Gant
Gant
Task Name
Duration
Start
Finish
Predecessors Jan 22, '12 S T M Feb 5, '12 F T S W Feb 19, '12 S T M Mar 4, '12 F T S W Mar 18, '12 S T M Apr 1, '12 F T S W
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
Mobilization Layout Excavation Soil Poisoning Back Filling Foundation Foundation - Column.F.(Rebars) Foundation - Column.F.(Concreting) Foundation - Wall.F.(Rebars) Foundation - Wall.F.(Concreting) Ground Column Ground Column - Rebars Ground Column - Formworks Ground Column - Concreting Masonry Masonry - CHB Walls Masonry - Cement Plastering Beams Beam - Rebars Beam - Formworks Beam - Concreting Removing of Formworks Staircase Construction Slab Slab (2ndFloor) - Rebars Slab (2ndFloor) - Concreting Slab (1stFloor) - Rebars Slab (1stFloor) - Concreting Roofing Roofing - Construction of Truss Roofing - Putting the purlins Task
1 day 1 day 2 days 2 days 2 days 6 days 2 days 4 days 2 days 4 days 4 days? 2 days 1 day? 3 days 4 days? 4 days 1 day? 3 days? 2 days 1 day? 2 days 1 day? 1 day 8 days 2 days 3 days 2 days 3 days 4 days? 3 days 1 day?
Wed 1/25/12 Wed 1/25/12 Thu 1/26/12 Mon 1/30/12 Wed 2/1/12 Fri 2/3/12 Fri 2/3/12 Tue 2/7/12 Fri 2/3/12 Tue 2/7/12 Mon 2/13/12 Mon 2/13/12 Tue 2/14/12 Tue 2/14/12 Fri 2/17/12 Fri 2/17/12 Wed 2/22/12 Tue 2/21/12 Tue 2/21/12 Wed 2/22/12 Wed 2/22/12 Thu 2/23/12 Fri 2/24/12 Mon 2/27/12 Mon 2/27/12 Tue 2/28/12 Fri 3/2/12 Mon 3/5/12 Thu 3/8/12 Thu 3/8/12 Mon 3/12/12
Wed 1/25/12 Wed 1/25/12 Fri 1/27/12 2 Tue 1/31/12 3 Thu 2/2/12 4 Fri 2/10/12 5 Mon 2/6/12 Fri 2/10/12 7 Mon 2/6/12 Fri 2/10/12 9 Thu 2/16/12 Tue 2/14/12 10 Tue 2/14/12 Thu 2/16/12 Wed 2/22/12 Wed 2/22/12 14 Wed 2/22/12 Thu 2/23/12 Wed 2/22/12 Wed 2/22/12 Thu 2/23/12 Thu 2/23/12 Fri 2/24/12 Wed 3/7/12 Tue 2/28/12 Thu 3/1/12 Mon 3/5/12 26 Wed 3/7/12 Tue 3/13/12 Mon 3/12/12 Mon 3/12/12 External Milestone Inactive Task Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only Progress Deadline
Project Guide: Critical Task Split Project: CE52fb1.mpp Date: Sun 2/5/12 Milestone Summary Project Summary External Tasks Page 1
ID
Task Name
Duration
Start
Finish
Predecessors Jan 22, '12 S T M Feb 5, '12 F T S W Feb 19, '12 S T M Mar 4, '12 F T S W Mar 18, '12 S T M Apr 1, '12 F T S W
32 33 34 35 36 37 38 39 40 41 42 43
Roofing - Laying the Roofing Material Roofing - Putting Roof Accessories Roofing - Construction of Ceiling Pipeworks Waterline Sanitary Line Catch Basin Septic Tank Electrical Works Cement Finishing Tileworks Painting
1 day? 1 day? 1 day? 6 days? 2 days 2 days 1 day? 1 day? 2 days 4 days 8 days 3 days
Mon 3/12/12 Mon 3/12/12 Tue 3/13/12 Wed 3/14/12 Wed 3/14/12 Fri 3/16/12 Tue 3/20/12 Wed 3/21/12 Thu 3/22/12 Mon 3/26/12 Fri 3/30/12 Wed 4/11/12
Mon 3/12/12 Mon 3/12/12 Tue 3/13/12 33 Wed 3/21/12 34 Thu 3/15/12 Mon 3/19/12 36 Tue 3/20/12 37 Wed 3/21/12 38 Fri 3/23/12 39 Thu 3/29/12 40 Tue 4/10/12 41 Fri 4/13/12 42
Task Project Guide: Critical Task Split Project: CE52fb1.mpp Date: Sun 2/5/12 Milestone Summary Project Summary External Tasks Page 2
External Milestone Inactive Task Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only