Estimation of Brickwork in Single Storey Buildings Stone Masonry General Spe
Estimation of Brickwork in Single Storey Buildings Stone Masonry General Spe
Structure
3.1 3.2 3.3 3.4 3.5 3.6 3.7 3.8 3.9 Introduction
Objectives
Quantification of Brick Masonry : Dimensions of Masonry Work in Buildings General Specifications for Brickwork Walls and Arches Classification of Ordinary Buildings : 1st Class, 2nd Class and 3rd Class Case Study : Brick Masonry and Other Items in a Building Estimation of Brick Masonry in Arches Typical Rate Analysis of Brick Masonry Stone Masonry Summary
3.1 INTRODUCTION
The oldest man-made building block is the unbaked brick and, it is still in use inspite of the increasing use of cement concrete with or without reinforcement. Bricks and the mortar to be used (foundations, walls, and now almost obsolete practice of reinforced brickwork in roofs and stairs, etc.) shall be fully specified (described) while measuring up the work. If any bond is specified (English, Flemish, etc.) it shall be so stated. General brickwork includes building in ends of beams, slabs, lintels, sills, trusses, joints etc.; building in hold fasts etc.; preparing tops of existing walls for further raising work to be carried out; leaving holes for pipes etc.; bedding wall plates, lintels, sills, corrugated sheets, etc. in or on walls if not paid for separately; etc. Footings (of foundations), plain copings (on compound or other exposed walls), etc. also fall in the general category of brickwork. Brickwork is generally measured in m3. However, one-brick-thick walls (and of lesser thickness) shall be measured in m2 stating specifically the thickness of the item. For a fraction of half brick wall thickness, occurring in architectural embellishments shall be measured such as : (a) (b) up to brick give actual measurements, more than brick taken as a full half-brick thick.
Deductions in the quantity of brickwork shall be made for lintels, doors, windows, etc. But, no deductions on additions shall be made for the following features done in the work :
73
a dissimilar material (say, beams, lintels, etc.) measuring up to 0.10 m2 in section, cement concrete blocks used for fixing hold fasts and holding down bolts, wall plates, bed plates, bearing of slabs etc., where thickness does not exceed 10.00 cm, and the bearing does not extend over the full wall thickness, and iron fixtures, i.e. wall ties, pipes up to 30 cm dia, and hold fasts for doors and windows.
(d)
Pillars and columns are to be measured in m3, and to be fully described rectangular, polygonal; curved (in plan); or any special shape. All circular brickwork, above 6.0 m radius, shall be included in the general brickwork. But, all brickwork, circular in plan and radius not exceeding 6.0 m is measured separately, and shall include all cutting and waste, etc. At certain places it is a practice to lay the damp proof courses of bricks too laid on edge. All such work shall be measured in m2, stating its thickness. Vertical and horizontal DPC shall be measured separately. As a common classification, brick masonry (or even stone masonry) shall have following categories (to be paid for accordingly as the height form GL increases, and labour to lift the brick too increases) : (a) (b) (c) brickwork in foundations (footings, etc.), brickwork in plinth below GL and above GL, and brickwork in superstructure work in each floor measured separately.
Scaffolding for ordinary works is not measured and paid for separately but is included in the rates for brickwork (BW). Rounded or splayed sides of walls are considered as rectangular, and those very dimensions are employed for computing quantities. As for other, such items, dimensions shall be measured to the nearest 0.01 m (i.e. 0.1 cm) areas shall be worked up to the nearest 0.01 m2; and the cubic contents shall be worked up to the nearest 0.01 m3. For bricks of nominal size (22.9 11.4 7.6 cm), the half-brick size is taken as 11.4 cm, for bricks of nominal size (25.4 12.7 7.6 cm), the half-brick size is 12.70 cm; and for model bricks of 20 10 10 cm, the half-brick size is 10.0 cm. Hence, for different brick sizes, wall thickness given in table below is taken into account :
Wall Size as Multiple of Brick Size Thickness of Brick Wall (cm) For Brick Size 20 10 10 cm One-brick wall 1 - brick wall 2-brick wall 2 - brick wall 3 - brick wall 20.0 30.0 40.0 50.0 60.0 22.9 11.4 7.6 cm 22.90 34.30 45.70 57.10 68.60
74
Objectives
After studying this unit, you should be able to estimate the quantity of brickwork (BW) in the foundations of a building, estimate the quantity of BW in plinth, and superstructure, develop a full plan of a building, given its line plan, estimate the quantity of BW in arch work, describe the general specifications regarding RCC work, and explain the general specifications about stone masonry.
Out-to-out and in-to-in method is the most commonly adopted procedure. Here the length of long walls (say for excavation purposes) are reckoned from out to out AB in Figure 3.1 and, the length of short walls measured in between the long walls in-to-in EF. These lengths shall, obviously, apply to foundation concreting also. The magnitude of these dimensions changes (in fact, decreases) for long walls, and increases for short walls at every change in the breadth (or, ray, thickness) of a course of brickwork :
[b b ] AB will decrease to AB 2 1 2 , i.e. for the first footing of the 2 foundation masonry the length of long wall shall be (2 3). And, EF shall [b b ] increase by the same amount, becoming EF + 2 1 2 , i.e. (5 6). Here, 2 the width for excavation is b1 and height (or thickness, vertically) is d1; while for the first footing, width = b2, and depth = d2. Similarly, in the plinth course (or for
75
next footing if it is there), long wall length shall be [(10) (11)], and short-wall length shall be [(15) (16)] width being b3, and depth = (d3 + d4). And for the superstructure, long-wall will have a length [(18) (19)], and short wall length will be [(23) (24)] width being = b4, and height = height of the room from the top of DPC (of floor top) to the underside of roof slab (or whatever it is). Here it is important to point out that the width and depth of excavation shall be b1 and (d1 + d2 + d3), respectively; while for foundation concrete the values will be b1 and d1, respectively.
l2 C 4
12 20 24 16 8 H G 7 23 15 10 11 3 B Centre Line
b1
b2
b3
b4
E 5 13 21 17 9 1 D
F 6 14 22 18 10 2 A
b4
DPC
d4
Superstructure
Masonry (Plinth) L
Footing
Foundation Concrete
b3
b2
d3
d2 Depth of Excavation d1
b1
(b) Section Figure 3.1 : A Simple Rectangular Trench Plan of a Building and Section of Wall-cum-Foundation
76
l1
It is obvious that with the decrease in the thickness of walls of a room, (i.e. proceeding up from the first footing towards the superstructure) the length of a long wall decreases, whereas the length of a short wall increases in accordance with the breadth (or, thickness as it is generally designated). At the plinth level, the length of long wall = the length of the room (wall to wall, i.e. inner dimension plus twice the wall thickness; and the length of short wall = width of the room (inner dimension). If the thickness of the walls is different, the dimensions are reckoned accordingly.
Example 3.1
A 20 cm brick wall (of a 4.8 3.30 m hut, having one door opening 1.5 2.5 m) has directly a beam built on a 30 cm thick plinth which goes 20 cm below ground level and remaining 50 cm above ground. Under this plinth there lie two footings 40 cm, and 60 cm thick (i.e., wide), respectively, while their respective heights are 10 cm and 20 cm. The LC is 100 cm wide and 20 cm deep. All this brickwork has been erected on LC 1.0 m thick (i.e., wide) and 20 cm deep. Draw the cross-section of the wall and the foundation (to an enlarged scale) and also the trench plan, superimposed with the plan for footings, plinth and wall. Calculate the following items of work by Long- and Short-wall method (as well as by centre line method) : (a) (b) (c) (d) (e) Earthwork in excavation, LC in foundation, Brickwork in first two footings, Masonry in the plinth, Masonry in superstructure.
[Note : The student shall draw the figures: section and plan as asked for and check the dimensions therewith as worked out in this solution.] The following Table presents the quantification of the required items by Long- and Short-wall procedure :
Quantification of Items
Sl. No. Items No. L (m) 1. Earthwork in excavation (i) Long walls (ii) Short walls 2 2 6.0 2.5 1.0 1.0 0.70 0.70 Total 8.4 3.5 11.9 m3 Dimensions B (m) H/D (m) Quantity (m3) Remarks
77
2.
LC in foundations
11.9
0.20 0.70
3.4 m3
Length and width of LC is same as for Item (1) except its depth being 20 cm (i) Long wall shorter by 2 0.2 m each; and short walls lengthen by 2 0.2 m each for 1st of footing (ii) For second footings these adjustments are 2 0.1 m and 2 0.1 m, respectively, w. r. t. the first footing lengths.
3.
Masonry (BW) in two footings 1st footing Long walls Short walls 2nd footing Long walls Short walls 2 2 5.40 3.1 0.40 0.40 0.1 0.1 0.43 0.25 2 2 5.60 2.90 0.60 0.60 0.20 0.20 1.34 0.74
Total of Item (3) 4. Masonry (BW) in the plinth Long walls Short walls 2 2 5.30 3.2 0.3 0.3 0.70 0.70 Total 5. Masonry in superstructure (BW) Long walls Short walls 2 2 5.2 3.3 0.20 0.20 Gross Total Deduct Door Opening 1 1.5 0.20 2.5 3.5 3.5
2.72 m3 Here, the adjustments are 2 0.05 m for the respective walls, w. r. t. the second footing
Here the adjustments for the lengths of respective walls are 2 0.05 m each w.r.t item (4)
() 0.75 11.15 m3
In crossing method (basically nothing but long- and short-wall method itself, suitable for symmetrical cases), length and breadth of walls are directly taken from the plan, such as : Length of any long wall (at any level of the cross section) = Inner length of the wall + 2 (wall thickness). Length of short wall = Inner length of the wall (i.e. inside to inside). It is by now obvious that this method is suitable only while the offsets (of one footing w.r.t. to the adjacent one) are symmetrical, and the building is more or less regular. For any asymmetries detailed calculations from the plan dimensions are called for. In centre line method, the plan of a building helps one to compute the total length of the centre line. This method is most suited to find the quantities of
78
earthwork in excavation, masonry in walls, etc., when the plan is curved, rectangular, circular, etc. In Example 3.1, one can see that the length of centre line = 2 [6.00 2 0.5 (i.e., width of the trench)] + 2 [4.5 2 0.5] = 2 (5) + 2 (3.5) = 10 + 7 = 17.0 m Hence, one can work out the required quantities also as follows : (a)
Earthwork in Excavation
Sl. No. 1 L (m) 17.0 B (m) 1.0 H (m) 0.7 Quantity (m3) 11.9 m3
(b)
LC in Foundation
Sl. No. 1 L (m) 17.0 B (m) 1.0 H (m) 0.2 Quantity (m3) 3.4 m3
(or 11.9
0.20 = 3.4 this mode of calculation being most common 0.70 for reasons given earlier).
(c)
(d)
(e)
In actuality, a full building plan is somewhat complicated in its juxtaposition there being cross walls joining two parallel walls (say, either long to long, or short to short), or there being walls that are of different thicknesses, etc. and, the application of centre line method shall not be done without applying a proper thought. While multiplying the length of a
79
centre line by the thickness of the trench or a course, one actually, in this process, accounts for that portion of the centre line that joins it via a cross wall or so. Hence, appropriate deductions (according to the width, i.e. thickness of the course) have to be applied to the gross length of the walls for getting correct results with respect to the quantification of an item these finer points shall be made clear in the following examples. It may be pointed out that sometimes for a quick approximate estimation, in the case of a number of foundation masonry footings such as shown in Figure 3.1 or, a section with still more footing the cubic quantity of masonry is taken as
Q = Appropriate mean length (i.e., the appropriate centre-line length)
It may again be emphasized that this formula is only an approximation, and not meant to replace detailed calculations. As mentioned elsewhere (later on) class of bricks, materials of mortar, and different heights of construction in a building, are the factors that govern the estimation of brickwork under various groups (headings). In general, scaffolding is included in the rates of payment, unless otherwise stated unit of measurement being m3. Brickwork in superstructure up to a height of 8.0 m, above the plinth level is taken under one item; and above 8.0 m height, the quantities for every 3.0 m height or its part are calculated under separate items. Rounded or splayed sides (as reiterated later on also for the sake of impressing the point) of walls are considered as rectangular, and extreme dimensions are taken for the purposes of computations.
Deductions Made in the Gross Contents
Deductions for openings (doors and windows and cup boards) are necessarily made in the gross cubic content of masonry to arrive at the appropriate quantity for which specified rates are given commonly, deductions are made in superstructure masonry only.
l
Lintel
Lintels over openings (doors, windows, cup boards) may consist of RCC, or RB work, or wood (as in earlier times), or simple bricks placed in transverse direction to the bricks of the wall unit of quantification is m3. These items are paid for separately, and are to be deducted from the gross quantity of masonry. In the absence of data about the bearing of lintel (on either side), l (the length of the lintel) is calculated as :
l = Clear Span + 2t
80
where, the value of 2t should, at least, be taken as 12 cm. Thus, the cubic content of the lintel, Q, is given as :
Q = l t (Thickness of wall)
Similarly, for rectangular openings (doors, windows, cup boards), Deduction = b h Wall thickness For doors and windows with small segmental arches (i.e. r is very small), the openings are considered as rectangular only : Deduction = b h Wall thickness
Segmental Arch
2 l r is an approximate estimation, but usefully adopted in 3 practice. where, For a small semi-circular arch opening, Deductions = [b h Wall thickness] + (
3 b r Wall thickness) 4
where,
b = 2r
r = (b/2)
Semi-circular Arch
81
However, large arches are dealt with on the basis of rigorous mathematical formulae. As pointed out in the general specifications, partition walls (that are not 1 load bearing) that may be 10 cm or 12 cm thick, are designated as -brick 2 2 walls (or brick on edge walls). The quantities are calculated in m or, sometimes in m3, as per given rates of payment.
Mensuration as Applied to the Quantification of Masonry
Knowledge about deciphering drawings (plan, sections, and elevation even side elevation sometimes) is the basic skill needed for an estimator. This calls for a clear concept (and imagination too) about the structure that is depicted: a prerequisite to reading a drawing, to enable taking length, breadth (width), thickness and heights accurately. Constant, and sustained practice goes a long way to render this seemingly difficult task very easy, because by this toil one develops an understanding about the various components of a structure. Mensuration (and, a knowledge of trigonometry), comes handy, once the dimensions are read accurately, in computing the quantities. Commonly used mensuration formulae are given as under, for a ready reference, and brushing up ones knowledge : (a)
Rectangle
A=
1 Base Altitude 2
abc 4R
Also, A = [ s ( s a ) ( s b) ( s c)] =
1 ( a + b + c) 2
82
(d)
Circle
A=
(diameter)2
= (radius)2 = 0.07958 (circumference)2 Side of an inscribed square = 0.707 (diameter) Side of a square that is equal to the circle in area = 0.8862 Diameter. (e)
Semi-circle
A=
By application of following rules, elaborate calculations can be replaced by easy and quick calculations. (a)
Foundation Concrete (LC/CC)
Quantity = Quantity of earthwork in excavation Depth of foundation trench (Thickness of foundation concrete)
This holds good only if the width (thickness) and depth of concrete is uniform throughout. For non-uniform dimensions, computation can be made by parts. (b)
Inside White Washing (or Distempering of Walls and Ceiling)
Its quantity (m2) shall be the same as for inside plastering of walls and ceiling. (c)
Outside Colour Washing
Its quantity (m2) shall be the same as for outside plastering or pointing. (d)
Sand (or Cinder) Filling in Plinth
83
84
It is to be emphasized that for any face work, bricks shall be selected for trueness of edges, shape and colour these shall not be chipped or stained during the progress of the work. Moreover, as is understood, bricks shall be laid as to give a perfectly straight and vertical face to the wall as to be always tested with a straight edge; and no chipping or rubbing of the faces will be permitted to remedy any bed laying. Bricks shall be cut or grooved where required for shaping jambs or fitting chowkats. Corners, where special bricks for the purpose are not available, shall be made with cut bricks, five being used per corner. Rates can include labour for this cutting of bricks and making of mitres, splays, etc., except grooving to receive chowkats. Holdfasts and similar fixtures shall be built in with the surrounding brickwork in their correct positions in 1 : 3 cement mortars.
First Class BW
Only headers shall be left out to allow of a putlog (one of the short timbers that support the flooring of a scaffold) to be inserted, and not more than one brick shall be left out for each putlog. Under no circumstances shall putlog holes be made in, or immediately under, or next to the imposts or skewbacks of arches. Brickwork laid in lime and/or cement mortar shall be protected during construction from the effects of the sun, rain, and frost, by appropriate covering if necessary, and shall be kept moist for a period of ten days. The work shall be, as per theoretical considerations, left flooded at the end of each day with 2.5 to 3.00 cam of water. In buildings where specified (say, hospitals, etc.), cut or specially moulded bricks shall be used at all angles (formed by the junction of two walls) to give rounded corners. Similarly, wherever required, cut or moulded bricks shall be used in joints, arches and projecting corners in order to avoid the formation of sharp angles from the inside of such buildings. Bed plates of 1 : 2 : 4 cement concrete (CC), or of stone shall be given under all beams and joists for stones 1 : 3 cement mortar (CM) shall be used. Bed plates must be laid to the correct level (as per drawing/estimate) packing up, if needed, with tiles or split bricks. In first class BW, the size of bricks shall be specified. These are made from good brick earth, free from saline deposits and shall be sand moulded. These shall be thoroughly burnt without being vitrified; shall be of good (reddish) colour, and be of regular and uniform shape and size, with sharp and square rises and parallel faces. First class bricks must be homogeneous in texture; and must emit a clear ringing sound when struck. These shall be free from flaws, cracks, chips, stones, nodules of lime or kankar and other blemishes. A first class brick shall not absorb more than 1/6th of its weight of water after being soaked for one hour, and shall show no signs of efflorescence on drying.
Second Class BW
Second class bricks shall be as well burnt as first class, or slightly over burnt, but not vitrified in any part and must give a clear ringing sound when struck. In second class bricks, slight irregularities in size, shape, or colour will be accepted, but in no case if these render the courses irregular or uneven when laid. Slight chips or flaws can be tolerated; but, must be free
85
from lime or kankar nodules. They shall not absorb water more than 1/4th their weight after one hours immersion. Second class brickwork shall differ from first class only in that it shall be laid out with second class bricks. Specifications laid down for first class brickwork (as detailed above) shall apply in toto, except that the select bricks may not be used in face work. However, no cut brickwork shall be executed with second class bricks.
Third Class BW
Third class bricks need not be so fully burnt (baked) as first class or second class however, they must be burnt to a reddish yellow colour throughout. Any defects in uniformity or shape can be accepted till these blemishes do not cause difficulty in obtaining uniform courses when laid. Third class BW shall differ from first class brickwork, in that it shall be laid with third class bricks. Under-mentioned modifications are applicable to the specifications meant for first class brickwork : (a) (b) (c) Brickwork laid in mud-mortar shall be protected during construction from rain or from uneven drying. Third class brickwork shall not be laid in 1 : 3 cement mortar. Joints in third class brickwork shall be 1.25 to 1.30 cm thick : but, in no case shall exceed 1.60 cm in thickness. The height of four courses as laid (with four joints) shall not exceed by more than 5.0 cm, the height of four bricks as piled dry one upon another. As the depth of courses is different from that in the case of first and second class brickwork, third class brickwork shall not be used where it has to bond with the brickwork of superior classes. No selection of bricks for face work shall be insisted upon. No cut brickwork shall be executed with third class bricks.
(d)
(e) (f)
Underburnt (or pilla) bricks shall not be used in the construction of brickwork except in sundried brickwork. Bricks that are so much overburnt as have gotten vitrified as distorted are known as jhama bricks, and are of no use for exact work. However, these are broken up for ballast provided the vitrified mass has not become porous or spongy in the process of being overburnt. Sundried bricks shall be made from the same kind of clay that will produce good bricks on being properly burnt. These shall be sand moulded and shall be uniform in size and regular in shape. If after drying, a few bricks (picked up at random) from a batch break into more than two pieces on being dropped on an even ground from a height of about 1.30 to 1.50 m, the batch must be rejected as having beam moulded with too much sand. Batches of bricks in which cracks appear on drying shall be rejected as having been moulded with too little sand. Special care shall be taken that the earth used for making sun-dried bricks is free from efflorescing salts and from all traces of white ants. All sun-dried bricks shall be thoroughly dried before
86
use; and have to be protected from rain sun dried brick walls are given a facing of burnt bricks, or given a mud-phaska (mud + cut paddy grass leaves, i.e. straw) plaster (or even cement plaster). These walls stand very well till no moisture goes into this masonry. These are laid in mud mortar. Unless otherwise specified, two courses, underneath the roof (say, a pitched roof) battens, and the jambs of doors and windows (to a depth of 23 cm) shall be built in second class brickwork in mud. All roof beams shall also be carried on piers of second class BW in mud for the full height of the wall. Brick tiles (burnt) are used in roofing (over, say, RCC slab) or even flooring.
Brick Ballast
Brick ballast shall be broken to the specified gauge, from first or second class bricks or their bats or from dense overburnt bricks. No under-burnt bricks or bats, nor jhama that has become spongy or porous in the process of burning, shall be broken up for ballast. Brick ballast is used as a flooring base (over the filled earth up to plinth top) over which LC/CC etc. is laid to give the designed floor level and finish. Ballast shall be free from surkhi, leaves, straw, earth, sand or any other foreign matter. To allow for loose stacking (before use, i.e., before spreading over earth between plinth walls, and ramming to adequate thickness), all stacks of ballast shall be paid as 30 cm for every 32.50 cm in height.
Half-brick Wall Masonry
The work shall be done in the same way as other brickwork, except that all the courses shall be laid with stretchers with staggered vertical joints. In special cases (like half brick walls for water tanks, and long-length half brick thick walls, etc.) sometimes reinforcement is provided to render the work structurally stronger. Generally, two lengths of 6 mm bars are provided at every third course. Reinforcement shall be clean from rust and loose flakes using a wire brush is quite adequate. The reinforcement is placed quite straight on the mortar laid on the course under consideration. For full embedment of the reinforcement, first half the quantity of mortar is laid and then the rod is placed in position which is later covered with the remaining half the quantity of mortar. This arrangement makes the joint between the two courses stronger. Such walls do serve as partition walls for WCs, baths, etc. Length and height of this wall shall be measured correct to a cm. If it is to be paid per m2 units, the area shall be calculated up to the line where the half-brick masonry wall is joined to the main wall of one brick or greater thickness the measurements shall be taken for its clear length from the face of the thicker wall. Reinforcement may be paid separately.
Brickwork in Arches
Arches shall not be commenced until the abutments (supporting structure wall or joist) are built to their full width up to the level of the skew-backs. Arch work shall be carried up evenly from both abutments; and as soon as the arch is complete, the masonry is to be built up evenly on both sides to the height of the crown so as to load the haunches.
87
Before the building of an arch is begun, the abutments must be exactly at the same level and the skew-backs must be in place. Skew-backs shall be formed of bricks correctly shaped to radiate truly from the centre of curvature, and shall not be packed up with mortar or chips. Skew-backs are not to be measured as part of the arch. Centering shall be strong enough to bear the weight of the arch without deflection. The surface of the centering shall be correctly struck to the curvature of the soffit of the arch. Cost of centering is generally included in the rate for arch work. Centering and shuttering shall also bear the live loads that are likely to come upon it during its construction. Shuttering shall be tightened with hard wood wedges or sand boxes to allow these to be eased without any jerks being transmitted to the arch. The sequence of easing the shuttering is to be planned before hand. Shuttering shall be struck (gradual lowering of the centres) within 48 hours of the completion of the arch but before 24 hours this shall be done after the spandrel has been filled in and the arch is loaded. A common schedule of striking the centers that can be followed is outlined as under :
Sl. No. 1 2 Type of Arches Single segmental arch Series of segmental arches Striking Schedule Centre shall be struck immediately after the arch is finished. Centre of each arch shall be struck as soon as the arch succeeding it is completed Centres shall be struck as soon as the brickwork has reached two thirds of the height of such arches
Specifications for brickwork (as outlined earlier) shall also apply to the brickwork in arches. Arch work shall comprise masonry for both gauged as well as plain arches in gauged arches, cut or moulded bricks shall be used; and, in plain arches uncut bricks are used. Defects in dressing of bricks shall not be covered up by any extravagant use of mortar, nor the use of chips, etc. shall be allowed. The length of the arch shall be measured as the mean of the extrados and intrados of the arch correct to a cm. Generally, the thickness of the arch shall be measured in multiples of half brick. For arches exceeding 6.0 m in span, extra payment shall be made for additional cost of centering, strutting, bolting, wedging, easing, striking and its removal.
Corbelling, Copings, Cornices, Strings, etc.
All corbelling, brick copings, cornices, strings, eaves bricks, window sills, drip courses and chimney stacks shall consist of first class brickwork laid in lime and/or cement mortar as specified in the design. Vertical joints in each case shall not exceed 3.0 to 4.0 mm in thickness. Bricks when laid flat in such courses shall either be altogether without frogs or with frogs at one end so as not to show, either on top or from below, when the bricks are in position. 88
Corbelling, commonly, shall be effected by -brick projections for ordinary work and 1/8 brick projections where great strength is required. Corbelling shall be measured by the actual cubic contents, and shall be paid for at ordinary rates for the class of brickwork executed. All the cornices shall be in accordance with the drawings, and accurately in line with straight and parallel faces. All exposed cornices shall be weathered and rendered on top in 1 : 3 cement mortar, and throated underneath. Brick cornices, if intended to be pointed, shall be made with specially moulded bricks or bricks cut and rubbed so as to give mouldings true to drawings. The profile shall be checked constantly during construction with a sheet iron template. Cornices, if required to be palstered, shall have bricks that are roughtly cut. Cornices shall be measured and paid for by a linear rate. For copings, unless otherwise specified, the top courses of all plinths, parapets, steps, etc. shall be built in brick on edge. Coping shall be measured by actual cubic contents. String courses shall be made in bricks laid flat (or on edge) consisting of one or more courses as required. This work is paid for in cubic contents. Eaves brick shall be laid flat with a projection of 7.5 cm with a chamfer on the upper edge. Eaves bricks are generally laid in 1 : 3 cement mortar these are paid by a linear rate. Window sills shall be made of bricks laid on edge on a tile creasing to keep the joints in line, and will extend to 7.50 cm beyond the opening on either side. The bricks shall project 7.5 cm from the outer face of the wall. Window sills are laid in 1 : 3 cement mortar. Sills shall be paid by a linear rate. Drip courses, when formed of flat bricks, shall follow the same specifications and are paid for at the same rate as eaves bricks. Sometimes these are built in brick on edge. Bricks on edge are also laid in flooring and small, minor partitions and are paid for in m2 measure.
3.4 CLASSIFICATION OF ORDINARY BUILDINGS : 1ST CLASS, 2ND CLASS, AND 3RD CLASS
With a large amount of data about cost and general specifications of a building one can determine the cost of a building (single, or more storeys high) per m2 of its plinth area, or covered area as the case may be. This unit cost (subject to variance with escalating material and labour costs) is a tool in the hands of a practising engineer to immediately (whenever asked to do so) estimate the total amount of money to be earmarked for a given construction it forms the first approximate estimate of cost which needs to be refined by actual, elaborate procedure as outlined so far in this presentation. When one talks of general specifications of a building (residential, public utility, office complex etc.), it covers all the main items of work. As an example, usual general specifications can be associated with different classes of a single storey residential/office building assumed up in Table 3.1.
89
Table 3.1 : General Specifications and Classifications of Single Storey Residential/Office Buildings
Item of Work Concrete in Foundations Brick masonry in foundations and up to plinth top DPC (Over plinth top) 1st Class Building LC or CC 1st class BW in lime or cement mortar Shall consist of CM (1 : 2) for 2.0 cm thickness; and, for 2.50 cm thickness it shall be 1 : 1.5 : 3 CC with 3.5 to 5.0 % (by weight) of suitable water proofing material. It shall consist of 1st class BW with lime or cement mortar. LC 1st class BW in lime mortar Shall consist CM (1 : 2) of 2.0 cm thickness with 3.5 to 5.0 % (by weight) of suitable water proofing material. 2nd Class Building LC 2nd class BW in lime mortar No DPC may be provided at all, or very ordinary type be made (i.e. just nominal one). 3rd Class Building
Superstructure
1st shall be of 2nd class BW in mud mortar, except for the use of LM (lime mortar ) in sills, pillars, etc. Flat terraced roof shall be provided that is supported over wooden battens and beams. Or, a reinforced brick (RB) roof shall be provided; or Jack arch roof (in BW) shall be given with usual terracing. Verandah roof shall consist of tiles or asbestos cement (AC) sheeting. For all inside floors (i.e., other than verandah) flooring shall consist of 2.5 cm CC over 7.5 c.m LC. Verandah floor shall be of bricks flat over LC. These shall be finished with cement pointing.
Roofing
Roof shall comprise RCC slab with an insular layer, and LC terracing over it. Thickness of RCC beams (if any as per design provisions) shall not be less than 30.0 cm.
Tile roofing or galvanized iron (GI) sheeting is provided on ordinary beams. Sometimes mud over planks, or bricks on planks supported by ordinary wooden beams is given.
Flooring
Flooring for drawing and dining room, bath room and WCs shall be of mosaic (chips in appropriate CM). For bed rooms, flooring shall be coloured and polished 2.5 cm CC over 7.5 cm LC Other floors in the building (say, passages, store rooms, etc.) shall be without colour (2.5 cm CC over 7.5 cm LC).
90
Finishing
Inside and outside walls shall be cement plastered. Further, drawing, dining, and bed rooms shall be distempered; other rooms (kitchen, stores, etc.) shall have walls white washed (i.e., inside) in three coats. Outside walls shall be colour washed in two coats over one coat of white wash.
Inside walls shall be plastered in lime or cement mortar. Outside walls shall also be lime or cement mortar-plastered or shall be painted. Inside walls shall be white washed in three coats; and outside one can have colour wash in two coats (over one coat of white wash). Chowkats of well-seasoned inferior wood. Shutters are paneled or glazed; or partly panelled and partly glazed in inferior quality timber. Two coats of painting shall be done.
Both inside and outside walls shall be plastered with LM and white washed.
Chowkats (frames 3-piece or 4-piece. In cold climates, 4-piece frames are a must) shall be of well seasoned good quality timber (or of iron). Shutters shall be paneled, glazed; or partly paneled and partly glazed in good quality wood. In addition wiregauze shutters may be provided. Varnishing or painting (two coats) shall be done.
Chowkats of wood as in 2nd class building. Shutters, however, shall be of still inferior timber. Shall be painted in two coats with ordinary paint.
Brass fittings are provided. Iron greatings (grills) for windows shall be there.
General specifications about buildings that categorise them into classes (1st, 2nd, 3rd; or A, B, C or D) also help in evaluating a given properly (this may not be a very exact evaluation) that is required to be sold/purchased, compensated for by the insurance agencies/or by the government in case of rioting, etc. It may be noted that there could be as diverse types of classification as the contents of specifications that can be framed. UP PWD has developed some important standard specifications for residential buildings, in order to classify them as : class A; class B; class C; and class D a summary of this is presented as under, giving an idea about the different ways in which things can be grouped. It is an expert eye of a practising engineer that sees through this maze of words/phrases and recognizes the fact that all the points of view discern the same thing after all.
Class A Building
Its foundation concrete shall have its ballast comprising fully burnt or over burnt bricks (known as chatka in and around Delhi) of 40 mm size with 91
1 : 6 (cement : sand), or 1 : 2 (white lime : surkhi); in both these mixes the proportion of kanaka (ballast) being 1.5. Its plinth shall be filled by earth (i.e., below the flooring). DPC shall be 2.00 cm thick with 1 : 2 (cement : coarse sand) mortar having 5% water proofing compound by weight of cement. Footing and plinth shall be built in 1st class BW in kankar lime or 1: 6 cement mortar or it shall have hard burnt brickwork in kankar lime or 1: 6 cement mortar. Superstructure shall be in 1st class bricks in kankar lime or 1: 6 cement mortar. Its 12.5 cm walls shall be in 1st class bricks in 1: 3 (cement, coarse sand) with reinforcement in place if it is self-supporting. Lintels shall consist of 1 : 2 : 4 RCC, or reinforced 1st class BW, in 1 : 3 (cement : coarse sand ) mortar. Roofs (both in single or double storey) shall comprise RCC or Jack arches, or RC hollow tiles, or RB slab. Terracing shall be 11 cm concrete in LM (kankar lime) or 1 : 2 (whitelime : surkhi) mortar. All balconies shall be of RCC. Class A buildings shall have granolithic floors in drawing, bed and bath rooms, while passages and kitchens shall have coloured cement floor with WCs having white glazed tiled floor and dado. 2.5 cm CC shall be laid over 7.5 cm LC floor in all rooms and verandah. Granolithic 90.0 cm dado shall be provided in bath rooms. In bed, drawing, and dining rooms there shall be granolithic 25 cm skirting. In kitchen and pantry there shall be cement dado (1 : 3) 90.0 cm high. And, there shall be no cement skirting in any room in this class of building. Rain water pipes of CI or AC pipes shall be provided.
Chowkats (frames) of doors and windows of class A buildings shall be of CP teak wood, while their shutters shall be of CP teak/P and G plyboarding. Wire gauze doors shall be provided in all outer doors of main rooms, kitchen and pantry; while for all windows and ventilators wire gauze shutters shall also be there.
Spar varnish (2 coats) shall be given on all wood work. Plastering of 1 : 1 : 6, cement : whitelime : local sand, shall be applied on all walls (inside and outside). Distempering shall be done in all the main rooms up to a height of 3.30 m. Inside finishing shall comprise three coats of white washing, while outside finishing shall consist of buff colour washing (or painting as specified). RCC sun shades shall be given over all doors and windows that are exposed to rains. Sanitary items in class A buildings shall be provided, such as : (a) (b) 92 Porcelain bath tub in two bath rooms. Procelain WC in all WCs (with one Indian type).
Wash basins in bath rooms and side, verandah adjacent to dining rooms. Shower in all bath rooms. Sink in pantry and kitchen. Mirror and glass shelf in all bath rooms. Towel and soap tray recess in all bath rooms. Dirty lines box in all dressing rooms.
Plinth protection (skirting the building, and laid on ground) shall consist of 2.5 cm CC over 7.5 cm LC which will be 130 cm wide or simply brick on edge in lime mortar shall be laid. Chick support in all verandah openings shall be in place. Curtain pelmets shall be provided for all external doors of main rooms. Door fittings of oxidized copper colour shall be provided. Fire place shall be provided in drawing and dining room. Hot water boiler shall be put up for two bath rooms. And, one hot case-cum-shelf facility shall be provided, either in pantry or dining room.
Class B Building
Specifications for foundations shall be same as for class A. Plinth filling, DPC, and footing and plinth shall be done as in class A. Similarly, construction of 12.5 cm walls, lintels, roofs, balconies and terracing shall follows class A specifications. In superstructure, second class bricks in kankar lime (or 1 : 6 cement mortar) shall be done in usual trimming (i.e. 30 cm masonry above DPC, jambs, top of walls near roof, and 30 cm wall/pillar at verandah); for the rest second class bricks in mud shall be used. As for WCs flooring and dado, floors in rooms and verandah (CC over LC floor), and rain water pipes specifications for class A shall hold. Granolithic floors shall be provided only in drawing room; and, coloured cement border (in floors) shall be given in dining room, and in bed rooms if so desired. No granolithic 90 cm dado shall be provided in class B building. Similarly, no granolithic 23 cm a skirting, or cement skirting shall be provided. However, a cement dado (1 : 3) 90 cm high shall be given in kitchen and pantry. For making chowkats of doors and windows sal wood shall be used; while door and window shutters shall be of CP teak, and P and G plyboarding (as for class A building). Wire gauze doors shall be provided in kitchen, pantry and dining room; and wire gauge shall be given over all windows. Painting, varnishing and plastering shall be provided as in the case of class A building. Distempering shall be done in drawing room up to the height as specified for class A. Finishing (outside and inside) also shall be done as for class A. Chick support shall be provided in all verandah openings, and all external doors of main rooms. Curtain pelmets shall be as for class A. 93
Plinth protection shall be as for class A, but only 90.0 cm wide. RCC sun shades shall be on all doors and windows exposed to rains (as in the case of class A building). Sanitary items shall be provided as detailed below :
Porcelain Bath Tub Porcelain WC Shall Not be Provided In all bathrooms (or WCs), one Indian type (with one European type in any one) As in class A As in class A As in class A
Wash basin Dirty linen box Shower; sink; mirror and glass shelf : and towel and soap tray recess
Door fittings shall be of iron; while no hot water boilers shall be provided. Fire place; and hot case-cum-shelf shall be provided as in class A.
Class C and D Buildings
Foundation concrete, plinth filling, DPC, and footing-cum-plinth shall follow specifications as for class A. Superstructure for class C as per class A, while for class D it shall be as per class B. There shall be no 12.5 cm walls at all. Lintels and roofs (single or double storey) shall be as per class A. Balconies for class C shall be of RCC, while there are no balconies for class D. Terracing for both shall be as per class A. In place of rain water pipes, class C shall have spouts; and class D too shall have spouts if necessary. These buildings shall have no granolithic floors, white glazed tiled floor and dado, or coloured cement floors; nor shall have granolithic 90 cm dado or granolithic 23 cm skirting. Both the classes shall have 2.5 cm CC over 7.5 cm LC floor as in class A. Both shall have cement dado (1 : 3) 90 cm high in kitchen, bath rooms and WCs. However cement skirting shall be there in the dining rooms of class C, while in class D it shall be provided wherever floors may have to be washed.
Chowkats of doors and windows shall be of sal wood (as in class B); while door and window shutters for class C shall comprise sal (or shisham) with P and G 5-ply panels, and for class D it shall be country wood (battened).
For both classes : wire gauze doors shall be provided in kitchen, and in window of the kitchen; and ordinary painting (3 coats) shall be given for wood work. 94
Plastering shall be same as for class A. There shall be no distempering, chick supports, or curtain pelmets. Finishing (outside) shall be as for class A and for inside it shall be 3 coats of white wash. Plinth protection for class C shall be 13 cm of kankar (or brick ballast), rammed to 7.5 cm, and shall be 90 cm wide : while there will be no plinth protection for class D. RCC sun-shades shall be over all doors and windows that are exposed to rains. Door fittings shall be of iron. Rest no sanitary items shall be there in these two classes of buildings. No hot water boiler, fire place, or hot case-cum-shelf shall be provided.
Servants quarters (in all 8 units, 4-units in ground floor + 4 units in first floor) were proposed to be built (Figure 3.2). The Figure presents the half-plan (at ground-floor level plan being symmetrical about the centre line as shown) of the complex. The work could not be completed. Only the ground floor (4 units) were in place, that too without baths, latrines, etc. (to be constructed at the back as indicated); moreover, no stairs could be built in the well earmarked for the purpose. The whole ground floor construction (incomplete in itself, though) was topped with an RCC (1 : 2 : 4) roof slab 15 cm thick. Hard murran filling was done everywhere. [Note : Verandah gap as well as stair case gap is 2.3 m high with respect to DPC top.] Develop the trench plan of the structure. Also estimate the following quantities (for 4 units) : (a) (b) (c) Earthwork in excavation in hard soil. Hard Murram filling. Brickwork (BW) first-class in : (i) (ii) plinth (below and above ground level), CM (1 : 6) including steps. superstructure in CM (1 : 4). (Note : Partition walls are to be paid cubic-content wise.) (d) (e) Stone rubble soling in foundations, including hand packing. Cement concrete (1 : 4 : 8) in foundations. 95
Figure 3.2 : Half Plan of 8-unit Servants Quarters (At Ground Floor) Example 3.2
96
30.0 cm, 1st Class BW DPC, 2.5 cm thick (1 : 2 : 4 CC) 30 cm 30 cm 35 cm GL 50 m 0.66 m 0.30 cm CC 0.5 m (1 : 4 : 8) CC 53 cm 1.10 m 0.5 m Rubble Soling 0.64 m 70 cm 15 cm Hard Murram Filling 2.0 cm CC over 3.0 cm LC
0.84 m
0.85 m
Figure 3.3 : A Typical Cross-section Combining Steps and a Wall with Foundations (Example 3.2)
Solution
With the help of the given plan (at plinth level) and the typical wall section (Figures 3.2 and 3.3), the required trench is drawn as shown in Figure 3.4. However, the student is expressly advised to first try, on his/her own, drawing the trench plan and then compare with the one shown in Figure 3.4. And, now it should be very easy to proceed with the preparation of bill of quantities.
11.20 m
2.9 m
9.0 m
0.65 m
2.6 m 3.25 m
0.75 m
Figure 3.4 : Trench Plan of Servants Quarters Example 3.2 Walls Clubbed together while Estimating Quantities are filled with different Markings (Symbol)
3.25 m
+ + + + +
+ + + + +
1.95 m
+ + + + + + + + + + + + + + + + + + + + + + + + +
+ + + + +
+ + + + +
+ + + + +
+ + + + +
+ + + + +
+ + + + +
+ + + + +
+ + + + +
+ + + + +
+ + + + +
+ + + + +
+ + + + +
+ + + + +
2.6 m
97
Total
(1)
Earthwork in excavation in hard soill (i) Front long walls of living rooms (hatched portion in Figure 3.4) (ii) Long walls of front verandah (dotted) (iii) Rear long walls of living rooms (crosses) 2 1 2 2 5.0 8.5 9.0 3.7 1.1 1.1 1.1 1.1 2.0 2.0 2.0 2.0 22.0 18.70 39.60 16.28
1 (iv) Rear long walls back verandah, and wall between back verandah and kitchen (slanting dash-anddot) (v) Long walls between kitchen and front verandah (plus signs) (vi) Crossing walls of living rooms (triangles) (vii) Cross walls between staircase and kitchen-cumverandah group (plain no signs used) (viii) Cross walls between living room and kitchen-cumverandah group (wavy, short markings) (ix) Cross walls of back verandah (squares) (x) Excavation for steps (in front only which are in place) 4
6.3 11.2
1.1 1.1
2.0 2.0
13.86 98.56
2.6
1.1
2.0
22.88
3.25
1.1
2.0
21.45
3.80
1.1
2.0
33.44
4.45
1.1
2.0
39.16
0.7
1.1
2.0
6.16
98
(2)
Filling rubble in foundations including hand packing (width and length of the soling item being same as for the relevant excavation item, except for its height i.e., thickness) Cement concrete (1 : 4 : 8) in foundations
332.09 2
0.5 = 83.02 m
(3)
4 1.46
0.66
0.3
1.156 m3
Grand Total = 84.18 m3 (4) Brickwork, first class in cement mortar (a) Plinth below GL, 0.84 m thick masonry, in 1 : 6 CM (i) 2 1 (ii) (iii) 2 2 1 (iv) (v) (vi) (vii) (viii) (ix) Partition wall (back verandah), 10 mm thick up to floor level
[1.45 2
4.74 8.24 9.26 3.70 6.56 10.94 2.86 3.51 4.06 4.71 0.96 1.25
0.84 0.84 0.84 0.84 0.84 0.84 0.84 0.84 0.84 0.84 0.84 0.4
0.85 0.85 0.85 0.85 0.85 0.85 0.85 0.85 0.85 0.85 0.85 0.75
6.77 5.88 13.22 5.28 4.68 31.24 8.17 7.52 11.60 13.45 2.74 0.76
4 4 3 4 4 4 2
= 1.25 m ;
0.84 0.64 2
70 + 2 + 3 = 75 cm = 0.75 m; and 0.40 m is its thickness below the floor level as mentioned, in Figure 3.2] Total 111.31 m3 (b) Plinth below floor level, 0.64 m thick masonry, in 1 : 6 CM up to GL (i) (ii) 2 1 2 4.54 8.04 9.46 0.64 0.64 0.64 0.85 0.85 0.85 4.94 4.37 10.29
99
2 1 4 4 4 4 4 4
[This part of masonry 4(b) up to this stage is 15/85th below GL, and 70/85th is above GL. Sometimes, rates for these two parts can be quoted separately.]
Steps
Brickwork below GL
4 4
1.46 1.3
0.66 0.6
0.55 0.15
2.12 0.47
[1.3 + 0.16 = 1.46; and 0.85 0.30 = 0.55; and 00.5 + 0.1 = 0.60] Brickwork above GL [0.35 + 0.15 = 0.50] 4 4 1.3 1.3 0.6 0.3 0.50 0.35 1.56 0.55
Total = 90.56 m3 (5) Superstructure (BW) 1st class, in 1 : 4 CM (i) (ii) (iii) (iv) (v) (vi) (vii) (viii) (ix) 2 1 2 2 1 4 4 3 4 4 4 4.2 7.7 9.8 3.7 7.10 10.4 3.40 4.05 4.60 5.25 1.5 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 3.5 3.5 3.5 3.5 3.5 3.5 3.5 3.5 3.5 3.5 3.5 8.82 8.09 20.58 7.77 7.46 43.68 14.28 12.76 19.32 22.05 6.30
Total = 171.11 m3 Partition wall above plinth level (1 : 4 CM) (This wall has a DPC 2.5 cm thick.) 2 1.45 0.10 3.5 1.02 m3
[Note: If the rate of payment for this partition wall is as per area, the quantity would be equal to 1.45 3.5 = 5.08 m2.] Grand Total 172.13 m3
100
No.
Deductions
H/D
Quantity
Doors Windows (W) Windows (W1) Cupboards (C) Verandah gaps* Staircase gap
2 6 (= 12) 2 4 = 8) 2 6 (= 12) 2 4 (= 8) 2 2 (= 4) 21
Over Ds Over Ws Over W1s Over Cs Over verandah gaps Over staircase gap
12 8 12 8 2 2 (= 4) 1 2 (= 2)
[0.85 + 0.20 = 1.05; 0.57 + 0.20 = 0.77; 2.3 + 0.2 = 2.5 and 2.5 + 0.2 = 2.7] Total Deductions
st
() 24.81 = 147.32 m3
(6)
No.
H/D
Quantity
4 4 2 4 2 2 (= 4)
Note : Where, (0.64 0.3 = 0.34); (4.05 0.34 = 3.71 m); [(3.4 + 0.3) (0.64) = 3.06 m]; (1.55 0.34 = 1.21 m); (4.60 0.34 = 4.26 m); (2.5 0.34 = 2.16); (2.75 0.34 = 2.41 m); 9.8 0.30 0.10 0.64 0.40 and = 4.9; 4.9 + + = 5.1; 5.1 = 4.58 m 2 2 2 2 2
where, 0.64 m and 0.40 m refer to plinth thickness of main and partition walls, respectively.
101
With reference to Figure 3.5 one can calculate the masonry (brick or stone work) in the arch ring in cubic meters (Q) as,
t Q = r + t b 2 where, r = inner radius of the arch ring, t = thickness of the arch ring, b = breadth of arch ring, i.e. the dimension perpendicular to paper, (r + t/2) = (central radius of the ring) = length of arched masonry.
Arch Ring
. . . (3.1)
Masonry Work
Segmental Arch
When a semi-circular arch (subtending an angle of radians (180o) at the centre of the corresponding circle) is cut short Figure 3.6 on either side so that the segment ABCD subtends an angle () that is less than 180o, at the centre, we get a segmental arch. Its span DC is, obviously, less than the diameter of the parent circle. Therefore, the cubic content of masonry contained in this segmental arch (which is b units long perpendicular to paper) is given by : 1 Q = 2 t + [t b] 2 360o . . . (3.2)
1 [t b] gives the mean (central) length (i.e., where, 2 t + 2 360o along the mean circumferential path) of the arch.
102
Masonry
A D l = Span
E t F r C
Arch CC Filling
EF = h = Rise of Arch O
(in Degree)
. . . (3.3)
and
l t Q = 2 + (t b) 2 sin ( / 2) 2 360
. . . (3.4)
It is a roof over a hall (or room) which is basically supported by segmental arch and, is also known as segmental arch roof. Each arch (there may be three, four or more such arches in the roof make up) is supported at the ends (Figure 3.6) by rolled steel joists or RCC beams. The thickness of the arch ring is commonly half-brick, its span varying from 90 cm to 200 cm; and its rise varies in between 1/6th to 1/10th of the span. Length of this arch (perpendicular to paper) is fixed as equal to the width of the room plus twice the thickness of the arch as supported over the walls. And, the curved length of the arch (i.e., length of arch ring) is the curved length of the intrados. As per IS code of practice (IS : 1200), Jack arch roofing is measured in m2, whose rate of payment takes into account the cost of brickwork, concrete in haunch (spandrel) filling, etc.
Example 3.3
Work out the quantity of masonry work (brick) for the following cases : (a) (b) (c) A segmental arch of clear span = 2.75 m, and rise of 0.6 m. Take the thickness of arch ring as 45 cm, and wall thickness = 50 cm. A semi-circular arch of clear span = 3.0 m; and thickness of arch ring 50 cm; and wall thickness = 50 cm, and A 70o segmental arch whose clear span (i.e. opening) is 2.5 m. Take the thickness of the arch ring as 50 cm, and wall thickness as 30 cm. 103
Solution
(a)
Here, with reference to Eq. (3.3), we have : l = 2.75 m; t = 0.45 m; b = 0.50 m and, h = 0.6 m
8 Q =
2 2 0.45 2.75 + 0.45 + 0.6 + (2.75 + 0.45) 2 2 0.45 0.50 3 8 (2.56 + 0.680) 3.20 = 0.225 3
= 0.84 m3
(b)
(c)
or,
104
10 m3 of Brickwork (1st class) in kankar lime in foundations and plinth (materials, labour, tools and plants, etc. are considered)
Required Material Bricks (@ 500 bricks per m3) Kankar lime Labour Mistri Mason Beldar Mazdoor Bhisti 0.6 Nos 7 Nos 7 Nos 7 Nos 2 Nos. 5000 Nos 3.0 m3
Tools or Plants (T and P), etc. Add the cost on lump sum bases
(b) 10 m3 of First Class Brickwork in white lime and surkhi mortar (1 : 2) in foundations and plinth including supply of materials and labour etc.
Material Required Bricks White Lime Surkhi Labour Same as for item (a) above.
(c) 10 m3 of First Class Brickwork in white lime and surkhi mortar (1 : 3) in foundations and plinth
Materials Required Bricks White lime Surkhi Labour Same as for items (a) above.
(d) 10 m3 of First Class Brickwork in 1 : 6 cement sand mortar in foundations and plinth
Materials Required Bricks Cement (0.45 m ) Local sand Labour Same as for item (b) above.
(e) 10 m3 of First Class Brickwork in 1 : 4 cement sand mortar in foundations and plinth.
3
105
Materials Bricks Cement (0.6 m3) Local sand Labour Same as for item (a) above.
(f) 10 m3 of First Class Brickwork in superstructure (including required cutting and moulding of bricks as required), that includes home comb brickwork thickness of walls being not less than 1.5 bricks.
Materials and Labour would be the same as for respective items above (a), (b), (c), (d) and (e), but following extra labour needs to be added to each item described above : Mason Mazdoor Scaffolding, etc
Note : (a) For 10 m3 First Class Brickwork in superstructure, as in items (a), (b), (c), or (d) and (e), but for walls of one-brick thickness materials and labour would be the same as for respective items, but with the following additional labour for each respective item :
For 10 m3 of First Class Work in superstructures as in items (a), (b), (c), (d) and (e), but for half-brick thick walls, materials and labour would be the same as for the respective items, but with following additional labour for each respective item :
For 10 m3 of First Class Brickwork in Arches in 1 : 3 cement and coarse sand mortar :
Materials Bricks Cement (0.75 m3) Coarse sand Labour 106 Mistri 0.6 Nos 5000 Nos. 22.5 bags 2.25 m3
Mason Beldar Mazdoor Bhisti Tools and Plants (sundries, etc.) Formwork Scaffolding
(d)
For 10 m3 of First Class Brickwork in Jack Arches in 1 : 3 cement and coarse sand mortar :
Materials Bricks Cement (0.75 m3) Coarse sand Labour Mistri Mason Beldar Mazdoor Bhisti Tools and plants (sundries etc.) Centering and shuttering Scaffolding
(e)
5000 Nos 22.5 bags 2.25 m3 0.6 Nos 21 Nos 15 Nos 23 Nos 2 Nos LS LS LS
Materials Bricks (2nd Class) Loamy soil (or any other suitable soil) Labour Mistri Mason Beldar Mazdoor Bhisti Scaffolding
(f)
Materials
107
Bricks (3rd Class) Loamy (or other, suitable ) soil Labour Same as for item (a).
108
The stones shall be hammer dressed on the face, sides, and beds allowing close position with the adjacent stones after chipping off their weak corners. Each stone will be laid on its quarry bed and shall be wedged or pinned strongly into position in the walls by spalls or chips, which may show on the face. No stone shall tail into the wall less than 1.5 times its height. Stones shall be arranged to break joint as much as possible long vertical lines of joining shall be avoided. The bushing in the face shall not project more than 4 cm on an exposed face, and one cm on a face, which is proposed to be plastered. Mortar that is used shall be as per specifications. One header or through stone shall be inserted in at least every 0.5 m2of the face, and shall run right through the wall if not more than 60 cm thick if more than 60 cm thick, a line of these shall be laid from face to back which shall overlap each other by at least 15 cm. The hearting or interior filling between the front and back face stones will consist of the same rubble stones, not less than 15 cm in any direction not dry work, or hollow spaces, or thick joints of mortar shall be left anywhere. The hearting will be laid nearly level with each course, except that at about 0.9 to 1.0 m intervals, vertical plums projecting 15 cm to 22 cm shall be firmly embedded to form a boud between the successive courses. Hearting must not be brought to the same level as the front and back stones by the use of chips. All the stones shall be washed and wetted before use removing dirt, dust, etc. The walls shall be built truly plumb or to the designed (specified) batter. Levelling up at plinth level, window sills and roof level shall be done with the specified mortar. Quins shall be of selected stones neatly dressed to form the required angle, and laid as header and stretcher alternately. All the face joints shall not be more than 20 m thick. Random rubble masonry work in cement or compsote mortar shall be constantly kept moist for a minimum of seven days. When fat lime mortar has been used, curing should be started two days after the laying of masonry and then curing must continue for seven days.
Coursed Rubble Masonry
Quality and size of stones shall be as for random rubble work. The stones shall be laid in horizontal course not less than 15 cm in height. All the stones in each course shall be of equal height. All stones shall be set full in mortar in all bed or vertical joints. Face stones shall be hammer dressed on all beds and joints, to allow giving them approximately rectangular outline. Mortar to be used shall be specified. Bed joints shall be rough chisel dressed. A course height may lie between 15 to 30 cm. Face stones shall be laid alternately headers and stretchers no face stone shall be less in breadth than its height; nor shall it tail into the work to a length less than its height. And, at least 1/3rd of the stones shall tail into the work at least twice their height, etc. Through stones shall be inserted at appropriate intervals. The quoins shall be of the same height as the course. 109
Ashlar Masonry
The length of stone shall not exceed three times the height, and the breadth (on base) shall not be greater than 3/4th of the thickness of wall, or 15 cm whichever is more. The height of stone may go up to 30 cm. In fine Ashlar work, every stone shall be dressed on all beds, joints and faces. The beds and joints must not exceed 3.17 mm (1/8th of an inch). In pain Ashlar work, the dressed stone shall be free from any waviness in case of exposed faces or the adjoining faces, there will be fine chisel dressing to a depth of 6 mm. Top and bottom faces shall also be chisel dressed; and also faces forming vertical joints. In rough tooled on bastard Ashlar, the faces exposed to view shall have a fine dressed chisel draft 2.54 cm wide, all round the edges; and be rough-tooled between the drafts. The stones shall be laid in regular courses not less than 30 cm in height. The face stones shall be laid header and stretcher alternately. Unless otherwise specified, in all walls not more than 90 cm thick, headers shall run right through the wall. Jambs for door and window openings shall be formed with quoins of the full height of the course. Ashlar facing often has a backing of brickwork, concrete, or rubble. The height of the courses shall be equal to an exact number of courses of brick or rubble. Bond stones shall be incorporated as in random rubble masonry. All joints shall be full of mortar, not more than 5 mm thick.
Block in Course Masonry
Stone shall be rough tooled on all beds and joints giving rectangular shaped stones. Each course shall consist of stones of even thickness, no course being less than 15 cm in height. Walls built in brickwork, concrete or rubble masonry may be faced with block in course masonry. One third of the entire length of each course shall be headers. Beds and joints shall be rough-tooled. Bond stones shall be used as for other stone masonry.
Dry Rubble Masonry
It is commonly called dry stone walling; it is used to build breast and retaining walls. Largest available stones shall be used in these constructions the largest being used in the lower courses. Unless otherwise specified, dry stone walling shall be built with a face batter of 1 : 4 with vertical back. The base as well as the course must run at right angles to the face. The stones shall be roughly dressed to secure the maximum bedding surface without unduly reducing the size of the stone. Bond stones shall be provided in each course at intervals of 1.5 m. Dry stone walls exceeding 6.0 m in height must be strengthened every 3.0 m by building three consecutive courses in coursed masonry in lime or cement mortar. Weep hole shall be left in dry stone walling built against a hill side (which is the common location for such walls). 110
Filling immediately behind the dry stone wells must, wherever possible, be done with stone refuse or chips.
Arch Work in Stone Masonry
Masonry in arches shall follow general specifications for masonry as such and for dressing and cutting stones, as well as the detailed specifications for the class of stonework in which the arch work is to be executed. All stones required for the arch masonry shall be cut to a zinc sheet template made against a full sized elevation of the arch. The stones shall be dressed on the face and on the bed and other joints. The full number of stones required for the completion of an arch are to be cut and dressed, and the arch erected dry on the ground before the commencement of work on the arch. No voussoir is to be cut or dressed after it is once laid in situ in mortar. In the case of arches in walls, the two springers and the key-stone shall be through stones as well as every third stone in between. Unless otherwise specified, the height of each stone will be equal to the thickness of the arch up to 37.5 cm (15 inches) above this, two stones may be used with no stone being less than 15 cm in height.
Measurements
All stonework generally, as all brickwork, shall be measured in m3, and face work, however, shall be measured in m2. No deductions or additions shall be made on any account for the item for which no deductions (or additions) have been specified in the case of brickwork. In stone masonry, the type of stone, kind of masonry, and mix of mortar shall be fully described. Rates shall include bond stones, preparation of top surface of existing half-done work (meant to be raised further in height), and raking out joints prior to plastering or painting.
Rate Analysis
Rate analysis of any stonework shall, as for any other masonry work, shall involve cost of materials and unskilled and skilled labour. Schedules are available that provide the required information on these counts.
Example 3.4
What are the materials and labour component required for the following items of work : (a) (b)
Solution Men and Materials Required Per 10 m3
Sl. Particulars Materials Labour
10 m3 coursed rubble stone masonry in superstructure in 1 : 6 cement-sand mortar, and 10 m3of random rubble stone masonry in superstructure in 1 : 6 cement-sand mortar.
111
No.
Cement
Sand
Mistri
Mason
Beldar
Mazdoor
Bhisti
(a)
Coursed Rubble Stone Masonry in 0.6 m3 3.6 16 superstructure, 12.5 m3 0.5 m3 = 18 bags in 1 : 6 cement and sand mortar (For complete rate analysis, add LS amount for scaffolding, T and P and sundries) (b) Random Rubble Stone 0.7 m3 Masonry in 4.2 11 12.5 m3 0.5 superstructure m3 = 21 bags in 1 : 6 cement sand mortar (For complete rate analysis, add LS amount for scaffolding, T and P and sundries)
16
1.5
11
11
1.5
SAQ 1
(a) With reference to the motor garage [Example 2.3 and Figure 2.3], estimate the following quantities; (i) First class BW in plinth and foundation, in 1 : 6 cement mortar, and (ii) First class BW in lime mortar, in superstructure. By both centre-line method, and Long and Short-wall method. Assume the following data : (i) Window (W) size 1.2 1.0 (height) m (ii) Almirah (A) size 1.0 1.2 (height) m Figure 3.7 gives the centre-line plan of a residential quarter for an overseer working in Public Works Department of a State in India. Compute the quantities of the following items of work, after developing the double line plan (above plinth level) of the structure: (i) Brick Masonry work in superstructure, in 1 : 4 CM. (ii) RCC (1 : 2 : 4) in roof slab, and lintels. Due to the possibility of first floor being constructed over the ground floor, there are no projections of the roof slab over the walls. Roof slabs at 3 m height go into full wall thickness. Following specifications are applicable: (i) Height of main rooms from DPC upwards = 4.0 m. (ii) Height of verandah, passage, kitchen, store, bath, and WC = 3.00 m. (iii) Thickness of walls above the plinth level = 20 cm. (iv) Sizes Doors, D 1 2.1 m Windows, W1 2 1.5 m (it is a double shutter window) Windows W2 1 1.5 m (a single shutter window) (v) Thickness of RCC roof slab = 15 cm Thickness of lintels over doors and windows = 10 cm Bearing of lintels on either side = 10 cm
(b)
112
Calculate the above mentioned brick masonry by centre-line as well as Long- and Short-wall methods. Also draw (to scale) : (a) Front elevation, (b) Side elevation of right and left side, separately, (c) Back elevation, and (d) One sectional elevation.
W2 1.6 m Store 1.9 1.6 m D Passage W2 8.1 m 2.5 m Kitchen 3.0 2.5 m D D D W1 Room 1 3.37 3.7 m Verandah 3.0 m W1 D D 2.1 m 1.4 m 3.7 m 7.3 m 20 20 cm pillar W2 1.4 m Bath 1.9 1.4 m 8.8 m W2 WC 1m D D Room 2 4.30 3.7 m W1 0.8 m W1
1.3 m D
W2 1.2 m
1.7 m Bath
0.9 m
1.3 m
0.8 m W1 20 cm
D Room 2
Passage
3.5 m
4.10 m W2
8.3 m
D W1
7.5 m
0.7 m 1.2 m
D 9.0 m W1
3.0 m
Figure 3.8 : Plan of a Building (Figure 3.7) above Plinth Level Developed from the Line Plan (Not to Scale)
113
3.9 SUMMARY
Brickwork (masonry) is one of the major items of work in a building foundations, superstructure, and arches (wherever incorporated) and its quantification calls for a clear headed understanding of plan, elevation, and sections of a building. Thickness, i.e. width of BW varies from foundation courses (of different widths, as is generally the case) up to the superstructure (exposed walls, i.e. above the ground/plinth level). Centre-line method, as well as Long- and Short-wall methods can be employed to estimate the quantity of BW the former method being effective where uniformity of foundation and wall thickness is prevailing. As explained elsewhere also, in Long- and Short-wall methods the lengths of long wall keep decreasing, and while of short walls keep increasing as one proceeds upwards from the bottom of the excavation trench and the width (thickness) of courses go on decreasing. Every kind of brickwork has to be constructed according to the relevant specifications. Buildings fall into various classes, depending, among other things, on the class of bricks and the richness of the mortar used. Stone masonry has its own specifications but its quantity is also expressed in cubical contents (m3) as in any brickwork. Its length, breadth, and height have to be measured for computing the contents.
(a)
Depth of plinth (under the ground + above the ground) = 30 cm + 15 cm = 45 cm = 0.45 m Length of centre line = (2 4.30) + (2 7.8) = 24.2 m 0.45 Length of LW (plinth) = 7.8 + 2 2 = 8.25 m 0.45 Length of SW (plinth) = 4.3 2 2 = 3.85 m Length of LW in superstructure = 7.5 + 2 (0.3) = 8.1 m Length of SW in superstructure = 4.0 m Height of superstructure masonry = 3.5 + 0.025 = 3.525 (However 0.025 m being a very small amount, one could as well take the garage height as 3.5 m only.) = 3.53 m (say).
114
Sl. No.
Description
No L (m)
Quantity (m3)
(1)
First class BW in plinth and foundations, in 1 : 6 CM (a) By centre-line method (b) By L-S wall method
1 2 2
LW SW (2)
First class BW in lime mortar, in superstructure (a) By centre-line method
1 2 2
Deductions [Some of the following items have already been done in the solution to Example 2.3] OPENINGS Windows 3 1.2 0.3 1 1.08 Almirahs 2 1.0 0.23 1.2 0.55 Gate opening 1 3.0 0.3 2.3 2.07 (Neglecting Almirah shelves that go into the masonry) LINTELS Over gate opening Over Windows Over Almirahs 1 5 3.4 1.2 0.3 0.2 0.2 0.18 4.08 m3 = 25.63 () 4.08 = 21.55 m3
(b)
Double-line plan, above the plinth level (say, at window level) is shown in Figure 3.8; calculations, explaining its various dimensions, are given below (for the student, to apply his/her mind to) in order the student correlates the same with the plan layout :
1 2 3 4 5 6 7 8 9 10 11 7.3 + 0.2 = 7.5 8.8 + 0.2 = 9.0 8.1 + 0.2 = 8.3 0.8 + 0.2 = 1.0 3.7 0.2 = 3.5 3.0 0.2 = 2.8 2.5 0.2 = 2.3 1.6 0.2 = 1.4 1.9 0.2 = 1.7 1.4 0.2 = 1.2 1.3 0.1 + 0.1 = 1.3 12 13 14 15 16 17 18 19 1 + 0.2 = 1.2 2.1 0.2 = 1.9 1.4 0.2 = 1.2 3.0 0.2 = 2.8 9.00 0.4 3.5 = 5.1 4.3 0.2 = 4.1 Passage
115
Sl. No.
Description
No
Quantity (m3)
(1)
Main Room 1 Long Wall Short wall Main Room 2 Long Wall Short Wall 3-m high walls (i) Store + Bath Long Walls (dotted) Short Walls (plain) (ii) Kitchen Short Walls (hatched) (iii) WC Long Wall inner (triangles) Outer (triangles) Short walls (plain) (iv) Passage Outer Wall (v) Verandah wall (excepting the portion considered under Room 2) (vi) Pillars
2 2 2 2
2 3 2 1 1 2 1 1
0.2
0.2
3.0
0.24 1350 m3
38.14 m3
D W1 W2 D W1 W2
9 4 4 9 4 4
Roof slab going into 4-m high walls at 3-m height Room 1 1 1 (3.5 + 0.4 = 3.90; 3.5 + 0.2 = 3.7) Room 2 (4.1 + 0.2 = 4.3) Total Deductions = 8.36 m3 38.14 1 1 3.90 4.3 0.2 0.2 0.15 0.15 0.12 0.13 3.90 3.7 0.2 0.2 0.15 0.15 0.12 0.11
116
Net BW in superstructure
() 8.36
29.78 m3
(2)
(i) (ii)
1 1 1
(2.8 + 0.2 + 0.2 + 1.9 + 0.2 = 5.3 ; Associated passage 2.3 + 0.2 + 1.7 + 0.2 + 0.2 = 4.6 ; or, 4.2 + 0.2 + 0.2 = 4.6) Rest of the passage (1.2 + 0.2 + 0.2 = 1.6) Verandah 1 1 1.6 3.2 (= 3 + 0.2) 0.5 0.15 0.12 2.54
Referring to Figure 3.8, following calculations are in order to compute the centre line length of 4-m, and 3-m high walls, respectively (keeping in mind the junctions of cross walls with the longer walls, where the length equal to the width of one wall is already accounted for when multiplying the centre line with the wall thickness). (i) Centre-line of 4-m high walls
0.2 0.2 = 2 3.5 + 2 + 3.5 + 2 2 2 0.2 0.2 + 2 4.1 + 2 + 3.5 + 2 2 2
= 30.8 m (ii) Centre line length of 3-m high walls Passage/verandah = 1.2 WC walls = [(0.8 + 0.8) + (1.3 + 0.2) + 0.8] WC/Bath passage = 0.9 Store/Bath = 1.7 Kitchen/Store-Bath = 2.8 Sub-Total = 10.5 m Walls surrounding (excepting one 4-m high side kitchen, store and bath) = 2.3 + 0.2 + 1.7 + 0.1 + 0.1 + 1.4 + 0.2 + 1.2 + 0.1 + 0.1+ 1.7 + 0.2 + 2.3 = 11.6 m Total length of this centre line = 22.10 m
Bill of Quantities By Centre Line Method
117
(Only Brickwork) Sl. No. Description No L (m) Brickwork in superstructure Measurements B (m) H/D (m) Quantity (m3)
(1)
1 1 2
4 3 3
Gross quantity of BW Deductions are same as for L/S method Net BW in superstructure
= 29.78 m3
118