0% found this document useful (0 votes)
25 views

Project Notice

This document outlines the schedule and deadlines for the term project of the Batch 19 students at SCMS - Cochin. It includes the dates for submitting the project joining report, 4 progress reports, the completion report, and draft and final versions of reports to the school. Key dates include starting the project work on June 20th, submitting the first progress report by July 18th, and submitting final reports by October 14th.
Copyright
© Attribution Non-Commercial (BY-NC)
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
25 views

Project Notice

This document outlines the schedule and deadlines for the term project of the Batch 19 students at SCMS - Cochin. It includes the dates for submitting the project joining report, 4 progress reports, the completion report, and draft and final versions of reports to the school. Key dates include starting the project work on June 20th, submitting the first progress report by July 18th, and submitting final reports by October 14th.
Copyright
© Attribution Non-Commercial (BY-NC)
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 1

SCMS - COCHIN NOTICE Attn.

Batch 19 Students Term Project Schedule Details (REVISED)

Project Work Begins Project Joining Report with Revised Synopsis (if applicable) Progress Report 1 Along with Company/Industry /Product Profiles, Research Methodology & Draft Questionnaire (Wherever field survey is involved) Progress Report 2 Progress Report 3 Progress Report 4 Project Work ends Reporting back to school / Submission of Completion Report Interaction with Guide & Report preparation Trimester V Begins Submission of draft reports Submission of final reports

20.06.11

: :

04.07.11 18.07.11

: : : :

01.08.11 16.08.11 29.08.11 16.09.11

19.09.11

: : : :

From 19.09.11 To 23.09.11 26.09.11 07.10.11 14.10.11

Reports should reach the School by the dates indicated through ordinary mail or courier only. (Email/fax will not be accepted). All reports should be addressed to the Project Co-ordinator and not to the respective guides. (Copies may be forwarded to the guides). Formats for the reports are available on the LAN 25/05/11 Dean-Management Studies Prof K.J.Paulose