Overhead Protection Systems
Overhead Protection Systems
Bill Roelofs and Michael Walton RefMet P. O. Box 126 PRAHRAN, Victoria 3181 Minvent Solutions P. O. Box 314 Como W. A. 6152
ABSTRACT In most cases a refractory repair involves dealing with used refractory linings above shoulder height. This paper details a method of personnel protection involving a low pressure inflatable balloon system, installed to prevent the dislodgement and free-fall of in-situ refractories. The technique may also prevent larger scale collapses with higher internal operating air pressure being applied, but in general is designed to protect against the smaller falls from which most injuries result. INTRODUCTION In many refractory structures, interim repairs require entry of personnel to affect these. Often, significant scaffolding is required to allow personnel to reach the work face. Whether in the Steel, Non-ferrous, Cement or other Process industry, vessels of any size will have refractory, other brickwork or concrete at a level above head height. This constitutes an overhead refractory where falls of surface material from walls or roof, during repairs present a safety hazard to those working in that area. This is particularly an issue shortly after cool-down when the surface temperature of the refractory lags that of the general environment. This means that the thermal contraction of the refractory has not been completed, and falls or spalling of material from the cooling surfaces is still likely. This system, originally developed for underground mining to use in shafts, ore/waste passes, bins and chutes, has now been adapted for use in minerals and petrochemical process vessels. This has been called the Overhead Protection System or OPS. SAFETY PROTOCOLS In the last decade or so, there have been two fatalities, and numerous other incidents involving overhead refractories or falls of objects within such process vessels under repair. The first of these, in 1997, led to a major revision in safety procedures relating to overhead refractories, with the Company involved developing more formal protocols for use in these situations. These, or similar protocols, are now the industry norm.
The general accepted approach to industrial safety hazards can be summarised in figure 1 below.
Coefficient properties at an internal air pressure of 1.5KPa will generate 250kg of positive pressure per square metre against the walls. example . Example, Coefficient calculated force of an OPS Coefficient/frictional resistance for OPS. Coefficient of static friction for the PVC is 0.8 The calculated force at 1.5Kpa internal OPS air pressure is 250 Kg/m. e.g. a Vessel (Quench Tower): 4.0m diameter x 4.0m high, sidewall only : 0.8(50.272 x 250) = 10054.445kg or 10.05 tonne. Additional frictional properties (positive pressure) from top panel contact to the roof area of the vessel have not been included. Additional roof properties: 0.8(12.568 x 250) = 502.72 or 0.5 tonne
1
Thus total wall and roof contact properties equivalent to 10.55 tonne for this example. MANUFACTURE All inflatables are fully welded with a 50mm wide weld for each seam, the industry standard for this type of welding is 25mm to 40mm. The fabric is not stitched, as this creates a perforated tear line and also creates leakage. PVC and PVC composite fabrics have a density range in GSM (grams per square metre) from 900 to 1500, with operating temperatures of -30 to +70 for PVC and -30 to +100 for PVC composite. Each roll of fabric has a section cut out for quality control testing to ensure that the specification parameters are being maintained. Tests for coating to scrim adhesion, coating to coating adhesion, scrim elongation, tear strength; fabric burst strength and puncture resistance are also conducted. All webbing /slings and internal bulge restraint straps are rated and tested. The webbing and anchor points are rated for a minimum of 2 tonne. The inflation system is custom designed with a moulded Venturi inflator. The venture delivers 30 times the volume of introduced compressed air. Example: a 200 m unit can be inflated in less than 5 minutes. All finished systems are pressure tested and leakage tested prior to dispatch. For refractory systems where higher temperatures usually exist, an internal air purge is available; this assists with maintaining acceptable air temperatures within the OPS. Several types of materials are available with temperature ranges up to 100C. One such material is detailed below in table 1.
1
Most OPS systems are designed as material freefall eliminators and not post incident systems such as nets and scaffolding which catch the falling material rather than prevent it from falling in the first instance. Full contact is the preferred installation methodology. The OPS system is generally not designed to protect from a major fall from a roof or upper wall, rather from small to medium fragments which often become loose from a refractory structure on cooling. These may be pieces of say up to 2-3kg, spalled by the cooling process, which occasionally fall when work below starts, dislodged by work activities, such as vibration of jackhammers and the like. With the OPS in position, these will be restrained until the OPS is removed To mitigate any potential free-fall, the OPS must be in contact with the relevant walls or roof. Major falls may also be prevented by this full contact method when internal air pressure of the OPS is adjusted to the required weight bearing setting. Where situation occur that the OPS is not in contact with the roof for varying reasons, an impact cover for the top of the OPS can be provided. The OPS operates on a continuous air trickle feed system through the Venturi, this mitigates any air leakage that may occur from cuts, holes and leakage from fittings. The Venturi simply replaces any lost air as and when required whilst ensuring optimum operating pressures are maintained. The Venturi also performs as an over-pressure valve, OPS systems also have comprehensive point of activity Audible/Visual alarm systems that provide warning for conditions such as mains power loss, OPS low & high pressure, Low pressure is generally the result of lack of air supply, or air loss due to damage such as cuts and holes, high pressure is generally the result of incorrect setting, to much air supply to the Venturi or top/side deforming of the OPS due to loading from debris. Each of these occurrences will result in the activation of the Audible and Visual alarm. APPLICATIONS To date, these systems have been applied to vessels/areas such as, but not limited to: Flash smelter reaction shafts. Fluid bed roaster domes and freeboard zones. Cement pre-calcination shafts. Acid plant towers. Combustors. Quench towers. Off-Gas Ducts. Venturi driers and cyclones. Scrubbers and cross-overs. The figure below shows an actual installation of an OPS in a Flash Furnace reaction shaft.