Assignment Submission on
Project Management
CASE: D.U. SINGER HOSPITAL
Done By : Raja Dhanapal, EMBA12039
7/25/2009
TABLE OF CONTENTS
1. ACTIVITY CHART
2. NETWORK DIAGRAM
3. POTENTIAL PATHS
4. SLACK ON ACTIVITY
5. GHANTT CHART
6. RESOURCE ALLOCATION ‐ LABOUR
7. RESOURCE ALLOCATION ‐ CASH
8. CASH FLOW STATEMENT
ACTIVITY CHART
Direct charges in $
Material and other
Hospital Products
Duration in week
Packaging Task
Manufacturing
Manufacturing
Maintenance
R & D Group
Engineering
Purchasing
Activity Description
Corporate
Packaged
Products
weeks
Force
a Product Rationale 1 12 1 1 2 0 0 17 10 0
b Develop Formula 0 16 4 2 0 0 0 22 14 500
c Product Specification 1 6 3 1 1 0 1 13 3 0
d Regulatory Documentation 0 12 4 2 0 0 0 18 3 0
e Develop Packaging Concept 12 8 4 2 8 0 2 36 10 4,000
f Design Packaging 12 2 3 0 3 0 3 23 6 2,000
g Develop Processing System 0 18 12 12 0 0 0 42 8 0
h Develop Packaging System 24 8 8 0 8 0 2 50 10 0
i Study Facilities Requirements 0 4 16 2 2 0 0 24 5 0
j Capital Equipment List 0 1 3 0 0 0 1 5 3 0
k Procurement of Process Equipment 0 1 1 1 0 0 7 10 18 40,000
l Procurement of Packaging Equipment 1 0 1 0 1 0 9 12 8 160,000
m Procure Facilities 0 0 1 1 1 1 6 10 6 30,000
n Install Process Equipment 0 2 4 8 0 4 1 19 5 4,000
o Install Packaging Equipment 2 0 4 0 8 4 1 19 5 8,000
p Install Facilities 0 0 5 5 5 10 1 26 5 6,000
q1 Written Procedures 5 5 5 10 15 10 0 30 7 3,000
q2 Written Procedures 20 5 2,000
r Pilot Test 3 6 6 6 6 6 0 33 8 0
Total no. of weeks 61 101 85 53 60 35 34 429 139 259,500
NETWORK DIAGRAM
d
3
c
3 g
b 8 q1
14 p
h i 7 m 5
5 6 q2
a e f 10 j l o 5 r
START END
10 10 6 3 8 5 8
k n
18 5
CRITICAL PATH
a e f h i j k n r TOTAL
10 10 6 10 5 3 18 5 8 75
POTENTIAL PATHS
Potential Paths a b c d e f g h i j k l m n o p q1 q2 r Total
Path1 10 10 6 10 5 3 18 5 8 75
Path2 10 14 3 8 5 3 18 5 8 74
Path3 10 10 6 10 5 3 6 5 5 8 68
Path4 10 10 6 10 5 3 8 5 8 65
Path5 10 14 3 8 5 3 8 5 8 64
Path6 10 10 6 10 5 7 5 8 61
Path7 10 14 3 8 5 7 5 8 60
CRITICAL PATH a-e-f-h-i-j-k-n-r 75
SLACK LIST ‐ BEFORE
Early Finish
Precedence
Duration in
Late Finish
Early Start
Late Start
Activity Description
SLCAK
week
a Product Rationale 10 ‐ 0 0 10 10 0
b Develop Formula 14 a 10 11 24 25 1
c Product Specification 3 b 24 25 27 28 1
d Regulatory Documentation 3 b 24 25 27 28 1
e Develop Packaging Concept 10 a 10 10 20 20 0
f Design Packaging 6 e 20 20 26 26 0
g Develop Processing System 8 c,d 27 28 35 36 1
h Develop Packaging System 10 f 26 26 36 36 0
i Study Facilities Requirements 5 g,h 36 36 41 41 0
j Capital Equipment List 3 i 41 41 44 44 0
k Procurement of Process Equipment 18 j 44 44 62 62 0
l Procurement of Packaging Equipment 8 j 44 54 52 62 10
m Procure Facilities 6 j 44 56 50 62 12
n Install Process Equipment 5 k 62 62 67 67 0
o Install Packaging Equipment 5 l 52 62 57 67 10
p Install Facilities 5 m 50 62 55 67 12
q1 Written Procedures 7 g,h 36 63 43 70 27
q2 Written Procedures 5 q1,n,o,p 67 70 72 75 3
r Pilot Test 8 n,o,p 67 67 75 75 0
Critical Path a,e,f,h,i,j,k,n,r
No.of Weeks in critical path 75
SLACK in the Following Activity in wks
b Develop Formula 1
c Product Specification 1
d Regulatory Documentation 1
g Develop Processing System 1
l Procurement of Packaging Equipment 10
m Procure Facilities 12
o Install Packaging Equipment 10
p Install Facilities 12
q1 Written Procedures 27
q2 Written Procedures 3
GHANTT CHART WITHOUT LEVELLING
Weeks 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36
a (10) e(10) f(6) h(10)
b(14)
g(8)
c(3), d(3)
16
1
15 d(18)
14
13
12
11
10
9
8 g(42)
7 c(13)
6 b(22)
5
4
3
2
1 a(17) e(36) f(23) h(50)
Wks 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36
Man
Wks. 2 2 2 2 2 2 2 1 1 1 5 5 5 5 5 5 5 5 5 5 6 6 6 6 14 14 15 10 10 10 10 10 10 11 11 5
Total Man Wks 429
CASH 1200 1200 1200 1200 1200 1200 1200 600 600 600 3000 3000 3000 3000 3000 3000 3000 3000 3000 3000 3600 3600 3600 3600 8400 8400 9000 6000 6000 6000 6000 6000 6000 6600 6600 3000
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36
16
15
14
13
12 d(18)
11
10
9
8 g(42)
7 c(13)
6 b(22)
5
4
3
2
1 a(17) e(36) f(23) h(50)
Wks 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36
Man
Wks. 2 2 2 2 2 2 2 1 1 1 5 5 5 5 5 5 5 5 5 5 6 6 6 6 12 12 12 12 10 10 10 10 10 10 11 11
Total Man Wks 429
CASH 1200 1200 1200 1200 1200 1200 1200 600 600 600 3000 3000 3000 3000 3000 3000 3000 3000 3000 3000 3600 3600 3600 3600 7200 7200 7200 7200 6000 6000 6000 6000 6000 6000 6600 6600
GHANTT CHART WITHOUT LEVELLING
Weeks 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 68 69 70 71 72 73 74 75
i(5) j(3) k(18) n(5) r(8)
l(8) o(5)
q(7)
16
15
14
13
12
11
10
9
8
7 o (19)
6 q(35) p(26)
5 m(10)
4
3
2 i(24) l(12)
1 j(5) k(10) q1(15) n(19) r(33)
Wks 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 68 69 70 71 72 73 74 75
Man
Wks. 9 9 9 9 9 9 9 1 5 5 5 5 4 2 7 7 8 8 9 9 9 3 3 3 0 0 4 4 4 4 3 5 4 4 4 4 4 4 4
CASH 5400 5400 5400 5400 5400 5400 5400 600 3000 3000 3000 3000 2400 1200 4200 4200 4800 4800 5400 5400 5400 1800 1800 1800 0 0 2400 2400 2400 2400 1800 3000 2400 2400 2400 2400 2400 2400 2400
37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 68 69 70 71 72 73 74 75
16
15
14
13
12
11
10
9
8
7
6 q(35) p(26)
5 m(10)
4 o (19)
3
2 i(24) l(12)
1 j(5) k(10) q1(15) n(19) r(33)
Wks 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 68 69 70 71 72 73 74 75
Man
Wks. 6 6 6 6 6 6 6 6 7 7 7 7 7 7 6 6 6 6 6 6 6 5 5 5 5 4 4 4 4 4 3 5 4 4 4 4 4 4 4
CASH 3600 3600 3600 3600 3600 3600 3600 3600 4200 4200 4200 4200 4200 4200 3600 3600 3600 3600 3600 3600 3600 3000 3000 3000 3000 2400 2400 2400 2400 2400 1800 3000 2400 2400 2400 2400 2400 2400 2400
10000
RESOURCE ALLOCATION ‐ CASH
9000
8000
7000
6000
5000 Cash Flow Before
Cash Flow After
4000
3000
2000
1000
0
1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 33 35 37 39 41 43 45 47 49 51 53 55 57 59 61 63 65 67 69 71 73 75
16
12
10
8 Series1
Series2
0
1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 33 35 37 39 41 43 45 47 49 51 53 55 57 59 61 63 65 67 69 71 73 75
CASH FLOW STATEMENT FOR THE PROJECT (After Levelling)
Weeks 5 10 15 20 25 30 35 40 45 50 55 60 65 70 75
Material - - 669.20 1,982.33 1,921.04 260.88 - 400.00 38,367.00 158,733.00 48,205.48 6,172.00 6,309.45 1,473.71 -
Labour 6 000 00
6,000.00 4 200 00
4,200.00 15 000 00
15,000.00 15 000 00
15,000.00 21 600 00
21,600.00 33 600 00
33,600.00 30 600 00
30,600.00 21 000 00
21,000.00 18 600 00
18,600.00 21 000 00
21,000.00 18 000 00
18,000.00 16 200 00
16,200.00 12 600 00
12,600.00 12 000 00
12,000.00 12,000.00
12 000 00
Total fund 6,000.00 4,200.00 15,669.20 16,982.33 23,521.04 33,860.88 30,600.00 21,400.00 56,967.00 179,733.00 66,205.48 22,372.00 18,909.45 13,473.71 12,000.00
Cum. fund 6,000.00 10,200.00 25,869.20 42,851.53 66,372.57 100,233.45 130,833.45 152,233.45 209,200.45 388,933.45 455,138.93 477,510.93 496,420.38 509,894.09 521,894.09
Assumption:
Assumption:-
It has been assumed that cash requirement for the material is uniform throughout the activity
Amount per
Total worker
Activity labour Amount week