Traveler Sample

This document is a traveler for manufacturing a fracture/maintenance/safety critical part. It specifies that the part must be manufactured, processed, inspected, identified and serialized according to specification #0001. Any changes to the manufacturing plan require approval from the engineering quality assurance department. It provides instructions for operations including verifying material and size requirements, maintaining serialization, and assuring serialization is maintained through each operation.

Uploaded by

Beny Blanko
Copyright
© Attribution Non-Commercial (BY-NC)
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
100% found this document useful (2 votes)
8K views

Traveler Sample

This document is a traveler for manufacturing a fracture/maintenance/safety critical part. It specifies that the part must be manufactured, processed, inspected, identified and serialized according to specification #0001. Any changes to the manufacturing plan require approval from the engineering quality assurance department. It provides instructions for operations including verifying material and size requirements, maintaining serialization, and assuring serialization is maintained through each operation.

Uploaded by

Beny Blanko
Copyright
© Attribution Non-Commercial (BY-NC)
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
You are on page 1/ 3

**FRACTURE/MAINTENANCE/SAFETY CRITICAL TRACEABLE DETAIL & ASSEMBLY

TRAVELER**
JOB NUMBER ABC Company SHOP TRAVELER
123 Main St.
Anytown, USA
SERIAL NUMBER 800-555-1234
www.abccompany.com
REVISION:
DATE:
P.O. # CUSTOMER: PART NAME:

PART NUMBER: REVISION:

QTY REQ: QTY RUNNING: QTY COMPLETE: DUE DATE:

PLANNED BY: ARDEN APPROVAL:

PLAN REV DESCRIPTION OF CHANGE DATE REVISED BY:

THIS PART IS FRACTURE/MAINTENANCE/SAFETY CRITICAL TRACEABLE.


MANUFACTURE, PROCESS, INSPECT, IDENTIFY AND SERIALIZE PER SPEC #0001

MANUFACTURING PLANS FOR FRACTURE/MAINTENANCE/SAFETY CRITICAL PARTS ARE


REQUIRED TO BE PREPARED AND MAINTAINED BY ABC COMPANY. ANY CHANGES TO
THIS PLAN REQUIRE 123 ENGINEERING QUALITY ASSURANCE APPROVAL

NOTE: ALL OPERATIONS AND/OR CERTIFICATIONS MUST USE THE LATEST REVISION,
AMENDMENTS, DEVIATIONS AND ENGINEERING ORDERS OF APPLICABLE SPECIFICATIONS &
IT’S DERIVATIVES
**FRACTURE/MAINTENANCE/SAFETY CRITICAL TRACEABLE DETAIL & ASSEMBLY
TRAVELER**
JOB NUMBER ABC Company SHOP TRAVELER
123 Main St.
Anytown, USA
SERIAL NUMBER 800-555-1234
www.abccompany.com
REVISION:
DATE:
P.O. # CUSTOMER: PART NAME:

PART NUMBER: REVISION:

AT TIME OF PROCESSING, LATEST REVISION MUST BE USED FOR ALL SPECIFICATIONS


LISTED

OPE AC DAT
OP WC DESCRIPTION REJ
R C E

ARDEN P.O. #:_________________________

SUPPLIER NAME: ________________________

MILL NAME & CERTIFICATION #:___________________

RECORD ARDEN SERIAL #:_________________________

INSP VERIFY THE FOLLOWING:

MATERIAL TYPE AND SIZE


DIRECTION OF GRAIN
VERIFY MATERIAL MEETS CALSS A ULTRASONIC
INSPECTION REQUIREMENTS
HEAT LOT:

MATERIAL TYPE AND SIZE REQUIREMENTS PER PDM


MATERIAL:
SIZE:

ALLOWABLE SUBSTITUTION PER __________________


MATERIAL: PER
SIZE:

OR
MATERIAL:
**FRACTURE/MAINTENANCE/SAFETY CRITICAL TRACEABLE DETAIL & ASSEMBLY
TRAVELER**
JOB NUMBER ABC Company SHOP TRAVELER
123 Main St.
Anytown, USA
SERIAL NUMBER 800-555-1234
www.abccompany.com
REVISION:
DATE:
P.O. # CUSTOMER: PART NAME:

PART NUMBER: REVISION:

SIZE:

OPE AC DAT
OP WC DESCRIPTION REJ
R C E
MANUFACTURE COMPLETE AS FOLLOWS:

VERIFY GRAIN DIRECTION

MAINTAIN SERIAL # _______________________


LIST SERIAL #’S GIVEN US BY ARDEN

VERIFY MACHINING OPERATION


INSP
ASSURE SERIALIZATION IS BEING MAINTAINED

More machining ops/instruction here

VERIFY GRAIN DIRECTION

ASSURE SERIALIZATION IS BEING MAINTAINED ON EACH


PART

VERIFY MILL OPERATION


INSP
ASSURE SERIALIZATION IS BEING MAINTAINED ON EACH
PART