This document provides a daily report on delayed activities for the World1 Project-King Tower. It summarizes the progress of 7 key items - Mobilization, Water Proofing, Concrete, Rebar, Shuttering, Manpower, and Miscellaneous. Many activities are behind schedule, with site offices only 30% complete and pile waterproofing only 15% done. Concrete pouring of the raft foundation is scheduled for May 15 but material and equipment procurement is still in progress. Overall progress appears delayed across several critical areas.
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0 ratings0% found this document useful (0 votes)
39 views2 pages
Report 2
This document provides a daily report on delayed activities for the World1 Project-King Tower. It summarizes the progress of 7 key items - Mobilization, Water Proofing, Concrete, Rebar, Shuttering, Manpower, and Miscellaneous. Many activities are behind schedule, with site offices only 30% complete and pile waterproofing only 15% done. Concrete pouring of the raft foundation is scheduled for May 15 but material and equipment procurement is still in progress. Overall progress appears delayed across several critical areas.
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 2
Daily Report, about delayed activities, on World1 Project- King Tower
Date: 12-04-2011 Day to complete the Raft Foundation: 56
S ITEM Details Action By: Target Day Completed on: Note
N
Site Offices 30-04-2011 30% done
Steel Yard Due 10% done Site fence (Hording) Due 0% done Jumping form assembling area 10-05-2011 0% done Labor camp 20-04-2011 2% done 1 Mobilization Storage Area Due 10% done Rest Shaded Area and site toilets Due 0% done Access Tower scaffolding stairs Due 50% done Earth Works, and temp roads 15-05-2011 5% done Drain water in pit, and dewatering Due 40% done Water, Power, and sewage connections Due 0% done Temp tower Crane Due 2% done Pile HT, membrane, Epoxy, testing, 15% done 2 Water Proof A1,A2,A3 Protection Screed 15-04-2011 0% done Mix Design Due 0% done Logistic, and delivery Histogram Due 50% done 3 Concrete Raft: Concrete Pumps and Placing 15-05-2011 ? Booms Contract with Lafarge Due ? Steel procurement Due 4% done 4 Rebar Bar Couplers Due 0% done Shop Drawings and BBS Due 20% done Spacer and Accessories 20-04-2011 10% done 5 Shuttering Single side shutter around the raft 10-05-2011 0% done All the rest, (Core- Slab-Columns-walls) 05-2011 ? Staff Due 6 Manpower Skilled labors, Carpenters, S. Fixer, 15-04-2011 10% done Masons 7 Miscellaneou Site logistic plan 30-04-2011 40% done s Pumping M100 concrete for high 10-06-2011 ? levels Heavy Equipments, Mobile crane, Due ? loader,… Staff Accommodation Due ? Method statements, HSEP and QPP Due U/R