Implementation Guidelines & Quality Processes - UPE
Implementation Guidelines & Quality Processes - UPE
Version :V1.0 Document Number : V1.0R001 Date of Release : 16th Feb,2011 Prepared By : Himanshu Nayak (00728210) Checked By : Himanshu Nayak (00728210) Approved by :Sanjay Kumar (00720434)
Huawei
INTRODUCTION
Your Name ?
Designation? Your Company Name? Education Details? Total Telecom Experience ? Expectation from this training ?
Huawei
Page 2
Training Schedule
Day Time 10: 00AM-11: 00AM 11: 00AM-11: 15AM DESCRIPTION OF TOPIC Environment, Health & Safety SOP Participants Team Leaders Team Leaders Name of Trainer
11:15AM-11:30AM
11:30AM- 1:30PM 13:30PM-14:30PM Day 1 14:30PM-15:00PM
Team Leaders
Team Leaders
Huawei
Page 3
Training Schedule
Day Time 10: 00AM-10: 45AM DESCRIPTION OF TOPIC Node B installation process Participants Team Leaders Name of Trainer
10:45AM-11:30AM
11:30AM- 11:45PM 11:45PM-13:30PM 13:30PM- 14:30PM 14:30PM- 16:30PM 16:30PM 16:45PM
Day 2
16:45PM-19:00PM
Day Time 10: 00AM-11: 15AM
11:15AM-11:30AM
Day 3 11:30AM- 13:00PM 13:00PM- 2:00PM 2:15PM- 3:45PM
4 Huawei
Team Leaders
CONTENTS
ENVIRONMENT, HEALTH & SAFETY
APPROACH TO SoP
Huawei BTS(GSM) ,CDMA & Node-B Product Overview INSTALLATION REQUIREMENTS MR & MATERIAL DELIVERY
CABINET APPERANCE(GSM,CDMA & NODE-B) HARDWARE & MODULE DESCRIPTION-GSM,CDMA & NODE-B
BTS INSTALLATION
TOOLS & TEST EQUIPMENTS BTS3900 ,BTS3900A & DBS3900-GSM/CDMA INSTALLATION & CABLING NODE-B INSTALLATION & CABLING SITE CABLING INSTRUCTION
Huawei
Page 5
CONTENTS
ANTENNA & FEEDER LINE INSTALLATION
TOOLS & TEST EQUIPMENTS. GSM ANTENNA INSTALLATION. FEEDER & JUMPER INSTALLATION. FEEDER CONNECTORIZATION FEEDER GROUNDINGS. WEATHERPROOFING. RTN605,RTN610 & RTN620 OVERVIEW. ODU & MW ANTENNA RTN605,RTN610&RTN620 & ODU INSTALLATION. RTN910 & RTN950 OVERVIEW. RTN910 & RTN950 INSTALLATION.
INVENTORY/MATERIAL RECONCILATION
Huawei
Page 6
Huawei
Huawei
Huawei
Only qualified First Aiders are allowed to render first aid to casualties. This is to prevent further complication to the injured.
DO NOT move an accident victim unless they are in danger of further injury. If you need a profesional help, call immediately.
10
Huawei
Inform your Site Manager immediately Incident : A work-related event in which an injury or ill health (regardless of severity) or fatality occurred, or could have occurred. Accident : An incident which has given rise to injury, ill health or fatality. Reporting is important to evaluate the root causes of the incident/accident and taking corrective/ preventive actions in order to prevent the occurance of the same or smillar incidents/accidents again.
11
Huawei
Safety Signs
Make sure you understand the signs used on site
Circle: white background with red borders and cross bar; black symbol
Mandatory signs
12
Huawei
When welding, grinding, or any other operations, always wear the specified PPE associated to that particular job: Eye protection Ear protection Protective gloves
13
Huawei
Damaged PPE does NOT provide full protection. Get your damaged PPE replaced.
14
Huawei
15
Huawei
Two ended lanyard will be attached to the safety harness during working at height. Lanyards standard should conform to EN 354, EN 362 (or equivalent)
16
Huawei
Manual Handling
Manual Handling means any activity requiring the use of force exerted by a person to lift, lower, push, pull, carry or otherwise move, hold or restrain a person, animal or thing.
Key Questions How Big is it? How much does it weigh? Can I move this comfortably or do I need assistance Remember if it can be moved in another way Do not lift it.
17
Huawei
Manual Handling
18
Huawei
Stack on level, firm surfaces and use packing where appropriate. Never stack materials higher than three times the base width.
Make sure you wear suitable protective clothing such as gloves and safety boots, and use handling accessories as required.
19
Huawei
Working at Height
Working at height means work in any place where, if precautions were not taken, a person could fall down and injure themselves. If you:
work above ground level. could fall from an edge, throgh an opening or fragile surface. could fall from ground level into an opening in a floor or hole in a ground;
You will be working at height, because you can fall from one level to another level. Fall prevention protection is required for any work where there is the potential to fall a distance of 2m or more. Wear and anchor your safety harness when working at height, near openings and edges. Use only a safety harness (safety belts are prohibited).
20 Huawei Telecom Implementation Process & Guidelines
Working at Height-Barricades
Do not used tape or ropes as barricades.
Only cable, tubular pipes and other rigid materials which are able to withstand 100 kg/f are allowed to be used as barricades. Appropriate barricades will prevent site personnel from falling off the edge or through openings.
21 Huawei Telecom Implementation Process & Guidelines
22 Huawei
When working near edges or openings, ENSURE that you are anchored to a lifeline.
23
Huawei
Be sure that:You never climb a tower alone, there must always be a watchman with you. You check your harness prior to use and wear your safety harness while climbing. Secure yourself with two lanyards from two different points. Carry your hand tools in a bag. Never climb a tower when its rainy or too windy.
24
Huawei
Face the ladder while climbing up or down and hold the side rails with both hands.
Carry tools up or down on a belt or with a rope or hoist, not in your hands. Maintain 3-point contact while climbing the ladder: 2 hands and one foot in transition.
When using a ladder ensure that it is secured in place to prevent the ladder slipping or moving while in use. Always inspect the ladder before use, do not use damaged or broken ladders. Home made ladders are NOT ALLOWED.
25
Huawei
Leaning Ladders in Use Short duration work (max. 30 minutes) Light work (up to 10 kg). Ladder angle 75 degree - 1 in 4 rule (1 unit out for every 4 units up). Always grip the ladder when climbing. Do not overeach. Do not work off the top three rugs this provides a handhold. Ensure the ladder is secure.
26
Huawei
27
Huawei
28
Huawei
Do not tamper with or remove safety guards. Do not use the equipment / machinery if there is no safety guard. Only use equipment for which you have been trained.
29
Huawei
House Keeping
Safety starts with good Housekeeping
Remove all protruding nails or bend them over. Do not dispose of your unwanted materials from a height. Keep your work area clean
30 Huawei Telecom Implementation Process & Guidelines
House Keeping
31 Huawei Telecom Implementation Process & Guidelines
32
Huawei
Electrical Safety
Do not overload power sockets.
Never use damaged electrical appliances, exchange them with your immediate supervisor.
IF YOUR INSTINCTS TELL YOU NOT TO. If you don't know what is burning. If the fire is spreading rapidly . That is producing a large amount of smoke . If you don't have adequate or appropriate equipment.
Huawei Telecom Implementation Process & Guidelines
Electrical
If you have the slightest doubt about your ability to fight a fire ....EVACUATE IMMEDIATELY!
36
Huawei
Damaged cabling and connectors can be unwanted sources of RF exposure report all such cases.
In addition to RF cabling, some base stations may have fibre-optic distribution systems. Workers shall follow the specific rules dealing with optical emissions. Without further analysis, personnel with active medical devices should not enter areas above the general public limits . Always follow the manufactures installation and operating instructions.
38
Huawei
39
Huawei
RF Safety-Type of Antenna
Omni-directional coverage These antennas radiate RF energy equally in all directions in the horizontal plane. The antenna input power is typically 10 80 watts, and the compliance boundary for a worker typically extends 0.1 1.5 meters from the antenna. Sector coverage These antennas restrict most of their radiated RF energy to a narrow angular sector in their forward direction (typically 60 to 20 degrees in the horizontal plane, typically 8 to 4 degrees in the vertical plane). The antenna input power is typically 10 80 watts, and the compliance boundary for a worker extends typically 0.2 3 meters from the front face of the antenna . Antenna farms (or clusters) Antennas are often grouped together on masts . The combination illustrated here is that of an omni-directional antenna mounted above a cluster of 3 sector antennas. In the case that multiple antennas are present on a site, whenever an additional antenna is installed, the compliance boundary of each antenna should be evaluated again, taking into account the additional exposure of the newly installed antenna.
40
Huawei
RF Safety-Type of Antenna
Radio relay (Microwave / fixed point-topoint link) These antennas concentrate their RF energy into a narrow beam in the forward direction. Since the power levels are typically low, less than 1 watt, the safety distances in this forward direction (L) are often small (in centimetres) and in many cases there is no need of any safety distance for occupational exposure . Areas above, below and to the sides of the antenna, as well as the area behind the antenna, are normally safe at even shorter distances.
The Compliance Boundary for safe working around antennas is shown in BLUE - Seek clarification before approaching antenna or working within 5m
41 Huawei Telecom Implementation Process & Guidelines
42
Huawei
Last and not least, whatever job you do, do it safely. Your family needs you!!!
44
Huawei
What is SoP?
A Standard Operational Procedure fractionalizes & Quantizes the key procedures and key points in an operation process , to institutionalize & regularly recurring work processes and reach to the optimum state process through continuous improvement. Establishing Standard operational process/procedure in a work is most essential to create Stable & consistent performance/result.
Standardizing of procedure/process is the basis for making continuous improvement , increasing efficiency, reducing cost & improving Quality.
Institutionalize
Institutionalize
45
Huawei
Procedure-4
SoP -Procedures
Procedure-2
Procedure-3
46
Huawei
Corrections Overproduction Multiple travels Resource to act a single activity Waiting for activity Inventory Improper processing
47
Huawei
Eliminate
Eliminate Waste
Combine
Collaborative Operation
Simultaneous Operation
Combined Operation
Re-arrange
Simplify
Make it Simpler
48
Huawei
49
Huawei
50
Huawei
BTS3900 Cabinet
The Capacity of the BTS3900 is represented by the number of carriers & that of cells.
Single cabinet can be configured with maximum 6 DRFU/GRFU. Single cabinet can serve upto 6 sectors. The maximum carriers with DRFU is 12 with single cabinet & 36 carriers with single site. The maximum carriers with GRFU is 36 with single cabinet & 72 carriers with single site. Cabinet size-600mm(W)x450mm(d)x900mm(h) Base Size-600mm(w)x420mm(d)x40mm(h). The Cabinet can support 3 types of input power supply,i.e. -48VDC,+24VDC & 230V/AC .
51
Huawei
Weight of Empty ID BTS Cabinet is 57 Kgs. Weight of BTS cabinet with full configuration is 132 Kgs.
52 Huawei Telecom Implementation Process & Guidelines
53
Huawei
RFC
RFC
RFC
RFU
RFU
RFU
54
Huawei
DBS3900-GSM
The functional modules of the DBS3900 consists of the
BBU3900 & the RRUs The RRUs are categorized into two types,i.e. DC RRU & AC RRU. The RRU3004 is an Outdoor remote radio unit & it supports 2 carriers. The RRU3008 is and outdoor remote radio unit & supports more than two carriers.
55
Huawei
DBS3900-CDMA
DBS3900-CDMA The functional modules of the DBS3900 consists of the
BBU3900 & the RRUs The RRUs are categorized into two types, i.e. DC RRU & AC RRU. The RRU3606 is an Outdoor remote radio unit.
56
Huawei
The Cabinet structure for both GSM & Node-B is same for GSM & Node-B. The difference to BTS3900 GSM is only hardwares/Modules.
57
Huawei
The Cabinet structure for both GSM & Node-B is same for GSM & Node-B. The difference to BTS3900 GSM is only hardwares/Modules.
58
Huawei
DBS3900-Node-B
DBS3900WCDMA
59
Huawei
60
Huawei
BBU-BTS3900/3900A/DBS3900-GSM
1 HU = 44.45mm
Providing physical ports for the communication between the BTS & BSC. Providing CPRI ports for communication between the BBU & RFUs. Providing the USB port for downloading the BTS software. Providing the OM channel for connection to LMT/M2000. Processing uplink & downlink data. Providing system clocks. External alarms.
Telecom Implementation Process & Guidelines
Huawei
GTMU Panel-BTS3900/3900A/DBS3900-GSM
GSM Transmission, Timing & Management Unit of BBU (GTMU)
GTMU
The GTMU Performs the following functions
Controlling ,maintaining and operating the BTS.
GTMUb
Providing fault management ,configuration management ,performance management & Security Management. Monitoring the fan module & the power supply modules. Distributing & managing BTS clock signals. Providing clock output for testing. Providing the Ethernet port for local maintenance.
UPEUA
UPEUB
Universal Power and Environment Interface Unit (UPEU) board of the BBU 3900 . It is Mandatory board of the BBU3900 that converts -48VDC to +12VDC/ Converts +24VDC to +12VDC. Functions are as below, Converting -48VDC/+24VDC to +12VDC that is applicable to the boards. Providing two ports with each transmitting one RS485 and another two ports with each transmitting four dry contact signals. Providing reverse connection protection for power cable connectors.
63
Huawei
Universal Environment Interface Unit (UEIU) board of the BBU 3900 . The UEIU transmits monitoring signals and alarm signals from external devices to the main control and transmission unit. Functions are as below, Providing two ports with each transmitting one RS485 Signal. Providing two ports with each transmitting four dry contact signals. Transmits monitoring signals and alarm signals from external devices to the main control and transmission unit.
64
Huawei
Label on Connector
INSIDE OUTSIDE CPRI0-CPRI5 E1/T1
Connector Type
DB25 Female DB26 Female SFP Female DB26 Female
Description
Transmits 4 E1/T1 between UELP & GTMU Transmits 4 E1/T1 between BBU & BSC Transmits the optical & electrical signal between GTMU and DRFU/GRFU Transmits E1/T1 between GTMU & UELP / between GTMU & BSC Connect the BBU to a routing devices in the equipment room through the Ethernet cable to transmit network information. Connect the BBU to a routing devices in the equipment room through the Ethernet cable to transmit network information. RS485 Signal RS485 Signal Four dry contact signals Four dry contact signals Transmits one RS485 environment monitoring Signal Transmits one RS485 environment monitoring Signal Four dry contact signals Four dry contact signals 24V/48VDC input
UFLP
FE0
RJ45
UEIU
UPEU UPEU
EXT-ALM1
MON0 MON1
RJ45
RJ45 RJ45
UPEU
UPEU UPEU
EXT-ALM0
EXT-ALM1 PWR
RJ45
RJ45 3V3
65
Huawei
UELP Panel-BTS3900/3900A/DBS3900-GSM,CDMA&NODE-B
Universal E1/T1 lightening protection unit (UELP) is a universal E1/T1 surge protection unit. The UELP optionally installed in the SLPU or BBU.Each UELP provides surge protection for four E1s/T1s.
66
Huawei
Universal FE lightening protection unit (UFLP) board is optionally installed in the SLPU or BBU3900. Each UFLP supports 2-Way FE Surge Protection.
67
Huawei
DCDU-01 Unit
Function of DCDU-01 are as below; Supporting one -48VDC input and 10 nos. of -48VDC outputs. The 10 Nos. of -48VDC outputs are 1x25A output to the spare-1 port. 9x12A output to the other-9 ports.
Supplying power to the BBU,RFUs Fan Unit and customer equipments in the cabinet.
Providing surge protection of 10KA in differential mode and 15Ka in common mode and providing dry contacts for surge protection failure.
68
Huawei
FAN Unit
The FAN Unit has following functions, Ventilating the cabinet and dissipating the heat in the cabinet. Supporting temperature detection. Supporting two modes of fan speed adjustment ,based on the temperature or controlled by the main control unit. Stopping the fans when the ambient temperature is low.
Fan Unit
Power Supply Socket Temperature Sensor
Label on Connector
48VDC Sensor
Connector Type
3V3 RJ45
Description
Input -48VDC to Fan Unit Connecting to ELU (Electronic label unit). Connecting to lower level cascaded Fan unit Connecting BBU / upper level cascaded Fan unit.
COM-OUT
Communication Port COM-IN
RJ45
RJ45
69
Huawei
70
Huawei
The fan box consists of the fan subrack, fans, HPMI, and CMUA.
71
Huawei
Adjusts and controls temperature of the cabinet in different temperature control modes. Reserves a port for three Boolean inputs and detects Boolean alarms in the cabinet. The remote detection, however, is not supported. Provides a port for the RJ-45 connector to enable electronic label and cabinet type detection.
72
Huawei
The Hert Power Monitoring Interface unit (HPMI) provides input and output ports for alarm signals.
73
Huawei
74
Huawei
NoteWhen the DRFU is configured , the maximum cell configuration is 444 & when GRFU are configured the maximum cell configuration of a single cabinet is 12/12/12
75
Huawei
The GSM Antenna and TMA control module (GATM) is a modules that controls the antenna and TMA. The GATM is optional and is optionally installed in the power cabinet or transmission cabinet when the DRFU Module is configured. The GATM has the following functions, Controlling the RET antenna. Supplying power to the TMA. Reporting the RET control alarm signals. Monitoring the current from the feeder. Not support common TMA and RET antenna at the same time.
76
Huawei
77
Huawei
The PMU has the following functions, Communicating with the BBU or cascaded through an RS232/RS422 serial port. Managing the power system and charge /discharge of battery. Detecting and reporting water damage alarm,smoke,door & customized Boolean values. Reporting the ambient temperature ,ambient humidity, battery temperature and customized analog values. Monitoring power distribution ,reporting related alarms and reporting dry contact alarms.
78 Huawei Telecom Implementation Process & Guidelines
Converting 220VAC to -48VDC. Supplying -48VDC power to the DCDU. Monitoring the unit and reporting alarms related to PSU faults, Such as output overvoltage,No output, fan faults etc.). Alarms related to PSU protection ,such as over temperature protection, Input over voltage /under voltage etc. PSU out of position alarm if any.
79
Huawei
80
Huawei
PDU-01
Dual Live AC distribution unit (for distributed Base Station) 1-Phase/3-Phase AC distribution Unit (for Separated Base Station) Dual Live AC distribution unit (for separated Base Station)
AC Input : L1 Side are short circuited & ,L2 Side are short circuited.
PDU-02 Dual Live 110VAC AC Output : L1out & L2out are short circuited. N1out & N2out are short circuited. PDU-03 1-Phase, 220VAC 3-Phase, 220 VAC Dual Live 110VAC
PDU-04
81
Huawei
12A 12A
1 1
4A
RFU
30A
Reserved Output Separated base station Six LLVD Output BBU FAN Transmission Devices
82 Huawei
1 1 1
4A
EPS Subrack
It provides 2 AC outputs, one for service outlet & other is for junction box. Reporting the AC input surge protection alarms. Provides 16/12A DC outputs for the distributed base station/macro base stations.
83 Huawei Telecom Implementation Process & Guidelines
MCB/Fuse
20A 25A 15A 15A 5A 100A 15A 80A 25A 15A 15A 15A 100A 5A
MCB/Fuse Qty
6 1 1 1 4 1 2 2 1 1 2 1 1 4
DCDU-02 in RFC
LEFTSIDE
RIGHTSIDE
Function of DCDU-02 are as below, Receives -48VDC power input. Supplies 04 ,-48VDC power outputs to boards & modules in the cabinet. Provides surge protection.
85
Huawei
Power Consumption Devices Temperature Control System Transmission system of the operator RRU BBU & Transmission system of the operator Transmission system of the operator & Fan BBU Transmission system of the operator & Fan
MCB Qty 1 8 6 3 6 1 2
DCDU-03B
DCDU-03C
Separated macro base station in the -48 V DC Power supply/ Transmission cabinet
86
Huawei
DC O/P Terminal
LOAD-0 & LOAD-1 LOAD-2 & LOAD-3
MCB Rating
30A 12A 12A 6A
MCB Qty
2 2 4 1
Application Scenarion
DCDU-03D
87
Huawei
RRU 3004(DC)
88
Huawei
89
Huawei
RRU 3008(DC)V1
90
Huawei
91
Huawei
RRU 3008(DC)V2
92
Huawei
93
Huawei
RRU 3004(AC)
94
Huawei
95
Huawei
RRU 3008(AC)V1
96
Huawei
97
Huawei
RRU 3008(AC)V2
98
Huawei
99
Huawei
BBU3900 CDMA
Implementing resource management, operation and maintenance, and environment monitoring for the system
100 Huawei Telecom Implementation Process & Guidelines
101
Huawei
QCU1HCPM panel
QCU3HCPM panel
102
Huawei
The HECM has the following functions; It processes the CDMA2000 EV-DO service data on forward and reverse channels.
103
Huawei
Function of UBRI Module It implements the functions of PN sharing, 1X resource pool, and convergence and distribution of baseband data.
104
Huawei
HCPM/ HECM
EXT-ALM1
105 Huawei
RRU3606-CDMA
Dimensions of the RRU that works in the 800 MHz AB and 450 MHz bands: 485 mm (19.10 in.) x 285 mm (11.22 in.) x 200 mm (7.87 in.) (with the shell) 480 mm (18.90 in.) x 270 mm (10.63 in.) x 170 mm (6.69 in.) (without the shell) Dimensions of the RRU that works in other bands: 485 mm (19.10 in.) x 285 mm (11.22 in.) x 170 mm (6.69 in.) (with the shell) 480 mm (18.90 in.) x 270 mm (10.63 in.) x 140 mm (5.51 in.) (without the shell) DC RRU3606
485 mm [19.21 in.] x 285 mm [11.02 in.] x 250 mm [9.84 in.] (with a shell)
DC RRU3606 -CDMA
107
Huawei
108
Huawei
109
Huawei
110
Huawei
BBU3900 NODE-B
112
Huawei
113
Huawei
114
Huawei
Modules of Node-B(WRFU)
Function of WRFU Module
The direct frequency conversion technique, which is directly implemented in the transmit channel, modulates the baseband signals to WCDMA RF signals. After being filtered and amplified, the RF signals are transmitted to the antenna for transmission through the duplex filter. The Uplink RF signals received from the antenna go through down-conversion, amplification, analog to digital conversion, digital down conversion, matched filtering, automatic gain control-AGC .Then they are sent to BBU. Power control & VSWR detection. Reverse power detection. Frequency synthesis & loopback test. Generation of CPRI clock, recovery of the CPRI clock of lost synchronization & alarm detection.
115
Huawei
Modules of Node-B(MRFU)
Function of MRFU Module
The direct frequency conversion technique, which is directly implemented in the transmit channel, modulates the baseband signals to WCDMA RF signals. After being filtered and amplified, the RF signals are transmitted to the antenna for transmission through the duplex filter. The Uplink RF signals received from the antenna go through down-conversion, amplification, analog to digital conversion, digital down conversion, matched filtering, automatic gain control-AGC .Then they are sent to BBU. Power control & VSWR detection. Reverse power detection. Frequency synthesis & loopback test. Generation of CPRI clock, recovery of the CPRI clock of lost synchronization & alarm detection.
116
Huawei
RRU3801C-NODE-B
Function of RRU3801C Module
Forward & Processes RF signals between BBU and the antenna system. Receives RF signals from antenna system, down converts the signals to IF signals,& then transmits them to the BBU or the macro Node-B after amplification, analog to digital conversion, digital down conversion ,matched filtering & digital automatic gain control. Receives downlink baseband signals from the BBU or the macro Node-B, forward data received from its cascaded RRU,performs filtering & digital to analog conversion, and up-converts RF signals to the TX band. Multiplexes RX & TX signals over RF channels, which enables the RX signals and TX signals to share the same antenna path.
117
Huawei
RRU3804-NODE-B
Function of RRU3804 Module
Forward & Processes RF signals between BBU and the antenna system. Receives RF signals from antenna system, down converts the signals to IF signals,& then transmits them to the BBU or the macro Node-B after amplification, analog to digital conversion, digital down conversion ,matched filtering & digital automatic gain control. Receives downlink baseband signals from the BBU or the macro Node-B, forward data received from its cascaded RRU,performs filtering & digital to analog conversion, and up-converts RF signals to the TX band. Multiplexes RX & TX signals over RF channels, which enables the RX signals and TX signals to share the same antenna path.
118
Huawei
119
Huawei
RRU3804 Vs RRU3801C-NODE-B
120
Huawei
RRU3805-Node-B
The functions of the RRU3805 are as follows;
121
Huawei
RRU3908-Node-B
The functions of the RRU3908 are as follows; The single RRU3908 module supports six carriers when working in GSM mode and GSM+UMTS dual mode, and four carries in UMTS mode. The RRU3908 provides the CPRI port for data communication with the BBU3900. When working in GSM mode, the RRU3908 adopts the direct frequency conversion technique, which is directly implemented in the transmit channel. The RRU3908 modulates the baseband signals into GSM RF signals. After being filtered and amplified, the RF signals are sent to the antenna for transmission, through the duplexer in the RF front-end unit. When working in UMTS mode, the RRU3908 directly sends the baseband signal to the antenna for transmission, through the duplexer in the RF front-end unit. The RRU3908 processes the uplink RF signals received from the antenna through down-conversion, amplification, analog-to-digital conversion, digital down-conversion, matched filtering, Automatic Gain Control (AGC), and then transmits the signals to the BBU3900 for further processing. The RRU3908 supports power control and Voltage Standing Wave Ratio (VSWR) detection. The RRU3908 supports frequency synthesis. The RRU3908 supports the generation and recovery of the clock circuitry, and alarm detection on the CPRI port.
AC RRU3908 DC RRU3908
122
Huawei
123
Huawei
Infrastructure Requirements
Basic Infrastructure required for BTS implementation
Space for ID BTS ,IDU /OD Cabinets or any third party supplied cabinet for equipments with recommended clearances inside equipment room/shelter or outside. Tower with GSM & MW antenna mounts at required RND/TND height & Azimuth. Cable Tray for routing of RF feeders & IF cable on tower as well as from tower to Shelter/equipment location. LA installed & connected to main grounding system. Aviation Lamp & operational. Grounding network & all equipments (DG, Shelter,AC/DC power system ,Tower etc) are connected to main grounding system. IGB & EGB installed & connected to main grounding network. E/A (DG Sets) with required capacity. Air-Conditioning inside shelter/room. DC Power as per requirements & MCB/fuses for proposed equipments of required capacity. Cable Tray inside shelter. Feeder entry for 6x7/8 RF cable , & 2x1/2 IF Cable on existing entry plate or space for new entry plate. Fire Fighting system (Sensor/detectors) with fire extinguisher.
124
Huawei
125
Huawei
900
The cabinets are as close to the feeder window as possible so that the feeders can be saved in length. The cabinets are installed in a row in the same equipment room for easy cabling.
40
The clearance requirements for the BTS3900 cabinets are as follows: The cabinet can be installed with its back against the wall. The cabinet can be installed with one side against the wall. At least 800 mm in front of the cabinet should be reserved for maintenance. At least 200 mm on top of the cabinet should be reserved for cabling.
126 Huawei Telecom Implementation Process & Guidelines
127
Huawei
The recommended clearances requirements of RRU3004 are, 300mm above the equipments. 500mm under the equipments for cabling. 800mm in front of the equipments for maintenance. 300mm on the left of the equipment for maintenance. 600mm on the right of the equipment for maintenance.
128 Huawei Telecom Implementation Process & Guidelines
The recommended Clearances requirements of RRU3008 are, 300mm above the equipments. 500mm under the equipments for cabling. 800mm in front of the equipments for maintenance. 300mm on the left of the equipment for maintenance. 600mm on the right of the equipment for maintenance.
INSTALLATING RRU ON WALL, For single RRU ,the pulling force would be 1.25KN,hence the wall Should be capable of bearing the above pulling force.
129
Huawei
Power Requirements
130
Huawei
Power Requirements
@ 23 Deg. Centigrade
Sl. No. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 Product BTS 3900 BTS 3900 BTS 3900 BTS 3900 BTS3900A BTS3900A BTS3900E BTS3900E BTS3900E BTS3900E BTS3900B BTS3900L BTS3900-WCDMA BTS3900A-WCDMA DBS3900-(BBU+ 3801C)WCDMA DBS3900-(BBU+ 3804)WCDMA BTS3012AE BTS3012AE BTS3012 BTS3012 2100MHz 2100MHz 2100MHz 2100MHz 900MHz 900MHz 900MHz 1800MHz 3x4 3x4 3x2 3x3 S222 S444 S444 S444 48VDC 48VDC 48VDC 48VDC 196V-240VAC 196V-240VAC 48VDC 48VDC 1020 1220 680 710 980 1550 950 1000 1330 1580 830 970 1280 2100 1850 2050 Frequency 900MHz 900MHz 1800MHz 1800MHz 900MHz 900MHz 900MHz/1800MHz 900MHz/1800MHz 900MHz/1800MHz 900MHz/1800MHz 900MHz/1800MHz Configuration S222 S444 S222 S444 S222 S444 S600 S600 S333 S333 Operating Voltage 48VDC 48VDC 48VDC 48VDC 220 V AC single phase: 176V AC to 290 V AC 220 V AC single phase: 176V AC to 290 V AC 48VDC 220 V AC single phase: 176V AC to 290 V AC 48VDC 220 V AC single phase: 176V AC to 290 V AC 48VDC Typical power Max Power consumption in consumption in watts watts 750 1050 1140/1000 2000/1360 740 1030 1130/1060 1960/1360 800 1200 100/110 100/110 360/420 420/420 20 1100 1560 140/130 150/130 510/570 570/540 30
131
Huawei
1 2 3 4 5
21 42 63 83 104
132
Huawei
BTS 3900
2 3
24VDC 220 V AC single phase: 176 V AC to 290 V AC 220 V AC single phase: 176 V AC to 290 V AC 48VDC
BTS3012AE
BTS 3012AE
BTS 3012AE
24VDC
BTS3012
48VDC
BTS3012
24VDC
133
Huawei
AC/DC
DC
DC AC DC
48/24/230
48
24 230 48
From
Power Plant
Power Plant ACDB/PIU Power Plant
To
DCDU
Power Subrack (DC/DC PSU) Power Subrack (AC/DC PSU) DCDU-01 in RFC/DCDU-03 in TMC11 Power Sub rack (DC/DC PSU) inside APM30H Power Sub rack (AC/DC PSU) inside APM30H/PDU in APM30H RRU (S2 to S4) RRU (S2 to S4) BTS3012 Input terminal at top of BTS BTS3012 Input terminal at top of BTS DC Power Subsystem DC Power Subsystem
MCB/Fuse Rating
63A,1Pole
160A ,1-Pole 32A , 2-Pole 100A,1Pole/63A,1Pole
BTS3900A
DC
24
Power Plant
160A ,1-Pole
BTS3900A DBS3900
AC DC
230 48
DBS3900
BTS3012 BTS3012 BTS3012 AE BTS3012 AE BTS3012AE
134 Huawei
AC
DC DC DC DC AC
230
48 24 48 24 230
PDU
Power Plant Power Plant Power Plant Power Plant External power interface
20A,1-Pole
80A ,1-Pole 160A ,1-Pole 80A ,1-Pole 160A ,1-Pole 32A , 2-Pole
AC Power Subsystem
The pre installation site survey is required to identify/check the site for feasibility (Infra Requirements, Environmental suitability & Security etc.) with respect to implementation of Telecom equipments (BTS,MW-PDH/SDH Hops , RF Antenna & Feeder line, Battery & SMPS etc). The Survey is required for Installation Material /Auxiliary Material estimation. The Survey is required for preparation of Proposed layout Plan for equipments. The standard Checklist can be used during pre-installation site survey & listing out the additional requirements along with proposed Equipments Layout Plan, Installation Material estimation sheet, Site Photographs etc.
135
Huawei
TRANSPORTER TEAM SHOULD CHECK THE NOS OF PACKETS AND QUALITY OF PACKING DURING MATERIAL HANDOVER
Ask transporter to keep all the boxes near room/shelter using proper tools/equipme nts.
Handover the signed POD to transporter after signing on it & keep one copy for record.
136
Huawei
OPENCASE INSPECTION/UNPACKING
137
Huawei
138
Huawei
Unpacking of Equipments & Installation Materials. Check again the boxes nos. as per POD .(if any box found missing ,communicate immediately to IM & Site Engineer) Unpack the equipment, and then check the total number of goods in the packing case according to the attached packing list and whether the packing cases are in good condition ? Unpack the packing case and then check the type & number of equipment in the cases according to the packing list. Packing list should be signed by subcon engineer , whoever is verifying & must be kept in good condition for site folder. If found any discrepancies (Packing list Vs actual in cases) ,must be informed to responsible Huawei Engineers.
139
Huawei
140
Huawei
SE will Verify the list as requested by Subcon & inform to IM & SCM.
END
The MR for short shipment materials to be prepared by IM & same is approved by CPM.
SCM & Warehouse team verify the short shipment against original POD/DN of site.
141
Huawei
BTS Installation
142
Huawei
143
Huawei
144
Huawei
145
Huawei
Installing the Cabinet Installing the PGND Cable NO Whether Optional Modules installed? YES
146
Huawei
(3) AC cabinet
147
Huawei
a
GRFU/DRFU
b
BBU3900 power module FAN unit
d e
Power cable
DCDU-01
(1) M12x60 bolt (2) Spring washer (3) Flat washer (4) Expansion tube
149 Huawei Telecom Implementation Process & Guidelines
Install the base and adjust the base level. Place the insulating spacer and the base on the floor, align the mounting holes in the base and in the insulating spacers with the holes of the expansion bolts in the floor, and then use four M12x60 bolts to secure the base. Check and adjust the base level. Place the level on the top plane of the base to check the base level. Use a level bar to check the levelness of the base, and then adjust the adjusting bolt until the base is horizontal. If the bubble in the level bar is in the middle, you can infer that the base is horizontal. The resistance between the base and the four expansion bolt assemblies should be respectively measured. If the resistance is less than 5 megohm, you can infer that the base and the earth are not insulated. In this case, you need to disassemble the expansion bolt and check whether the insulating washer is installed or damaged. If the insulating washer is not installed or damaged, install the washer again and adjust the levelness of the base.
150 Huawei Telecom Implementation Process & Guidelines
Defective Picture
Correct Picture
151
Huawei
45Nm
During the installation, discard the installation blocks delivered with the base and use installation blocks delivered with the cabinet.
152
Huawei
M12X60
45Nm
M12x25 bolt
153 Huawei Telecom Implementation Process & Guidelines
Procedure of Cable through to BTS, Route and bind the cables by using the method mentioned in Routing the Cables for a Single Cabinet. Lead the 12 feeders of the upper cabinet out directly from the panels of the RFUs. In this case, remove the cover plate on the top of the upper cabinet.
PGND cable OT terminal Screw Internal grounding bar (IGB) To Main Equipment Earth pit 35 Sq.mm Copper flexible Cable Procedure of Installing PGND Cable; Prepare the PGND cable & check the length first & then cut the cable. Prepare the cable of proper length based on the actual cable route. Add OT terminals to both ends of the cable & Correct OT terminals to be used with proper crimping tools. Use a PGND cable with a cross-sectional area of 25/16 mm2 to connect the ground point on the -48 V cabinet to an external ground bar. Use heat shrink/insulation tape on OT terminal & ensure no strands are visible.
155 Huawei Telecom Implementation Process & Guidelines
(1) External ground bar (2) OT terminal (M8) (3) OT terminal (M8)
156
Huawei
157
Huawei
Defective Picture
Correct Picture
158
Huawei
159
Huawei
E1 Cabling in BTS3900
Connection of the E1 cable
Cable connections with the UELP configured Prerequisite Ensure that both ends of the E1 cable are disconnected. Then, weld connectors to the bare wires at one end of the E1 cable all at once. Procedure Install the E1/T1 cable. If the UTRP is not configured, link the DB26 male connector of the E1/T1 cable to the port labeled E1/T1 on the GTMU. If the UTRP is configured, link the DB26 male connectors of the E1/T1 cables to the ports labeled E1/T1 on the GTMU and UTRP, and then tighten the screws. Route the E1/T1 cable along the cable trough on the right of the cabinet, and then use cable ties to bind the cable. Attach labels to the installed cables by referring to Attaching an L-Shaped Label.
OUTSIDE
INSIDE
E1/T1
160
Huawei
FE Cabling-BTS 3900
Connection of the FE cable Cable connections with the UFLP configured Context The FE/GE cable is a shielded straightthrough cable. It has an RJ-45 connector at each end. Procedure Connect the FE/GE cable to the port labeled FE0 on the GTMU. Route the FE/GE cable along the cable trough on the right of the cabinet, and then use cable ties to bind the cable. Attach labels to the installed cables by referring to Attaching an L-Shaped Label.
INSIDE
OUTSIDE
FE0
161
Huawei
CPRI Electrical cable used for high speed communication between BBU3900 & RFUs. The CPRI high speed transmission cable that has SFP200 male connector at both ends.
162
Huawei
163
Huawei
164
Huawei
3 RFUs; 3 sectors
6 RFUs; 6 sectors
ANT_RXB ANT_TX/RXA
ANT_RXB ANT_TX/RXA
The installation sequence is from top to bottom and from both sides to the middle. When bending the RF jumpers, do not damage the jackets of the jumpers.
To facilitate future capacity expansion by stacking cabinets, ensure that an extra length of 300 mm is reserved for each jumper. If a single cabinet is installed, the RF jumpers are routed along the left and right cable troughs. When adding a DIN connector, use a wrench to tighten it until the fastening torque is 25 Nm to 35 Nm. The connectors of the jumpers should be properly added and securely linked to the modules. The requirement for bending radius of the 1/2-inch super-flexible jumper is more than 50 mm.
165
Huawei
RX_INBRX_OUTA
ANT_TX/RXA
RFU RFU0&1
RFU2&3
When bending the RF jumpers, do not damage the jackets of the jumpers.
166 Huawei Telecom Implementation Process & Guidelines
RFU4&5
RFU4 RX_INB
RFU4 RX_OU TA
RFU5 RX_OU TA
RFU5 RX_INB
BBU
167 Huawei Telecom Implementation Process & Guidelines
Remove the equipotential cable from the lower part of the cabinet door. After that, rotate the spring pin counter clockwise by 90 degrees and press the pin to remove the cabinet door. When removing the cabinet door, make sure that it does not fall off suddenly and hurt operators.
168 Huawei Telecom Implementation Process & Guidelines
After the spring pin is rotated towards the installation hole, rotate it clockwise until it is tight against the cabinet door.
After the cabinet door is installed, install the equipotential cable for the cabinet door.
Defective Picture
Correct Picture
6A MCB used for BTS power cable termination 63A MCB used for BTS power cable termination
169
Huawei
BTS3900A INSTALLATION
170
Huawei
Install RF Jumpers
END
171 Huawei Telecom Implementation Process & Guidelines
NoteThe TMC11H has the following features in terms of its structure, According to different applications scenario, the TMC11H can be configured with DCDU-03A,DCDU-03B,DCDU-03C or DCDU-03D. The DCDU-03 provides 9 Nos. of O/P & reports surge protection alarms. The TMC11H provides 11U space for user equipments.
172
Huawei
Installation Of Base
Procedure of Positioning, Determine the position for installing the cabinet according to the approved Layout Plan. On the concrete pad, mark holes to determine the installation position of the base. After marking all the holes, use the measuring tape to check whether the distances between the holes are accurate.
Pre-requisite of Concrete Plinth, The height of the concrete pad must meet the heat dissipation and waterproofing requirements of the cabinet. The concrete pad must be at least 200 mm above the floor. The horizontal error of the poured concrete pad must be less than 5 mm.
173 Huawei Telecom Implementation Process & Guidelines
Installation Of Base
Drilling the Hole for fasteners
Use Hammer drill with M16 bit to drill holes at the anchor points & ensure that the depth of each holes ranges from 52mm to 60mm. Dont drill holes through the holes in the base by using hammer drill. Drilling holes through the holes in the base may damages the paint on the base. Take proper safety measures to protect eyes & respiratory system against dust before drilling. Use vacuum cleaner to clear the dust inside & around holes. If the inner hole spacing is too wide /narrow ,locate & drill holes again. Slightly tighten the expansion bolt, and then put the expansion bolt assembly into the hole vertically. Use a rubber mallet to hammer the expansion bolt until the expansion tube is buried into the hole, and then tighten the bolt. Remove the bolt, spring washer, and flat washer counterclockwise. After dismantling the expansion bolt assembly, ensure that the top of the expansion tube is on the same level as the floor. Align the base, and then install the bolt with the spring washer and flat washer. Use a level to check the base level. If the base is not level, use adjusting pads to adjust the base level.
174 Huawei Telecom Implementation Process & Guidelines
175
Huawei
NOTE
DONT DAMAGE PLASTIC SCREWS,KEEP THEM FOR USE
177
Huawei
178
Huawei
179
Huawei
Signal Cable
Power Cable
180
Huawei
181
Huawei
3-Phase Supply
1-Phase Supply
182
Huawei
183
Huawei
184
Huawei
185
Huawei
Before installing modules and cables, you must disconnect the external power. Take proper ESD protection measures, for example, wearing an ESD wrist or a pair of ESD gloves, to prevent electrostatic damage to the boards, modules, or electronic components. Install the mounting ears on the two sides of the BBU reversely, and remove the grounding screw on the right side. Push the BBU case into the cabinet.
186
Huawei
187
Huawei
188
Huawei
Signal Cable
Power Cable
189
Huawei
190
Huawei
DCDU-03
Procedure of DC Cabling, APM30/TMC11 CABINET WITH DC SCENARIO. KEEP PROPER DISTANCES BETWEEN SIGNAL & POWER CABLES. 6 Sq.mm copper cable shall be used between DCDU-03 to DCDU-02. -48VDC Input to DCDU-03 ,the cable specs is 16Sq.mm Copper flexible.
191
Huawei
DCDU-06
DC Power Cabling-TMC11 (DCDU-06)
Before installing the cables, open the DCDU-06A by the four screws on the cover of the DCDU-06A. Use Temporary Labels to the Cable before cut/Laying. Finish installation of the cables, close the DCDU-06A. Make the cord end terminals on site. Connect the cables to the DCDU-06A. Check the rating of Fuse/MCB at mains. If length is insufficient ,then replace the cable with longer length (avoid joints on power cable). Use proper lugs & crimp with cable. Run each cable that leaves the cabinet in the PVC corrugated pipe, and then tie the pipe to the cable hole in the cabinet. Label the installed cables by referring to Attaching a Sign Plate Label. The bending radius of the power cable or PGND cable must be at least five times the diameter of the cable. The MCB used for controlling the BTS is set at 80 A on the configuration interface of the PDB. The cross-sectional area of the DC input power cable is 16mm2, the length of the cable must be shorter than 15m.
192 Huawei Telecom Implementation Process & Guidelines
193
Huawei
NOTE Before installing the power cables, remove the protecting hood from the DC input wiring terminal block on the DCDU-01. After the cables are installed, reinstall the protecting hood.
Install the input power cable for the TMC11H. 1. If the TMC11H obtains power from the external equipment, install the cable by referring to Step 2. 2. If the TMC11H obtains power from the RFC, link the parallel terminal at one end of the power cable to the DC output terminal labeled SPARE2 on the DCDU-01 in the RFC, and then link the OT terminal at the other end to the DC input wiring terminal on the DCDU-03 in the TMC11H. Route the cable as per Cabling Requirements, and then use cable ties to bind the cable. Attach labels to the installed cable. Run each cable that leave the cabinet in a PVC corrugated pipe, and then tie the pipe to the cable hole in the cabinet.
194 Huawei Telecom Implementation Process & Guidelines
196
Huawei
Preparing OT Terminal
197
Huawei
E1/T1 Cabling
Connect the E1/T1 cable to the OUTSIDE port on the UELP in the cabinet. Lead the other end of the E1/T1 cable out of the cabinet through the cable holes at the bottom along the right of the cabinet. The bending radius of the E1/T1 cable must be at least five times the diameter of the cable. Different types of cables must be separately routed and cannot be entangled. The cables must be bound tightly and neatly. The sheaths of the cables must not be damaged. The cable ties must face the same direction, and those at the same horizontal line must be in a straight line. Extra length of cable ties must be cut. Labels or nameplates must be attached to the cables after they are installed. Different types of cables must be separately routed with a minimum space of 30 mm between every two cables.
198 Huawei Telecom Implementation Process & Guidelines
199
Huawei
200
Huawei
FRONT OF CABINET
RFC CABINET
When leading the RF jumpers through the cable hole at bottom of the cabinet into the cabinet, ensure that the DIN Male elbow connector is perpendicular to the DRFU/GRFUs. During the installation , don't rotate the DIN male elbow connector. This may cause damage to the connector. The bending radius of the feeders should be --- For 7/8 coaxial Cable- >120mm. , for 5/4 Coaxial Cable >380mm. The bending radius of the Jumpers should be --- For 1/4 coaxial Cable- >35mm. , for 1/2 Coaxial Cable (super flex) >50mm. & for Coaxial Cable (flexible)->127mm
BASE
201
Huawei
Installation Procedure
Lead cables with different cross-section areas through the holes of the cable module based on the aperture, and then insert the cable module into the cable hole of the cabinet. Use rubber caps to seal the idle cable holes. Tighten the screws in the front of the cable module to fix the module.
202
Huawei
Installation of RF Jumpers
Dont Use any tools for tightening The Din Connectors at Equipment End, only Hand tight is recommended.
203
Huawei
Defective Picture
Correct Picture
Defective Picture
Correct Picture
Defective Picture
Correct Picture
208
Huawei
209
Huawei
Site Preparedness
Installing E1/FE Surge Protection Transfer Cables ( Optional Cables) Installing Monitoring Signal Cable (Optional)
Powering ON RRU
END
210
Huawei
PROCEDURE USE RIGHT LUGS WITH PROPER CRIMPTING TOOL. PGND CABLE SHOULD BE OF 25/16 SQ.MM COPPER FLEXIBLE CABLE. TIGHTEN PROPERLY BOTH AT BUS BAR & EQUIPMENT ENDS.
213
Huawei
ProcedureConnect the OT terminal of the power cable to the LOAD3 terminal of the PDU, and then fix the 3V3 connector of the power cable to the PWR port on the BBU.
214
Huawei
NOTEThe single-mode optical module is labeled "SM" and multi-mode optical module is labeled "MM. If the puller of an optical module is blue, the module is a single-mode optical module. If the puller of an optical module is black or grey, the module is a multi-mode optical module. The TX port on the BBU is connected to the RX port on the RRU. The RX port on the BBU is connected to the TX port on the RRU.
ProcedureConnect the fiber tails labeled 2A and 2B to one of the CPRI0 to CPRI5 ports on the GTMU, and connect the fiber tails labeled 1A and 1B to the CPRI_W port on the RRU. Insert the optical module into the CPRI0,CPRI1, CPRI2 CPRI3, CPRI4 orCPRI5 port, and then turn outwards the puller on the optical module. Insert one end of the CPRI optical cable into the optical module, and then lead the CPRI optical cable out of the cabinet along the right side of the cabinet. Wrap the fiber tail with the winding pipe.
215 Huawei Telecom Implementation Process & Guidelines
216
Huawei
FE Cable Installation
Install the FE Transfer Cable (FE Transmission Mode). Connect one end of the FE transfer cable to the FE0 port near the INSIDE label on the UFLP and the other end to the FE0 port on the GTMU. Install the FE cable (FE transmission). Connect one end of the FE cable to the FE0 port near OUTSIDE label on the UFLP.Then lead the other end out of the cabinet along the right side of the cabinet. Thread the FE cable through the grounding clip. Then tighten the screw on the grounding clip to make the shielding layer of the FE cable in full contact with the grounding clip. Connect the PGND cable on the grounding clip to the grounding bolt of the APM30.
217
Huawei
218
Huawei
ProcedureThe DC RRU power cable is connected to one of the LOAD8 to LOAD13 terminals of the EPS. Strip the jacket of the DC RRU power cable for a strap, press the exposed shielding layer on the Strap and then connect the PGND cable on the strap to the nearest grounding bolt on the side in the APM30H(Ver.B).
219
Huawei
220
Huawei
221
Huawei
2
3
Strip off the shielding layer and then lead the cable through a heat-shrinkable tube.
Assemble an OT terminal at one end of the cable
4
5
6
7
222
Huawei
3 4
Make the both ends of the power cable with OT terminals. Use and terminated proper color coding cables as indicated in pics.
Tighten all the terminals properly. Use proper tools for stripping, crimping & tightening of all connectors.
Connect one end of the cable to the MCB/Fuse at incomer & connect the other end to the PDU inside AMP30.
223
Huawei
224
Huawei
225
Huawei
226
Huawei
227
Huawei
228
Huawei
229
Huawei
Procedure of Cabling,
The DC RRU Power Cable is connected to one of the LOAD0 to LOAD5 terminals of the DCDU-03B. When connecting the DC RRU power cable to the DCDU-03B,must add an OT terminal to the shielding layer. Then fix the OT terminal to the corresponding PGND terminal of the DCDU03B.
230 Huawei Telecom Implementation Process & Guidelines
INSTALLATION OF RRU
231
Huawei
INSTALLATION OF DC RRU
232
Huawei
233
Huawei
234
Huawei
235
Huawei
When installing the main fixture ,ensure that the contact piece on the fixture is fixed & ensure that the arrow on the main fixture is upward. It is recommended that the bottom of the highest main fixture be 1200mm to 1600mm above the ground for easy maintenance. Fit one end of the auxiliary mounting bracket to one dual-nut bolt assembly of the main mounting bracket. Install main and auxiliary mounting brackets on the pole, and then fit the other end of the auxiliary mounting bracket to the other dual-nut bolt assembly Fasten the two dual-nut bolt assemblies alternatively. After the brackets are secure, use a tape to measure the spacing between the main bracket and the auxiliary bracket at the two sides and ensure that the spacing is the same. Use an adjustable wrench to tighten the nuts until the fastening torque is 40 N-M.
237
Huawei
Install the RRU on main bracket ,when you hear the click sound , it can be infer that the RRU is installed correctly. The weight-bearing capacity of the RF ports at the bottom of the RRU is low. Do not place the RRU at its. During the operation, place the foam pad or cardboard under the RRU to prevent any damage to the housing of the RRU.
238
Huawei
ProcedureThe procedure for installing the RRU on U-steel is the same as that on a metal pole. Only one RRU can be installed on U-steel.
239
Huawei
ProcedureThe procedure for installing the RRU on U-steel is the same as that on a metal pole. Only one RRU can be installed on U-steel.
240
Huawei
Procedure It is recommended that the auxiliary bracket be 1,200 mm to 1,600 mm above the ground. The RRUs cannot installed on a wall in centralized mode. Therefore, expansion bolt assemblies should be prepared for each RRU. For one RRU, the wall has a weight-bearing capacity of 68 kg. The fastening torque of the expansion bolt reaches 30 Nm, the expansion bolt works properly, and no damages such as cracks are on the wall.
241
Huawei
Fit the auxiliary mounting bracket on the expansion bolt, and then use a combination wrench (17 mm [0.67 in.]) to tighten the expansion bolt to 30 Nm (265.52 lbf.in.). Install the main mounting bracket. Install the RRU on the main mounting bracket until the RRU snaps shut.
242
Huawei
243
Huawei
(1) PGND cable (2) RRU RF jumper . (3) CPRI optical fiber (4) RRU power cable (5) RRU alarm cable
A lower-level RRU obtains power directly from the external power system, but not from an upper-level RRU using a power cable. If you must cascade two or more RRUs in the same cell, for example, when expanding capacity, install the alarm cable to the last RRU.
244
Huawei
245
Huawei
(1) Dustproof cap (2) PVC insulation tape (3) Waterproof tape
246 Huawei Telecom Implementation Process & Guidelines
(1) Cover plate (2) Cable diagram on labels (3) Cable trough for the optical fiber (4) Cable trough for the power cable (5) Waterproof block (6) Clip (7) Cabling cavity Procedure; Wear an ESD wrist strap or ESD gloves. Loosen the protection screw on the cover plate of the RRU cabling cavity using an M4 Phillips screwdriver, and then push the handle outwards to open the cover plate.
247
Huawei
(1) Cover plate (2) Cabling cavity (3) Waterproof block (4) Cable trough for the power cable (5) Cable trough for the optical fiber (6) Clip
248 Huawei Telecom Implementation Process & Guidelines
Procedure Install an RRU power cable that feeds power to an RRU from a DCDU-03B when the DCDU-03B is configured. Connect the OT terminals of the blue and black/brown core wires at one end of the RRU power cable to the NEG(-) and RTN(+) ports on the RRU cabling cavity respectively. Connect the OT terminals of the blue and black/brown core wires at the other end of the RRU power cable to the NEG(-) and RTN(+) ports of the LOAD0 on the DCDU03B respectively.
249 Huawei Telecom Implementation Process & Guidelines
251
Huawei
252
Huawei
253
Huawei
254
Huawei
Procedure-
Bundle the outdoor engineering label on the RRU power cable, CPRI fiber cable ,RF cable with black cable tie. The label is 200mm away from the connector.
255 Huawei Telecom Implementation Process & Guidelines
256
Huawei
Procedure of OT Terminals
Determine lengths of power cables for different operations according to the scales on the inner side of the cover plate of the cabling cavity. Based on the determined length, remove the jacket and shielding layer from the power cable.
The assembling of OT terminals to the power cable must be complete before the BTS3900E is installed on a metal pole.
Add OT Terminals to each wires Strip a 15 mm jacket off the power cable to reveal the shielding layer of the power cable.
257
Huawei
Procedure of OT Terminals
Do not damage the shielding layer of the power cable when cutting the jacket.
258
Huawei
259
Huawei
260
Huawei
END
END
261
Huawei
262
Huawei
263
Huawei
264
Huawei
265
Huawei
266
Huawei
267
Huawei
1. Hold the BBU with your hands and align the holes for mounting ears with the holes for installing the cabinet. 2. Push the BBU in the cabinet slowly along the guide rails. 3. Use a Phillips screwdriver to tighten the four screws (M6 x 12) on the panel to fix the BBU in the cabinet
268
Huawei
269
Huawei
270
Huawei
271
Huawei
272
Huawei
273
Huawei
274
Huawei
275
Huawei
276
Huawei
277
Huawei
278
Huawei
279
Huawei
280
Huawei
Installation of RRU3606 on Metal Pole of Dia 60mm-114mm (Single RRU on the Pole (Regular Mode))
281
Huawei
Installation of RRU3606 on Metal Pole of Dia 60mm-114mm (Single RRU on the Pole (Regular Mode))
282
Huawei
Installation of RRU3606 on Metal Pole of Dia 60mm-114mm (RRU on the Pole (Back to Back Mode))
283
Huawei
Installation of RRU3606 on Metal Pole of Dia 60mm-114mm (RRU on the Pole (Back to Back Mode))
284
Huawei
285
Huawei
286
Huawei
287
Huawei
288
Huawei
289
Huawei
290
Huawei
291
Huawei
292
Huawei
NOTE
After all cables are installed, bock all the unused cable troughs with proper waterproof plugs. Close the cover plate of the cabling cavity.
294
Huawei
295
Huawei
296
Huawei
Whether /not installing the optional modules NO YES Install the Modules
Installing the (opt) Monitoring Signal cable between cabinets Install the RF Cables
297
Huawei
Power Cables
Signal Cables
298
Huawei
NoteThe Cabinet Installation & its PGND, Power DC/AC cabling of BTS3900 WCDMA is same as the BTS3900 GSM .
299
Huawei
Remove the connecting piece from the cabinet top, and then install the support for the GPS surge protector in the original position of the connecting piece. Link the SMA male connector of the GPS signal cable to the GPS surge protector on the USCU and the N-type connector to the support for the GPS surge protector. Install the GPS surge protector to the support, and then connect cables. Route the cable. Attach labels to the installed cables.
300
Huawei
If the UTRP is not configured, link the DB26 male connector of the E1/T1 cable to the port labeled E1/T1 on the WMPT. If the UTRP is configured, link the DB26 male connectors of the E1/T1 cables to the ports labeled E1/T1 (0-3) and E1/T1 (4-7) on the UTRP, and then tighten the screws. Route the E1/T1 cable along the cable trough on the right of the cabinet, and then use cable ties to bind the cable. Attach labels to the installed cable.
301
Huawei
If the UTRP is not configured, link the RJ-45 connector of the FE cable to the port labeled FE0 on the WMPT, If the UTRP is configured, link the RJ-45 connectors of the FE cables to the ports labeled FE/GE0 and FE/GE1 on the UTRP, and then tighten the screws. Route the FE cable along the cable trough on the right of the cabinet, and then use cable ties to bind the cable. Attach labels to the installed cable.
302
Huawei
3x1
303 Huawei Telecom Implementation Process & Guidelines
3x4
3x1
304 Huawei Telecom Implementation Process & Guidelines
3x4
3x1
305 Huawei Telecom Implementation Process & Guidelines
3x4
307
Huawei
308
Huawei
BTS3900A-WCDMA Configuration
NoteThe Cabinet Installation & its PGND, Power DC/AC cabling of BTS3900A WCDMA is same as the BTS3900A GSM .
309
Huawei
310
Huawei
311
Huawei
312
Huawei
313
Huawei
314
Huawei
NoteInstallation of Cabinets,& all related cabling and BBU inside cabinet is same as DBS3900 GSM.
315 Huawei Telecom Implementation Process & Guidelines
Powering ON RRU
END
316
Huawei
317
Huawei
318
Huawei
319
Huawei
320
Huawei
321
Huawei
322
Huawei
323
Huawei
324
Huawei
NoteInstallation of RRUs ,its clearances ,& all related cabling are same as RRU incase of DBS3900 GSM.
325 Huawei Telecom Implementation Process & Guidelines
326
Huawei
BTS grounding cable size is 16mm2. DDF grounding cable size is 6mm2. EMU grounding Cable Size is 6mm2
DDF
EM U
Proper tools have to be used during grounding cable installation & crimping.
All cables have to be fixed properly. SS nuts Bolts & washers shall be used for grounding terminations.
Label
CRIMPING OF CABLES HAS NOT DONE AS PER RECOMMENDATIONS/PROPER TOOLS NOT USED/ LUGS USED NOT AS PER CABLES.
328
Huawei
Defective Picture
Correct Picture
329
Huawei
Defective Picture
Correct Picture
330
Huawei
Defective Picture
Correct Picture
331
Huawei
Defective Picture
Correct Picture
333
Huawei
Cables of different types must be routed separately. The cables cannot be coiled. The cables should be tightly bound in neat appearance. The jackets of the cables should be free from damage. The cable ties should be horizontal and should face the same direction. The extra length of the cable ties should be cut off. Labels or nameplates must be attached or bound on the installed cables.
Cables of different types must be routed separately. Cables of different types cannot be cross-routed. Space between cables of different types must be greater than 30 mm or separated by special objects when the cables are routed in parallel.
334
Huawei
The PGND cables and DC grounding cables must be connected to the same grounding body. The PGND cable must be buried in the ground or routed indoors. The PGND cable cannot be routed overhead outdoors before it is led to the equipment room. The cross-sectional area of the grounding cable between the cabinet and the lightning protection unit must be greater than 50 mm2. The external conductor of the coaxial cable and both ends of the shielding layer on the shielding cable must be in proper electrical contact with the outer surface of the metallic casing of the connected equipment. The grounding lead-in and the signal cable cannot be bound together or coiled. A certain distance should be reserved to avoid mutual interference. Adding switches or fuse boxes on the PGND cable is forbidden. Other devices cannot be used as a component of the electrical connection for the grounding cables. All the accessible conductive metallic parts in the casing of the equipment must be in reliable connection with the protection grounding terminal.
The E1 cables cannot be cross-routed with the power cables, PGND cables, or RF cables. If the transmission cables are routed in parallel with the power cables, PGND cables, or RF cables, the space between the cables of different types must be greater than 30 mm. The E1 cables should be tightly bound with cable ties and be routed in neat appearance. A slack of E1 cables should be reserved at the turnings.
335 Huawei Telecom Implementation Process & Guidelines
Signal cables should be routed separately from power cables, fiber jumpers, and jumpers. The specifications and cross-sectional area of the cable, and the route and position for the cabling should be designed beforehand. All the cables should be arranged neatly. Cable turns should be smooth. The bending radius of cable turns should be larger than 60mm, and the bending radius of fiber turns should be larger than 40 mm. There should be no damage to the insulating layer of the conducting wire. They should be bundled closely with appropriate tightness. The spacing between cable ties should be even. IDU cables should be routed along the left and the right to facilitate operations, and should not cover the board indicators. In other words, the cables of the boards in the left slots should be routed to the left of the cabinet and those in the right slots should be routed to the right of the cabinet.
336
Huawei
337
Huawei
338
Huawei
339
Huawei
340
Huawei
Cut the Feeder-After measuring the routing distance of feeders, cut feeders according to the length identifiers on the feeders.
341 Huawei
Put Color Rings on Feeders Stick color rings corresponding to the sectors at both ends of the feeder at the position 200 mm away from the connector.
342
Huawei
343
Huawei
NoteDo not over tighten the screws of the upper and lower supports. But the screws can not be too loose, or the antenna may slide. Bind the jumpers at several positions on the pole and tower platform. The operation must be performed by two personnel. The personnel under the tower use the compass at the position where is 10 m to 20 m away from the tower. The personnel on the tower adjust the antenna. After the azimuth reaches the requirement, tighten screws of the upper and lower supports.
344
Huawei
345
Huawei
3
NotePush the antenna forward and backward till the scale is adjusted properly. After the down tilt angle reaches the requirement, tighten screws of the scale. Before adjusting the down tilt angle, adjust the angle of the inclinometer to the desired angle. Push or pull the antenna till the bead in the inclinometer is located in the middle horizontally. After the down tilt angle reaches the requirement, tighten screws of the scale. Turn the adjustment tool until it aligns with the scale on the ruler.
346
Huawei
347
Huawei
NoteFix a DIN female connector to one end of the feeder. Stick color rings at one end of the feeder. Ensure that the first color ring is at the position 200 mm away from the feeder connector. Stick color rings at the other end of the feeder. Ensure that the first color ring is at the position 200 mm away from the feeder end.
348
Huawei
NoteInstaller D wraps the feeder connectors with plastic bags and tape, fasten the lifting rope to the feeders at the position 0.4 m away from the feeder connectors and fasten the traction rope at the position 4.4 m away from the feeder connectors. Installer C pulls down the lifting rope, and installer D pulls the traction rope outwards to prevent the feeders from hitting the tower. Installers A and B hold the feeders, unfasten the ropes, and fasten the feeders onto the tower platform to prevent them from falling down to the ground. After six feeders are lifted onto the tower one by one, installer B removes the fixed pulley.
349
Huawei
NoteThe installation spacing of the clips for the feeder (7/8 inch) is 1.5 m to 2 m. The installation spacing of the clips for the feeder (larger than 7/8 inch) can be extended. If multiple rows of feeder fasteners need to be fixed, arrange the fasteners properly to keep a neat appearance. TAKE CARE OF sharp edes ! Clamps FIXED TOO TIGHT cause rising of the return loss Takecare of NOT TO DROP plastic cushions Cables shall be terminated by the resistive load (or source) impedance equal to the characteristic impedance, which generally is 50 .
350
Huawei
351
Huawei
RF 1 1/4-50
RF 1 5/8-50
200 mm
250 mm
350 mm
500 mm
352
Huawei
TAKE CARE OF: BENDING RADIUS MAXIMUM PULLING FORCE CORRECT DRUM HANDLING CORRECT TOOL/CABLE HANDLING ORDINARY CABLE FIXING COMPLETE WATER PROOFING TIGHTENING OF THE RF CONNECTORS.
Defective Picture
Correct Picture
354
Huawei
355
Huawei
356
Huawei
OK
NOT OK
OK
3 meter Jumper 3 meter Jumper
NOT OK
Jumper Cables have to be installed as straight as possible , Avoid additional bendings. Follow manufacturers bending instructions. Proper tools have to be used during jumper installation. All cables have to be fixed properly. Prefabricated jumpers have to be used always when possible. On existing sites most practical solution should be used.
357
Huawei
358
Huawei
Defective Picture
Correct Picture
359
Huawei
FEEDER
360
Huawei
361
Huawei
362
Huawei
NoteEnsure that the feeder cable is cut with reference to the guide in the package box of the connector. Ensure that the cross-section of the cut feeder cable is smooth ,intact & round. Ensure that the feeder cable is cut at the wave crest of the outer conductor.
363
Huawei
364
Huawei
365
Huawei
366
Huawei
2.
Confirm proper center conductor length by comparing it to the connector back nut barrel or the gauge located on the front of the coring tool. A properly cored cable end will have a chamfer on the end of the center conductor.
3.
Carefully remove the dielectric materials from the center conductor using a knife
Note-It is important to remove the dielectric Materials before installing the back nut. It Will be difficult to remove the materials after The back nut is installed. The dielectric materials must be removed 360 Deg. Around the center conductor.
367
Huawei
5.
To flare the outer conductor slide the B-body over the end of the center conductor & begin spinning the drill Use slight inward & even pressure to flare the outer conductor.
Important- Remove any residue or debris from the Flaring process before proceeding to the next step.
Caution-Do not use a steel bristle Brush ,it could potentially Harm the electrical performance.
Note-When flaring by hand , apply slight inward pressure until the flare begins. Then increase even inward pressure to complete the flare & cleaning process.
368 Huawei Telecom Implementation Process & Guidelines
7.
Continue to tighten the connector with the wrenches until metal to metal contact is reached.
Important- During the tightening process ,make sure the back nut doesnt turn. Tighten the connector until you achieve a positive stop & the O-ring completely disappears.
369
Huawei
FEEDERS GROUNDING
370
Huawei
Feeder Cable
Feeder Cable
Upside Down!
371
Huawei
372
Huawei
d
200mm < d < 1500mm
Grounding Bar
(behind cable ladder)
Note: Grounding bar should be fixed directly to the tow er w here the tow er is itself the main ground dow n-conductor!
373
Huawei
Note, The Stripped Part of the feeder should have The same length as the metal jacket of The grounding clip.
374
Huawei
375
Huawei
Feeder Groundings have been terminated On Cable tray which is rusted & not connected To main earth.
Feeder Groundings Cables have been terminated Upward direction on Cable tray .(Should be made straight as much as possible)
376
Huawei
FEEDERS GROUNDING IS VERY CLOSE TO ENTRY ,THIS CAUSES GROUNDING CABLE LOOP
377
Huawei
378
Huawei
The grounding kit must always be positioned on the straight part of feeder cable and never on a bend or curve on the feeders cable.
Grounding kit's earthing cable can be cut or extended to make grounding cable connection to busbar as straight as possible. Make sure that before terminations of feeders on tower portions ,the paints shall be removed from the terminations point for proper continuity & Ensure the grounding of Tower..
379
Huawei
380
Huawei
381
Huawei
382
Huawei
FEEDERS WATERPROOFING
383
Huawei
All ourdoor antenna line connections, grounding kits and wall entries have to be weather proofed. Connections where weather proofing is needed: Feeder to jumper at antenna end. Feeder to antenna Feeder to Jumper at BTS End (if located outdoor) Grounding kits have to be sealed according to manufacturer instructions. Wall feed through have to be properly sealed. Ensure that all connectors are on correct torque before sealing!
384 Huawei Telecom Implementation Process & Guidelines
Procedures of Weatherproofing
385
Huawei
Procedures of Weatherproofing
CONNECTION TO BE TAPED USING APPROVED TYPE OF INSULATION TAPE CONNECTION TO BE TAPED USING APPROVED TYPE OF WATER PROOF TAPE
CABLE TIE
50 20
1. 3 - WRAPS OF WATERPROOF TAPE (OVERLAPPING 50%) 2. 3-WRAPS OF PVC TAPE (OVERLAPPING 50%)
386
Huawei
Procedures of Weatherproofing
1.CONNECTION TO BE TAPED USING APPROVED TYPE OF WATER PROOF TAPE. 2.CONNECTION TO BE TAPED USING APPROVED TYPE OF PVC TAPE.
20
50
50
20
FEEDER
JUMPER
1. 3-WRAP OF WATERPROOF TAPE (OVERLAPPING 50%) 2. 3- WRAPS OF PVC TAPE (OVRLAPPING 50%)
CABLE TIE
387
Huawei
Procedures of Weatherproofing
388
Huawei
Examples of Weatherproofing
389
Huawei
Examples of Weatherproofing
390
Huawei
391
Huawei
Installation tools
392
Huawei
393
Huawei
394
Huawei
Antenna Support
Surge Protector
395
Huawei
Measure the routing distance between the GPS antenna and main equipment. Then, use a cable cutter to cut the feeder according to the length identifiers on the feeder.
396
Huawei
397
Huawei
398
Huawei
1. Every time you coil a layer of tape, ensure that the new layer covers the area of previous layer by 50% or more. 2. Before wrapping the waterproof tape, stretch the tape till the width of the tape becomes 1/2 of the original.
3. Wrap the metal connector using waterproof tape with extended lengths about 20 mm, and wrap the waterproof tape using insulation tape with extended lengths about 10 mm.
399
Huawei
Route the feeder along the cable rack that is mounted on the wall and use feeder fasteners to fix the feeder. The interval between feeder fasteners is 1 m.
400 Huawei Telecom Implementation Process & Guidelines
401
Huawei
Cut the redundant feeder to fit the surge protector. Make a N male connector for the feeder. 3. Connect the feeder to the surge protector
Route the feeder along the indoor cable rack and bind the feeder with cable ties.
402
Huawei
The positions of the labels are as follows: 200 mm away from the outdoor feeder connector 200 mm away from the surge protector
403 Huawei Telecom Implementation Process & Guidelines
404
Huawei
405
Huawei
406
Huawei
407
Huawei
408
Huawei
409
Huawei
INTRODUCTION TO RTN600
The OpitX RTN 620 is one of the series products of the OptiX RTN 600 radio transmission system.
The OptiX RTN 600 radio transmission system product series are classified into the OptiX RTN 620 and the OptiX RTN 605. The OptiX RTN 620 and the OptiX RTN 605 share one set of ODUs. The OptiX RTN 620 adopts 2U-high IDU (namely, IDU 620), supports one to four microwave directions, and provides the TDM microwave and Hybrid microwave integrated solution. The OptiX RTN 605 adopts 1U-high IDU (namely, IDU 605), supports one microwave direction, and provides the TDM microwave and Hybrid microwave terminal access solution.
AppicationThe OpitX RTN 620 is a split microwave transmission system developed by Huawei. The OpitX RTN 620 provides several types of service interfaces and features flexible configuration and easy installation . the OpitX RTN 620 can provide a TDM microwave and Hybrid microwave integrated solution according to the network requirements.
410
Huawei
IDU 605 1A
IDU 605 2B
IDU 605 1F
411
Huawei
RTN605,IDU Description
412
Huawei
RTN605,IDU Description
Physical & Electrical Specifications of IDU Size- 442mm (w) x 220mm(d) x 44 mm (h) Weight- 2.5 to 2.7 Kgs. Power Consumption 17 Watts to 31 Watts @ -48VDC.
413
Huawei
414
Huawei
415
Huawei
IF Processing
Service Processing
IDU 605 1A can access 5xE1 signals. IDU605 1B/2B can access 16xE1 signals. IDU 605 supports the setting of the impedance of E1 signals by using the software (75 / 120 Ohms)
The IDU 605 1A/1B/2B supports 1+1 protection for the input power supplies. The IDU 605 2B supports the 1+1 HSB/FD/SD protection & 1+1 FD/SD hitless switching.
Provides the system control & communication to manage the IDU & ODU. Provides the function of collecting performance events & alarm information. Provides the function of communicating with the NMS.
Processes the overhead of PDH microwave frame signals. Supports the setting & query of the link ID.
Function-RTN605,IDU 1F/2F
Multiplexes E1 Service signals into microwave frame signals. Supports AM technology. Codes & decodes microwave frame signals. Modulates & demodulates PDH microwave frame signals. Modulates & demodulates ODU control signals. Combine & splits service signals,ODU control signals & -48V power supply. ATPC function.
IF Processing
Supports the EPLAN service that are based on the IEEE802.1d bridge. Supports EVPLAN services.
E1 Service Processing
The IDU 605 1F/2F can access 16xE1 Signals. Supports the setting of the impedance of E1 signals by using the software (75/120 Ohms).
IDU 605 1F/2F provides one FE/GE electrical interface & three FE electrical interfaces. Supports the setting & query of the working modes of the ethernet ports- 1)The FE electrical interface supports 10M full & half duplex,100M full & half duplex, & auto negotiation.2)The FE/GE electrical interface supports 10M full & half duplex,100M full & half duplex & auto negotiation. Supports the setting & query of the TAG attributes of the ethernet ports (tag aware,access & hybrid). Support the link aggregation group (LAG).
417
Huawei
Function-RTN605,IDU 1F/2F
Protection Processing
IDU 605 1F/2F supports 1+1 protection for the input power. IDU605 2F supports the 1+1 HSB/FD/SD protection , 1+1 FD/SD hitless switching.
Provides the system control & communication function to manage the IDU & ODU. Provides the function of collecting performance events and alarm information. Provides the function of communicating with NMS.
Provides one NM ethernet interface & one NE cascading interface. Provides one management serial port. Provides one 3-Input & 1-output alarm interface. Provides one RS232 asynchronous data interface.
418
Huawei
419
Huawei
2.
The separate mounting method is adopted when a double-polarized antenna or big-diameter and singlepolarized antenna is used.
420
Huawei
421
Huawei
Antenna Interface- N type Female Connector IF interface connector- N type Female RSSI BNC Female
422
Huawei
MW Antenna Specification
423
Huawei
424
Huawei
The hybrid couplers are classified into the hybrid coupler with waveguide interfaces and the hybrid coupler with coaxial interfaces according to the type of the branch interfaces of the hybrid coupler. The ODUs with waveguide interfaces use the hybrid couplers with waveguide interfaces, and the ODUs with coaxial interfaces use the hybrid couplers with coaxial interfaces.
The hybrid couplers is available in two series: 3 dB balanced hybrid coupler and 6 dB unbalanced hybrid coupler. A 3 dB balanced hybrid coupler can split one RF signal into two RF signals that have almost the same power. In other words, each of the two RF signals is attenuated about 3 dB, compared with the original RF signal. A 6 dB unbalanced hybrid coupler can split one RF signal into two RF signals that have different power. The RF signal that has the smaller power is attenuated about 6 dB, compared with the original RF signal.
425
Huawei
426
Huawei
Note: - The Hybrid microwave and the PDH microwave do not support the N+1 protection configuration and the XPIC configuration
427
Huawei
The Board details are as below, IF Board : IF1A/IF1B,IFX,IF0A/IF0B,IFH2. SDH Board: SL4,SL1,SD1,SLE & SDE. PDH Board:PL3,PO1,PH1,PD1. Ethernet Board:EFT4,EMS6. Integrated power cross connect board:PXC. System Control and communication board: SCC. Fan Board :FAN
Dimension of one IDU 620 is 442 mm x 220 mm x 87 mm . I/P Power Supply & MCB Requirements are as below, I/P Voltage- ( - 40VDC to -60VDC) ,MCB required is 2 Nos of 10A.
428
Huawei
Function are as below, The IF1A/IF1B receives & transmits one IF signal & provides the management channel to the ODU and the 48VDC to ODU. IF Processing Maps PDH ,SDH & Ethernet Service signals to MW signal. Code & Decodes Microwave Signals. Modulate & demodulate MW signals. Overhead Processing Pointer Processing Process AU Pointer in SDH & TU Pointer in PDH MW signals. Protection Processing
429
Huawei
TNC
SMA Dimension & Weight of one IF Board is 203.6 mm x 201.3 mm x 19.6 mm . Weight 450 Gms. I/P Power Supply is as below, Power Consumption is 14.5 Watts.
Function are as below, The IFX receives & transmits one IF signal & provides the management channel to the ODU & the -48V power that the ODU requires. The IFX can cancel the cross polarization interference in the IF signal. IF Processing Maps VC-4 Service Signal to SDH MW frame signal . Code & Decodes SDH Microwave Signals. Modulate & demodulate SDH MW signals. Pointer Processing Process AU Pointer in SDH MW signals. Protection Processing
430
Huawei
TNC
Dimension & Weight of one IF Board is 203.6 mm x 201.3 mm x 19.6 mm . Weight 520 Gms. I/P Power Supply is as below, Power Consumption is 13.7 Watts.
Function are as below, IF Processing Multiplexes 2E1/5E1/10E1/16E1 service signal to PDH MW frame signal. Code & Decodes PDH Microwave Signals. Modulate & demodulate PDH MW signals. Modulate & demodulate ODU control signal.
431
Huawei
Dimension & Weight of one IF Board is 203.6 mm x 201.3 mm x 19.6 mm . Weight 580 Gms. I/P Power Supply is as below, Power Consumption is 16.4 Watts. Function are as below, IF Processing Support the Hybrid MW frame & supports the pure transmission of the E1 / Ethernet signals and the hybrid transmission of the E1 & Ethernet signals. Support adaptive modulation. Maps service signal to MW frame signals. Code & Decodes Microwave frame Signals. Modulate & demodulate MW frame signals. TNC Modulate & demodulate ODU control signal.
432
Huawei
RJ45
Dimension & Weight of one SL4 Board is 203.6 mm x 201.3 mm x 19.6 mm . Weight 290 Gms. I/P Power Supply is as below, Power Consumption is 7.2 Watts.
Function are as below, Process the regenerator section overhead of the STM-4 signals. Process the multiplex section overhead of the STM-4 signals. Process the higher order path overhead of the STM-4 signals. Process AU pointer.
433
Huawei
Dimension & Weight of one SL1 & SD1 Board is 203.6 mm x 201.3 mm x 19.6 mm . Weight 290 Gms. For SL1 & 300 Gms for SD1 I/P Power Supply is as below, Power Consumption is 3.9 Watts.
434 Huawei Telecom Implementation Process & Guidelines
Function are as below, Process the regenerator section overhead of the STM-1 signals. Process the multiplex section overhead of the STM-1 signals. Process the higher order path overhead of the STM-1 signals. Process AU pointer.
Function are as below, Process the regenerator section overhead of the STM-1 signals. Process the multiplex section overhead of the STM-1 signals. Process the higher order path overhead of the STM-1 signals. Process AU pointer. Supports the setting of the SNCP switching conditions. Supports the setting of the linear MSP switching conditions. Dimension & Weight of one SLE & SDE Board is 203.6 mm x 201.3 mm x 19.6 mm . Weight 300 Gms. For SLE & 330 Gms for SDE I/P Power Supply is as below, Power Consumption is 4.9 Watts.
SMB Connector
435
Huawei
SMB Connector
Function are as below, Supports the settings & querying of the type of the accessed service signal by the software (E3/T3). Supports the setting & querying of the Input/Output equalization of the T3 signal. Processes overhead & pointers at the VC-3 level. Supports the first & third E3/T3 signals to be extracted as the tributary clock source. Dimension & Weight of one PL3 Board is 203.6 mm x 201.3 mm x 19.6 mm . Weight 310 Gms. I/P Power Supply is as below, Power Consumption is 5.1 Watts.
436 Huawei Telecom Implementation Process & Guidelines
RJ45 Connector
DB44 Connector Function are as below, Supports the retiming function of E1 signals. Supports the 1st & 5th E1 signals to be extracted as the tributary clock source. Supports the in loop & out loop at the E1 tributary. Supports the querying of the manufacturing information of the board.
437 Huawei Telecom Implementation Process & Guidelines
MDR68 Connector
Dimension & Weight of Boards are, 203.6 mm x 201.3 mm x 19.6 mm . Weight PO1-280Gms ,PH1-310Gms,PD1-380Gms.
438
Huawei
Dimension & Weight of Boards is, ----203.6 mm x 201.3 mm x 19.6 mm . Weight 306Gms. I/P Power Supply is ---7.5 Watts
439
Huawei
LC SFP
RJ45 Connector
Dimension & Weight of Boards is, ----203.6 mm x 201.3 mm x 19.6 mm . Weight 400Gms. I/P Power Supply is ---12.3 Watts
440
Huawei
Dimension & Weight of Boards is, ----203.6 mm x 201.3 mm x 19.6 mm . Weight 540 Gms. I/P Power Supply is ---7.5 Watts
441
Huawei
442
Huawei
END
443
Huawei
444
Huawei
445
Huawei
Determine the installation location of the chassis in the cabinet. Fasten the captive nuts into the corresponding installation holes in the upright posts of the cabinet. Replace the rack-mounting ears for the 19-inch cabinet on both sides of the IDU with the rack-mounting ears for the ETSI cabinet packed with the IDU. Fasten two captive nuts on each side of the cabinet. All the captive nuts should be at the same level.
446
Huawei
447
Huawei
Procedure of IDU grounding; Fasten the protection grounding cable on the grounding point that is on the right on the front panel of the IDU 605. Cut the protection grounding cable to the correct length and connect the OT terminal, depending on the distance to the grounding point. Connect the protection grounding cable to the grounding point provided by the cabinet (for example, the grounding bar). Bind the cable. IDU cables should be routed along the left and the right to facilitate operations, and should not cover the board indicators. Cables that are routed along the wiring frame must be bundled. The specifications and cross-sectional area of the cable, and the route and position for the cabling should be designed beforehand. All the cables should be arranged neatly.
448
Huawei
449
Huawei
Determine the installation location of the E1 panel in the cabinet. Fit the captive nuts into the corresponding installation holes in the upright posts of the cabinet. Fit two captive nuts on each side. All the captive nuts should be level. Use the four M6 panel screws to fasten the E1 panel on the cabinet. Fix the OT terminal of the protection grounding cable onto the grounding stud of the E1 panel. Cut the protection grounding cable to the correct length and connect the OT terminal, depending on the distance to the grounding point. Connect the protection grounding cable to the grounding point provided by the equipment room (for example, the grounding bar). Bind the cable.
450 Huawei Telecom Implementation Process & Guidelines
Steps for installation of DDF frameTake out DDF Frame from Box. Remove the Cage nuts and panel screws. Install the cage nuts on vertical mounting bar on the rack ,according to approved location of DDF frame. Tighten the screws. Install grounding of DDF frame & connect at IGB/Bus bar of 19 Rack. Ensure that the bus bar at 19 rack is connected at IGB.
451
Huawei
Procedure of DC Power Cabling for IDU 605; Depending on the distance between the IDU 605 and the power supply equipment, cut the power cable at the end that is connected to the power supply equipment. Then, make terminals according to the regulations for preparing power cables. Connect the power cable to the output terminal of the power supply equipment and fasten the power cable. If the IDU 605 uses the 48 V /60 V power system, connect the black wire of the power cable to the power ground, and connect the blue wire of the power cable to the 48 V /60 V power.(6A MCBx2 Nos is required for 1 IDU). Route the power cable to the IDU 605. Connect the connector of the power cable to the power port of the IDU 605 and tighten the connector. Bind the power cables. Affix engineering labels to both ends of the power cables.
452
Huawei
Procedure of IF Jumper Cabling for IDU 605; Affix temporary labels to both ends of the IF jumper. Lead the IF jumper through the cable hole from outside the cabinet and route the jumper to the IDU. Connect the TNC connector of the IF jumper to the IF port on the front panel of the IDU 605 and leave enough slack. Bind the jumper. Use a multimeter to check whether there is a short circuit or an open circuit in the IF jumper. Tighten the connector of the jumper. If the IF cable is installed, connect the jumper to the IF cable on the wiring frame and tighten the connection. Remove the temporary labels and affix the engineering labels.
NOTE In the case of the IDU 605 1A/1B/1F, connect the TNC connector of the IF jumper to the ODU port on the front panel of the IDU. In the case of the IDU 605 2B/2F, connect the IF jumper that is connected to the IF cable of the main ODU to the ODU-M port on the front panel of the IDU, and connect the IF jumper that is connected to the IF cable of the standby ODU to the ODU-S port on the front panel of the IDU. In the case of earlier product deliveries, the silkscreen on the front panel of the IDU 605 2B may be slightly different from the silkscreen depicted in this document. On the silkscreen of earlier product deliveries, ODU1 refers to the ODU-S, and ODU2 refers to the ODU-M.
453 Huawei Telecom Implementation Process & Guidelines
Procedure of E1 Cabling for IDU 605; Affix temporary labels to both ends of the E1 Cable. Route the cables from the DDF to the cabinet, lead them through the cable hole, and finally route them to the IDU 605 1A/1B/2B. Connect the DB44 connectors of the cables to the E1 ports of the IDU 605 1A/1B/2B. Bind the Cable. Disconnect the cables from the IDU 605 1A/1B/2B. On the DDF side, cut off the cable slack and make cable connectors. Use a multimeter to check if there is a short circuit or an open circuit in the cables. Connect the connectors on both sides of cables and fasten them. Remove the temporary labels and affix the engineering labels.
454
Huawei
Steps for installation of E1 CablesConnect the E1 cable to the E1 interface on tributary board & tighten the screws to fix the cables. Route the E1 cables from the equipment side to the DDF. Cut the E1 cables top a proper length & mark the cables for the transmit and receive direction.
455 Huawei Telecom Implementation Process & Guidelines
Procedure of E1 Cabling for IDU 605; Affix temporary labels to both ends of the E1 Cable. Route the cables from the DDF to the cabinet, lead them through the cable hole, and finally route them to the IDU 605 1F/2F. Insert the MDR68 connector of the E1 transit cable into the E1 interface on the IDU 605 1F/2F, and connect the DB44 connector to the E1 cable that connects to the external equipment. Bind the Cable. Disconnect the E1 transit cable from the E1 interface on the IDU 605 1F/2F. On the DDF side, cut off the cable slack and prepare cable connectors. Use a multimeter to check if there is a short circuit or an open circuit in the cables. Connect the connectors on both sides of cables and fasten them. Remove the temporary labels and affix the engineering labels.
456
Huawei
Procedure of Ethernet Cabling for IDU 605; Depending on the distance between the Ethernet Equipment and the IDU, cut off a length of Ethernet cable. Make connectors for both ends of the Ethernet cable. Affix temporary labels to both ends of the Ethernet cable. Route the Ethernet cable from the Ethernet Equipment to the cabinet, lead it through the cable hole, and finally route it to the IDU. Connect the RJ-45 connector at one end of the Ethernet cable to the Ethernet electrical interface EF1 of the IDU 605 1F/2F,and connect the connector at the other end to the electrical interface on the Ethernet Equipment. Bind the cable. Remove the temporary labels and affix the engineering labels.
457
Huawei
458
Huawei
1. 2. 3. 4. 5. 6. 7. 8.
IF Interface ODU Power Switch STM-1 Optical Interface. STM-1 electrical interface. Input Power Input Power Switch External clock/WS service interface. E1 interface.
Management serial port. NM Ethernet interface. NE cascading interface. Order wire phone interface External alarm
NoteAccording to different board configurations , the position of the IDU interfaces in the actual Application may be different from the positions shown in above figure.
459 Huawei Telecom Implementation Process & Guidelines
460
Huawei
Installation holes for the T63/T66/ N66T cabinet of Huawei Rack Mounting Ears for 19 Rack Rack Mounting Ears for ETSI Rack-IDU620 Rack Mounting Ears for ETSI Rack-IDU610
461
Huawei
Procedure of installing IDU 620; Determine the place where the chassis is to be installed in the cabinet. Fit the cage nuts into the corresponding installation holes in the upright columns of the cabinet. As the IDU620 applies air cooling, there must be enough space around the air intake vent on the left side panel of the chassis & around the air exhaust vent on the right side panel to ensure no blocking. Replacing the rack mounting ears for the 19 inch cabinet with the rack mounting ears for the ETSI cabinet .
462
Huawei
463
Huawei
While IDU is installed in closed rack ,connect the PGND cable at front. Procedure of PGND Cable Installation; PGND Cable should be of 6Sq.mm Copper Cable. Correct nuts & bolts with washers shall be used. Tighten properly at both equipment & IGB end. Use labels at both ends. Route the cable properly.
464
Huawei
Boards Installation-IDU-620
Pre-requisite of Board Installation; Insert one end of the ESD wrist strap into the ESD connector on the cabinet. Wear the ESD wrist strap. Hold the ejector levers with hands on the panel. Push them outwards so that the angle between the ejector lever and the panel is 45 degrees or so. Push the board gently along the slot guide rail until the board cannot slide further.
465
Huawei
Procedure of Power cabling; Route the ends of the cables that have cord end terminals, to the output terminals of the power box and fasten them. Ground the black cable and connect the blue cable to the -48 V power. Route the power cables to the IDU. Connect the type-D connectors of the cables to the sockets on the PXC board and fasten them. Bind the power cables. Affix the engineering labels to both ends of the power cables. 2 Nos of 10A MCB required for IDU610/620.
466
Huawei
Procedure of IF Jumper installation; Affix temporary labels to both ends of the IF jumper. Lead the IF jumper through the cable hole from outside the cabinet and route the jumper to the IDU. Connect the TNC connector of the jumper to the IF port of the IF board and leave enough slack. Bind the Jumpers. Use a multimeter to check if there is a short circuit or an open circuit in the IF jumper. Tighten the connector of the jumper. If the IF cable is installed, connect the jumper to the IF cable on the wiring frame and tighten the connection. Remove the temporary labels and affix the engineering labels.
467
Huawei
NoteDont insert or Remove IF cable from/to IDU while the toggle switch is in ON position. Also dont insert or remove IF cable from/to ODU while the toggle Switch is in ON position.
468
Huawei
Procedure of Installing XPIC Cable; Select proper XPIC cables. One pair of IFX boards is configured with four XPIC cables. If the IFX boards are installed in slot 5 and slot 7, or in slot 6 and slot 8 of an NE, use the pair of XPIC cables that is shorter in length. Otherwise, use the pair of XPIC cables that is longer in length. Connect the XPIC cables to the IN/OUT ports of the pair of IFX boards. The IN port of one IFX board must be connected to the OUT port of the other IFX board. Bind the cables. If the XPIC function of an IFX board is disabled, use a shorter XPIC cable to connect the IN port of the IFX board to the OUT port of the same IFX board. Otherwise, the signals in the IFX board are deteriorated.
469 Huawei Telecom Implementation Process & Guidelines
470
Huawei
471
Huawei
472
Huawei
473
Huawei
475
Huawei
Remove the antenna & accessories From the boxes. Use proper tools to unpack the boxes.
476
Huawei
By default, the antenna applies vertical polarization. If horizontal polarization is required, rotate the feed boom at the back of the antenna to change the polarization direction of the antenna. If the waveguide on the feed boom is a round waveguide, the polarization direction of the antenna need not be changed. Check if the antenna is vertically polarized. Loosen the fixing screws to allow the feed boom to rotate freely. Rotate the feed boom 90 degrees to the right or left until its positioning pin is plugged into the positioning slot in the base. Tighten the fixing screws. Apply glue around the screws.
477
Huawei
Procedure of installing ODU on Antenna Remove the protective caps from the feed boom of the antenna and from the ODU antenna port. Apply the appropriate quantity of lubricant on the gasket of the feed boom and the surface of the waveguide near the gasket Do not apply the lubricant on the surface of the feed boom. Otherwise, the transmission of signals is affected. Do not apply the lubricant on the internal surface of the antenna port on the ODU. Otherwise,the transmission of signals is affected. Ensure that the polarization indicator on the ODU points to the required polarization direction of the antenna. If the antenna is vertically polarized, ensure that the polarization indicator points upwards. If the antenna is horizontally polarized, ensure that the polarization indicator points right. Place the ODU antenna port against the feed boom. Slowly fit the feed boom in such that the four ODU latches engage with the four antenna hooks. Close the four latches cornerwise.
478 Huawei Telecom Implementation Process & Guidelines
By default, the antenna applies vertical polarization. If horizontal polarization is required, rotate the feed boom at the back of the antenna to change the polarization direction of the antenna. If the waveguide on the feed boom is a round waveguide, the polarization direction of the antenna need not be changed. Check if the antenna is vertically polarized. Loosen the fixing screws to allow the feed boom to rotate freely. Rotate the feed boom 90 degrees to the right or left until its positioning pin is plugged into the positioning slot in the base. Tighten the fixing screws. Apply glue around the screws.
479
Huawei
Check the polarization direction of the antenna. Install a horizontal polarizer. 1. Remove the protective cap from the antenna port on the coupler. 2. Remove the polarization component on the antenna port of the coupler. 3. Replace the polarization converter on the polarization component by using a horizontal polarizer. 4. Install the polarization component back onto the antenna port on the coupler. Remove the protective cap from the feed boom. Apply the appropriate quantity of lubricant on the gasket and the surface of the waveguide near the gasket. Apply appropriate anti-seize grease to the four captive screws of the coupler. Align the antenna port of the coupler over the feed boom. Slowly let the feed boom fit in such that the four latches engage with the antenna hooks. When installing the hybrid coupler on the antenna, the ODU port identifiers marked on the hybrid coupler such as "MAIN" and "STD BY" should face upwards. Close the four latches cornerwise.
480 Huawei Telecom Implementation Process & Guidelines
Remove the protective caps from the feed boom of the hybrid coupler and from the ODU antenna port. Apply the appropriate quantity of lubricant on the gasket of the feed boom and the surface of the waveguide near the gasket. Ensure that the polarization indicator on the ODU points right and the IF port faces downwards. Place the ODU antenna port against the feed boom of the coupler. Slowly fit the feed boom in such that the four ODU latches engage with the four coupler hooks. Close the four latches cornerwise. The main ODU must be installed on the MAIN port of the coupler and the standby ODU must be installed on the STD BY port of the coupler. When you install the ODU, the IF port of the ODU should face downwards.
481
Huawei
Check if the antenna is vertically polarized. Loosen the fixing screws to allow the feed boom to rotate freely. Rotate the feed boom 90 degrees to the right or left until its positioning pin is plugged into the positioning slot in the base. Tighten the fixing screws. Apply glue around the screws.
482
Huawei
Install the ODU adapter onto a proper position on the antenna pole. Keep the direction of the waveguide cavity of the flexible waveguide consistent with that of the adapter or the antenna. Then, install the flexible waveguide onto the flange interfaces of the ODU adapter and of the antenna using screws, Use the corresponding cramping kit to fix the flexible waveguide. waterproof the interface of the flexible waveguide.
483
Huawei
Procedure of Installing ODUs with dual polarized antenna; Install the antenna by following the instructions provided in the packing box. Adjust the polarization directions of the dual-polarized antenna by following the instructions for installing the antenna. The feed booms of the adjusted dual-polarized antenna are arranged in two ways. Install the ODU adapter onto a proper position on the antenna pole. Keep the direction of the waveguide cavity of the flexible waveguide consistent with that of the adapter or the antenna. Then, install the flexible waveguide onto the flange interfaces of the ODU adapter and of the antenna using screws, Use the corresponding cramping kit to fix the flexible waveguide. Install the vertically polarized ODU on the vertically polarized feed boom of the dual-polarized antenna according to the installation type.
484 Huawei Telecom Implementation Process & Guidelines
485
Huawei
486
Huawei
Check if the antenna is vertically polarized. Loosen the fixing screws to allow the feed boom to rotate freely. Rotate the feed boom 90 degrees to the right or left until its positioning pin is plugged into the positioning slot in the base. Tighten the fixing screws. Apply glue around the screws.
487
Huawei
Use the four M5 screws to install the ODU onto the ODU bracket. Use the fastening supports and bolts to install the ODU on the pole. The installation location must be proper. The IF port and RF port of the ODU must face downwards. Use the matching bolts to install the waveguide-to-coaxial converter onto the feed boom of the antenna. Connect one type-N connector of the RF cable to the coaxial port of the waveguide-to-coaxial converter. Connect the other type-N connector of the RF cable to the ANT port of the ODU. waterproof the connection between the RF cable and the waveguide-to-coaxial converter and the connection between the RF cable and the ODU.
488 Huawei Telecom Implementation Process & Guidelines
Check if the antenna is vertically polarized. Loosen the fixing screws to allow the feed boom to rotate freely. Rotate the feed boom 90 degrees to the right or left until its positioning pin is plugged into the positioning slot in the base. Tighten the fixing screws. Apply glue around the screws.
489
Huawei
Use the matching bolts to install the hybrid coupler onto the feed boom of the antenna. If the feed boom of the antenna is vertically polarized, the coaxial port of the hybrid coupler should face downwards. Connect one type-N connector of the RF cable to the coaxial port of the hybrid coupler. Connect the other type-N connector of the RF cable to the ANT port of the ODU. When you connect the RF cables, the main ODU must be connected to the MAIN port of the hybrid coupler and the standby ODU must be connected to the STD BY port of the hybrid coupler. Otherwise, transmission of signals will be affected. waterproof the connection between the RF cable and the waveguide-to-coaxial converter and the connection between the RF cable and the ODU.
490 Huawei Telecom Implementation Process & Guidelines
Procedure of Installing ODUs with dual polarized antenna; Install the antenna by following the instructions provided in the packing box. Adjust the polarization directions of the dual-polarized antenna by following the instructions for installing the antenna. The feed booms of the adjusted dual-polarized antenna are arranged in two ways. Install the ODU adapter onto a proper position on the antenna pole. Keep the direction of the waveguide cavity of the flexible waveguide consistent with that of the adapter or the antenna. Then, install the flexible waveguide onto the flange interfaces of the ODU adapter and of the antenna using screws, Use the corresponding cramping kit to fix the flexible waveguide. Install the vertically polarized ODU on the vertically polarized feed boom of the dual-polarized antenna according to the installation type.
491 Huawei Telecom Implementation Process & Guidelines
Grounding of ODU
One end of the protection grounding cable of the ODU is connected to the grounding stud of the ODU, and the other end is connected to a grounding point.
Fasten the OT terminal of the protection grounding cable to the grounding stud of the ODU. Fix the grounding clip base at the other end of the protection grounding cable on the tower. Pay attention to the following points: Before the connection, first remove the anticorrosion paint and the oxidizing layer on the grounding points. The grounding cable should not be spiral. After the connection, rustproof and waterproof the grounding points.
492
Huawei
Change the antenna polarization. Refer to the manufacturers instruction on installing the antenna to the pole. Put two M8 Allen Screws into the holes on the antenna flange. (Put two M8 Allen screws out of total four into the holes on the Antenna flange ,upper left and lower right holes and turn only a few turns.). Fix the snap-on mounting to the antenna. (put the snap-on mounting into place, with the screws through the widened holes in the mounting. Turn the mounting clockwise.) Add the two remaining M8 screws and tighten all four screws with a 6mm Allen key. The torque is 8 N-M. If the antenna feeder is protected with a cover or tape then, Remove the cover or tape.
493
Huawei
IF Connectorization-TNC Connector
One end of the IF cable needs to be terminated with a type-N connector and is connected to the ODU or lightning arrester. The other end of the IF cable needs to be terminated with a TNC connector and is connected directly to the IF cable or IDU.
Use an electric knife to strip back the 16 mm cable sheath. Fit the lock nut and clamp 1 on the cable. Fit clamp 2. Fold back the braided shield to cover clamp 1. Tidy the braided shield and use clamp 2 to bind the braided shield. Cut the redundant part of the shielding layer. Use the electric knife to strip back the dielectric insulating layer in front of clamp 2. During the operation, the exposed cable wire should be 6 mm long. Use a file to taper the edge of the core wire about 0.5 mm to make the top in an arc shape, and clean out the metal filings. Fit the connector. Connect the connector and the lock nut. Use a wrench to tighten the connection. Use a wrench to rotate the lock nut and another wrench to position the body of the connector. The recommended torque is 152 Nm.
494 Huawei Telecom Implementation Process & Guidelines
IF Connectorization-N Connector
Both ends of the RG-8U or 1/2inch IF cable need to be terminated with type-N connectors. An IF jumper is required to connect the RG-8U or 1/2inch IF cable to the IF board or IDU.
Use an electric knife to strip back the 16 mm cable sheath. Fit the lock nut and clamp 1 on the cable. Fit clamp 2. Fold back the braided shield to cover clamp 1. Tidy the braided shield and use clamp 2 to bind the braided shield. Cut the redundant part of the shielding layer. Use the electric knife to strip back the dielectric insulating layer in front of clamp 2. During the operation, the exposed cable wire should be 6 mm long. Use a file to taper the edge of the core wire about 0.5 mm to make the top in an arc shape, and clean out the metal filings. Fit the connector. Connect the connector and the lock nut. Use a wrench to tighten the connection. Use a wrench to rotate the lock nut and another wrench to position the body of the connector. The recommended torque is 152 Nm.
495 Huawei Telecom Implementation Process & Guidelines
IF Connector-Continuity Check
During the procedures of routing or bundling cables, and installing connectors, the circuit in a cable may become open or broken. Hence, you need to test the connectivity of the cables after the preceding procedures are completed. Procedure; At one end of the IF cable, use a short-circuiting line to shortcircuit the internal and external conductors, and then use a multimeter to test the resistance. The resistance should be 0 ohms. Remove the short-circuiting line, and use a multimeter to test the resistance between the internal conductor and the external conductor. The resistance should be infinite. Connect one end of the IF cable to the ODU, and connect the other end to the IDU.
496
Huawei
IF Cable Installation
Depending on the distance between the IDU and the ODU, cut off the extra length of IF cable after retaining a slack of 3 m to 5 m. Take protective measures to avoid damage to the connectors during hoisting and routing of the IF cables. Affix temporary labels to both ends of the IF cable. Leave enough slack on the IF cable. Then, route it and bind it along the pole, the wiring ladder, and the wiring frame. Connect the IF cable to the IF port of the ODU. If the RG-8U or 1/2inch IF cable is used, make the type-N connectors and connect the type-N connectors to the RG-8U or 1/2 inch IF cable. Connect the IF jumper to the IF cable. In the case of the IDU 605 2B/2F, the IF cable of the main ODU is connected to the IF jumper connecting to the ODU-M port and the IF cable of the standby ODU is connected to the IF jumper connecting the ODU-S port. In the case of the IDU 620, if IF 1+1 protection is configured, the IF cable of the main ODU is connected to the IF jumper of the main IF board and the IF cable of the standby ODU is connected to the IF jumper of the standby IF board. If the IFX board is used and supports the XPIC function, the IF cable of the vertically polarized ODU is connected to the IF jumper of the IFX board that processes the vertically polarized waves; the IF cable of the horizontally polarized ODU is connected to the IF jumper of the IFX board that processes horizontally polarized waves.
497 Huawei Telecom Implementation Process & Guidelines
IF Cable Installation
If the 5D IF cable is used, make the TNC connector and connect the TNC connector to one end of the 5D IF cable. Connect the 5D IF cable to the IF interface of the IF board or IDU. In the case of the IDU 605 2B/2F, the IF cable of the main ODU is connected to the ODU-M port and the IF cable of the standby ODU is connected to the ODU-S port. In the case of the IDU 620, if IF 1+1 protection is configured, the IF cable of the main ODU is connected to the IF jumper of the main IF board and the IF cable of the standby ODU is connected to the IF jumper of the standby IF board. If the IFX board is used and supports the XPIC function, the IF cable of the vertically polarized ODU is connected to the IF jumper of the IFX board that processes the vertically polarized waves; the IF cable of the horizontally polarized ODU is connected to the IF jumper of the IFX board that processes horizontally polarized waves.
498
Huawei
IF Cable Grounding
To ground the IF cable, first determine the grounding point depending on the installation mode and the length of the IF cable, and then ground the cable by using the grounding clip. The grounding point depends on the installation mode and the length of the IF cable. Generally, the IF cable should be grounded to a minimum of three points. When the IF cable is longer than 60 meters, add a grounding point for every extra 30 meters. If the distance between the grounding point 2 and the grounding point 3 (or the grounding point 5) is smaller than 20 m, cancel the grounding point 3 (or the grounding point 5). Depending on the installation mode and the length of the IF cable, determine the installation location of the grounding clips. Connect the grounding cable to the grounding points.
499
Huawei
IF Cable Grounding
Pay attention to the following points: Before the connection, first remove the anticorrosion paint and the oxidizing layer on the grounding points. The angle between the grounding wire of the clip and the IF cable should not be larger than 15 degrees. When the IF cable is vertically routed, the grounding wire of the clip should be led downwards. The grounding cable should not be spiral. After the connection, rustproof the grounding points. Use an electric knife to strip the cable sheath with the openness being the clip size at the installation location of the grounding clip and expose the external conductor. Clip the cable by using the grounding clip and press the clip tightly. The angle between the grounding wire of the clip and the IF cable should not be larger than 15 degrees. When the IF cable is vertically routed, the grounding wire of the clip should be led downwards.
500
Huawei
501
Huawei
POWERING ON OF IDU
Procedure of Power ON of IDU; Before powering ON of IDU, Check the voltage at MCB/Fuse where IDU is connected & record the voltage. If the voltage is OK ,within operating range ,then switch ON the MCB. Turn ON the system power switch of the PXC board on the IDU ,and then the ODU power switch on the IF board. The startup time of the equipment is about 3 to 5 minutes. If the Standard I/P voltage is -48VDC ,then the range should be 38.4VDC to -57.6VDC. If the Standard I/P voltage is -60VDC ,then the range should be -48 VDC to -72VDC.
502 Huawei Telecom Implementation Process & Guidelines
NOTEPull out the toggle switch.(ODU & IDU) Move the toggle switch to the left (I) or to the right (o). Release the toggle switch.
Alignment of MW Antenna
HORIZONTAL ALIGNMENT
503
Huawei
Alignment of MW Antenna
Procedure of alignment; 1. Determine the azimuth of an antenna according to the installation position and height of the antenna. Then, adjust the elevation of the antenna to the horizontal position. 2. Connect a multimeter to the received signal strength indicator (RSSI) port on the ODU at the local end and test the voltage value VBNC. 3. Adjust the azimuth and elevation of an antenna . 4. Retain the position of the antenna at the remote end. 5. Use the multimeter to measure VBNC. At the local end, rotate the antenna widely in the horizontal direction. 6. Adjust the antenna until VBNC reaches the peak value. Then, fix the antenna at the local end. 7. Repeat the steps 1 & 2 at remote end to adjust the antenna at the remote end. When VBNC reaches the peak value, tighten the antenna at the remote end.. 8. Repeat Step 2 to 4 for two to four times. When VBNC at the local end and VBNC at the remote end reach the peak value, tighten the antennas at both ends.
VERTICAL ALIGNMENT
504 Huawei Telecom Implementation Process & Guidelines
505
Huawei
IDU-RTN910-Components
Chasis height is 1HU =44.45mm No of MW directions is 1 or 2 RF configuration mode are 1+0 non protection, 2+0 non-protection,1+1 protection ,N+1 protection & XPIC configuration.
The OptiX RTN 910 forms different configuration modes by flexibly configuring different control, switching, and timing boards, IF boards, and ODUs to meet the requirements of different microwave application scenarios.
506
Huawei
IDU-RTN910-Boards(CSTA)
Cross-connect capacity System control and communication. Port for monitoring an outdoor cabinet Asynchronous data port Clock synchronization at the physical layer
Supports full time division cross-connections (equivalent to 8x8 VC-4s) at the VC-12, VC-3, or VC-4 level. Manages, monitors, and controls the running status of the IDU, and works as a communication service unit between the NMS and boards to help the NMS to control and manage the NE. 1 The port shares the same port with the external time port and its specifications comply with RS-485. 1 The transmission rate of the port is equal to or less than 19.2 kbit/s and the interfacing level complies with RS-232. Provides the system clock and frame headers for service signals and overhead signals for the other boards when tracing an appropriate clock source. The traced clock source can be any of the following: 1) External clock 2) SDH line clock,3) PDH tributary clock,4) Clock at the air interface. Warm reset and cold reset. In-service FPGA loading. Board manufacturing information query. Board temperature detection. Board voltage detection.
OM
507
Huawei
IDU-RTN910-Boards(CSTA) Function
SDH Service Function
Protection. Outband DCN.
Receives and transmits 2xSTM-1 optical signals.
Linear MSP & SNCP. Each SDH line port can provide one DCC that is composed of three DCC bytes, nine DCC bytes, or twelve DCC bytes. Supports the following loopback types:1) Outloops at optical ports,2) Inloops at optical ports,3) Outloops on VC-4 paths,4) Inloops on VC-4 paths Automatic laser shutdown (ALS) function. Detection and query of SFP optical module information.
OM
PDH Function. Port specifications Clock
16x 75-ohm/120-ohm E1 port. Supports a tributary clock source extracted from the first or fifth E1 signal. Supports clock protection based on clock source priorities. E1 retiming function.
508
Huawei
IDU-RTN910-Boards(CSHA/CSHB/CSHC)
The CSHA/CSHB/CSHC is the integrated Hybrid system control, switching, and timing board. The CSHA, CSHB, and CSHC differ from each other with regard to the types and number of service ports. The CSHA/CSHB/CSHC provides 4.2 Gbit/s packet switching, full time division crossconnection, system control and communication, and clock processing functions. The CSHA/ CSHB/CSHC provides FE/GE service ports, PDH/SDH service ports, auxiliary ports, and management ports.
CSHA
Power consumption of the CSHA: < 18.0 W Power consumption of the CSHB: < 22.7 W Power consumption of the CSHC: < 19.6 W
509
Huawei
IDU-RTN910-Boards(CSHA/CSHB/CSHC)
CSHB
CSHC
510
Huawei
IDU-RTN910-Boards(CSHA/CSHB/CSHC) Function
Basic Functions as follows;
Clock
Supports 4.2 Gbit/s packet switching function. Supports full time division cross-connections (equivalent to 8x8 VC-4s) at the VC-12, VC-3, or VC-4 level. Provides the system clock and frame headers for service signals and overhead signals for the other boards when tracing an appropriate clock source. The traced clock source can be any of the following:1) External clock,2) SDH line clock,3) PDH tributary clock,4) Clock at the air interface,5) Synchronous Ethernet clock.
DCN
Outband DCN-CSHA & CSHB Supports a maximum of five DCCs , CSHC Supports a maximum of Seven DCCs. Inband DCN-Supports the inband DCN function. The DCN bandwidth is configurable.
Supports
Only CSHC supports & Receives and transmits 2xSTM-1 optical signals. Each SDH line port can provide one DCC that is composed of three DCC bytes, nine DCC bytes, or twelve DCC bytes. Supports the following loopback types:1) Outloops at optical ports,2)Inloops at optical ports,3) Outloops on VC-4 paths,4)Inloops on VC-4 paths. Receives and transmits E1 signals. 75-ohm/120-ohm E1 port (16 for CSHA,32 for CSHB & 16 for CSHC). Supports a tributary clock source extracted from the first or fifth E1 signal. Supports clock protection based on clock source priorities.
PDH Functions.
511 Huawei
IDU-RTN910-Boards(CSHD)
The CSHD provides 4.4 Gbit/s packet switching, full time division cross-connection, system control and communication, and clock processing functions. The CSHD provides FE/GE service ports, E1 service ports, auxiliary ports, and management ports.
CSHD
512
Huawei
IDU-RTN910-Boards(CSHD) Function
Basic Functions as follows;
Supports 4.4 Gbit/s packet switching function. Supports full time division cross-connections (equivalent to 8x8 VC-4s) at the VC-12, VC-3, or VC-4 level.
Clock
Provides the system clock and frame headers for service signals and overhead signals for the other boards when tracing an appropriate clock source. The traced clock source can be any of the following:1) External clock,2) SDH line clock,3) PDH tributary clock,4) Clock at the air interface,5) Synchronous Ethernet clock.
DCN
Outband DCN-Supports a maximum of five DCCs . Inband DCN-Supports the inband DCN function. The DCN bandwidth is configurable.
MPLS/PWE3 functions
Static LSPs 1:1 MPLS tunnel APS Supports the following OAM functions:l MPLS OAM that complies with ITU-T Y.1711,1) LSP ping and LSP trace route functions. Supports the following service categories:1)CES services,2) ATM PWE3 services,3) ETH PWE3 services. Static PWs. 1:1 PW APS
513
Huawei
IDU-RTN910-Boards(CSHD) Function
QoS functions
Supports traffic classification based on C-VLAN IDs, S-VLAN IDs, C-VLAN priorities, S-VLAN priorities, C-VLAN IDs + C-VLAN priorities, S-VLAN IDs + SVLAN priorities, or DSCP values carried by packets. Provides the CAR function for traffic flows at ports. Supports the following queue scheduling policies:1) SP ,2)WRR,3) SP+WRR.
Receives/Transmits FE/GE service signals and works with the packet switching unit to process the received FE/GE service signals. Four FE electrical port: 10/100BASE-T (X) Two GE port: SFP module (1000BASESX, 1000BASE-LX, and GE electrical module). The FE port supports 10M full-duplex, 100M fullduplex, and auto-negotiation. The GE electrical port supports 10M full-duplex, 100M full-duplex, 1000M fullduplex, and autonegotiation. The GE optical port supports 1000M full-duplex and auto-negotiation. Supports jumbo frames with a maximum frame length of 9600 bytes.
E1 service functions
Receives and transmits E1 signals, and supports flexible configuration of E1 service categories. Supports the following E1 service categories:1) Native E1,2) CES E1,3) ATM/IMA E1. 16 - 75-ohm/120-ohm E1 port. Supports transparent service transmission at the 64kbit/s level. Maximum 64 number of ATM services. Maximum 256 number of ATM connections. Supports the following ATM encapsulation modes:1) N-to-one VPC,2) N-to-one VCC,3) One-to-one VPC,4) One-to-one VCC.
514
Huawei
IDU-RTN910-Boards(IF1)
The IF1 receives and transmits one IF signal, provides management channels to the ODU, and supplies the required -48 V power to the ODU.
IF1
Dimensions- 19.82mm(H)x 193.80mm(W)x225.80mm(D). Weight-IF1-0.72Kg.
Function of IF1 are as follows; Receives and transmits one IF signal. Provides management channels to the ODU. Supplies the required -48 V power to the ODU. 1+1 HSB/FD/ SD protection N+1 protection. Protection based on clock source priorities Protection by running the SSM protocol (supported only in SDH radio mode) Protection by running the extended SSM protocol (supported only in SDH radio mode) Inband DCN is not supported. Outband DCN is supported & The PDH radio mode supports one DCC that is composed of one DCC byte if the capacity is less than 16xE1. The PDH radio mode supports one DCC that is composed of three DCC bytes if the capacity is equal to or more than 16xE1. The SDH radio mode supports one DCC that is composed of three DCC bytes, nine DCC bytes, or twelve DCC bytes. Supports the following loopback types: Inloops at IF ports,Outloops at IF ports,Inloops at composite ports,Outloops at composite ports
515
Huawei
IDU-RTN910-Boards(IF2)
The IFU2 receives and transmits one IF signal, provides management channels to the ODU, and supplies the required -48 V power to the ODU.
IF2
Dimensions- 19.82mm(H)x 193.80mm(W)x225.80mm(D). Weight-IF2-0.79Kg. Power consumption of the Function of IF2 are as follows IF2:23Watts Receives and transmits one IF signal. Provides management channels to the ODU. Supplies the required -48 V power to the ODU. 1+1 HSB/FD/ SD protection N+1 protection. MPLS & PWE3 functions Protection based on clock source priorities Protection by running the SSM protocol Protection by running the extended SSM protocol Inband DCN -The DCN bandwidth is configurable. Outband DCN Supports one DCC that is composed of three DCC bytes. E-Line services based on ports- E-Line services based on port+VLAN , E-Line services carried by QinQ links, ELine services carried by PWs.
516
Huawei
IDU-RTN910-Boards(IFX2)
The IFX2 receives and transmits one IF signal, provides management channels to the ODU, and supplies the required -48 V power to the ODU. The IFX2 supports cross-polarization interference cancellation (XPIC) processing for IF signals.
IFX2
Dimensions- 19.82mm(H)x 193.80mm(W)x225.80mm(D). Weight-IFX2-0.80Kg.
Function of IFX2 are as follows Power consumption of the Receives and transmits one IF signal. IFX2:33Watts Provides management channels to the ODU. Supplies the required -48 V power to the ODU. Supported only in Integrated IP radio mode, in which native TDM services are E1 services. XPIC Function. 1+1 HSB/FD/ SD protection N+1 protection. MPLS & PWE3 functions Protection based on clock source priorities Protection by running the SSM protocol Protection by running the extended SSM protocol. In-service FPGA loading. PRBS BER test at IF ports. Board temperature & Voltage detection Inband DCN -The DCN bandwidth is configurable. Outband DCN Supports one DCC that is composed of three DCC bytes. E-Line services based on ports- E-Line services based on port+VLAN , E-Line services carried by QinQ links, E-Line services carried by PWs.
517 Huawei Telecom Implementation Process & Guidelines
IDU-RTN910-Boards(ISU2)
The ISU2 receives and transmits one IF signal, provides management channels to the ODU, and supplies the required -48 V power to the ODU.
ISU2
Dimensions- 19.82mm(H)x 193.80mm(W)x225.80mm(D). Weight-ISU2-0.60Kg.
Function of ISU2 are as follows Power consumption of the Receives and transmits one IF signal. Provides management channels to the ODU. ISU2:22Watts Supplies the required -48 V power to the ODU. Radio Type -Integrated IP radio & SDH radio. Native E1 + Ethernet & Native STM-1 + Ethernet. Service Category-STM-1 & 2xSTM-1 1+1 HSB/FD/ SD protection N+1 protection. MPLS & PWE3 functions Protection based on clock source priorities Protection by running the SSM protocol Protection by running the extended SSM protocol. PRBS BER test at IF ports. Board temperature & Voltage detection Inband DCN -The DCN bandwidth is configurable. Outband DCN Supports one DCC that is composed of three DCC bytes for each channel in Integrated IP radio mode.Supports one DCC that is composed of D1D3 bytes, D4-D12 bytes, or D1-D12 bytes, for each channel in SDH radio mode. E-Line services based on ports- E-Line services based on port+VLAN , E-Line services carried by QinQ links, E-Line services carried by PWs.
518 Huawei Telecom Implementation Process & Guidelines
IDU-RTN910-Boards(ISX2)
The ISX2 receives and transmits one IF signal, provides management channels to the ODU, and supplies the required -48 V power to the ODU. In addition, the ISX2 provides the crosspolarization interference cancellation (XPIC) function for IF signals by transmitting/receiving XPIC reference signals.
ISX2
Dimensions- 19.82mm(H)x 193.80mm(W)x225.80mm(D). Weight-ISX2-0.60Kg. Power consumption of the ISX2:23Watts
519
Huawei
IDU-RTN910-Boards(ISX2) Functions
Receives and transmits one IF signal. Provides management channels to the ODU. Supplies the required -48 V power to the ODU. Integrated IP radio & SDH Radio . Service Category in Integrated IP mode -are Native E1 + Ethernet & Native STM-1 + Ethernet. Service Category in SDH Radio Mode are -STM-1 & 2xSTM-1. Supports high-efficiency encapsulation for L2 Ethernet packets and L3 IP packets. Supported only in integrated IP radio mode with native TDM services being E1 services. XPIC is supported. Link Protection - 1+1 HSB/FD/SD protection & N+1 protection. E1 services and STM-1 services & SNCP Protection. MPLS & PWE3 functions . Clock Protection-Protection based on clock source priorities ,Protection by running the SSM protocol &Protection by running the extended SSM Protocol. Inband DCN supported & Outband DCN -Supports one DCC that is composed of three DCC bytes for each channel in Integrated IP radio mode. Supports one DCC that is composed of D1-D3 bytes, D4-D12 bytes, or D1-D12 bytes, for each channel in SDH radio mode. In-service FPGA loading. PRBS BER test at IF ports Board manufacturing information query. Board temperature & Voltage detection. E-Line services based on ports. E-Line services based on port+VLAN. E-Line services carried by QinQ links. E-Line services carried by PWs.
520 Huawei Telecom Implementation Process & Guidelines
IDU-RTN910-Boards(EM6T/EM6F)
The EM6T/EM6F receives/transmits, processes, and converges four FE signals and two GE signals.
EM6T
Dimensions- 19.82mm(H)x193.80mm(W)x225.80mm(D). Weight-EM6T & EM6F are -0.37Kg & 0.40 Kg. Power consumption of the EM6T & EM6F are :10.4 & 11.3 Watts
EM6F
521
Huawei
IDU-RTN910-Boards(EM6T/EM6F) Function
Function of EM6T/EM6F are as follows; Receives/Transmits FE/GE service signals and works with the packet switching unit to process the received FE/GE service signals. Both EM6T/EM6F Provides four 10/100BASE-T(X) ports. EM6T Provides two 10/100/1000BASE-T(X) ports (fixed) & EM6F Provides two GE ports by using SFP modules of any of the following types: 1) 1000BASE-SX l 1000BASE-LX, 2) 10/100/1000BASE-T(X). The FE port supports 10M full-duplex, 10M halfduplex, 100M full-duplex, 100M half-duplex, and autonegotiation. The GE electrical port supports 10M full-duplex, 10M half-duplex, 100M full-duplex, 100M halfduplex,1000M full-duplex, and auto-negotiation. The GE optical port supports 1000M full-duplex and auto-negotiation. Supports the following types of E-Line services: E-Line services based on ports E-Line services based on port+VLAN E-Line services based on port+QinQ Supports simple traffic classification by specifying PHB service classes for service flows based on their QoS information (C-VLAN priorities, S-VLAN priorities, and DSCP values) carried by the packets. Supports traffic classification at Ethernet ports based on C-VLAN IDs, S-VLAN IDs, C-VLAN priorities, SVLAN priorities, C-VLAN IDs + C-VLAN priorities, S-VLAN IDs + S-VLAN priorities, or DSCP values carried by packets. Supports the following queue scheduling policies: 1) SP, 2) WRR, 3) SP+WRR. Management of OAM maintenance points-1)Continuity check test, 2)Loopback test, 3) Link trace test. Board voltage & Temperature detection.
522
Huawei
IDU-RTN910-Boards(EFP8)
The EFP8 receives/transmits 8xFE signals from its front panel and 1xGE packet plane signals from the backplane, and encapsulates the Ethernet signals into E1 signals, and transmits the Ethernet signals on the PDH network. Dimensions- 19.82mm(H)x 193.80mm(W)x225.80mm(D). Weight-EFP8-0.60Kg. Power consumption of EFP8: < 13.5 W Function of EFP8 are as follows; Receives/Transmits 8xFE signals and 1xGE packet plane signals and performs EoPDH processing. Eight FE electrical port:10/100BASE-T(X). The FE port supports 10M full-duplex, 100M full-duplex, and autonegotiation. Supports the following types of EVPL services: EVPL services based on port +VLAN EVPL services based on QinQ. Maximum 16 number of VCTRUNKs supported by the board. Maximum 1xVC-4 (63xE1) TDM service capacity supported by the backplane. Maximum 16E1 number of E1s that can be bound with a single VCTRUNK. Traffic classification based on ports Traffic classification based on port +VLAN ID Traffic classification based on port +VLAN ID+VLAN PRI Traffic classification based on port +S-VLAN ID Traffic classification based on port+C-VLAN ID+S-VLAN ID Board manufacturing information query. Board temperature detection.
523 Huawei Telecom Implementation Process & Guidelines
IDU-RTN910-Boards(SL1D)
The SL1D receives and transmits 2xSTM-1 optical signals.
Function of SL1D are as follows; Receives and transmits 2xSTM-1 optical signals. Supports the following clock protection schemes: Protection based on clock source priorities. Protection by running the SSM protocol. Protection by running the extended SSM protocol. Supports the following loopback types: Outloops at optical ports. Inloops at optical ports. Outloops on VC-4 paths. Inloops on VC-4 paths. Detection and query of SFP optical module information. Board manufacturing information query.
524 Huawei Telecom Implementation Process & Guidelines
IDU-RTN910-Boards(ML1/MD1)
The ML1 is a 16xSmart E1 service processing board. The MD1 is a 32xSmart E1 service processing board.
Dimensions- 19.82mm(H)x 193.80mm(W) x225.80mm(D). Weight-ML1/MD1-0.50Kg. Power Consumption-7.0Watts for ML1 & 12.2Watts for MD1.
Function of ML1/MD1 are as follows; Receives and transmits E1 signals, and supports flexible configuration of E1 service categories. Supports the following E1 service categories: CES E1. ATM/IMA E1. ML1 Supports 16E1 & MD1 supports 32 E1. Maximum number of IMA group for ML1 is 16 & MD1 is 32 Maximum number of ATM services 64 & 256 Connections. Supports inloops and outloops at E1 tributary ports. Supports the following encapsulation modes: CESoPSN SAToP PRBS tests at E1 ports. Board manufacturing information query.
525 Huawei Telecom Implementation Process & Guidelines
IDU-RTN910-Boards(SP3S/SP3D)
The SP3S is a 16xE1 75-ohm/120-ohm tributary board. The SP3D is a 32xE1 75-ohm/120-ohm tributary board.
Dimensions- 19.82mm(H)x 193.80mm(W) x225.80mm(D). Weight-SP3S/SP3D-0.64Kg. Power Consumption-5.7Watts for SP3S& 9.6Watts for SP3D.
Function of SP3S/SP3D are as follows; Supports a tributary clock source extracted from the first or fifth E1 signal. SP3S Supports 16E1 & SP3D supports 32 E1. Supports inloops and outloops at E1 tributary ports. PRBS tests at E1 ports. Board manufacturing information query.
526
Huawei
IDU-RTN910-Boards(PIU)
The PIU is the power interface board and can access two -48 V DC or -60 V DC power supplies.
Function of PIU are as follows; One PIU is provided and the PIU accesses two -48 V DC or -60 V DC power inputs. The PIU provides other boards with -48 V power. Supports 1+1 HSB protection. Protection against overcurrent. Protection against short circuits.
527
Huawei
528
Huawei
IDU-RTN950-Product Overview
The IDU 950 is the indoor unit of an OptiX RTN 950 system. It accesses services, performs multiplexing /demultiplexing and IF processing of the services, and provides system control and communication function. Chasis Height-2U No of MW Direction -1 to 6. RF Configuration 1+0 non-protection. N+0 non-protection. (N5). 1+1 protection. N+1 protection (N4). XPIC Configuration.
Different radio link forms of OptiX RTN 950 support different types of microwaves. The radio link form of the SDH/PDH microwave supports the PDH microwave and the SDH microwave.
529
Huawei
IDU-RTN950-Boards
CXPR- System control, switching and timing board , Valid Slot is Slot-7 & 8. AUXQ- Auxiliary board, with 4xFE service interfaces, Valid Slot is Slot-1 to 6. IFE2- Packet IF board, which provides the packet-based microwave service, Valid Slot is Slot-1 to 6. IFU2- Universal IF board, which provides the hybrid microwave service and the packet-based microwave service, Valid Slot is Slot-1 to 6. IFX2- Universal IF board, which provides the hybrid microwave service and the packet-based microwave service, and supports the XPIC function of the hybrid microwave, Valid Slot is Slot-1 to 6. EM6T- 6-port RJ45 Ethernet/Gigabit Ethernet Interface Board, Valid Slot is Slot-1 to 6. EM6F- 4-port RJ45 + 2 Port SFP Fast Ethernet/Gigabit Ethernet Interface Board , Valid Slot is Slot-1 to 6. EF8T- 8xFE service interface board (electric interface),Valid Slot is Slot-1 to 6. EF8F- 8xFE service interface board (optical interface), Valid Slot is Slot-1 to 6. EG2- 2xGE service interface board, Valid Slot is Slot-1 to 6. ML1-16xE1 service processing board (75 ohms), Valid Slot is Slot-1 to 6. ML1A- 16xE1 service processing board (120 ohms), Valid Slot is Slot-1 to 6. CD1-1-channel STM-1 service processing board, Valid Slot is Slot-1 to 6. PIU- Slot 9 and 10. FAN-Slot 11
NOTE When housed in slot 1 or slot 2, the EG2 can process 2xGE signals. When housed in any other slot, the second port of the EG2 is not available. The second port of the CD1 can be used for only the LMSP protection. As the ML1 and ML1A have the same functions except for the match impedance, this document describes only the ML1 instead of both. All the boards except the power board support hot plugging.
530 Huawei Telecom Implementation Process & Guidelines
Board dimensions (mm): 22.86 (H) x 225.75 (D) x 193.80 (W) Weight (kg): 0.66
531
Huawei
532
Huawei
533
Huawei
The Function are as follows; IF Processing Supports the XPIC function, provides the XPIC input and output interfaces, and supports the manual configuration of the XPIC function. Supports the Packet microwave frames and supports the packet service transmission. Supports the adaptive modulation (AM) technology. Maps service signals into microwave frame signals. Codes and decodes microwave frame signals. Modulates and demodulates microwave frame signals. Modulates and demodulates ODU control signals. Combines and splits service signals, ODU control signals, and -48 V power supplies. Provides the maximum signal bandwidth of 56 MHz and supports the highest modulation mode of 256QAM. Overhead Processing Processes the overheads of the Hybrid/Packet microwave signals. Supports the setting and query of the link ID. Protection Processing Supports 1+1 HSB/FD/SD protection. Supports 1+1 FD/SD hitless switching.
534 Huawei Telecom Implementation Process & Guidelines
The Function are as follows; Supports the CES services and IMA services at 64 kibt/s level. Supported 32 ATM E1 Services. Supported 32 IMA group. Supported 63 VC-12 timeslots in each IMA group. Supported CBR,UBR,UBR+,rt-VBR & nrt-VBR traffic type. Supported 63 CES Services. Supports the 1+1 LMSP protection for two STM-1 ports on the same board and the inter-board 1:1 LMSP protection.
535
Huawei
Functions are as follows; Ethernet Service Signal Processing. The EM6T provides two GE electrical interfaces whereas the EM6F uses the SFP optical modules to provide two GE optical or electrical interfaces. The GE electrical interfaces are compatible with the FE electrical interfaces. Supports the setting and query of the working modes of the Ethernet interfaces. The supported working modes are as follows: The FE interfaces support 10M full duplex, 10M half duplex, 100M full duplex, 100M half duplex, and auto-negotiation. The GE electrical interfaces support 10M full duplex, 10M half duplex, 100M full duplex, 100M half duplex, 1000M full duplex, and auto-negotiation. The GE optical interfaces support 1000M full-duplex and auto-negotiation. Supports Jumbo frames with the maximum frame length of 9600 bytes. Clock Processing Supports synchronous Ethernet. Supports receiving and transmitting SSM messages through Ethernet interfaces. Maintenance Features Supports the inloop at the PHY layer over Ethernet ports. Supports the inloop at the MAC layer over Ethernet ports. Supports the mirroring function over Ethernet interfaces. Supports the warm reset and cold reset on the board. Supports the detection of the board temperature. Supports the query of the board manufacturing information. Supports the query of the manufacturing information about the SFP module.
536 Huawei Telecom Implementation Process & Guidelines
Functions are as follows; Supports eight FE electrical interfaces. Accesses 8 x FE electrical signals, and processes the services with the CXPR. Supports the inband DCN. By default, the DCN function is enabled at the first four ports. In addition, this function can be disabled or enabled manually. Detects the temperature and voltage of the board. Automatic loopback release at the port.
537
Huawei
Functions are as follows; Supports eight FE optical interfaces.Accesses 8 x FE optical signals, and processes the services with the CXPR. Supports the inband DCN. By default, the DCN function is enabled at the first four ports. In addition, this function can be disabled or enabled manually. Detects the temperature and voltage of the board. PHY-layer inloop & MAC-layer outloop
538
Huawei
Functions are as follows; Supports two GE optical or electrical interfaces. Accesses 2 x GE signals, and processes the services with the CXPR. Supports the inband DCN. By default, the DCN function is enabled at the two ports. In addition, this function can be disabled or enabled manually. PHY-layer inloop and outloop & MAC-layer outloop.
539
Huawei
The Functions are as follows; Each of the two PIU accesses one -48 V DC (or -60 V DC) power supply for the equipment. The PIU protects the power supply against overcurrent and short circuit. In this way, the overcurrent is prevented from shocking boards and components on them. The PIU protects the equipment against lightning and reports an alarm if the protection fails. Two PIU can achieve 1+1 hot backup. One PIU is capable of supplying power for the entire chassis.
541
Huawei
542
Huawei
Insert fillers panels into vacant slots on An NE to prevent foreign matters from Getting into NE,which may result faults On NE. Boards are fragile & valuable.When Handling or placing a board,ecercise cautioon & put it into a dedicated packing box.
543 Huawei Telecom Implementation Process & Guidelines
When tightening floating nuts ,ensure a minimum of 25mm space on the Left & right sides of the RTN910 is left for ventilation.
Remove & Kept the above detached screws for PGND cable termination.
544
Huawei
Connect PGND cables NoteConnect the PGND cable at side of the IDU ,if the rack is open Connect the PGND cable at front of the IDU ,if the rack is closed type.
545
Huawei
Loosen the screws on the filler panel & remove the filler panels. Hold the ejector levers on the panel with hands & raise them to form an angle of 45degree between the ejector levers & the panel .Push the board gently along the guide rail until the board is secured. Lower the two ejector levers of the boards. Tighten the screws on the panel. NoteBefore installing & removing/inserting a board, wear an ESD wrist strap or ESD gloves .Also ensure that the board is inserted on correct slot.
546
Huawei
Assemble a proper terminal for the power cable according to power cable processing specification. Insert the power cable into the DC connector based on the pin assignment. Loosen the screws on the DC connector, insert the conductor of the bare crimp terminal of the power cable into the DC connector,& then tighten the screws. Check the fuse rating of external power source, i.e 2x10A MCB. Check the voltage & polarity of external power source. NoteWhen assembling a terminal, press the connector securely & equip it with a heat shrink tube to avoid Exposure of the bare & the handle of the connector.
547 Huawei Telecom Implementation Process & Guidelines
Ensure that the circuit breaker of the PDU is set to the OFF state. Insert the DC connector into the power port of the chasis.Ensure that the two groups of power cables are connected to different wiring terminals,& then tighten the screws of the power connectors & the chassis.
548
Huawei
549
Huawei
550
Huawei
Insert fillers panels into vacant slots on An NE to prevent foreign matters from Getting into NE,which may result faults On NE. Boards are fragile & valuable.When Handling or placing a board,ecercise cautioon & put it into a dedicated packing box.
551 Huawei Telecom Implementation Process & Guidelines
Dont pickup the tail end of the red latch by Using a finger or a screwdriver To avoid damage.
552
Huawei
NoteBefore installing the chassis in the ETSI cabinet adjust The holes for installing mounting ears based on the type Of cabinet used for IDU.
NoteWhen tightening floating nuts ,ensure a minimum of 25mm space on the Left & right sides of the RTN950 is left for ventilation.
553
Huawei
Remove & Kept the above detached screws for PGND cable termination.
Connect PGND cables NoteConnect the PGND cable at side of the IDU ,if the rack is open Connect the PGND cable at front of the IDU ,if the rack is closed type.
554 Huawei Telecom Implementation Process & Guidelines
Loosen the screws on the filler panel & remove the filler panels. Hold the ejector levers on the panel with hands & raise them to form an angle of 45degree between the ejector levers & the panel .Push the board gently along the guide rail until the board is secured. Lower the two ejector levers of the boards. Tighten the screws on the panel. NoteBefore installing & removing/inserting a board, wear an ESD wrist strap or ESD gloves .Also ensure that the board is inserted on correct slot.
555
Huawei
Assemble a proper terminal for the power cable according to power cable specification. Then insert the power cable into the DC connector based on the pin assignment. Loosen the screws on the DC connector, insert the conductor of the bare crimp terminal of the power cable into the DC connector & then tighten the screws. Check the fuse capacity of external power source.i.e 2x20A. Check the voltage & polarity of external power source before power ON.
556
Huawei
557
Huawei
Dont do these
558
Huawei
Dont do this
559
Huawei
After Completion of Installation Works ,clear all the cable ties pcs., polythene & other debris from Shelter/Cage. Dispose the debris at an isolated place ,where debris can be dumped. Collect all extra inst materials ,Hardware (uninstalled) and keep at a single place. Remove all dusts from site & clean the site. Keep all site documents (site folder ,inst & comm. manuals of SMPS & Batt. at safe place .
560
Huawei
561
Huawei
562
Huawei
PURPOSE
The purpose of Project Quality process to provide guidance for project management personnel and project quality management team, and to ensure smooth delivery of the project and customer satisfactory delivery with quality.
563
Huawei
Only prevention can satisfy requirements with low cost and high efficiency.
564
Huawei
Take the
565
Huawei
566
Huawei
QUALITY PROCESS-SELF-ASSESSMENT
Main purpose is to:
Identify deficiencies during assessment against the predefined project check-list and close the issue immediately at site before equipment power on.
Requirement:
Subcontractor will do the self-assessment of each and every site i.e. 100% selfassessment and submit site quality assessment report (HSQR) to Huawei project team within 48hrs after completion of hardware installation work.
567
Huawei
Class-B
ClassC
Major Non Conformance points & Score of each point is 4 Major problem means that the violation of this will influence the normal running of equipments /brings hidden troubles to the normal running.
Minor Non Conformance points & Score of each point is 1 Minor problem means that the violation of this will not influence the normal running of equipments but will have an impact on the future capacity expansion/the convenient of O&M.
The Site Quality score of site = The sum of all recorded non conformance scores corresponding to hardware quality standard of the product installed at a site. Higher the score , indicates the worse quality.
The site will be treated as PASS , if the site quality score of the site is < 8 & FAIL if Site Quality Score is 8 Average Site Quality Score is = ((SQS of Site 1 + SQS of Site 2 + SQS of Site 3 +..SQS of Site n )/n)
568 Huawei Telecom Implementation Process & Guidelines
Example
The Site Quality Score of this site is 24 , which means this site is failed
569 Huawei Telecom Implementation Process & Guidelines
MATERIAL RECONCILATION
570
Huawei
customer
M A N A G E M E N T
571 Documents SRN Checklist Milestone GSM/MW Antenna with Feeder line Installation as per Huawei guidelines. Subcons IM Reco ncilia tion Call Test Site Cleaning & finishing Circle IM
Site Documents Verified & Quality Report submitted to QC for Sample site audit
Huawei
MATERIAL RECONCILATION
After completion of Implementation work ,Following to be reconciled after implementation. Installation/auxiliary materials reconciliation to be done. HW Inventory to be done. All above documents to be kept in site folder. The auxiliary material reconciliation is done to understand The wastage of materials (delivered vs. utilization). The wastage should not be more than 5% of delivered materials. Below are the formats for maintaining reconciliation (SRN) & HW inventory.
572
Huawei
Thanks
573 Huawei Telecom Implementation Process & Guidelines