Full Report On Isolated Footing
Full Report On Isolated Footing
The building foundation or sub structure is that part of a structure which is placed below the surface
of the ground and which transmits the superstructure load to the underlying soil ultimately. It is the
part of a structural system that supports and anchors the superstructure of a building. Foundation is
the most important part of a building. Building activity starts with the formation of foundation. Main
activities of building foundation are:-
Any part of a structure that serves to transmit the load to the earth or rock can be called foundation.
The higher and heavier the building is to be, the wider and deeper the supports of footings for the
foundation have to be.
PURPOSE OF FOUNDATION
TYPES OF FOUNDATION:
Depending on the depth of the load-transfer member below the super-structure and the
type of transfer load mechanism foundation can be classified into two types:
a) Shallow Foundation
b) Deep Foundation.
1
The classification on foundation has been provided in flow chart as follows:
n
d
i
-
t
s
p
e
c
a
o
r
l
F
u
S
W
I
G
g
b
m
M
E
P
C
ff
o
l
s
w
ti
i
n
h
m
e
d
a
u
S
L
y
F
C
p
e
D
o
P
s
t
e
l
F
ti
n
-
u
i
m
a
g
Classification of Foundation
a) SHALLOW FOUNDATION:
A shallow foundation is a type of foundation which transfers building loads to the
earth very near the surface. The objective of shallow foundation is to distribute the
structural concentrated load over a wide horizontal area at a little depth rather than
a range of depths.
Shallow foundation is often selected when the soil has a good bearing capacity and
the structural load will not cause excessive settlement of the underlying soil layers.
In general, shallow foundations are more simple and cost effective to construct than
deep foundations because little soil is removed or disturbed. Shallow foundation
construction is typically utilized for most residential and light commercial raised floor
buildings.
2
SPREAD FOOTINGS:
Spread footing is a common term used to refer shallow foundations which
transfer’s concentrated loads to a wide range
area. It includes reinforced concrete footings,
wall footings, isolated column footings. Spread
footing provides a stable base or platform at a
low depth and it prevents the structure from
settling into the ground.
Spread Footing
WALL FOOTINGS:
This type of shallow footing supports a wall by providing footing beneath the entire
wall structure. This type of footing is used when columns are made of bricks.
3
GRILLAGE FOOTINGS:
In case of low bearing capacity of soil and avoiding deep excavation grillage
foundation can be used. Grillage foundation can reduce the superimposed
load of column within the safe bearing capacity of the soil. The grillage can be
made of steel or timber.
COMBINED FOOTINGS:
A combined footing is nothing but a combination of pad footings having a
common base. A combined footing is constructed when (i) a column lies very
close to the property line and (ii) to prevent overlapping of footings when
columns are very adjacent. They can be rectangular or trapezoidal in plan.
Combined footing proves to be more cost effective than a single column
footing.
MAT FOUNDATION:
A mat is a slab that supports multiple columns. It is typically used when the
bearing capacity of soil is very low. When required footings will cover more
than half the area beneath a structure, it is often desirable to enlarge and
combine the footings to cover the entire area. A mat foundation may be
cheaper than individual footings because of reduced forming costs and
simpler excavation procedures. Although mat foundations are more difficult
and more costly to design but they prove to be more effective.
b) DEEP FOUNDATION:
A deep foundation is used when the bearing capacity of soil is low near ground.
When a building structure transmits excessive loads to a soil with low bearing
capacity near ground, settlement of the foundation takes place which endangers the
stability of the structure. In that case deep foundation is used to ensure good
bearing capacity of soil at a considerable amount of depth. A deep foundation
requires considerable amount of materials and earthwork resulting increased cost
and effort. Piles, cofferdams and caissons are some the familiar forms of deep
foundations.
4
ISOLATED COLUMN FOOTING:
Depending on structural load and soil isolated footing can be of following types:
BRICK PILLAR FOOTING: When the structural columns are made of bricks this type
of isolated footing is often used. This is the most economic type of isolated
column footing. The width and the depth of the footing depend on load to be
carried and bearing capacity of the soil. The width is found by offsets running
symmetrical round the column.
Stone Pillar Footing: Stone pillar footings are stronger than brick pillars.
Construction of this type of footing is similar to brick pillar footing. The width and
the depth of this footing is a bit bigger because of the stone sizes. This type of
footing is weak in resisting bending. So they are not used against long heavy
structural loads.
R.C.C. Column Footing: In case of column subjected to heavy loading and
bending this type of column footing provides a superior solution in shallow
foundation. Made with reinforcement and concrete this type of footing is high on
strength and bending. The footing is reinforced cross ways by re-bar placed at
right angles to one another. This type footing is capable of transmitting massive
loads with a reduced footing depth. This type is used as a most effective form of
isolated footing. Due to its strong structure this footing is used against high
building structures provided that the soil has sufficient bearing capacity.
5
STEPS OF ISOLATED FOOTING
SOIL EXCAVATION
PLACING OF REINFORCEMENT
SHUTTERING
CONCRETE CASTING
REMOVAL OF FORMWORK
CURING
6
SOIL EXCAVATION
To set a footing, the first step is to excavate the soil of respective area. At first the area
should be located. The depth of excavation depends on the desired strength as strength
increases with depth. We see the tools that are used in excavation below,
PICS
In most cases, baskets & spades are used for excavation. Deep excavation damages adjacent
constructions. In this phase, shore piles or other preventive means are used. Soil sloping can
also reduce this damage. The picture below shows how workers dig soil during excavation,
Fig: Excavation
7
The area of footings are chosen according to design. First the C.G of footings is located.
The excavated soil is kept near the footing as later it can be used for backfilling.
After excavation, the most important step is to level the soil surface. The load of the
construction should be vertical & for this, leveling & dressing is must. Otherwise the
construction might be subjected to tilting to one side. Sand layer & brick chips are often used
for leveling & dressing.
8
PLACEMENT OF BRICK FLAT SOLING LAYER
Now a hard & plane surface is needed. For this purpose we place a brick layer on previous
layer. It is called BRICK FLAT SOLLING. In this layer bricks are arranged in a regular
combination. The upper surface of the layer should be uniformly planed. Below we see a
brick flat soling.
PICS
Generally a C.C (cement concrete) layer having 3” height is kept on the brick layer. It is
named as CEMENT CONCRETE LAYER. It provides a smooth, uniform & strong surface
for reinforcement frame. The mix ratio for C.C layer is cement:sand:aggregate=1:3:6.
Usually some CC blocks are kept on the CC layer to maintain the clear cover between CC
layer & reinforcement. It is also very important to prevent the reinforcement from corrosion.
There is no standard size of blocks. It varies with size of footing & clear cover.
Sometimes brick or half brick can be used instead of CC block. But bricks are not uniformly
smooth plane. Its strength is also less than CC block. So, it is better to use CC blocs as clear
cover. Generally its size is 3”x3”x3”.
9
PLACING OF REINFORCEMENT
Now it is a very important step to place reinforcements. First we should maintain available
clear cover by using CC blocks. We must tie rebar’s with G.I wires or welding. It is done so
that rebars remains intact in all the time even during the casting. First a single frame of
horizontal reinforcement is kept upon the CC block. The number & diameter of
reinforcements depends upon the strength of construction. And it is determined by design
engineer.
The rebars are tied by hand at the outer place if the case is respectively small. But for large
case, it is done on the brick flat soling. Because it is difficult to move & place a large case.
10
Fig: Preparing column
The case must remain horizontal. It is done by plumb bob. The figure below we see how a
case is being horizontal by plumb bob.
11
After placing the case, the centre of case is marked as the column can be placed.
Now the column is placed upon the marking space. It must be vertical. Then it is also tied
with case. After making vertical the column is supported to remain fixed.
12
Fig: Placing of column & making it vertical
SHUTTERING
Shuttering means the solid boundary around the concrete. It resists water flow. It also bears
the load of concrete. So a shuttering should be enough water tight & strong. The amount of
water should remain constant in order to get a proper hydration. There are two kinds of
shuttering,
2. Steel shuttering
Wooden shuttering is more chip than steel shuttering. But it is less water proof & less strong.
It also lasts a short time. On the other hand steel shuttering is strong enough. It also can be
used more times. But it is costly. Side shuttering can be removed after 3 days as after this
time concrete get required strength.
13
Fig: Wood shuttering
*It should retain the concrete shape from all types of distortions.
Concrete Casting
Concrete:
14
Concrete is any product or mass by the use of a cementing medium. Generally, this medium
is the product of reaction between hydraulic cement and water including aggregates and
admixtures.
Composition:
Roll of Components
Cement : Used as binding material. Fill voids between C.A and F.A.
Fine aggregates: Fill voids among C.A.
Coarse aggregates: Carry the load.
Water: Used in hydration process to develop strength. Impart workability.
Range of Proportion:
Cement: 7-15%
Aggregates: 60-70%, F.A = 35-45% , C.A = 25%
Water = 14-21%
Mixing Ratio:
Concrete casting:
Working procedure:
It is very important to make plan before casting .The factors which are to be considered
before casting is stated as follows:
After the completion of footing casting, column is casted. After casting compaction is done
with the help of a vibrator which is a type of mechanical compactor. The vibrator is kept
immersed in one place until the surrounding concrete is fully compacted. This is usually
judged by observing the formation of a circular shaped laitance around the compacted area.
Mixing Machine is used to mix cement, coarse aggregates and fine aggregates in correct
proportion to prepare concrete. While using the mixing machine, coarse aggregate is added
first followed by fine aggregates and then cementitious material. Water is added at regular
time intervals while the materials are mixed. The hydration process of concrete starts as soon
as water is added, therefore concrete should be mixed, transported, placed and compacted
within the setting time of cement. Usually the concrete is casted within 30 minutes after
mixing.
Safety purposes:
15
Sufficient safety arrangement should be ensured for roadside people.
To keep the surrounding building safe it should be well fenced during casting
work.
CURING
Curing of concrete is one of the essential requirements of the process of concrete. The object
of curing at normal temperature is to keep concrete saturated, or as nearly saturated as
possible, until the originally water-filled space in the fresh cement paste has been occupied to
the desired extent by the products of hydration of cement. In the case of site concrete, active
curing nearly always ceases long before the maximum possible hydration has taken place.
The strength of concrete increases more rapidly in the first few days after setting and
afterword’s the rate of increase in strength goes on retarding. The period for which curing
should be continued depends upon atmospheric conditions such as temperature, humidity and
wind velocity. It should be carried out at least 21 days after the casting of concrete is done
efficient curing increases both impermeability and durability of concrete and increases
resistance of concrete to abrasion and reduces shrinkage. Correct curing also increases
resistance of concrete to abrasion and reduces shrinkage.
By covering the surface with moist sand, sacks or sprinkling water at regular intervals
to keep the covering wet.
By ponding the surface where the depth of water in the enclosed square is maintained
from 5 to 8cm
Columns, walls or other such vertical surfaces are cured by wrapping jute bags or
canvas over the surface and keeping the wrapped material continuously wet by
sprinkling water or by some other means.
BACKFILLING
After completion of curing, the excavated soil is filled up. This process is called backfilling.
Ideal backfill materials are purely granular soils(clean sand, gravel, or sand and gravel)
containing less than about 5% of very fine sand, silt, or clay particles. Normally the soil that
has been excavated out is used for this purpose but if the condition of the soil is not good then
soil from a different area is used for this purpose. While backfilling, anti termite chemical
16
mixed water is sprayed on the sides and bottom of foundation trench. The filling is done in
layers and then it is compacted since loosely placed backfill material will eventually settle
under its own weight and will not be capable of supporting structures.
The excavated soil in our project site was full of organic materials and rubbish hence it was
dumped and not used for backfilling.
REMOVAL OF FORMWORK
The formwork should be planned and constructed in such a manner that it is possible to
remove the different components in a particular order. Duration of times up to which the
formwork should be kept in place depends upon many factors such as type of cement used,
shape and position of the member loads to be carried by the members and the temperature of
the air. As the column shutter does not bear any load it can be removed after 3 days. Its
purpose is only to provide shape. If the shuttering bears load it is removed after 14 days
(bottom part of beam).All formwork should be eased gradually and carefully in order to
prevent the load being suddenly transferred to concrete. The formwork should, under no
circumstances be allowed to be removed until the concrete reaches strength of at least twice
the stress to which the concrete may be subjected to at the time of removal of formwork.
Where the shape of element is such that formwork has re-entrant angles, the form work is
removed as soon as possible after the concrete has set, to avoid shrinkage cracking due to the
restraint imposed. The forms can be easily stripped by loosening the double wedges.
Sometimes the swelling of timber may result in shuttering getting jammed at places. In such
situation a small crowbar can be used to strike off the shuttering.
17
Concrete is being thrown fro about 10’ height
Figure: segregation.
Segregation occurs due to the difference in particles size (sometimes in the specific gravity
of the mix ingredients) .There are two types of segregation. In the first, the coarser particles
tend to separate out since travel further long distance. In the second, segregation is
occurred by separation of grout (water &cement). Here in our project aggregates were
thrown from a remarkable height. As a result the ingredients were separated as they hit the
lower rebar layer. This segregation will ultimately decrease the strength of the concrete. So
proper arrange should be taken to prevent segregation.
2. Compaction: In our observed site, for compacting concrete they used both rodding &
vibration procedure.
18
Roding with
bamboo
In case of using vibrator, it should kept in mind that vibrator must be vertical. But in our
project vibrator was used aligned.
Aligned
vibrating
Figure:
Aligned vibrating.
3.Improper clear cover maintainance: Clear cover is a very important fact in structure. For
the structure under the ground clear should be maintained at least 3”. If clear cover is not
maintained properly then the moisture content around the structure will penetrate into the
19
structure & cause corrosion to the reinforcement . Finally collapse the structure.
Improper
clear cover
4. Water logging during casting: Mix proportion is very much important for the design
strength. In our site during casting, water logged continuously. The source of water may be
rain water or leakage from nearby pipes or drains.
Logged
water
5. Brick as C.C block & no C.C layer: In isolated footing we normally use BFS & C.C layer to
provide a flat surface. But in our project BFS was used with no mortar. Here they also did
not use C.C layer as well as C.C block. For maintenance of the clear cover between the BFS
bricks were directly used as C.C block that is shown in the following figure.
20
Bricks as
C.C block
21
22