Preliminary Buffer
Preliminary Buffer
package the activities can be started, without the subsequent due dates being changed. You specify a preliminary buffer of 5 days for each maintenance package in the strategy. The planned date calculated by the system is September 30. The start date proposed in the maintenance order is therefore September 25. Follow-up Buffer The follow-up buffer specifies how long after the maintenance package is due the processing of the activities can be finished, without the subsequent due dates being changed. You specify a follow-up buffer of 5 days for each maintenance package in the strategy. The planned date calculated by the system is September 30. The end date proposed in the maintenance order is therefore October 5.