D1.2 Symbols Convention for Grooves Welded from Both Sides with Back-Gouging
The use of GTSM (gouge to sound metal) in the tail of the welding symbol designates that a complete joint penetration groove weld is to be produced. The Contractor may choose to make the GTSM reference a general note on the shop or erection drawing. Alternatively, the convention of the Contractor identifying clearly to the Engineer all groove welds requiring such back-gouging operations may be used on the drawings, thus qualifying them as complete joint penetration groove welds. For complete joint penetration groove welds, as specified above, the symbol need not include the designations of the effective throat (E) for each side of the joint. Examples:
S G
S2 S1
August 2003
183
W59-03
D1.3 Symbol Presentation of Complete Joint Penetration Groove Welds in Joints of Clause 10 Other than Those Requiring Back-Gouging D1.3.1
Single SAW groove welds in joints* welded from both sides without gouging to sound metal, for which the symbol shows only the depth of preparation S, are complete joint penetration groove welds. Their effective throat is stated separately. Example:
Effective Throat = T
*Joints = S2-2, S2-6, S6-1, S6-4, S8-1, S8-4 of Clause 10.
D1.3.2
Square groove welds in joints welded from both sides*, for which the symbol shows neither the depth of preparation S nor the effective throat (T), are complete joint penetration groove welds. Their effective throat is stated separately. Example:
G Effective Throat = T
Effective Throat = T
*Joints M1-3 and F1-3 of Clause 10.
D1.3.3
Single groove welds in joints with steel backing are complete joint penetration groove welds. Their effective throat is indicated in the respective welding symbol. Example:
184
August 2003
*The following letters may be used as applicable: S SR T F C - steel or other material as specified - same as S but removed after welding - tape - flux ceramic
August 2003
185
W59-03
W = weld face width (E) W Note: This welding symbol is specific to CSA Standard W59.
(E)
186
August 2003
Stud
Arc Spot
Effective Throat Depth of preparation; size for certain welds Specification; process; or other reference
S (E)
(Both sides)
F A R
L-P
Weld-all-around symbol
Other Side
Not Used
Tail (omitted when reference not used) Basic weld symbol or detail reference
Not Used
Not Used
Not Used
Not Used
Elements in this area remain as shown when tail and arrow are reversed
Not Used
Not Used
Not Used
Not Used
Not Used
Supplementary Symbols
Weld All-Around Field Weld Backing, MeltSpacer, or Through Consumable Insert Contour Flush Convex Concave
Where letter designations of processes are to be used in the tail of the welding symbol, they shall conform to Table 1, Letter Designations of Welding and Allied Processes and Their Variations of AWS A2.4-98
6. Weld-All-Around Symbol
Weld-all-around symbol indicates that weld extends completely around the joint
Convex contour symbol indicates face of weld to be finished to convex contour by grinding
CJP
8. Melt-Through Symbol
Any applicable weld symbol
1
Arrow of welding symbol Other side of joint Size (height) Omission indicates no special height desired
MR
16. Abbreviations
GTSM Gouge To Sound Metal CJP Complete Joint Penetration PJP Partial Joint Penetration
M
Double bevel symbol 030
see Notes
(Continued)
August 2003
187
W59-03
Other Side
Both Sides
Groove angle
Omission of depth of preparation and effective throat indicates complete joint penetration is required.
8 8
50-150 50-150
(25) (30)
26. Welding Symbols for Grooves Welded from Both Sides with Back-Gouging
Only depth of preparation is required in the welding symbol
GTSM 12 10 GTSM
12 12
75-125 75-125
10
Length of increments
GTSM signifies total effective throat is equal to the thickness of material. See Clause D1.2 of Appendix D.
OR
First operation
Flare-Bevel
(3) 1
Pitch
Number of studs
Notes: (1) Stud weld symbol is always below the reference line. (2) The location of the first and last stud weld in each single line shall be specified on the drawing. Notes: (1) Arc spot weld symbols can be placed above or below the reference line, depending on whether welding is to be done on the other side or the arrow side member respectively. (2) The location of the first and last arc spot weld in each single line shall be specified on the drawing.
Omission of effective throat without designating the weld as seal weld in the tail of the symbol indicates complete joint penetration is required
Figure D1 (Concluded)
188
August 2003
/--
Groove Angle; Included Angle of counters~nk Plug Welds for Length of Weld Weld symhol Pitch (centre-to-centre spac~ng) Welds of Arrow connecting Reference Line ta arrow-side member of Joint
Contour symbol Effective Throat Depth of Preparation; sire for certain welds
rField
T i
Used
1
MeltThru
'~eference Line
Weld All-Around
Field Weld
&, ::: 8
CONWMABLE
CONTOUR
,,. ,,,
~ ~ u s h
I on vex I
concave
breviations are t o be included i n the tail of the weldina symbol, reference is made toTable A, De-
Flush con tour symbol indicates face of weld t o be made approximately flush.
------A-
When used w i t h o u t a surface finish symbol. i t Indicates weld w i t h out su bsequent finishing
/ =
BUTT JOINT
WELD-ALL-AROUND SYMBOL
112
Field weld symbol indicates that weld is to be made at a place other than t h a t o f i n ~ t i aconstruction l
Indicates complete j o i n t penetration groove weld regardless o f type of w e l d and joint preparation
i JOINTS
CORNER JOINT
M E L T - T H R U SYMBOL
F ~ r s operation shown on t
reference line nearest arrow Second operation. or supplementary data T h i r d operation. a r test informationP
4 BASIC JOINTS
LAP JOINT
JOINT W I T H BACKING
NOTES
- Mater~al M ) and (
I
I
5
BASIC JOINTS EDGE JOINT
10
R - Rolling
H
- Hammering
W t h m o d i f i e d groove-weld symbol
NOTES Material (M) and dimensions of spacer as specified. See Clause D1.6.
S I N G L E - V - G R O O V E WELDING SYMBOL
A
Size (length of leg) Specification. process, or other reference Lengtii Om~ssion indicates that weld extends between abrupt changes i n direction ar as dimensioned
I
Root opening
Omission o f depth preparation and effective throat indicates complete 101ntpenetration is required.
polnts
Eff.y-yy: \
LlllVdl
toward be.pIepared
-1
iength of increments
L 26
i3~)&
Omission of depth o f preparation and effective throat indicates total depth o f preparation - symmetrical i n case of doubleilroovn welds equal t o the thicknessof the member and.hence.complete j o i n t peneyration groove weld is required
19
(distance between increments Size (length of leg) incrernen ts GTSM signifies total effect~ve throat ~ s e q u a l the thickness of material. to See Clause 01.2 o f Appendix D.
20
27
BACK-WELDING SYMBOLS
Any single-groove weld with a pass f r o m the Other side w i t h n o special identification i n the tail is considered a groove weld w i t h a back weld. Second operatior OR First operation
of countersink
21
S L O T WELDING SYMBOL
28
BACKING W E L D I N G SYMBOLS
Any single-groove weld w i t h a pass f r o m one side identified i n the tail by "backing weld" is considered t o be a groove weld w i t h a backing weld. Depth of filling in m m (omission indicates fiil~ng com~letel is Second operation Orientation, location. and all dimensions other than depth o f f i l l i n g as shown on the draw in^
S ELD WA C K I N G
0R
First operation
22 F L A R E - V AND F L A R E - B E V E L - G R O O V E WELDING S Y M B O L S
29
Effect~ve Throat
r
DoubkfllM Wmldlng Sybd
In dlmtkm w
aa d l m s M i d
--,
( I
~ p o WWng symbol r
k r n wmld~ng y m w ~
Slu or
Increment
Slze
Number d studs
pmss
Weld &e
WeM slze
G m e angle
Compkt. hmtratlon
Icdkxtes mmplete ]ant penetrahon ragerdless of hlpe 01 weM or pint pmparallon Weld
82 18
3rd operatm
f
Jolnt wfth B.oldng
awt-T~N Symbol
Process reference
Root rmnforcement
*
Jolnt rvlth Spscsr With modified groove weld symbol Double bwel gmove
~ r u contour Symbol h
'H should be understood that these charts are intended only as shop aids. The only complete and official presentation of the standard welding symbols is in A2.4.