Methods of Project Appraisal
Methods of Project Appraisal
Project Appraisal is the analysis of costs and benefits of a proposed project with a
goal of assuring a rational allocation of limited financial resources amongst alternate
Investment opportunities with the objective of achieving specific goals.
Technical Factors
Financial Factors
Economic Factors
Social Factors
Commercial Factors
Managerial Factors
Methods of Project Appraisal
METHODS OF
PROJ ECT APPRAISAL
The Pay-Back Period is the length of time required to recover the initial outlay on
the project Or It is the time required to recover the original investment through
income generated from the project.
Decision Rule: - A project which gives the shortest pay-back period, is considered
to be the most ACCEPTABLE
For Example: - If a Project involves a cash outlay of Rs. 2,00,000 and the Annual
Cash inflows are Rs. 50,000, 80,000, 60,000, and 40,000 during its
economic life of 4 years.
The standard NPV method is based on the assumption that the intermediate
cash flows are reinvested at a rate of return equal to the cost of capital. When
this assumption is not valid, the investment rates applicable to the intermediate
cash flows need to be defined for calculating the modified NPV.
Pros and Cons of NPV: -
Pros: -
a) This method introduces the element of time value of money and as such is a
scientific method of evaluating the project.
b) It covers the whole project from start to finish and gives more accurate
figures
c) It Indicates all future flows in today’s value. This makes possible comparisons
between two mutually exclusive projects.
d) It takes into account the objective of maximum profitability
Cons: -
a) It is difficult method to calculate and use.
b) It is biased towards shot run projects.
c) In this method profitability is not linked to capital employed.
d) It does not consider Non-Financial data like the marketability of a product.
For Example: -
Initial Investment – 20,000
Estimated Life – 5 years
Scrap Value – 1000 XYZ Enterprise’s Capital Project
Year Cash flow Discount factor Present Value
@10%
1 5.000 0.909 4545
2 10,000 0.826 8260
3 10,000 0.751 7510
4 3,000 0.683 2049
5 2,000 0.621 1242
5 1,000 0.621 621
PV of Net Cash Inflows = 24227
NPV = PV of Net Cash Inflows – Cash Outflows
= 24227 – 20,000
NPV = 4227
Here, NPV is Positive (+ ve) The Project is ACCEPTED.
Profitability Index Method: -
Profitability Index is the ratio of present value of expected future cash inflows
and
Initial cash outflows or cash outlay. It is also used for ranking the projects in order
of their profitability. It is also helpful in selecting projects in a situation of capital
rationing. It is also know as Benefit / Cost Ratio (BCR).
In this Method, the IRR can be ascertained by the Trial & Error Yield Method,
Whose the objective is to find out the expected yield from the investment.
Bigger Smaller
= Smaller discount rate + NPV @ Smaller rate X discount – discount
Sum of the absolute values of the rate rate
NPV @ smaller and the bigger
Discount rates
Decision Rule: - In the Case of an Independent Investment, ACCEPT the project if
Its IRR is greater than the required rate of return and if it is lower, Then
Reject it. In Case of Mutually Exclusive Projects, ACCEPT the project with the
largest IRR, provided it is greater than the required rate of return &
Reject others.
Pros: - a) It considers the profitability of the project for its entire economic life and
hence enables evaluation of true profitability.
b) It recognizes the time value of money and considers cash flows over
entire life of the project.
c) It provides for uniform ranking of various proposals due to the
percentage rate of return.
d) It has a psychological appeal to the user. Since values are expressed in
percentages.