Report 2

This document provides a daily report on delayed activities for the World1 Project-King Tower. It summarizes the progress of 7 key items - Mobilization, Water Proofing, Concrete, Rebar, Shuttering, Manpower, and Miscellaneous. Many activities are behind schedule, with site offices only 30% complete and pile waterproofing only 15% done. Concrete pouring of the raft foundation is scheduled for May 15 but material and equipment procurement is still in progress. Overall progress appears delayed across several critical areas.

Uploaded by

smaliscribd
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
39 views2 pages

Report 2

This document provides a daily report on delayed activities for the World1 Project-King Tower. It summarizes the progress of 7 key items - Mobilization, Water Proofing, Concrete, Rebar, Shuttering, Manpower, and Miscellaneous. Many activities are behind schedule, with site offices only 30% complete and pile waterproofing only 15% done. Concrete pouring of the raft foundation is scheduled for May 15 but material and equipment procurement is still in progress. Overall progress appears delayed across several critical areas.

Uploaded by

smaliscribd
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 2

Daily Report, about delayed activities, on World1 Project- King Tower

Date: 12-04-2011 Day to complete the Raft Foundation: 56

S ITEM Details Action By: Target Day Completed on: Note


N

Site Offices 30-04-2011 30% done


Steel Yard Due 10% done
Site fence (Hording) Due 0% done
Jumping form assembling area 10-05-2011 0% done
Labor camp 20-04-2011 2% done
1 Mobilization Storage Area Due 10% done
Rest Shaded Area and site toilets Due 0% done
Access Tower scaffolding stairs Due 50% done
Earth Works, and temp roads 15-05-2011 5% done
Drain water in pit, and dewatering Due 40% done
Water, Power, and sewage connections Due 0% done
Temp tower Crane Due 2% done
Pile HT, membrane, Epoxy, testing, 15% done
2 Water Proof
A1,A2,A3
Protection Screed 15-04-2011 0% done
Mix Design Due 0% done
Logistic, and delivery Histogram Due 50% done
3 Concrete Raft: Concrete Pumps and Placing 15-05-2011 ?
Booms
Contract with Lafarge Due ?
Steel procurement Due 4% done
4 Rebar Bar Couplers Due 0% done
Shop Drawings and BBS Due 20% done
Spacer and Accessories 20-04-2011 10% done
5 Shuttering Single side shutter around the raft 10-05-2011 0% done
All the rest, (Core- Slab-Columns-walls) 05-2011 ?
Staff Due
6 Manpower Skilled labors, Carpenters, S. Fixer, 15-04-2011 10% done
Masons
7 Miscellaneou Site logistic plan 30-04-2011 40% done
s Pumping M100 concrete for high 10-06-2011 ?
levels
Heavy Equipments, Mobile crane, Due ?
loader,…
Staff Accommodation Due ?
Method statements, HSEP and QPP Due U/R

Mustafa Y. Intabli