Bcis Analysis Example 2
Bcis Analysis Example 2
http://service.bcis.co.uk/v2000/BCIS/fusebox/analyses_circuit/index.cfm?fuseaction=... 26/11/2008
Analysis 24503 Page 2 of 3
Analysis
Cost Element Unit Element Percent-
Element Total Cost
per m2 Quantity Unit Rate age
1 Substructure £ 298,646 £ 131.56 8%
2A Frame £ 337,257 £ 148.57 9%
2B Upper floors £ 128,986 £ 56.82 3%
2C Roof £ 33,756 £ 14.87 1%
2D Stairs £ 79,730 £ 35.12 2%
2E External walls £ 783,457 £ 345.14 20 %
2F Windows and external doors £ 140,857 £ 62.05 4%
2G Internal walls and partitions £ 128,282 £ 56.51 3%
2H Internal doors £ 63,440 £ 27.95 2%
2 Superstructure £ 1,695,765 £ 747.03 44 %
3A Wall finishes £ 114,229 £ 50.32 3%
3B Floor finishes £ 92,372 £ 40.69 2%
3C Ceiling finishes £ 34,379 £ 15.14 1%
3 Internal finishes £ 240,980 £ 106.16 6%
4 Fittings £ 12,927 £ 5.69
5A Sanitary appliances Included in element 5F
5B Services equipment
5C Disposal installations Included in element 5F
5D Water installations
5E Heat source
5F Space heating and air treatment
£ 172,650 £ 76.06 5%
(includes others)
5G Ventilating systems
5H Electrical installations (includes
£ 278,300 £ 122.60 7%
others)
5I Gas installations
5J Lift and conveyor installations £ 74,020 £ 32.61 2%
5K Protective installations Included in element 5H
5L Communications installations Included in element 5H
5M Special installations Included in element 5H
5N Builder's work in connection
5O Builder's profit and attendance
5 Services £ 524,970 £ 231.26 14 %
Building sub-total £ 2,773,288 £ 1,221.71 72 %
6A Site works £ 102,447 £ 45.13 3%
6B Drainage £ 60,410 £ 26.61 2%
6C External services £ 103,201 £ 45.46 3%
6D Minor building works
6 External works £ 266,058 £ 117.21 7%
7 Preliminaries £ 674,000 £ 296.92 18 %
Total (less Contingencies) £ 3,713,346 £ 1,635.84 97 %
8 Contingencies £ 117,875 £ 51.93 3%
Contract sum £ 3,831,221 £ 1,687.76 100 %
Specification
http://service.bcis.co.uk/v2000/BCIS/fusebox/analyses_circuit/index.cfm?fuseaction=... 26/11/2008
Analysis 24503 Page 3 of 3
Element Specification
1 Substructure Contractor designed pre-formed concrete piles and underpinning of existing.
RC pile caps, ground beams and slab.
2A Frame 240 tonne structural steel frame.
2B Upper floors RC coffered floors on permanent formwork.
2C Roof Steel flat roof with Kingspan KS1000 cladding.
2D Stairs Contractor designed PCC stairs.
2E External walls Red sandstone, areas of granite and Kingspan cladding; aluminium curtain
walling.
2F Windows and external Double glazed aluminium windows.
doors
2G Internal walls and Block and metal stud partitions.
partitions
2H Internal doors Pre-finished veneered flush softwood doors.
3A Wall finishes 73m2 ceramic tiles.
3B Floor finishes 244m2 vinyl, 44m2 rubber, 1226m2 access flooring with carpet.
3C Ceiling finishes Gyproc MF and mineral fibre suspended ceilings.
4 Fittings Kitchen units.
5A Sanitary appliances 13No WCs, 13No wash basins, 4No Doc M packs, 10No stainless steel sinks.
5C Disposal installations uPVC soil and waste pipes.
5F Space heating and air Contractor designed gas HW central heating.
treatment
5G Ventilating systems Central mechanical ventilation.
5H Electrical installations Contractor designed electric light and power.
5J Lift and conveyor 10-person passenger lift ground to 4th floor, wheelchair lift basement to
installations ground; beer keg lift cellar to street.
5K Protective installations Lightning protection; emergency lighting.
5L Communications Fire and intruder alarms, door entry, data cabling.
installations
5M Special installations BMS.
5N Builder's work in Builder's work in connection with services.
connection
6A Site works Replace Tarmac with Marshall's Conservation paving slabs.
6B Drainage Foul and surface water.
6C External services Site lighting.
6D Minor building works Work to existing.
7 Preliminaries 22.18% of remainder of Contract Sum (excluding Contingencies).
8 Contingencies 3.88% of remainder of Contract Sum (excluding Preliminaries).
Credits
Submitted by: CRGP Ltd
Client: Co-Proprietors
Architect/QS: CRGP Ltd
Structural Engineer: Woolgar Hunter
Services Engineer: Hawthorne Boyle Partnership
General Contractor: Henry Boot Scotland Ltd