Float Exercise

This document summarizes a project network diagram and provides the steps to find the available float for each activity. It includes the forward and backward pass calculations. Key activities on the critical path have 0 available float, while others have positive available float values.

Uploaded by

voravan
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 4

4 4

B G
3
J

1 4
2
6 E 5 L
A
C H
4
K
3
D 4 7
F I

Directions: The underlined number in the node represents the activity duration.
Complete the forward and backward pass for the entire project network diagram.
Find the available float for each activity.
The answer is on the next page.
6 10 13
3
4 4
G 14 16
B
3
J
21 24
1 2 9 9
3 8 1 10 14 4
2
6 E 5 L
A
C H 17 20
4
3 K
5
3 6 9 10 16
D 4 7
F I

ABEGJL = 18 days
ABEHKL = 20 days
ACEGJL = 20 days
ACEHKL = 2 days This illustration shows the completed forward pass.
ADFIKL = 24 days Activities ADFIKL represent the critical path at 24 days.
4 4
B G
10 17 3
7 14
J
18 20
1 4
2
6 E 5 L
A 3
1 C 11 11 H 21 24
2
5 10 12 16 4
K
3 17 20
D 4 7
3 5 F I
6 9 10 16

ABEGJL = 18 days
ABEHKL = 20 days
ACEGJL = 20 days
ACEHKL = 2 days This illustration shows the completed backwards pass.
ADFIKL = 24 days Activities ADFIKL represent the critical path at 24 days.
4 4
6 10 13
3
4 4 4
G 14 16
B
10 17 3
7 14
2 J
21 24
1 2 3 8
9 9
10
2 18 20
4
3 1 14
2
6 E 5 L
A 3
1 C 11 11 H 17 20 21 24
2
5 10 12 16 4
3 K
5
3 6 9 10 16 20
17
D 4 7
3 5 F I
6 9 10 16

ABEGJL = 18 days
ABEHKL = 20 days
ACEGJL = 20 days
ACEHKL = 2 days This illustration shows the completed analysis
ADFIKL = 24 days and the available float on activities B,C, E, G, H, J, and K.