Modularization
Modularization
Close
http://www.powergenworldwide.com/index/display/generic-article-tools-template/_printArticle/articles/power-engineering/volume-105/i... 31/08/2010
Page 2 of 4
fiberglass, with synthetic fill. The overall plant water balance is based on a conservative zero discharge station design. The flue gas exiting from the steam generator passes through a dry SO2 removal system for the PC case, while SO2 removal for the fluidized-bed case is accomplished via the limestone bed. The dry scrubber is modularized in several sections, including the inlet and outlet ducts, the spray dryer assembly, and the vessel assemblies for each parallel system. The flue gas finally passes through either one or two modular baghouses and clean gas is extracted via two induced draft fans, where it exits up the chimney. The baghouse modules are fabricated into modular compartments with pulse jet headers, controls, hoppers/hopper heaters and ash discharge valves attached. Much of the materials handling systems and equipment is amenable to modularization because of its repetitive, consistent design. Fuel for the boiler is delivered to the site by rail car and is unloaded in a continuous car dumper. Coal is moved automatically by belt to concrete live storage silos with an alternate route to inactive or dead storage. Mobile equipment is used to reclaim coal from inactive storage. For the most part, all coal handling and conveying equipment is modularized into individual structural cages that include rollers, idlers, emergency trip switches, and electrical and instrumentation hardware. The conveying equipment will be shipped in 60 to 80 foot lengths, depending on site and local conditions. The lime reagent or limestone for the SO2 collection processes is delivered either by truck or rail cars, unloaded into a transfer tank, and then conveyed to lime/limestone storage silos by a pneumatic transport system. All lime/limestone equipment - blowers, silos, feeders - is skid-mounted, while transfer lines or conveyors are modularized in shippable lengths. Bottom ash from the economizer section of the boiler and ash from the fabric filters is collected and conveyed to holding silos, from which it is transported to an off-site disposal area. The bottom ash conveyor and ash conveying systems are completely modularized, delivered on-site with blowers/vacuum pumps, valves, motors and instrumentation pre-installed. The plant water/wastewater treatment systems, including fire water, are all modularized onto skids complete with piping, structural, valving, electrical, and instrumentation and controls. The water treatment system (demineralizer system) is fabricated into four modules (regeneration/degasifier, anion, cation, polisher) that will plug directly into the backbone pipe rack, which in turn feeds the boiler make-up system. The major advantage of modularizing the control and instrumentation for equipment comes from moving the instrument modules out of the field. Time and cost savings are achieved by shipping split assemblies of control panels; pre-wiring from control panel to direct digital controller, printers, relay and recorder board, logic cabinets, and data logger; installing in-line instruments and sensors on the modules; and pre-wiring to instruments from the DDC. The electrical switchgear, motor control centers and power distribution centers are skid-mounted into modules to support the systems that each electrical system supplies. For example, the power distribution center for the ash handling system is located near the ash handling equipment itself and is fed from a main switchgear center close to the main auxiliary transformer. Even though the main power distribution center is in two modules instead of one, this approach results in a net loss in wiring because of the close proximity between the equipment and the power distribution center. Warehouse, administration building, machine shop and electrical shop space has been removed from the power building block. Space for these functions can be more economically provided in a separate structure. The same building codes and design load criteria apply for the backbone design. The main difference is that the structure for the main power block and individual modules is much different as a result of the unique layout. Shop assembly of the critical piping module provides better access for the heat treatment and radiographic inspection of main steam and hot and cold reheat piping welds. This permits better quality control for assembly of critical piping since field welding and inspection will be reduced. The piping engineering and design involved with this type of plant consists of assembling spool pieces on appropriate modules at a central facility and then shipping the modules to the plant site for erection. Foundations will be similar for both cases, i.e., spread footings, mats or pile and caisson supports if required. The building column foundations will be smaller due to the smaller building profile and lighter loads. The floor slab may require additional thickening due to the numerous floor mounted pipe supports, movement during installation of the skid mounted equipment modules, and the profusion of equipment on the grade slab. The plant design has not compromised the good engineering practices of generous equipment laydown and maintenance areas throughout the facility. This includes pull areas for heat exchanger tubes, pumps, compressors and electrical equipment. Ease of equipment maintenance is also enhanced by this approach since significantly fewer pipes need be routed around equipment, thereby increasing available access area to any particular component.
Schedule
Click here to enlarge image As depicted in the schedule shown in Figure 2, a modularized power plant from the start of engineering and design through completion of plant start-up will require 34 months for completion. This is compared to a standard stick-built power plant that would require 43 months for completion, or a savings of nine months in the total project duration. The bulk of the time savings comes from three
http://www.powergenworldwide.com/index/display/generic-article-tools-template/_printArticle/articles/power-engineering/volume-105/i... 31/08/2010
Page 3 of 4
significant items: Use of pre-fabricated and pre-tested modules that only require installation and final piping and electrical hookup. Reduced amount of field labor associated with assembly and construction. Reduced time required for plant start-up since the modules will have been shop-tested prior to shipment. The modular assembly approach displaces 40 percent of the stick-built field manhours, which can be expended more efficiently in a shop environment than in the field. The engineering schedule will be different for the backbone case. The main power block is fairly independent of the equipment details, and design may proceed after initial size requirements are established. Module designs may proceed after initial size requirements are established. The pipe rack modules may be designed as general design, prior to final print layouts, thereby shortening the structural design schedule. In addition, the logistics effort for setting modules into the building will be minimized. The backend facility design will be similar to the conventional case. Click here to enlarge image The construction schedule for the main power block in the modular design approach will also be different from that of the conventional case. Underground utilities will either be in standard trenches and ducts or will be run overhead on racks. The building foundations and buildings are smaller than in conventional designs and can be installed at an early date. The module mat foundations can be oversized and poured, enabling the concrete foundation contractor to leave the site early. Modules can then be supplied and installed on their own completion schedule.
Cost
Current cost estimates for a stick-built solid fuel-fired facility are in the range of $1,250-$1,360/kW, while the modular plant costs are in the range of $1,080-$1,190/kW (Figure 3). Specific cost savings for a modularized power plant over a stick-built power plant come in a number of areas: The total labor cost savings for a modularized plant are driven by the displaced stick-built field hours, at an improved efficiency of 15 percent and a bare wage rate at 20 percent less than the field labor rate. The resulting labor savings are in the range of $15-20 million. Equipment rental, small tools, expendable supplies and temporary facilities for the stick-built portion of the plant are significantly reduced due to the lower amount of field labor expended and the shorter overall duration in the field for both direct construction and plant start-up. These savings amount to $5-8 million. The construction staff cost savings, which are due to the overall shorter duration in the field for construction and plant start-up, are in the range of $2.5-4 million. The two offsets to the above savings are increased home office and engineering costs due to the modular design, and increased structural costs for the modules and modular logistics and transportation costs. The increased costs are in the $1.52.5 million range. Other savings associated with modularization of the piping, electrical, buildings and structures equate to $23-28 million.
AuthorsJerry Gotlieb is the Denver Unit Manager of Project Management and Construction Management with Carter & Burgess Inc. Tom Stringfellow is Project Manager with Carter & Burgess Inc.
http://www.powergenworldwide.com/index/display/generic-article-tools-template/_printArticle/articles/power-engineering/volume-105/i... 31/08/2010
Page 4 of 4
Ron Rice is Project Controls Manager with Carter & Burgess Inc.
Acknowledgements:
Peerless Manufacturing and Kodiak Industries Inc. provided input to the article with respect to the modular equipment. Foster Wheeler Corp. provided information for the boilers analyzed and United Conveyor provided information for the materials handling systems.
http://www.powergenworldwide.com/index/display/generic-article-tools-template/_printArticle/articles/power-engineering/volume-105/i... 31/08/2010