CPT Environmental Presentation
CPT Environmental Presentation
SECOND SECTION
• Who can conduct EIA Study ?
• How to conduct EIA ?
• Project Approving Authority
ENVIRONMENTAL IMPACT ASSESSMENT
Presented by :
WIRANDA (M) SDN. BHD.
INTRODUCTION
The Environmental Impact Assessment (EIA) procedure in Malaysia has been developed
primarily as an aid to the environmental planning of new development projects or to the
expansion of existing development project.
The procedure and guidelines for EIA in Malaysia have been developed in line with the
Government policy statements contained in the Malaysia Plan.
DEFINITION
A study to :
- Identify
- Predicts
- Evaluate
- Communicate information
about the impacts on the environment of a proposed project and to detail out the
mitigating measures prior to project approval and implementation.
AIM OF EIA
The aim of environmental impact assessment in Malaysia is to assess the overall impact
on the environment of development projects proposed by public and private sector.
OBJECTIVES OF EIA
With the amendment of the Environmental Quality Act, 1974 in 1985, a new sections i.e.
Section 34A has been introduced which requires any person intending to carry out any
prescribed activity to submit a report on the impact on the environment to the Director
General, Department of Environment (DOE) for approval
“Any person who contravenes this section shall be guilty of an offence and shall be liable to a
fine not exceeding RM 100,000 or to imprisonment for a period not exceeding 5 years or to
both and to a further fine of RM 100,000 for every day that the offend is continued after a
notice by the Director General requiring him to comply with the act specified therein served
upon him.”
Environmental Quality (Prescribed Activities)
(Environmental Impact Assessment) Order 1987
In exercise of the power conferred by Section 34A of the Environmental Quality Act 1974,
the Minister, after consultation with the Environmental Quality Council, makes the following
order :
2. Prescribed activities
- DETAILED EIA
9. Infrastructure
(a) Construction of hospitals with outfall into beachfronts used for recreational
purposes.
(b) Industrial estate development for medium and heavy industries covering an area of
50 hectares or more.
(c) Construction of expressways
(d) Construction of national highways
(e) Construction of new townships
The proposed development for new university or college can be categories under Schedule 9(e)
WHY DO WE NEED EIA ?
• Preventing environmental problems due to an action.
• Ensures that the potential problems are foreseen and addressed at an early stage in the
project planning and design.
• Avoid costly mistakes in project implementation, either because of the environmental
damages during project implementation, or because of modifications that may be
required subsequently in order to make the action environmentally acceptable.
• Provides additional information towards a better decision-making.
PROJECT CONCEPT
The concept of the proposed project must not contradict any of the following plan:-
Site suitability investigated through site visits and analysis of existing information.
Measures to protect the environment and resolve socio economic issues are also
considered.
Where the project is situated on public land or near waterways, and alternative users will
be affected by the project, the issue of compensation and offset investment should be
addressed in the EIA.
ESA shall be integrated in the planning and management of land use and natural
resources to ensure sustainable development.
• The management of ESA shall be guided by the following criteria:-
i. ESA Rank 1 – All protected areas, potential protected areas (wetlands, turtle
landing sites), catchment areas of existing and proposed dams and all areas
above 1000m. Areas under proposed dams catchment can be sustainably logged,
subject to local constraints, until the dams are built
ii. ESA Rank 2 – All other forests, corridors linking important protected areas, buffer
zone around Rank 1 areas and all areas between 300m – 1000m.
iii. ESA Rank 3 – All marine park islands, buffer zone around Rank 2 areas, catchment
areas for water intakes, areas for groundwater extraction (well fields), all areas
between 150m – 300m, all areas with erosion risk greater than 150 ton / ha / yr, all
areas experiencing critical or significant coastal erosion.
Controlled development where the type and intensity of the development shall be
strictly controlled depending on the nature of the constraints.
ESA AREA
No Prescribed
EMP Activities
Yes
Preliminary EIA
FIRST SESSION
Submission EIA
Report to DOE Addendum EIA
EIA Approval
Condition
WHO INVOLVE IN EIA ?
• Client – e.g. : MOHE, MOH, MOA
• Project proponent – e.g. : JKR, LLM,
• Consultant – C&S, Environment, Architect
• Public & NGO – especially in DEIA
• Competent individuals who are registered with the Department of Environment under
the EIA Consultant Registration Scheme.
• EIA reports conducted by individuals who are not registered with the Department will
be rejected.
Habitats Species
Surface Water & &
PHYSICO-CHEMICAL Communities Populations
(EARTH SCIENCES) LIFE SCIENCES
Groundwater (BIOLOGICAL)
Atmosphere
EIA
Aesthetic
Noise & Health & Safety
Cultural
SOCIAL SCIENCES
(HUMAN)
Socio-economic
Described the proposed project as well as the option
METHODOLOGY OF CONDUCTING
Described the existing environment
a) The condition in qualitative and quantitative terms, of the physical, biological and
human environment prior to implementation of the project;
MITIGATION MEASURE
Discuss all the design measures which have been adopted into the project plan to
reduce significant potential environmental impact.
FIELDWORK
Fauna Survey - Elephant Dung Trekking to carry out Flora & Fauna Survey
Crossing River During Site Survey Plankton Net to collect Zooplankton Visual
Fish samples- the Osteochilus vittatus or Muddy Road at The Project Site
Rong (malay name).
FIELDWORK
HARD TIME
APPROVAL AUTHORITY
EIA approval is from the Director General of Environment.
The Approving Authority is the Government Authority that has the task of deciding, whether
or not a project should proceed. The authorities include the following:
The respective State Planning Authorities for State Government sponsored projects.
The Regional Development Authorities for the State Executive Committee (EXCO).
Ministry of International Trade and Industry (MITI) (with due reference to the
Malaysia Industrial Development Authority (MIDA) – industrial project)
5 weeks
OSA Presentation
Addendum
Presented by :
WIRANDA (M) SDN. BHD.
ENVIRONMENTAL MANAGEMENT PLAN
Introduction
Policy
Environmental Requirement
Monitoring Programmes
Conclusion of EMP
INTRODUCTION
The Environmental Management Plan (EMP) for the project is prepared to ensure
compliance with the regulations and conditions of the Department of Environment
(DOE) for the project activity.
The EMP will outline key strategies and action to protect the environment, in
particular during construction phase where environmental degradation can occur.
Main Contractor
JKR as Project To ensure that the Contract Documents include provisions for compliance
Proponent with environmental requirements. The Environmental Quality Act, 1974
and other subsidiary legislation and guidelines shall be used as reference.
Organization Responsibility
The audit shall focus on the implementation of the EMP and/or other environmental
management elements.
The environmental auditor shall have the necessary expertise and experience to execute the
tasks diligently and professionally in accordance with the requirements of JKR EMS: MS ISO
14001 and shall undertake the following tasks :-
a. carry out environmental compliance audits quarterly and closure audit on completion
of the project;
b. evaluate monitoring data for water quality, air quality and noise;
The Project Proponent/Contractor shall at all times adhere to all existing statutes
regarding the protection of the Environment.
Prior to the execution of the project, the Project Proponent/Contractor shall comply
with :
- EIA Approval Conditions
and other related environmental legislation including, but not limited to:
The Project Proponent/Contractor shall be liable for and shall indemnify the Government
against any damages, expenses, liability, losses, claims, prosecution, proceedings, fines and
penalties caused by any non-compliances or contraventions of the above legislation and
regulations.
JKR ENVIRONMENTAL MANAGEMENT
SYSTEM
MS ISO 14001
In line with the MS: ISO 14001 requirement, a continual improvement of the system must be
done to ensure success and effectiveness of environmentally sustainable approach in
construction.
In 2006, a committee comprising multi-disciplinary personnel was set up to revise the Arahan
Teknik 16/03.
Changes have been made in accordance to problems encountered and inadequacies of the
previous Arahan Teknik.
The overall improvement is aimed to ensure contractors understand the application of the
environment protection works that they have tendered in the Bill of Quantities.
Cont’d
The revised Arahan Teknik 16/03 is made applicable, not only to road projects, but to all
projects in JKR.
It is important that all parties involved in the construction industry, be made aware of the
latest government requirements in environment protection to ensure our nation has the
capacity to be sustainable in the long term future.
STANDARD GUIDELINE – JKR : CORPORATE
ENVIRONMENTAL OBJECTIVES REQUIREMENT
Notes
The Planning Guidelines for Environmental Noise Limits and Control (Schedule 1: Maximum
Permissible Sound Level (LAeq) by Receiving Land Use for Planning and New Development)
STANDARD GUIDELINES
SOLID WASTE - Local Government Act 1976 and Refuse Collection,
Removal and Disposal By-laws
Under the First Schedule of this Regulations, 107 categories of toxic and
hazardous waste have been classified as scheduled wastes.
SCHEDULED WASTE
MANAGEMENT
a. Baseline studies for Noise Level, Air & Water Quality prior to any construction
activity for data comparison with future monitoring data.
b. Identification and justification of sampling stations for Noise Level, Air & Water
Quality.
d. Frequency of monitoring
• Turbidity
• pH
• Total Suspended Solid (TSS)
• Biochemical Oxygen Demand (BOD)
• Chemical Oxygen Demand (COD)
• Dissolved Oxygen (DO)
• Oil & Grease
• E-Coli
• Ammoniacal Nitrogen (NH3-N)
Type of Monitoring
Monitoring Parameter Locations
Frequency
River Quality / Effluent Discharge
pH
Temperature
Turbidity
Water Quality Dissolved Oxygen (DO) Monthly
Total Suspended Solid (TSS)
Ammoniacal nitrogen
Chemical Oxygen Demand (COD)
Biological Oxygen Demand (BOD5)
Oil & Grease
E.coli
Air Noise
Site Clearing /
Pollution Pollution
Earthwork / Structure
Control Control
Water Pollution
Tyre Water Control/ESCP Noise
Washing Sprinkler Barrier
Facilities
During Operation Planting buffer areas between the roadside and premises with
Phase trees and vegetation to trap dust and particles.
Cont’d
NOISE & All equipment and machinery are in proper working condition
VIBRATION
During Construction Noise levels of Leq = 65 dBA should not be exceeded
Phase
Noise barrier shall be provided in sensitive areas
During Operation Green buffer strips along the residential perimeters shall act as natural
Phase absorbents of noise
Traffic Noise
Monitor and recommend appropriate mitigation measures if the noise
level exceed baseline levels
Cont’d
IMPACTS MITIGATION MEASURES
WASTE MANAGEMENT
During Construction Phase
Open burning of all construction waste material, which
Disposal of Biomass includes biomass is totally prohibited
Municipal Solid Waste Consider recycling practices ( paper, cans and plastic)
Domestic waste generated should be stored in garbage
bins/secure containers and be collected regularly
Unsalvageable construction spoil should be stockpiled at a
designated site
Scheduled Waste Scheduled wastes generated must be properly stored
Any scheduled wastes identified will need to be disposed off by
a licensed transporter at a recycling facility
Scheduled wastes generated for180 days or less after its
generation shall not exceed 20 metric tones
During Operation Phase Proper cleansing practices should be observed and wastes are to
be disposed off at approved landfills
IMPACTS MITIGATION MEASURES
TRAFFIC & Transportation of construction machinery and materials,
TRANSPORTATION will be carried out during off-peak hours of the day
(7.00am - 9.00am and 4.00pm - 7.00 pm);
During Construction Phase Speed of vehicles will be restricted
Affected residents will be informed of any traffic
diversion and alternative access routes.
• FLORA
– Relocated, transport and
maintain trees with
conservation value of girth
300mm and below:
– Silt Fence
• Construction of 1.0m high, including non-woven geotextile and
wooden post with dimension as specified, shown in the drawing or
as directed by the Superintendent Officer (S.O)
Silt Fence
– Sand Bags
• Supply and lay gunny sack filled with
sand as specified and shown in the
drawing or as directed by the S.O
– Check Dam
• Construction using rocks as
specified and a shown in the
drawing or as directed by the S.O
CHECK DAM
– Silt Trap and Sediment Basin
• Gabion cage with rock fill and geotextile including excavation, jointing,
backfilling and disposal of surplus materials as specified and shown in
the drawing or as directed by the S.O
Gabion Wall
– Silt Curtain
• Installation include non-woven geotextile and floats as specified a shown
in the drawing or as directed by the S.O
BEFORE
AFTER
Silt Curtain
AFTER
BEFORE
Silt Curtain
Silt Trap
Silt Fence
WATER BROWSER
The ECP shall be integrated as part of the project inculcating general awareness on
safety, health and environment.
ECP must be ready for any emergency such as landslide, spillage of oil or
hazardous chemical substances, failure of any pollution control equipment, etc.
inform
Determine severity of
injury
3
Perform first aid if trained Perform first aid if
trained