Avik Pandit Report
Avik Pandit Report
SCFT
TOOLS USED................................................................................................................................................3
RF Design Plots;...........................................................................................................................................10
......................................................................................................................................................................12
Short Call......................................................................................................................................................16
Event Statistic...............................................................................................................................................16
Documentation.............................................................................................................................................17
Signature.......................................................................................................................................................17
Site verification aims to guarantee that each cell is performing according to specifications and RF design. It
shall fulfill the design objectives. Both coverage and functionality tests will be performed to evaluate every cell
in the network. At the end of the exercise the RF engineer should be able to:
Detect the possible causes if the coverage levels are too low against plan.
Verify correct antenna orientation and fix swapped sectors, if any.
Ensure that basic cell functionalities are executed properly and systematically.
Document and compile log files and test sheets for each site tested. These can be useful references,
especially while during cluster tuning.
Data fill verification.
TOOLS USED
Upon arrival at the site, Engineer would validate site design information. This information must be checked
against the antenna design plan.
A laptop with drive test software is needed to make test calls and to check cell parameters. Perform test the
following call scenarios in each sector; please refer to “Single Site Test Checklist” for details:
Verification of Correct Antenna Orientation and correct BCCH on each Sector.
Verification of Handover and Signal Quality.
MM (mobile-to-mobile) calls.
Engineer Should Start in First Sector, perform all Voice Test and proceed to Sector 2 ( record
Handover from Sector 1-2), perform all tests in Sector 2 and finish all 3 sector tests to stop at starting
point.
The same process should follow in reverse directions from start to stop point.
Drive Test Car, equipped with drive test facilities, GPS with cord to laptop (COM port) & I/O card for
extra dual COM port.
Highly Stable DC power distribution system, DC/AC Inverter if required for laptop.
Test SIM cards.
And below mentioned tools; (please specify in below table)
Antenna orientation: Y
• The site is performing well in all respect. There is no handover fail & call drop.
Incoming Outgoing
HO 1-Tier HO 1-Tier
Remarks
Long Call
Event Statistic
UNINOR – SCFT
16TH SEP 2010
Documentation
Signature
Vendor :
Uninor:
UNINOR – SCFT
16TH SEP 2010