 3 hardcopy

SILVER SPRING STATION


60% Design - 3 copies in .dgw on CD - 3 copies in .dgw on CD *thru Takoma Park Station
- 3 copies in pdf on CD - 3 copies in pdf on CD - 3 copies in .dgw on CD
- 3 hardcopy - 3 hardcopy - 3 copies in pdf on CD
- 3 hardcopy

90% Design - 3 copies in .dgw on CD - 3 copies in .dgw on CD - 3 copies in .dgw on CD


- 3 copies in pdf on CD - 3 copies in pdf on CD - 3 copies in pdf on CD
- 3 hardcopy - 3 hardcopy - 3 hardcopy

IFC Set - 3 copies in .dgw on CD - 3 copies in .dgw on CD - 3 copies in .dgw on CD


- 3 copies in pdf on CD - 3 copies in pdf on CD - 3 copies in pdf on CD
Phase 4

- 3 hardcopy - 3 hardcopy - 3 hardcopy

TAKOMA PARK STATION


60% Design - 3 copies in .dgw on CD - 3 copies in .dgw on CD
- 3 copies in pdf on CD - 3 copies in pdf on CD
- 3 hardcopy - 3 hardcopy

90% Design - 3 copies in .dgw on CD - 3 copies in .dgw on CD


- 3 copies in pdf on CD - 3 copies in pdf on CD
- 3 hardcopy - 3 hardcopy

IFC Set - 3 copies in .dgw on CD - 3 copies in .dgw on CD


- 3 copies in pdf on CD - 3 copies in pdf on CD
- 3 hardcopy - 3 hardcopy