Project Finance: Professor Pierre Hillion
Project Finance: Professor Pierre Hillion
Project Finance
project company is like a leveraged buyout (LBO), except that an LBO is a financing decision involving existing assets, whereas project finance is an investment and a financing decision involving new assets B. Esty
Outline
Introduction Part 1: Overview of Project Finance Part 2: Statistics Part 3: Project Finance versus Corporate Finance Part 4: Leverage and Financing Issues Conclusion Appendices
3
INTRODUCTION
Definition: Project Finance
PART 1
Overview of Project Finance
Government: project company need to obtain a concession from the host government. Role of type of contract: Build-own-operate (BOO) or Build-transfer-operate (BOT). Control on revenues such as for example: Eurostar, British Jail,
Suppliers and Contractors: Role of turnkey contracts to make sure that construction is completed within costs and on schedule. Turnkey contracts specify a fixed price and penalties for delays. Customers: Depending on the contract, multiple or a single customer.
7
Concession agreement with a government Engineering, Procurement and Construction (EPC) Contract between the Project Company & the Engineering Firm Operations and Maintenance (O & M) Agreement between the Operations Contractor and the Project Company, obligates the Operator to operate and maintain the project Shareholders Agreement governs the business relationship of the equity partners Inter-creditor Agreement an agreement between lenders or class of lenders that describes the rights and obligations in the event of default. Supply Agreement agreement between the supplier of a critical key input and the Project Company (e.g. agreement between a coal supplier and a power station) Purchase Agreement agreement between the major user of the project output and the Project Company 10 agreement between a metropolitan council and a power station
- Binary risks including: technology failure, full expropriation, counterparty failure, regulatory risk, force majeureThese risks increase the probability that an asset ends up worthless. In practice, projects have relatively low asset risk allowing a high debt capacity. The use of leverage introduces financial risk which allow equityholders to capture unlimited upside once debt claims have been satisfied. 12
Sponsors (suppliers) 3rd party insurers Sponsors (contractors) Sponsors (contractors) Sponsors (contractors)
Subsidiary debt
15
PART 2
Statistics
From early 1990s, private firms start financing a wide range of assets such as toll roads, power plants, telecommunications systems located in a wider range of countries.
Project sponsors have been pushing the boundaries of project finance for most of the last 15 years by increasing sovereign, market and technology risks. World Bank study: global investment in new infrastructure assets $369 billion per year from 2005-2010 with 63% in developing nations, e.g. Asia, Africa.
17
Overall 5-Year CAGR of 19% for private sector investment. Project Lending 5Year CAGR of 21%.
Bank loans
Bonds
MLA/ BLA
Equity Finance
19
Other Water & Sewage Mining Industrial Telecom Leisure & Property Petrochemicals Oil & Gas Transportation
03
04
05
06
07
08
20
20
20
20
20
20
Power
22
5-Year CAGR for Power Projects: 30%, Oil & Gas:30%, Mining: 59% and Leisure & Property: 36%.
M W in at in er g & Se w ag e
23
PART 3
Project Finance (PF) versus Corporate Finance (CF)
to minimize the net costs associated with market imperfections such as:
- incentive conflicts, - asymmetric information, - financial distress, - transaction costs, - taxes.
26
The investment is financed as part of the companys existing balance sheet. The lenders can rely on the cash flows and assets of the sponsor company apart from the project itself. Lenders have a larger pool of cash flows from which to get paid. Cash flows and assets are cross-collateralized.
- Conflicts between ownership and control - Conflicts between ownership and related parties - Conflicts between ownership and debtholders Project finance reduces information costs (asymmetric information).
Project finance reduces costly underinvestment, in particular leverageInduced underinvestment. Project finance, as a organizational risk management tool, reduces the potential collateral damage that a high risk project can impose on a sponsoring firm, i.e., risk contamination. It also reduces the costs of financial distress and solves a potential underinvestment problem.
30
Certain asset characteristics make assets prone to costly agency conflicts: Tangible assets that generate high operating margins and significant amounts of cash flow can lead to:
- inefficient investment - excessive perquisite consumption - value destruction Ex: The agency costs of free cash flows are higher in cement than in drugs. Solving the problem of ownership and control is important in project companies where few of the traditional sources of discipline are present or 32 effective.
Project Finance
Project company is dissolved once the project gets completed. No future growth opportunities. Cash flows of the project are separated from cash flows of sponsors. The single discrete project enable lenders to easily monitor project cash flows.
The verifiability of CFs is enhanced by the waterfall contract that specifies how project CFs are 33 used.
Project finance
Monitoring mechanisms include: Managerial discretion is constrained by extensive contracting. Claims on cash flows are prioritized through the CF waterfall.
Staged investment
Staged financing Leverage: high debt service forces managers to disgorge free cash flows. Creditors rights: lenders threat to seize collateral and threat of liquidation to deter borrowers opportunism.
Concentrated equity ownership provides critical monitoring, The unique board of directors and separate legal incorporation makes monitoring more simple and efficient.
High leverage both the amount and type (maturity); Bank loans provide credit monitoring. Senior bank debt disgorges cash in early years.
34
Standard Approach Vertical integration (not always possible or desirable). Long term contracts, with contract duration increasing with asset specificity. Project Finance Approach Joint ownership that allocate the residual cash flow rights and asset control rights among the deal participants.
High debt level. With high leverage, small attempts to appropriate value will result 37 In costly default and possibly a change in control.
Standard Approach
Visibility/reputation High leverage.
Standard Approach
Strong debt covenants allow both equity/debt holders to better monitor management.
Standard Approach
Disclosure. Analyst-relationship.
Standard Approach
Hedging, or foregoing the project (under-investment)
49
Firm value decreases due to cost of financial distress which increases with combined variance Project finance is preferred when joint financing (corporate finance) results in increased combined variance.
Corporate finance is preferred when it results in lower combined variance due to diversification (co-insurance).
50
Project Finance as an Organizational Risk Management Tool Impact of Project Size on Total Risk (Project Risk = 50%)
Return Variance Big Project (wP = 50%)
20%
Project Finance as a n Organizational Risk Management Tool Impact of Project Size on Total Risk (Project Risk = 33%)
Return Variance
20%
1.0
If corporate-financed investment causes total risk, and hence costs of financial distress to increase enough, PF may reduces the incremental costs of financial distress by isolating and containing project risk.
- For project finance to make sense, the reduction in the costs of financial distress must exceed the incremental transaction costs . - Project finance lowers the net costs of financing certain assets. Large, tangible, risky assets make the best candidates for project finance, particularly when they have returns that are positively correlated with the sponsors existing assets.
55
Corporate financed investment: Assets are reduced by 5 in both states of the world. The new debt-holders invest only 75 for the project and equityholders the remaining 25. Equity is worth 65 (=90-25). The equity-holders bear the distress costs. Managers acting on behalf on existing shareholders would not make the investment.
Project-financed investment: The sponsor raises 42.5 of new project debt and invests 57.5 into the project. Default is contained at the project level and there is no collateral damage inflicted at the sponsor level. The sponsor does not incur incremental distress costs.
57
When sponsors use corporate finance, they expose themselves to the full range of outcomes (NPVs).
When sponsors use project finance, they truncate the downside. The decision to use project finance can be thought of as the decision to buy a walkaway put option on the project. The combination of holding an underlying asset (project) and buying a put option on that asset gives the payoff function of a call option.
The downside protection may be valuable but the choice between corporate finance and project finance depends on the put premium and the willingness of sponsors to exercise the put option.
59
$0
Project Value
Location: Large projects in emerging markets cannot be financed by local equity due to supply constraints. Investment specific equity from foreign investors is either hard to get or expensive. Debt is the only option and project finance is the optimal structure.
Heterogeneous partners: Financially weak partner needs project finance to participate. Financially weak partner if using corporate finance can be seen as free-riding. The bigger partner is better equipped to negotiate terms with banks than the smaller partner and hence has to participate in project finance.
63
Part 4
Leverage and Financing Issues
There are lower bankruptcy costs than in corporate finance (large tangible assets).
65
Disadvantages
66
Disadvantages
Disperse ownership: less monitoring less efficient negotiations New market Lump sum nature Negative carry Markets can change at any time making issuance difficult Bond need investment grade rating
67
Project Bonds
Project bonds have negotiated ratings: sponsors adjust leverage, covenants and deal structure until the projects achieve an investment-grade rating. The largest advantage in pricing and liquidity occurs above the BBB- cutoff due to institutional restrictions against investment in sub-investment grade securities. Bonds must have an investment grade to sell in the market.
Since 1998, the percentage of project bonds with an investment grade (BBB- or higher) has ranged from 63% to 67%.
68
Disadvantages
Cost (300 bp) Time (12-18 months to arrange)
Insider debt:
Reduce information asymmetry for future capital providers.
69
Conclusion
Valuation of infrastructure assets with the infrastructure sector in danger of suffering from the dual curse of over-valuation and excessive leverage, the classic symptoms of an asset bubble.
72
APPENDIX
Project Finance versus Corporate Finance: An example
Business Units
Treasury Group
$400m
40% of Cash Flow
$250m
Business Units
Project
Cost = $1 billion Equity = $400 million Debt = $600 million
Banks
payback+interest
Risk
Completion Risk
Solution
Contractual guarantees from manufacturer, selecting vendors of repute. Hedging Keeping adequate cushion in assessment.
Operating Risk
Environmental Risk Technology Risk